4b supp
Item No. 4b_Supp Date of Meeting: September 13, 2016 Electric Ground Support Equipment (EGSE) Charging Stations 1 LEGEND GSE CHARGER DEMONSTRATION PROJECT (COMPLETED - RELOCATED BY NORTH STAR PROJECT) GSE CHARGER PHASE 1 CHARGING CORALS PROJECT (INSTALLATION COMPLETED) CONCOURSE D - GSE PHASE 1 - POWER CENTER (MODIFICATIONS COMPLETED) GSE CHARGER PHASE 2 CHARGING CORRALS PROJECT (DESIGN 85% COMPLETE) GSE CHARGER PHASE 2 PROJECT - NEW POWER CENTERS (DESIGN 85% COMPLETE) CONCOURSE C - NEW POWER CENTER (NOTEBOOK 85% COMPLETE) EGSE Locations & Power Centers 2 Project Scope of Work Summary of Work Phase 1 & 2 (Bold Items Phase 2 Work) Upgrade Concourse D existing Power Center - install controls to automate existing bus transfer scheme. Reduce electrical load on Concourse C power center by re-routing sub-feeder circuits to C1 power center. Install electrical GSE chargers throughout AOA ramp area that includes approx. 500 charge ports at: Concourses A, B, C and D North and South Satellites Add two new power centers to support the additional GSE Charger electrical loads at: Concourse C (Separate Project C800724 ) Concourse B South Satellite Install a distributed data collection network that will collect metered power consumption charger log data for billing & other historical system reports. Develop reporting system to provide various system historical, trend and GSE vehicle maintenance reports. Simplified overview of project scope of work 3 GSE Phase 1 Installation Summary GSE CHARGER PHASE 1 LOCATIONS TOTALS Concourse C Total Corrals 16 Total Charger Ports 114 Concourse D Total Corrals 16 Total Charger Ports 72 North Satellite Total Corrals 14 Total Charger Ports 92 CTE BAGWELL Total Corrals 4 Total Charger Ports 8 Grand Totals Grand Total Corrals Installed 50 Grand Total Charger Ports 286 Summary of Charger Ports for Phase 1 4 GSE Phase 2 Installation Summary GSE CHARGER PHASE 2 LOCATIONS TOTAL Concourse A Total Corrals 17 Total Charger Ports 76 Concourse B Total Corrals 19 Total Charger Ports 70 South Satellite Total Corrals 11 Total Charger Ports 72 Grand Totals Grand Total Corrals Installed 47 Grand Total Charger Ports 218 Summary of Charger Ports for Phase 2 5 Accomplishments 6 Typical GSE Charger Corrals The electrical charging system allows the airlines at the Airport to use electrically powered ground service equipment. Two Charger Ports Four Charger Ports Ten Charger Ports Multiple Charging Ports can be Derived from One Branch Circuit Reduces Costs 7 Charger Technical Specifications The Fast Charge GSE system consists of a PowerServer, multiple Power Stations and a Battery Monitor Identifier (BMID) installed in each GSE vehicle. The BMID communicates with the Battery Charger Rated for outdoors. Automatic start/stop. Anti-arcing disconnect. High power factor. Ultra-low harmonic distortion. Branch circuit 480VAC, 3 Phase input. Charger ratings 30kW, 40kW & 80kW DC output. Eliminates the need for battery changing. Electric GSE Tugs running on one battery all day. Multiple Charging Ports can be Derived from One Branch Circuit Reduces Costs 8
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.