4g supp

Item No.     4g_Supp 
Date of Meeting   August 9, 2016 

Central Terminal Expansion (CTE) Heating
Ventilation Air Conditioning (HVAC) Upgrade 
C800722 WP# U00199

Project Locations 
New Space on                                                        New Space on
South                                                           North
Mezzanine                                                       Mezzanine
level                                                                          level 

Existing North
Existing South                                                               Penthouse on
Penthouse on                                                       roof 
roof 

New South                                                         New North 
Penthouse Addition                                                   Penthouse Addition
on roof                                                                  on roof 


Collocation of new & existing equipment is cost effective and efficient 
2

New Mezzanine Spaces as seen from CTE
floor level 
NEW SOUTH MEZZ                          NEW NORTH MEZZ
SPACE                                       SPACE 





6000 square feet of under utilized space made available with this project

CTE HVAC Upgrade C800722

Project background 
CTE currently served by six Air Handling Units
(AHU's). 
All six AHU's are operating at peak capacity. 
Additional passenger growth requires use of the
North and South CTE mezzanines, which will require
additional HVAC in support of this expansion. 
CTE HVAC systems operating at peak capacity 

4

Project Scope 
Construction of two new roof top mounted AHU's in
support of the planned expansion of the CTE North
and South mezzanine spaces. 
Provide ductwork from the new AHU's to the CTE
mezzanine level for future build-out and expansion. 
Improve CTE smoke control systems. 

Complex construction required to accomplish this scope 

5

Project Schedule 
Start Design 2nd quarter 2015 
Complete Design 2nd quarter 2016 
Start Construction 3rd quarter 2016 
Complete Construction 4th quarter 2017 
Complex design and construction due to project location 

6

Project Budget 
Design         $1,114,300 
Construction    $5,078,000 
Sales Tax         $420,000 
Total            $6,612,300 
Project cost estimates remains unchanged since design authorization 

7

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.