7a supp

Item No. 7a_supp 
Meeting Date: March 22, 2016 
Transportation Network
Company (TNC)
Implementation Plan

TNC SCHEDULE 
February     March 
Week   3    4   1   2   3   4   Notes 
Environmental                                  Socialize E-KPI approach with TNCs 
Technology                                     Connect Port/TNC IT teams, agree on interim reporting 
Finalize Contract                                    Finalize terms, draft actual agreement documents 
Management Approval/Commission
Commission briefing March 22 
Awareness 
Service Ramp-up                                Prepare operating areas, signage, training 
Prepare public launch communications/question
Public Outreach 
responses 
Begin Operations                                  March 31 
Commence TNC Operations by March 31, 2016 
2

CONTRACT TERM SHEET 
TERM                     1-YEAR PILOT PROGRAM 
On-Going Per-Trip Fee              Per-trip fee, currently at $5.00 (may be split between drop-off and pick-up) 
Activation Fee                 Tiered approach based on inbound trips 9/1/15-2/29/16. One time fee up to $100,000. 
Operating Area                3rd floor of garage 
Staging Area                 South 160th Street 
Geo-fence required for 1) vehicle tracking, 2) trip reporting, and 3) "blackout" so drivers cannot accept rides
Technology 
within the area as a way to eliminate cruising or loitering for ride requests. 
Monthly reports on all drop-off and pick-up activity and E-KPI data. If and when a real-time solution is
Reporting 
implemented, TNC must participate. 
Trade Dress                  Required 
Wheelchair Accessibility              Must fulfill ride if requested, or, provide information and contact for an alternative provider 
Green Initiatives                 Environmental KPI's established for equivalency to green fleet 
Insurance                  $1 million while on Port property per recently enacted Senate Bill 5550 
Customer Feedback              App must allow customers to provide feedback 
Proposed TNC Terms 
3

TNC OPERATIONS TIMELINE 
TNC Operating Area (3rd Floor & South 160th Available)                               Completed: February 2016 
TNC's Notified of 3/31 Start Date                                              Completed: Notified on 2/26/2016 
Painting and Striping Completed                                             Completed: February 2016 
Sign Mock-ups Complete and Ready For Production                               Completed: February 2016 
Finance and Budget Billing Process Created                     Target: Week of 3/21 
Signage Updated                                   Target: Week of 3/21 
ICT/Env Monthly Report Template Completed                  Target: Week of 3/21    Unable to complete without TNC agreement 
Press Release to Announce Start of TNC's At Sea-Tac Airport           Target: Before 3/31     Once contract is signed, Public Affairs will send out PR 
Website Updated                                     Target: 3/31      Once contract is signed, website will be updated 
Contract Signed by TNC's                                 Target: Before 3/31     Pending current negotiations 
TNC Driver's Manual Distributed                            Target: Before 3/31     Manual is being finalized and printed at this time 
Implementation Work Plan 
4

Washington State: On-app without passenger: $50,000/Person,
Liability Insurance        $100,000/accident, $30,000/property damage. On-app with passenger:
Requirements            Combined single limit of $1,000,000 for death, personal injury, and
property damage.
Underinsured Insurance     Washington State: On-app without passenger: Insured can waive.
Requirements                    On-app with passenger: $1,000,000 
A personal vehicle with a TNC vehicle endorsement. Minimum vehicle age
restriction 10 years or less (City) no current age restriction in County. No
Vehicle Requirements 
limit on the number of endorsed vehicles allowed to operate. County has
records of all vehicles associated with each TNC driver, as does TNC. 

Certificate of Safety issued by a City approved ASE Certified Inspector,
Vehicle Inspection 
Multi-point vehicle inspection 

TNC Regulatory Requirements 
5

Valid WA State Driver's License, For-hire Driver's Permit and Vehicle
Licensing Requirements 
Endorsement, Individual Business License (City only) 
TNC's pay a quarterly fee of $0.35 per ride for each trip originating in
unincorporated King County or one of 16 contract cities. In the City of
Licensing Fees: 
Seattle, a $0.10 fee per ride for each trip originating in the City of Seattle
is paid by TNC's. Operators submit fees on a quarterly basis.
Initial license requires completion of an approved For-hire Driver training
Driver Training           and exam, and completion of the National Safety Council's four-hour
Defensive Driving Course (DDC-4) 
King County requires the TNC to provide criminal background checks and
driving abstracts/DMV reports for any driver without a For-hire Driver's
Permit and Vehicle Endorsement, conducted by County approved third
Background Checks 
party providers, as part of the TNC For-hire driver permit application
process. Documents received by TNC and transmitted to King County with
driver applications.
Uniforms                      Not required by any regulatory agency 
TNC Regulatory Requirements 
6

COMPLIANCE MONITORING 
Department     Frequency              Role 
Operations          Real-time     Monitor activity, vehicle, and licensing compliance.
monitoring    Perform periodic unscheduled activity observations
(license plates and vehicle data). 
Environmental       Monthly      E-KPI calculation and compliance determination 
Finance and Budget    Monthly      Ongoing analysis of TNC data, BI hub data coordination,
compare periodic activity observations to TNC selfreported
data 
Accounting         Monthly      Monthly billing, annual reconciliations, payment collection 
ICT                 Monthly       Monitor geofencing operation, TNC reporting format
compliance, coordination with TNC technology staff 
Business Development  Monthly      Verify insurance and surety compliance 
Continuous, Periodic and Ongoing Monitoring Efforts 
7

CONTRACT MANAGEMENT 
Department               Role 
Business Development    Overall TNC Agreement Oversight 
Finance and Budget      Financial Analysis and Data Analytics 
Accounting           Billing and Payment Collection 
Operations           Monitoring TNC Activity on 3rd Floor, Drives, 
Holding Area 
ICT                  Geofencing, TNC Reporting Format,
Ongoing Technology Enhancements 
Environmental         Environmental Contract Terms Oversight 
Coordinated Effort to Manage Contract 
8

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.