7a report reduced

Item Number:   7a_Report
Meeting Date: March 8, 2016


Commission Staff Brieng
Capital Improvement Projects
Fourth Quarter Report 2015

This page intentionally left blank









ii  Port of Seattle 4Q 2015 Report

PortofSeattle
CapitalImprovementProjectReport
FourthQuarter2015
Introduction
ThePortofSeattleisamunicipalcorporationcharteredbytheStateofWashingtonwiththemissiontobeaneconomic
engineforthePugetSoundregionandtheState.AprimaryactivityofthePortistocreatecapitalassetsthatallowthe
efficientflowofgoodsandpeopleintoandoutofthearea.Theintentofthisreportistoprovidethepublicwithhigh
levelinformationonthestatusofthePort'scapitalprojects.
Background
During2015,thePortplanstoinvest$373,800,000toexpandandupgradetheinfrastructurethatsupportsmarine and
aviationcommerce.FundingforthePortcomesmainlyfromtheusersofthefacilities,includingshipping companies,
airlines,rentalcarcompanies,concessionairesandpublicparking.About2percentofthePort'scapital budgetcomes
fromataxlevyonpropertyinKingCounty.TheTaxLevyfundsareusedselectivelyforinvestmentsin transportation
facilities,realestatecapitalprojectsandenvironmentalandnoisemitigationprojects.
ThePortisdedicatedtosoundstewardshipoftheresourcesitscustomersandthepublicentrusttoit.Thismeans
accomplishingitsmissionefficiently,effectivelyandeconomically,andmakingitsactionstransparenttoitsbusiness
partnersandthegeneralpublic.
AbouttheReport
Thereportwillprovidegeneralinformationontheprojectdescription,status,significantdevelopments,schedule,
budget,changeorders,risks,budgettransfers, and cost growth of construction if it exceeds 10% of contract.The
reportmayincludegraphicsthatreportprojectcostscompared toauthorization,constructioncosts(includingchange
orders(CO))comparedtotheconstructioncontract,locationmaps,andphotographs.ThePortimplementsanumber
ofdifferenttypesofprojectsandnotallinformationmaybe relevanttoaspecificproject;assuch,thereportsmayvary
indetailandcontent.Projecttypesmayrangefrom construction,tonoisemitigation,totechnology.
Theprojectdescriptionincludestheprojecttitle,projectnumber(CapitalImprovementProject(CIP)),projectphase,
andestimatedcompletiondate(substantial completion).Thissectionalsoincludes"Project Status"illustratingata
glanceiftheprojectisonschedule,and withinbudget,andthe date Construction authorization received.
x SignificantDevelopments coversitemssuchasaccomplishments,significanteventsormilestones, contract
advertisementsandawards,upcomingactivities,andenvironmentalissues.
x Schedule includesinformationontheprojectschedule,thetotalschedulevarianceandvariancesincethelast
report,contractextensions,andinformationoncriticaldates.
x Budget addressesthetotalprojectbudgetandincludesinformation on theoverallbudgetstatus,recent
Commission authorizations,forecastedoverrunsorsavings,andscopechanges.
x ChangeOrders providesinformation on current quarter'sCOs and total project COsincluding justification for CO's for
thereportingperiodandinformationonanyCOover$200,000or10%ofthecontractvalue.
x CostGrowthofConstruction providesabriefdescriptionofanyprojectwithCOexceeding10percent.
x Risks describeanysignificantriskofdelay,anysignificantrisktocost,oranysignificantCO.
x BudgetTransfers reportsanytransfersbetweenauthorizedprojectsduringthereportingperiod.
Additionalinformationmayincludegraphicsindicatingbudget,constructioncosts,location,andphotographs.These
reportsintendtomeetthereportingrequirementsofPortofSeattleCommissionResolution3605, as amended by
Resolution No. 3628, and the CommissionmotiononJanuary8,2008regarding"ReportsonMajorCapitalProjects."
AdditionalInformation
Foradditionalinformation,pleasevisitthe ContactUs pageon the Port of Seattle web site to askaquestion,makeacommentor
requestacopyoftheStateAuditReportsResponseandActionPlan.

Port of Seattle 4Q 2015 Report  1

Aviation
Overall Project   Variance
S tatus 
CIP Number  Project Title             Page     Schedule  Budget
C101107 ................160th GT Lot ..........................................................6 ......................................... 
C102032 ...............Sanitary Sewer Pump Station Upgrade ................7 .........................................
C102112 ................Hennelly Service Tunnel Renewal Rep .................8 ...........
C102573 ...............Aireld Pavement Replacement ............................9 ...........
C800019 ...............Gate Utilities Improvement ...................................10 ..........
C800061 ...............Main Terminal South Low Voltage ........................11 ..........
C800107 ...............C4 UPS System Improvements ............................12 ........................................ 
C800168 ...............C60-C61 BHS Modications ................................13 ..........
C800218 ...............Security Exit Lane Breach Control Phase I ..........14 ..........
C800230 ...............Emergency Lighting Parking.................................15 .......... 
C800238 ...............Central Plant Pre-Conditioned Air ........................16 ..........
C800247 ...............Cargo 2 West Hardstand ......................................17 ........................................
C800251 ...............Vertical Conveyance Modernization.....................18 ..........
C800253 ...............Parking System Replacement ..............................19 ........................................
C800254 ...............Aircraft RON Parking Post Ofce Site..................20 ........................................
C800274 ...............8th Floor Weather Proong ..................................21 .......... 
C800324 ...............Long-Term Cell Phone Lot ....................................22 ........................................
C800335 ...............EGSE Electrical Charging Stations ...................23-24 ....... ..............
C800390 ...............Cargo 6 Enhancements ........................................25 .......... ..............
C800406 ...............RW 16C/34C Reconstruction ...............................26 .......... ..............
C800451 ...............Doug Fox Site Improvement .................................27 .......... ..............
C800464 ...............Fiber Infrastructure to Gate Backstands ..............28 ..........
C800479 ...............Fire Station Electrical Upgrades...........................29 ........................................ 
C800483 ...............Aireld Pavement Program ..................................30 ..........
C800495 ...............Facility Monitoring System Renewal ....................31 ........................................
C800497 ...............Airport Wide Mechanical Controls System ..........32 ..........
C800538 ...............Utility ER Backup Standby....................................33 ..........
C800544 ...............NorthSTAR Program.............................................34 ..........
C800545 ...............NorthSTAR Main Terminal Improvements............35 ..........
C800549 ...............SSAT Interior Renovations ...................................36 .......... .............. ......................................
C800551 ...............Grease Interceptor Augmentation ........................37 ........................................
C800556 ...............NorthSTAR North Satellite Lobbies ......................38 ..........................................................................................
C800560 ...............MT Mezzanine Tenant Relocation ........................39 ..........
C800581 ...............Parking Garage Lights ..........................................40 ..........
C800583 ...............International Arrivals Facility ................................41 ..........



2  Port of Seattle 4Q 2015 Report

Aviation, cont.
Overall Project   Variance
S tatus 
CIP Number  Project Title             Page     Schedule  Budget
C800585 ...............Wi-Fi Enhancement for Ramp and Terminal........42 ........................................
C800612 ...............Checked Baggage Recapitalization/Optimzation.43 ..........
C800629 ...............S1 Ramp ...............................................................44 ..........
C800637 ...............2014-15 Roof Replacement ..................................45 ........................................
C800638 ...............Dining and Retail Infrastructure Modernization ....46 ..........
C800642 ...............CCTV Camera Data Improvements ....................47 ..........
C800648 ...............Emergency Phones Rev .......................................48 ........................................ 
C800653 ...............Passenger Loading Bridge Renew .......................49 ........................................
C800657 ...............Domestic Water Piping .........................................50 ........................................ 
C800658 ...............Mech Energy Conservation ..................................51 ..........
C800662 ...............S4 and S6 IC Connection .....................................52 ........................................
C800667 ...............Automated Passport Control ................................53 ..........
C800688 ...............Construction Logistics Expansion ........................54 ..........
C800692 ...............2016 Fuel System Modications...........................55 ........................................
C800699 ...............Electric Utility SCADA Utility.................................56 ..........
C800702 ...............2015-2016 C Concourse Roof Repl .....................57 ..........
C800708 ...............S. Utility Tunnel Steam Pipe Upgrade ..................58 ..........
C800716 ...............Central Terminal Stairs .........................................59 ..........
C800717................N. Terminal Utilities Upgrade ................................60 ..........
C800722 ...............CTE HVAC ............................................................61 ..........
C800724 ...............Concourse C New Power Center .........................62 ..........
C800825 ...............Interim Baggage System Program .......................63 ..........
U00234-U00237 ...Tenant US Air Ticketing ATO Zone 3....................64 ..........
U00239 .................NERA Program .....................................................65 ..........
Other Aviation
Overall Project   Variance
S tatus 
CIP Number  Project Title             Page     Schedule  Budget
C200007...............Highline School Noise Insulation ..........................66 ........................................
C200048 ...............Home Insulation Retrot .......................................67 ..........
C200093 ...............Single Family Home Sound Insulation .................68 ..........
C800154 ...............Tenant Reimbursement ........................................69 ..........




Port of Seattle 4Q 2015 Report  3

Seaport
Overall Project   Variance
S tatus 
CIP Number  Project Title             Page     Schedule  Budget
C102554-U00050 Terminal 46 Development....................................70 ..........
C102554-U00175.Container Dock Upgrade .....................................71 ..........
C102858 et al .......Street Vacations T-5/18/105..............................72-73 ......................................
C800132 ...............T-5 Berth Modernization .......................................74 ..........
C800137 ...............FT C15 HVAC Improvements ...............................75 ........................................
C800160 ...............T-91 Lighting Upgrade ..........................................76 ........................................
C800196 ...............T-102 Roof and HVAC ..........................................77 ..........
C800356 ...............Shilshole Tenant Service Buildings .....................78 ..........
C800439 ...............T-91 Substation Upgrades ....................................79 ..........
C800546 ...............Argo Yard Truck Roadway ....................................80 ..........
C800603 ...............T-46 Dock Rehabilitation ......................................81 ........................................
C800678 ...............HIM E Dock Rehab ..............................................82 ..........
C800691 ...............P69 Carpet Replacement .....................................83 ........................................
C800698 ...............P69 Beam Rehab .................................................84 ..........
C800721 ...............T18 S. Gate Rail spur Westway ............................85 ..........

WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ..................86 ..........
E104324 ................Viaduct Construction Coordination ......................87 ........................................ 
E104838................FT Net Shed Code Compliance ...........................88 ........................................
E104840................T-5, T-18 and T-91 E. Maintenance Dredging ......89 ........................................
U00033 .................T-18 Maintenance Dredging .................................90 ..........
U00099 .................IHI Cranes Removal .............................................91 ........................................









4  Port of Seattle 4Q 2015 Report

Corporate
Overall Project   Variance
S tatus 
CIP Number  Project Title             Page     Schedule  Budget
C800162 ...............ID Badge Replacement ........................................92 ........................................
C800519 ...............Contractor Data System Upgrade .........................93 ........................................ 
C800521 ...............Construction Document Management .................94 ........................................
C800728 ...............Parking System Replacement ..............................95 ..........
C800746 ...............Maximo Upgrade ..................................................96 ..........
C800763 ...............Performance Management ...................................97 ..........


Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Negative Variance Status
New Variance
Previously Reported
Schedule Completion on the Project Reports refers to:
Benecial Occupancy or Last Asset In-Use date









Port of Seattle 4Q 2015 Report  5

FOURTHQUARTER REPORT, 2015 
So. 160th GT Lot Expansion 
Project: C101107             Improve lot drainage, underground    Project Status:
Budget: $3,559,000            existing overhead utility lines, fencing   Schedule: Delayed
Phase: Design                and landscaping.                Budget: On or Under
Start: 2/1/2013                                             Status Reset: 9/22/2015
Schedule Completion: 6/30/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Construction work was reformulated as a small works project and placed out to
2.5
bid. Bid responses are due January 2016.                                 2.1
2           1.8
Schedule                                      1.5
Major scope revisionat 100% designhas led to a delay in the projectschedule.    Dollars in Millions 1               0.5
0.5
Budget
0
The project forecast is within the approved budgetand authorization.Project        Authorized Forecasted  Costs
Incurred
savings of $1,322,000 was realized in the 4th quarter of 2015.
Construction Costs
Change Order
None at this time 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The project may be subject to weather delays.
Budget Transfers
Amount       From         To
$1,322,000         C101107         C800405




AIRPORT 
6  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Sanitary Sewer Pump Station Upgrade 
Project: C102032            Upgrade the aging control systems of 22 Project Status:
Budget: $1,133,000           sanitary sewer lift stations.           Schedule: Delayed
Phase: Construction                                     Budget: On or Under
Start: 3/1/2013                                            Status Reset: N/A
Schedule Completion: 7/31/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
All control panels have been installed. Minor punch list items remain.              1.1
1.2
1.0
1
Schedule                                                   0.8
0.8
The project is behind schedule due to changes to the control panels and         0.6
installation challenges. We are carefully proceeding forward in a manner that
minimizes risk during and after system switchover.                      Dollars in Millions 0.40.2
0
Budget                                       Authorized Forecasted  Costs
Incurred
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Noneidentified at this time.
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 4Q 2015 Report  7

FOURTHQUARTER REPORT, 2015 
Service Tunnel Renewal/Replace 
Project: C102112             Project will seismically retrofit and   Project Status:
Budget: $27,586,000            structurally strengthen the airport     Schedule: Within or Ahead
Phase: Design                Service Tunnel that resides between    Budget: On or Under
Start: 11/4/2012                the Main Terminal and Airport       Status Reset: 8/5/2014
Schedule Completion: 12/31/2018   Garage.                     (Commission Design Auth.)
Significant Developments                             Budget/Costs Incurred
Design and analysis models are complete and functioning.During a meeting
30           27.6
held with Aviation senior staff, apreferred design alternative was selectedfrom
25
three possibilitiesfor the central portions of the tunnel.The preferred
20
alternative will have minimal operational impacts to the Departure and Arrivals   Dollars in Millions 15                                                         Drives during construction. The project will now move into the design.
10
4.6
5
Schedule                                                   0.6
0
Projectis on schedule.                                           Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
The project is within budget.
None at this time 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Certain SAMP outcomes may impact this project.This projectinvolves
coordinatingwith several other projects, and Aviation Operations and
Maintenance to minimize the risk of conflicts.
Budget Transfers
Amount       From         To
$0



AIRPORT 
8  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Airfield Pavement Replacement 
Project: C102573             This is a multi-year program to      Project Status:
Budget: $23,117,213            replace distressed pavement and joint   Schedule: Within or Ahead
Phase: Construction            seal on the airfield.              Budget: On or Under
Start: 5/2/2010                                             Status Reset: 4/1/2014
Schedule Completion: 6/30/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Two phases on the 2015 Apron Panel Replacement have been completed.
40
Remaining areas will utilize quick setting concrete.Work has been delayed and
30.2
will resume in the spring.                                         30
23.5      22.0
Schedule
20
2015 Panel Replacement work was delayed to avoid interference with the 16C    Dollars in Millions 10
Reconstruction work. Work has been delayed for the winter season and is        0
scheduled now to resume 2nd Quarter 2016.                            Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
The project forecast is within the approved budget.$1,000,000in savings was
returned back to the Overall Program in the 4th quarter of 2015.                20  17.1       16.8
15
Change Order
Current Quarter     Project Total         10
Number of COs           0             13
5
Amount of Cos           $0           $100,024          Dollars in Millions        0.1
0
Justification for COs: None this quarter.
Initial Change Spent
Orders
Risks
Phasing coordination with airline/operation gate impacts.                 Photo
Budget Transfers
Amount       From         To
$1,000,000         C102573         C800404



AIRPORT
Port of Seattle 4Q 2015 Report  9

FOURTHQUARTER REPORT, 2015 
Gate Utility improvements 
Project: C800019             Upgrade the Concourse B loading    Project Status:
Budget: $16,734,282         bridges to the standard 400Hz power.   Schedule: Within or Ahead
Phase: Design              Thiswill reduce aircraft emissions and  Budget: On or Under
Start: 6/28/2007               noise;improve energy efficiency and   Status Reset: N/A
Schedule Completion: 10/16/2017   save money for the airlines.         (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Concourse B 400Hz project 100%design complete. Commission Authorized     20
16.7      16.7
project to proceed to construction phase.
15
Schedule                                      Dollars in Millions             9.5
10
On schedule
5
Budget
0
Within existing approved budget.                                   Authorized Forecasted  Costs
Incurred
Change Order
Construction Costs
Current Quarter     Project Total
Number of COs           0             46             6
5.1          5.1
Amount of COs          $0          $299,867           5
Justification for COs: None this quarter                             Dollars in Millions  4
3
2
Risks
1        0.3
Bidding environment for previously sole sourced equipment could negatively
0
impact costs in construction and increase risks associated with                    Initial Change Spent
unknown/untested equipment.                                        Orders
Budget Transfers
Amount       From         To
$0



AIRPORT 
10  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Main Terminal Low Voltage 
Project: C800061            Renewal and replacement of low      Project Status:
Budget: 20,730,000           voltage (600 volts and below) electrical   Schedule: Within or Ahead
Phase: Design              distribution equipment in the Main      Budget: On or Under
Start: 6/28/2007              Terminal.                      Status Reset: N/A
Schedule Completion: 7/31/2019                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Due to project deferral and the possibility of changes in siteconditions and
25
building codes, the design phase changed from 100%to 0% complete.                   20.7
Commission re-approvedthe project in Q32014.Design team completed initial   20
site investigations and reported as-built findingsin a 15% submittal.           Dollars in Millions 1510   8.1
Schedule
5
1.0
The scopeof work, schedule and design budgetfinalized.The 100% design
0
documents scheduled for completionby the end of Q42017.                 Authorized Forecasted  Costs
Incurred
Budget
The forecast is within the approved budget.                          Construction Costs
Not Applicable 
Change Order
Photo
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
This area is a 24/7/365 operation. Sequencing of this work is critical and
electrical power has to be maintained without interruptions.Significant work
growth is possible due to lack of project definition.
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 4Q 2015 Report  11

FOURTHQUARTER REPORT, 2015 
C4 UPS System Improvement 
Project: C800107            Replace existing Uninterruptible Power Project Status:
Budget: $4,555,238          Supply (UPS) System, including      Schedule: Delayed
Phase: Design             batteries, with a new system located in   Budget: On or Under
Start: 4/14/2015              the Airport Combined Communications  Status Reset: 4/14/2015
Schedule Completion: 5/15/2017  and Command Center (C4).          (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Sixty percentDesign Submittal issued. Comments received. Moving intothe
$5            4.6
90% phase. No net change in construction budget.
$4
Schedule                                      Dollars in Millions $3   2.3
Project reactivated. Preliminary schedule shows Substantial Completion as      $2
0.8
May2017.                                    $1
$0
Budget                                       Authorized Forecasted  Costs
Incurred
New estimate has been developed based on new design concept.
Construction Costs
Change Order                               Not Applicable 
Current Quarter     Project Total
Number of COs           0             0          Photo
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The C4 center is a 24/7/365 operation. Detailed construction sequencing of
work in design documents. Thisis critical since electrical power has to be
maintained without interruptions.Risk mitiagated in design. Cut-overs limited
to short low traffic time frames.
Budget Transfers
Amount       From         To
$0



AIRPORT 
12  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
C60 -C61 BHS Modifications 
Project: C800168            This work represents a critical       Project Status:
Budget: $11,084,991          component to providing improved      Schedule: Within or Ahead
Phase: Construction          operational baggage in-line screening at   Budget: On or Under
Start: 6/1/2012               the South end of the Airport and more    Status Reset: 4/14/2014
Schedule Completion: 6/30/2015  baggage make-upcapacity for airlines.    (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
All work has been completed on this contract. The RE sent the Completion
15
letter to the Contractor on January11, 2106. Brock has also completed their          11.9
11.1
work on the additional scope on the EDS and reporting enhancements. This                     9.5
Dollars in Millions 10                                                                                 project is now complete. This is the final report. 
5
Schedule
This project is complete.
0
Authorized Forecasted   Costs
Budget                                                Incurred
Work is complete and savings are being returned.
Construction Costs
Change Order
6   5.2        5.1
Current Quarter     Project Total          5
Number of COs           0             26             4
Amount of Cos           $0           $216,104          Dollars in Millions  3
Justification for COs:None this quarter.                                2
1        0.2
Risks                                           0
Initial Change Spent
None                                             Orders
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 4Q 2015 Report  13

FOURTHQUARTER REPORT, 2015 
Security Exit Lane Breach Control Exit B Phase II 
Project: C800218            Procure and extend new automated,    Project Status:
Budget: $1,558,300          exit-land breach control,equipment at   Schedule: Within orAhead
Phase: Construction          the Concourse B exit.             Budget: On or Under
Start: 3/1/2012                                           Status Reset: N/A
Schedule Completion: 11/30/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The security exit lanes opened on schedule.Opening of the side bypass lane for    2
emergency responders has been delayed due to the long lead time for light           1.6     1.5
fixtures.                                                          1.5
1.0
1
Schedule
The security exit lane doors opened on schedule. The opening of the side       Dollars in Millions 0.5
bypass lane for emergency responders is schedule to open in February2016.       0
Authorized Forecasted   Costs
Incurred
Budget
The project forecast is within the approved budgetand authorization.
Construction Costs
Not Applicable 
Change Order
Current Quarter     Project Total       Photo
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No major risks at this time
Budget Transfers
Amount       From         To
$0



AIRPORT
14  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Emergency Lighting -Parking 
Project: C800230            Provide electrical infrastructure for a    Project Status:
Budget: $2,383,179           new source of emergency power to feed   Schedule: Within or Ahead
Phase: Closeout             the parking garage emergency lighting    Budget: On or Under
Start: 7/24/2012              circuits and ensure that code required     Status Reset: N/A
Schedule Completion: 7/16/2014  level of egress illumination is provided   (Commission Construction Auth.)
for safety.
Significant Developments                             Budget/Costs Incurred
This project is complete.This is the final report.
5    4.7
Schedule                                       4
This project is complete.                                        Dollars in Millions 3         2.2     2.1
2
Budget                                      1
Project is complete. Savings are in process of being returned.                 0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0
Amount of Cos           $0             $0             2
1.7
1.6
Justification for COs: N/A                                      1.5
Risks                                           1
None                                       Dollars in Millions 0.5     0.0
Budget Transfers                                    0
Initial Change Spent
Amount       From         To              Orders
$0




AIRPORT 
Port of Seattle 4Q 2015 Report  15

FOURTHQUARTER REPORT, 2015 
Central Plan Pre-Conditioned Air 
Project: C800238            Provide a centralized pre-conditioned   Project Status:
Budget: $55,140,463         air (PC-Air) plant (PCAP), associated   Schedule: Within or Ahead
Phase: Construction         heating and cooling piping systems,    Budget: On or Under
Start: 6/15/2009              and jet bridge terminal air handling     Status Reset: 2/25/2014
Schedule Completion: 3/31/2017  units to serve airplanes with heating    (Commission Construction Auth.)
and cooling while at the gates.
Significant Developments                             Budget/Costs Incurred
The major-works Contractor's construction is complete. PC-Air is operating at
56    55.3     55.1
72gates. Work onthe fourremaining gates is complete. Design to replace the
55
chilled water insulation, anchor and guides on Concourse A,and the anchors
Dollars in Millions 54                                                                                and guides on Concourse B, C and South Satellite is complete.                     53
52                   51.4
Schedule                                       51
Completion of the final gate systemin 2Q2015.One hundred percent         50
49
documents for PC Air Chilled Water Piping regrade are complete. Major works
Authorized Forecasted   Costs
contract for this work will be advertised Q2 2016. Work is expected to                         Incurred
complete by Q1 2017.
Budget                                    Construction Costs
The major works contract is complete. Work for completing the remaining four     40           36.6
gates and anchors and guides is withinthebudget.                        35
30   27.0
Dollars in Millions  25
Change Order
20
Current Quarter     Project Total          15      9.9
10
Number of COs           0            230
5
Amount of Cos           $0          $9,886,034           0
Justification for COs: None this quarter                                  Initial Change Spent
Orders
Risks
None at this time
Budget Transfers
Amount       From         To
$0


AIRPORT 
16  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Cargo 2 West Cargo Hardstand 
Project: C800247            Enlarge the western cargo hardstand in the  Project Status:
Budget: $7,890,000           Cargo 2 area. Includes buyout of two      Schedule: Delayed
Phase: Construction          cargo buildings and tenant relocations;     Budget: On or Under
Start: 9/5/2012               relocation of FAA antenna, security gate,    Status Reset: 10/8/2013
Schedule Completion: 10/31/2015 and guard shack; and installation of 400Hz   (Commission Construction Auth.)
in-ground power. 
Significant Developments                             Budget/Costs Incurred
Due to the widthof Gate E190 and the lengthy opening/closing times,a new
15
operating system is being upgraded with a magnetic induction mechanism and        12.5
is being installed separate from the contract. Modifications to the 400 Hz
10
electrical vaults have beenevaluated to addresspotential fall hazards Retrofit   Dollars in Millions           7.2     6.8
/ replacement options are being explored. A new project is being opened for
5
completion of this work and will be performed under a separate contract.
0
Schedule                                        Authorized Forecasted  Costs
Incurred
New gate operating system is anticipated being installed by the end of first
quarter 2016.
Construction Costs
Budget
5   4.5
The project forecast is within the approved budgetand authorization.                        3.8
4
3
Change Order
2
Current Quarter     Project Total
Number of COs           0             7            Dollars in Millions  1
0.0
Amountof Cos          $0          $41,909           0
Initial Change Spent
Justification for COs: None this quarter.                                     Orders
Risks                                        Photo
None 
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 4Q 2015 Report  17

FOURTHQUARTER REPORT, 2015 
Vertical Conveyance Modernization Program -
Aeronautical 
Project: C800251            Perform modernization on 9 existing    Project Status:
Budget: $24,556,408          elevators and 4 escalators: SSAF, MT-2,  Schedule: Within or Ahead
Phase: Construction          MT-3, MT-4, MT-5, MT-6, MT-7, SSB,  Budget: On or Under
Start: 10/25/2011             SSC. Install new elevators SSM and     Status Reset: 11/11/2013
Schedule Completion: 10/30/2016 SSN. Install cooling packages on 12     (Commission Construction Auth.)
existing hydraulic elevators throughout
Main Terminal. 
Significant Developments                             Budget/Costs Incurred
Construction continued with the contractor working on the first sixelevators.
20
Elevators MT-2 and MT-7 have been opened for public use.                   16.4
15           13.2
Schedule                                      Dollars in Millions 10            7.1
Construction is underway. Partial substantial completion of portions ofthe first
phase of construction occurredin Q42015.                          5
0
Budget                                       Authorized Forecasted  Costs
Incurred
The project forecast is within the approved budget and construction is
underway. Project has returned budget upon deferralof second phase of work.
Construction Costs
Change Order
5    4.6
Current Quarter     Project Total
4
Number of COs           10            42                         3.1
3
Amount of Cos          $30,298         $161,606
2
Justification for COs: differing site conditions, sequencing of work, and
administrative changes.                                        Dollars in Millions  1
0.2
0
Risks                                             Initial  Change  Spent
Orders
Contractor is projecting missing delivery milestonesand will failto complete
work on time in 2016.
Budget Transfers
Amount       From         To
$0


AIRPORT 
18  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Parking System Replacement 
Project: C800253             Replacethe previous Parking Revenue Project Status:
Budget: $5,427,364            Control System, which manages      Schedule: Delayed
Phase: Closeout               parking access and revenue collection   Budget: On or Under
Start: 4/6/2010                 in the Airport's Main Parking Garage.   Status Reset: 3/8/2011
Schedule Completion: 5/31/2014                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Scheidt & Bachmann (S&B) system is operational and exhibits accuracy and
12
availability rates above 99.99%. Aletter, reviewed by the Legal and ICT            9.8
10
departments, informing the contractor of the Port's intention to close out their
8
contractwas mailed. The Port letter noted the contractor's inability to deliver a   Dollars in Millions           5.4
6                  5.1
key certification, and our intent to withhold payment for this task.
4
2
Schedule
0
The system is complete and in use. However, acritical Payment Card Industry      Authorized Forecasted  Costs
Incurred
(PCI)certification issueremainsoutstanding.
Budget                                    Construction Costs
None this quarter 
The project remains within its' approved budget.
Photo
Change Order
Current Quarter     Project Total
Number of COs           0             9
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Scheidt andBachmann could respond adverselyto the Port's letter.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 4Q 2015 Report  19

FOURTHQUARTER REPORT, 2015 
AircraftRONParking USPS Site 
Project: C800254             Prepare the site for the construction of Project Status:
Budget: $41,456,350            hardstands for use as Remain        Schedule: Delayed
Phase: Construction            Overnight (RON) parking of aircraft at  Budget: On or Under
Start: 8/26/2008                the Cargo 5 areaincluding new      Status Reset: 10/8/2013
Schedule Completion: 7/31/2015    Security Guard Shelterat Gate E125.   (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
E125 Security Guard Shelter Gate E125 operating system is being upgraded
50    45.6
with a magnetic induction mechanism for greater open/close speed. Additional              38.3
40                  36.7
safety measures have been completedfor the Variable Message Sign
maintenance.                                           Dollars in Millions 3020                                                    Schedule
10
Hardstand was completed and operational on schedule. E125 Security Guard     0
Shelter will be open as soon as TSA acceptance testing is completed. Gate         Authorized Forecasted  Costs
Incurred
operating system at E125 completion first quarter 2016 (not required for shelter
occupation and operation).
Construction Costs
Budget
30
25.4
The project forecast is within the approved budgetand authorization.            25          23.3
20
Change Order                                 15
Current Quarter     Project Total         10
Number of COs           6             14           Dollars in Millions  5
0.3
Amount of Cos          $67,914         $270,235           0
Initial Change Spent
Justification for COs: 1) Provide a credit for Communication material; 2)               Orders
Wiring diagramfor future camera at gate E-125; 3) Provide 2 additional patch
panels; 4) Additional chain link fences at gate E-125; 5) Add Bldg.E-125      Photo
Commissioning requirements; 6)Modify 60Hz receptacle.
Risks
A significant amount of contaminated soil at Cargo 5 was managed through
construction contingency.Two PO's are still outstanding and negotiations are
on-going regarding two claims filed by the contractor.
Budget Transfers
Amount       From         To
$0

AIRPORT 
20  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
8th Floor Weatherproofing 
Project: C800274             Removal and replacement ofthe floor  Project Status:
Budget: $9,324,000            covering system on the eighth floor of   Schedule: Within or Ahead
Phase: Closeout               the STIA parking garage and of the    Budget: On or Under
Start: 3/23/2010                expansion joints and flashing.        Status Reset: 6/14/2011
Schedule Completion: 10/31/2013                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The project is inclose out.Port is waiting on final documentation from               WP 104325
15    13.1
contractor to complete release of retainage.
Dollars in Millions 10             8.4       8.4
Schedule
Project is complete.                                             5
Budget
0
The project forecast is within the approved budgetand authorization.Project        Authorized Forecasted  Costs
Incurred
savings were returned during the 4th quarter.
Construction Costs
Change Order
Current Quarter     Project Total          7  6.1      5.9
6
Number of COs           0             34
5
Amount of Cos           $0           $184,555
4
Justification for COs: None this quarter.                               3
2
Risks                                         Dollars in Millions  1     0.2
0
None.                                               Initial Change Spent
Orders
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 4Q 2015 Report  21

FOURTHQUARTER REPORT, 2015 
Long-Term Cell Phone Lot 
Project: C800324             Construct a new cell phone waiting lot Project Status:
Budget: $3,300,000           to replace the existing lot that is being  Schedule: Delayed
Phase: Construction          displaced, including permanent access  Budget: On or Under
Start: 12/31/2012              control on South 170th Street.        Status Reset: 4/14/2015
Schedule Completion: 12/31/2018                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Coordinated with the City of SeaTac and determined that a traffic signal, and      6         5.2
associated roadway improvements, is the likely permanent access solution.       5
Given the uncertainty of future development associated with the Sustainable     Dollars in Millions 4   3.3
Airport Master Plan,continueto evaluate options in order to minimize the        3               2.6
overall investment.                                            2
1
Schedule                                       0
Authorized Forecasted   Costs
Recommendation on the permanent accesssolutiondelayed to Q2 2016,given
Incurred
delays in the Sustainable Airport Master Plan work.
Construction Costs
Budget
The current authorized budget for the Cell Phone Lot is $3,300,000.The total       1
0.8
budget forecastis$5,200,000, whichincludes the permanent access solution.      0.8   0.7
0.6
Change Order
0.4
Current Quarter     Project Total        Dollars in Millions         0.2
0.2
Number of COs           0             6
0
Amount of Cos           $0           $204,664              Initial  Change  Spent
Orders
Justification for COs: None this quarter.
Risks                                        Photo
Displacement of completed improvements by future development in 5-10 years.
Until completion of the permanent access solution, congestion and complaints
during summer/holidaymonthscontinue. Completion of the permanent access
solution improvements to satisfy State Environmental Protection Agency and
roadway standard requirements.
Budget Transfers
Amount       From         To
$0

AIRPORT
22  Port of Seattle 4Q 2015 Report

)2857+ 48$57(5 5(3257 
(OHFWULFDO *URXQG 6XSSRUW (TXLSPHQW (*6( 
(OHFWULFDO &KDUJH 6WDWLRQV 
3URMHFW &            $LUSRUW ZLGH HOHFWULFDO FKDUJLQJ V\VWHP 3URMHFW 6WDWXV 
%XGJHW          IRU HOHFWULFDO JURXQG VXSSRUW HTXLSPHQW 6FKHGXOH 'HOD\HG 
3KDVH 'HVLJQ               DW WKH &RQFRXUVHV DQG WKH 1RUWK DQG      %XGJHW 2Q RU 8QGHU 
6WDUW              6RXWK 6DWHOOLWHV                  6WDWXV 5HVHW 
6FKHGXOH &RPSOHWLRQ                            (Commission Construction Auth.) 
6LJQLILFDQW 'HYHORSPHQWV                              %XGJHW &RVWV ,QFXUUHG 
(*6( 3KDVH 3URMHFW  &RQFRXUVH & &RQFRXUVH ' DQG 1RUWK 6DWHOOLWH 
x &RPSOHWHG DOO RSHQ SXQFK OLVW LWHPV UHFRQFLOHG SURMHFW DFWLYLW\ EXGJHWV 
FRPSOHWHG DQG VXEPLWWHG LQYHQWRU\ RI QHZ FDSLWDO DVVHWV WR DFFRXQWLQJ DQG 
LVVXHG IDFLOLW\ WUDQVIHU GRFXPHQW WR $9) , 
x ,QVWDOOHG FKDUJLQJ FRUUDOV DQG DVVRFLDWHG SRUWV DUH                     'ROODUV LQ 0LOOLRQV                                                        o &KDUJLQJ &RUDOV  
o &KDUJLQJ 3RUWV 
$XWKRUL]HG )RUHFDVWHG   &RVWV
(*6( 3KDVH 3URMHFW  &RQFRXUVH $ &RQFRXUVH % DQG 6RXWK 6DWHOOLWH                   ,QFXUUHG
x &RPSOHWHG *6( FKDUJHU PDWHULDOV WDNH RII IRU &RQFRXUVH $ &RQFRXUVH % 
DQG 6RXWK 6DWHOOLWH DQG VXEPLWWHG SXUFKDVHG UHTXLVLWLRQ WR &32 WR SXUFKDVH   &RQVWUXFWLRQ &RVWV 
FKDUJHUV IRU &RQFRXUVH $ 
x 'HVLJQ UH PRELOL]DWLRQ LV XQGHUZD\ IRU &RQFRXUVH $ &RQFRXUVH % DQG 
6RXWK 6DWHOOLWH $( FRPSOHWHG VLWH ZDON DQG ZLOO EH VXEPLWWLQJ VFRSH RI 
ZRUN DQG OHYHO RI HIIRUW WR FRPSOHWH ILQDO ELG GRFXPHQWV 
6FKHGXOH                                         'ROODUV LQ 0LOOLRQV
3KDVH &RPSOHWHG WKLV SKDVH RI WKH &KDUJHU 3URJUDP RQ 'HFHPEHU 
3KDVH &RQVWUXFWLRQ VFKHGXOHG IRU ODWH                              ,QLWLDO &KDQJH 6SHQW
2UGHUV
%XGJHW 
7KH SURMHFW IRUHFDVW LV ZLWKLQ WKH DSSURYHG EXGJHW 5HTXHVW WKH UHPDLQLQJ      3KRWR 
DXWKRUL]DWLRQ IRU WKH FRQVWUXFWLRQ IXQGLQJ DQG DXWKRULW\ WR DGYHUWLVH IRU 
FRQVWUXFWLRQ ZKHQ WKH GHVLJQ DQG ELG GRFXPHQWV DUH FRPSOHWH IRU (*6( 
&KDUJHU 3KDVH 3URMHFW 
&KDQJH 2UGHU 
&XUUHQW 4XDUWHU      3URMHFW 7RWDO 
1XPEHU RI &2V 
$PRXQW RI &2V 
-XVWLILFDWLRQ IRU &2V 1RQH WKLV TXDUWHU 

Port of Seattle 4Q 2015 Report  23

5LVNV 
&RRUGLQDWH ZLWK RWKHU DLUILHOG SURMHFWV DQG $LUOLQH *DWH 5HDOLJQPHQW SURJUDP 
%XGJHW DQG VFKHGXOH PD\ DIIHFW SURMHFW LPSOHPHQWDWLRQ DQG FRPSOHWLRQ RI WKH 
(*6( 3KDVH 3URMHFW. 
%XGJHW 7UDQVIHUV 
$PRXQW         )URP          7R 

&RVW *URZWK 'XULQJ &RQVWUXFWLRQ 
$LUOLQH 5HDOLJQPHQW FRQWULEXWHG WR FRVW LQFUHDVH FRQWLQXRXV FKDQJHV ZLWK VLWH 
FRQGLWLRQV UHODWHG WR HTXLSPHQW LQVWDOODWLRQ $( GHVLJQ VFRSH FKDQJHV WR DOORZ 
IRU VLWH FRQGLWLRQ FKDQJHV 










$,53257 
24  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Cargo 6 Enhancements 
Project: C800390            Enlarge the Cargo 6 off-gate hardstand  Project Status:
Budget: $6,428,000          to allow simultaneous nose-loading of   Schedule: Delayed
Phase: Construction         wide-body freight aircraft as well as    Budget: On or Under
Start: 9/25/2012              provide fuel hydrant and ground power   Status Reset: 10/8/2013
Schedule Completion: 7/31/2015  capabilities.                   (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Modifications to the 400Hz electrical in ground vaults for fall protection have
8
been evaluated. Retrofit / replacement options are being explored. A new           6.3
5.9
project is being opened for completion of this work and will be performed        6
Dollars in Millions                        4.9
under a separate contract.
4
Schedule                                       2
Hardstand is complete and operational.                              0
Authorized Forecasted   Costs
Incurred
Budget
The project forecast is within the approved budgetand authorization.
Construction Costs
Change Order                                  4
3.4          3.3
Current Quarter     Project Total
3
Number of COs           1             6
Amount of Cos          $15,000         $470,000           2
Justification for COs: 1) Provide grounding system within the fuel vault at      Dollars in Millions  1       0.5
Cargo 6.
0
Initial Change Spent
Risks                                                Orders
None
Photo
Budget Transfers
Amount       From         To
$0



AIRPORT
Port of Seattle 4Q 2015 Report  25

FOURTHQUARTER REPORT, 2015 
RW16C/34C Design and Reconstruction 
Project: C800406           Produce final design and reconstruct the   Project Status:
Budget: $101,395,000          existing RW 16C/34C in its existing      Schedule: Delayed
Phase: Construction          location, replace TW C and N,         Budget: On or Under
Start: 5/4/2010                reconfigure TWs H and J, install FOD     Status Reset: 12/2/2014
Schedule Completion: 6/30/2016   detection equip, and LED lighting system.   (Commission Construction Auth.)
Significant Developments                         Budget/Costs Incurred
Runway 16C/34C and associated taxiways reopened on December 18th.
120   110.2
Design at 100%for the SR 518 Interchange,currentlyused as a haul
100           84.8
route for the runway reconstruction.
Dollars in Millions 80                     67.5
60
Schedule
40
Runway 16L/34R is scheduled for closure on April 1st and reopen on
20
May 15th. Runway 16C/34C will close May 16th for 21 days to finish
0
punch list items.                                             Authorized Forecasted  Costs
Incurred
Budget
The project forecast is within the approved budget and authorization.    Construction Costs
$10,000,000 in savings has been returned to the Overall Program in the         57.0
60
4th quarter of 2015.                                                    47.7
50
Change Order
40
30
Current Quarter     Project Total       20
Number of COs          6            12        Dollars in Millions 10     1.2
Amount of Cos        $90,369.16       $1,246,204.89       0
Initial Change Spent
Justification for COs: 1) Removal, Replacement and Renaming of              Orders
Existing Airfield Signs; 2) P-403 Revision (Addition to RAP) and
Revise MTV requirements in 02743 P-403; 3) 08/29/2015 Weather
Photo
Impact Acceleration; 4) PCCP ACP Joint replacement; 5) Procure
ceramic metallic basecoated flange bolts; 6) Move Light C3-6.
Risks
Inclement weathermay impact the schedule.
Coordination with the FAA contractor.
Budget Transfers
Amount       From        To
$10,00,000        C800406         C800404

AIRPORT
26  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Doug Fox Lot Service Upgrades 
Project: C800451             Construct a new drainage system,    Project Status:
Budget: $6,909,000          asphalt resurfacing, improved lot     Schedule: Delayed
Phase: Construction          lighting, new building, and road      Budget: On or Under
Start: 2/29/2012               signage to improve lot appearance,     Status Reset: 1/6/2015
Schedule Completion: 3/31/2015   function, and revenue generation.     (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The Port has received protests (claims) from the contractor totaling $303,491      7   6.9     6.9
andhas hired outside legal services to support the on-going dispute resolution     7
process.                                                  Dollars in Millions 76               6.2
Schedule                                       6
The overall project wasdelayed with project beneficial occupancy occurring on    6
February 27, 2015.Closeout is delayed by the Contractor's claim.              6
Authorized Forecasted   Costs
Incurred
Budget
Project forecast, including the resolution of the claims, is within the revised     Construction Costs
budget.
5                 4.4
4.0
Change Order                                  4
Current Quarter     Project Total          3
Number of COs           1             43           Dollars in Millions  2
Amount of Cos           $0           $51,467
1
Justification for COs: Revision to general conditions in support of dispute                  0.1
0
resolution process.                                                  Initial  Change   Spent
Orders
Risks
Project is complete noadditional risks identified.                     Photo
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 4Q 2015 Report  27

FOURTHQUARTER REPORT, 2015 
Fiber Infrastructure to Gate Backstands 
Project: C800464            Extend airport provided          Project Status:
Budget: $3,195,000          communications infrastructureto      Schedule: Within or Ahead
Phase: Construction         additional gates, gate information      Budget: On or Under
Start: 7/9/2013               displays to all gatesand Wi-Fi antennas  Status Reset: 5/26/2015
Schedule Completion: 9/30/2016  throughoutConcourses A and B.      (Commission Construction Auth.)
Provide redundant fiber backbone
between Concourse A communication
rooms and MDR-2. 
Significant Developments                             Budget/Costs Incurred
Contractor has1)completedfour gates in Concourse A and one in Concourse B;
4
2) continuestowork between the IC rooms in Concourse A to MDR-2; and         3.20    3.01
3) installed first wireless access point.                                  3
Schedule                                      Dollars in Millions 2                                             Contractor'sschedule indicatestheproject is on schedule.NTPwas issuedlater   1            0.60
than expected due to late pre-construction submittals, but Contractor has
0
indicated utilizingtwo working crews to ensure project is completed within
Authorized Forecasted   Costs
contracted time allotment.                                                      Incurred
Budget
Construction Costs
PCS has been authorized to complete some work, including the removal of     Not Applicable 
metal ceiling tiles, upon the request of Port Maintenance. This additional cost
does not exceed the delta between the low bid and the Engineer's estimate, so
the project remains withinbudget.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of COs           0             $0
Justification for COs: N/A
Risks
Some columns in Concourse A have covers that aremore difficult to remove
than the design team had anticipated. A no-cost design change allowed for the
conduit to be run through the columns without their removal.
This project is the Contractor's first experience at the Airport and as a General
Contractor. This may lead to a schedule delay as the Contractor becomesmore
familiar with the Port and its unique operating environment.
Budget Transfers
Amount       From         To
$0
AIRPORT 
28  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Feeder 101 Taps Replacement/Fire Station
Electric Upgrades 
Project: C800479            Replace: 1) existing 208V transformer,   Project Status:
Budget: $4,775,400           12.47 KV feeder,and add a 500 KVA     Schedule: Delayed
Phase: Construction          generator and a 1000KVA transformer; 2)   Budget: On or Under
Start: 4/1/2013               electrical feeds to13 locations along Air    Status Reset: 7/1/2014
Schedule Completion: 10/31/2016 Cargo Road; and 3)electrical transformer   (Commission Construction Auth.)
and associated switchgear for Air Cargo
#4.
Significant Developments                             Budget/Costs Incurred
All work is complete with the exception of the existing automatic transfer
6
switch (ATS). The ATS failed when it was tied tothe new system. The new          4.8    4.8
5
switch will be replaced by the end of February.                                          3.9
4
3
Schedule
2
The Contractor wasscheduledto complete the project in Q4 2015; however,the   Dollars in Millions 1
existing ATShad to be replaced. Construction will be complete by Q1 2016.      0
Authorized Forecasted   Costs
Incurred
Budget
The project is onbudget.
Construction Costs
Change Order                                 2.5  2.3     2.4
Current Quarter     Project Total          2
Number of COs           11            32
Amount of Cos          -$9,165         $158,613
Justification for COs: Replacedfeeders (wire) that were to remain in place;      Dollars in Millions 1.510.5       0.2
however, water damagewas foundinside the insulation of the feeders. Damage
0
was notseen until the wire was de-energized and the insulation was removed to
Initial Change Spent
be spliced. The existing ATS failed and had to be replaced to complete the               Orders
project.
Risks
The replacement ATS is delayed.
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 4Q 2015 Report  29

FOURTHQUARTER REPORT, 2015 
Airfield Pavement Program 
Project: C800483              This is a multi-year program to    Project Status:
Budget: $32,500,000            replace distressed pavementand    Schedule: Within or Ahead
Phase: Design              joint seal on the airfield starting in   Budget:On or Under
Start: 5/5/2011                2016 through 2020.            Status Reset: 2/24/2015
Schedule Completion: 6/30/2021                            (Commission Design Auth.)
Significant Developments                             Budget/Costs Incurred
2016 Airfield Replacement Project is at 60% Design andis being combined
40
with NSTAR Taxiway A SMGCS project into a single contract.Because of the            32.5
impact on 16L,closure work cannot be completed atthe same time as the       30
remaining 16C work. 2016 work and NSTAR Taxiway A work is being       Dollars in Millions 20                                                   delayed until 2017.
10
Schedule                                          0.2        0.1
0
Projects willoccur annually through 2020.Work has been delayed until 2017,      Authorized Forecasted  Costs
Incurred
anticipated completion November 2017
Budget                                    Construction Costs
None at this time 
Within budget 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: None at this time
Risks
Coordination of Runway 16L closure is necessary to complete the Taxiway
work significant impact to airline operations with runway closure.
Budget Transfers
Amount       From         To
$0



AIRPORT 
30  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Facility Monitoring System Renewal 
Project: C800495            Provide a system upgrade that will allow Project Status:
Budget: $2,796,500           the system to maintain and expand      Schedule: Delayed
Phase: Construction          monitoring of critical systems such as    Budget: On or Under
Start: 10/23/2011             elevators, escalators, moving walks,     Status Reset: 12/10/2013
Schedule Completion: 4/11/2015  passenger boarding bridges and baggage  (Commission Construction Auth.)
systems.
Significant Developments                             Budget/Costs Incurred
F&I and maintenance will need to work with manufacturer that has been
4    3.4
unresponsive to complete the efforts.
3
Dollars in Millions                2.3
Schedule                                                   1.9
2
Project is anticipated to be completed by Q2 2016.
1
Budget
0
The forecast is within the approved budget and authorization.Savings of          Authorized Forecasted  Costs
Incurred
$627,000 was returned in Q4 2015.
Change Order                               Construction Costs
Current Quarter     Project Total        0.4   0.3         0.3
Number of COs           0             6            0.3
Amount of Cos           $0           $1,310
Justification for COs: None this quarter.                             Dollars in Millions 0.30.20.2                                                          Risks
0.1
Noneidentified at this time.                                      0.1
0.0             0.0
Budget Transfers                                     Initial ChangeOrders Spent
Amount       From         To
$0



AIRPORT 
Port of Seattle 4Q 2015 Report  31

FOURTHQUARTER REPORT, 2015 
Airportwide Mechanical Controls System 
Project: C800497            Upgrade the Mechanical ControlSystem Project Status:
Budget: $3,500,000           for Concourse A at the Airport. This    Schedule: Within or Ahead
Phase: Construction          includes adding a wireless connection to  Budget: On or Under
Start: 5/1/2013               the Logistics area to the south of the     Status Reset: 12/9/2014
Schedule Completion: 3/11/2016  Airport.                      (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
TheContractor accelerated installation of control panels. 50 of 66 panels have     4   3.5     3.5
been installed. The electrical contractor started installing the fiber optics
"backbone."                                           3
Dollars in Millions 2                     1.5
Schedule
1
Project is within schedule.
0
Budget                                       Authorized Forecasted  Costs
Incurred
Project is within budget.
Construction Costs
Change Order
3.0
Current Quarter     Project Total            2.4
2.5
Number of COs           0             0
2.0
Amount of Cos           $0             $0
1.5
Justification for COs: N/A                                     Dollars in Millions             1.0
1.0
0.5
Risks                                                 0.0
0.0
Unplanned electrical shut downs could affectthe project schedule. The             Initial Change Spent
contractor is running conduit through mechanical chases, there are possible              Orders
conflicts. An allowance added to the estimate.
Budget Transfers
Amount       From         To
$0



AIRPORT 
32  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Standby Power Facility
Project: C800538              Build and house a new 25MW     Project Status:
Budget: $37,200,000            electrical backup power generation   Schedule: Within or Ahead
Phase: Planning             facility for the Airport.         Budget:On or Under
Start: 8/4/2015                                        Status Reset: 8/4/2015
Schedule Completion: 9/30/2017                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Working withCPO to develop the Building Engineered systems procurement.
40    37.2     37.2
Schedule                                       30
Project is currently on schedule.                                    20
Budget                                     Dollars in Millions 10           0.2
Commission authorizedfull funding of project on August 4, 2015.             0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0
Not applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Federal regulatory requirements may adversely impact schedule and budget.
Budget Transfers
Amount       From         To
$0




AIRPORT
Port of Seattle 4Q 2015 Report  33

FOURTHQUARTER REPORT, 2015 
NorthSTAR Program 
Project: C800544            Includes programmatic project       Project Status:
Budget: $19,514,150          management and project controls costs   Schedule: Within or Ahead
Phase: Design              for the NorthSTAR program;consisting   Budget: On or Under
Start: 4/5/2012               of 5 capital projects that representa      Status Reset: N/A
Schedule Completion: Q4 2020   unique partnership between the Port and  (Commission Construction Auth.)
Alaska Airlines.
Significant Developments                             Budget/Costs Incurred
Updated the NorthSTAR webpage in conjunction with Port Public Affairs.
25
Transferred $750,000 from management reserve for continued program                  19.5
20
management support.
Dollars in Millions 15                                                                                 Schedule                                                                      10
4.3
Continue programmatic linkage coordination to assure airport-wide gate         5               3.5
availability is not compromised during construction.                      0
Authorized Forecasted   Costs
Incurred
Budget
The project forecast is inclusive of Programmatic Management Reserve and is
Construction Costs
within the approved budget.
None at this time 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Communication and coordination across multiple teams and stakeholders along
with identification/monitoring of all "linked" Capital projects outside of
NorthSTAR.
Budget Transfers
Amount       From         To
$750,000         C800547         C800544
Transfer of $750,000 received from C800544 for project savings into Program
Management Reserve.


AIRPORT 
34  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
NorthSTAR Main Terminal Improvements 
Project: C800545            Renovate the North Main Terminal    Project Status:
Budget: $29,200,000          security checkpoint, curbside and       Schedule: Within or Ahead
Phase: Design              ticketing lobby areas incorporate self-    Budget: On or Under
Start: 12/3/2013              operated technologies and improve      Status Reset: N/A
Schedule Completion: 11/29/2018 aesthetics.                    (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
An analysis of the final design determined there is insufficient space to
40
accommodate security checkpoint and passenger check-in/circulation
29.2
requirements.The final report was issued in September.                  30
20
Schedule
Project is on HOLDpending SAMP recommendation for project area.         Dollars in Millions 10   1.5          0.3
0
Budget                                       Authorized Forecasted  Costs
Incurred
Project forecast is within the approved budget.
Construction Costs
Change Order
Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Project scope definitioncould increase scope and budget.
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 4Q 2015 Report  35

FOURTHQUARTER REPORT, 2015 
South SatelliteInterior Renovations 
Project: C800549            Modify the mezzanine and concourse   Project Status:
Budget: $5,167,000          levels of the South Satellite to improve   Schedule: Delayed
Phase: Construction         the passenger experience.          Budget: Forecast Overrun
Start: 11/4/2012                                         Status Reset: 12/9/2014
Schedule Completion: 10/31/2016                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Construction bidswere opened for this project.Bids were significantly over the
Engineer's Estimate.Port staff is evaluating alternatives.                    5   4.36    4.36
4
Schedule
3
Project is behind schedule due to lengthy design reviews.Increased flight
2
activity has reduced the construction window of opportunitybuilt into the                        1.07
1
project schedule and will lengthen constructionas well.                   Dollars in Millions
0
Authorized Forecasted   Costs
Budget                                                Incurred
Budget to be increased due to increaseinscope and higher bids.
Construction Costs
Change Order                               Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of COs          $0            $0
Justification for COs: N/A
Risks
The high bidsmay require additional funding to complete the project.
Budget Transfers
Amount       From         To
$0



AIRPORT 
36  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Grease Interceptor Augmentation 
Project: C800551            Install one underground 9,000 gallon   Project Status:
Budget: $1,484,200          grease interceptor and one 6,000 gallon  Schedule: Delayed
Phase: Construction         above ground interceptor to service the   Budget: On or Under
Start: 5/1/2013               South Satellite, as well as hooking up    Status Reset: N/A
Schedule Completion: 3/1/2016   an existing interceptor to concessions at  (Commission Construction Auth.)
Concourse C.
Significant Developments                             Budget/Costs Incurred
PCS is currently procuring materials to begin construction.                      1.5     1.5
1.6
1.4
Schedule
Submittals and material procurementbeganQ3 2015.Scheduled to break
ground in January 2016.                                      Dollars in Millions 1.210.80.6              0.4
0.4
0.2
Budget                                      0
Authorized Forecasted   Costs
The project forecast is within the approved budgetwith PCS performing work.                  Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Construction impacts Delta Operations at S. Satellite.Risk of encountering
contaminated soilin excavation-but not expected.
Budget Transfers
Amount       From         To
$75,000         C800551         C800547




AIRPORT 
Port of Seattle 4Q 2015 Report  37

FOURTHQUARTER REPORT, 2015 
NorthSTAR North Satellite Renovation and NSTS Lobbies 
Project: C800556            Renovation and expansion of the North  Project Status:
Budget: $421,682,944         Satellite (NSAT), including NSAT      Schedule: Within or Ahead
Phase: Design              Satellite Transit System (STS) stations   Budget: Forecast Overrun
Start: 7/24/2012              "refresh", ramp level, Concourse level,    Status Reset: 12/8/2015
Schedule Completion: Q4 2020   and new rooftop airline lounge.        (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Reviewed60% design package and validated60% design estimate. Value             TOTAL
Engineering optionswereidentified andare beingincorporated into 90% design             475.8
500.0
package. Received authorization to proceed with preliminary construction
Dollars in Millions 400.0                                                                                  enabling work. Continuing collaborative efforts with AAG to achieve optional
300.0
construction phasingplanand revised project budget.
200.0   157.7
Schedule                                       100.0           23.5
Continue to evaluateand finalizeconstruction phasingoptions in collaboration     0.0
AuthorizedForecasted  Costs
with the GC/CM contractor and AAG.                                         Incurred
Budget
Construction Costs
The 60% estimates have come in above budget. Value engineering efforts have
Not Applicable 
identified savings while maintaining Port standards in appearance,
functionality, maintainability and retainingprogram requirements.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Delayed AAG concurrence for construction phasing and project budget may
impact design schedule and subsequent early construction packages.
Budget Transfers
Amount       From         To
$0

AIRPORT 
38  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Main Terminal Mezzanine Tenant Relocations 
Project: C800560            Construct new tenant leased spaces in   Project Status:
Budget: $2,025,000           order to move existing tenants and      Schedule: Within or Ahead
Phase: Construction          provide new leasable office space for    Budget: On or Under
Start: 3/26/2013              airlines on the mezzanine of the main    Status Reset: 11/19/2013
Schedule Completion: 3/30/2015  terminal.                     (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The project is in close out, this is the final report.                            2.1   2.03    2.02
2.0
Schedule
Dollars in Millions  2.0
Construction of all spacescompletedon schedule.                                     1.91
1.9
Budget                                      1.9
The project forecast is within the approved budgetand authorization.            1.8
AuthorizedForecasted  Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             26
1.2
Amount of COs          $0          $118,159.98                   1.0
1   0.9
Justification for COs: None this quarter
Risks                                         Dollars in Millions 0.80.60.4                                               None identified at this time.                               0.2     0.1
0
Budget Transfers                                     Initial Change Spent
Orders
Amount       From         To
$0
Photos




AIRPORT 
Port of Seattle 4Q 2015 Report  39

FOURTHQUARTER REPORT, 2015 
Parking Garage Lights (CA) 
Project: C800581            Use current technology to replace all    Project Status:
Budget: $5,535,000           normal lighting in the Airport Parking    Schedule: Within or Ahead
Phase: Construction          Garage on all 8 floors and in the helices.  Budget: On or Under
Start: 1/31/2014              This will reduce energy consumption     Status Reset: N/A
ScheduleCompletion: 12/31/2019 over 60%.                   (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Phase 1Major Works:Work is continuing and has moved to the first floor.
7    6.2
There are no significant issues.
6           5.5
Phase 2 Maintenance: Maintenance will continue to complete their scope as
Dollars in Millions 5                                                                             time permits. We are in the new rebate period and the work does not have to be     4
completed until a few more years in order to receive the full rebate amount.       3                2.4
2
Schedule                                       1
0
The Project ison schedule.                                        Authorized Forecasted  Costs
Incurred
Budget
The forecast is within the approved budget and authorization.              Construction Costs
$500K savings returned in Q42015.                                  1.1
1.2
1.0
Change Order
0.8
0.8
Current Quarter     Project Total
0.6
Number of COs           0             1
0.4
Amount of Cos           $0           $2,403          Dollars in Millions 0.2
Justification for COs: None this quarter                                       0.0
0.0
Initial Change Spent
Risks                                                Orders
Norisks at this time.
Budget Transfers
Amount       From         To
$0



AIRPORT 
40  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
International Arrivals Facility (IAF) 
Project: C800583            Planning, design,and construction of a   Project Status:
Budget: $608,365,000         new Federal Inspection Services (FIS)    Schedule: Within or Ahead
Phase: Planning            facility including an international       Budget: On or Under
Start: 6/25/2013              passenger bridge connectingthe South    Status Reset: 12/8/2015
Schedule Completion: 11/9/2019  Satellite and seven ConcourseA gates to  (Commission Authorization to start
the new IAF.                   Design & Construction)
Significant Developments                             Budget/Costs Incurred
Clark/SOM completed the 120-day IAF Validation Periodon November 17,
700
2015. The Design-Builder delivered three key deliverables: the Early                    608.4
600
Schematic Design; a Target Schedule; and a Target Budget. On December 8,
500
2015, the Commission approved $275.5M for the IAF Program.The Design-    Dollars in Millions 400  300.0
Builder's contract was amended on January 4, 2016,and workbegan on the      300
second of the three phases of Design-Build Contract-the Guaranteed          200
Maximum Price (GMP) Development Period.                       100            12.4
0
AuthorizedForecasted  Costs
Schedule                                                  Incurred
The project is on schedule. The Design Buildersubmitted a Target Schedule
for design and construction, which finishes in 4th Quarter 2019.             Construction Costs
Not Applicable 
Budget
TheTarget budget delivered by Clark/SOM is in alignment with the overall
program Budget. The Guaranteed Maximum Price will be negotiated between
the IAF team and the DB at approximately 60% overall design, when both
parties agree that the risks and opportunities presented by this project have been
sufficiently identified and addressed.
Change Orders
Current Quarter     Project Total
Number of COs           0             0
Amount of COs          $0            $0
Justification for COs: N/A
Risks
x Potential cost and schedule impacts from forecasted shortages of materials
and skilled labor in the current robust Seattle construction market.
x Programming and scope changes driven by dynamic operational
environment and emerging customer/stakeholder interests and requests
Budget Transfers
Amount         From           To
$0
AIRPORT 
Port of Seattle 4Q 2015 Report  41

FOURTHQUARTER REPORT, 2015 
Wi-Fi Enhancement 
Project: C800585             Upgrade Wi-Fi system in the public   Project Status:
Budget: $9,880,000            and ramp operational areas of the      Schedule: Delayed
Phase: Design                Airport.Provide micro-distribution     Budget: On or Under
Start: 11/4/2012                cabinets on the ramp of each         Status Reset: N/A
Schedule Completion: 6/5/2017    concourse to extend communications   (Commission Construction Auth.)
infrastructure.
Significant Developments                             Budget/Costs Incurred
Thirty percent design review has completed.Negotiations for 60% Design
12
Service Directive are underway.Thirty percent estimate complete.                      9.87
10
8
Schedule                                      Dollars in Millions 6                                             Long designer procurement has delayed the projecteightmonths. Difficulty     4
1.95
obtaining accurate as-built drawings has added approximately twomonths to      2              0.19
the project.                                                     0
Authorized Forecasted   Costs
Incurred
Budget
Withinbudget, however, the 30% Design estimate is higher than notebook
Construction Costs
estimate. The PM will discuss options with the project sponsor and present to
Not Applicable 
the Investment Committee this quarter.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of COs          $0            $0
Justification for COs: N/A
Risks
Design has taken longer than expected to start. Tenants have constructed their
own Wi-Fi systems, which will need to be removed after the Port's system is
constructed. As-built documentation may not be accurate or complete, leading
to design changes during construction. Wi-Fi signal audits have prescribed
more access points than currently budgeted.
Budget Transfers
Amount       From         To
$0


AIRPORT 
42  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Checked Baggage Recapitalization/Optimization 
Project: C800612            TSA approached the Airport in 2012    Project Status:
Budget: $320,550,000         with plan to replace all federally owned   Schedule: Within or Ahead
Phase: Design              and operated baggage scanning        Budget: On or Under
Start: 2/26/2013              equipment, known as Explosive        Status Reset: N/A
Schedule Completion: 12/31/2024 Detection System (EDS) equipment.     (Commission Construction Auth.)
The EDS equipment is approaching the
end of its life.
Significant Developments                             Budget/Costs Incurred
In October TSA requested we make the design compliant with their newly
400
released Planning Guidelines and Design Standards version 5.0 PDGS. The                320.5
original 100%design submittal was due November 7,2015. The Port of Seattle   300
and TSA agreed to move the submittal due date to Jan 15,2016 for the 100%
200
design submittal to allow our design team to incorporate the changes. Project
team presented the overall program progress to the airlines.                  Dollars in Millions 100   20.4          13.4
0
Schedule                                         AuthorizedForecasted  Costs
Incurred
The project is currently on schedule, but is being reviewed for 10-year plan
Budget                                    Construction Costs
The project forecast is within the approved budget. When the bid documents are  Not Applicable 
completed, request Commission Authorization for construction funding and
authority to advertise for construction.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Noneidentified at this time.
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 4Q 2015 Report  43

FOURTHQUARTER REPORT, 2015 
Gate S1 Ramp 
Project: C800629            Install a ramp to facilitate travel      Project Status:
Budget: $1,405,000           between the ramp surface and the       Schedule: Within or Ahead
Phase: Construction          International arrivals facilityfor       Budget: On or Under
Start: 11/24/2013             passenger use.                    Status Reset: 12/9/2014
Schedule Completion: 6/1/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The small works glazing contract has been award to Herzog. Steel is in
1.5     1.4
fabrication.                                                              1.2
1.1
Dollars in Millions 1                                                                             Schedule
To complete this work we neededto procure a new small works contract for
0.5
glazing, this willextend the project schedulefrom Februaryto April2016.
0
Budget                                       Authorized Forecasted  Costs
Incurred
The projectforecastis within approvedbudgetand authorization.
Construction Costs
Change Order
Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Photo
Amount of Cos            0             0
Justification for COs: N/A
Risks
The project team will monitor the weather protection work to remain within the
project budget.
Budget Transfers
Amount       From         To
$0



AIRPORT 
44  Port of Seattle 4Q 2015 Report

THIRDQUARTER REPORT, 2015 
2014-2015 Roof Replacement 
Project: C800637            Remove and replace the current roofing Project Status:
Budget: $1,927,000          system on the Alaska Hangar One and   Schedule: Delayed
Phase: Design             associated maintenance building.      Budget: On or Under
Start: 4/1/2014                                          Status Reset: N/A
Schedule Completion: 10/2/2016                            (Commission Construction Auth.)

Significant Developments                             Budget/Costs Incurred
This project was taken off hold and directed to remove the Cargo Facility roofs
2.5
that were previously part of the scope. Project scope is now only for the Alaska        1.9     1.9
2
Hangar One and GSE building. Designers directed to restart design by
reviewing the documents at 90%.
Schedule                                      Dollars in Millions 1.510.5            0.1
Project is behind schedule while the project scope is being reviewed against the    0
Strategic Airport Master Plan.                                       Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
Project forecast is within the approved budget.
Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Delaying this project could increase costs.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 4Q 2015 Report  45

FOURTHQUARTER REPORT, 2015 
Dining and Retail Infrastructure Modernization 
Project: C800638            Project is to provide infrastructure     Project Status:
Budget: $13,953,000         modifications, re-demise of spaces, two  Schedule: Within or Ahead
Phase: Design             new elevators, and two new Children's   Budget: On or Under
Start: 10/28/2014             Play Areas in support of the Airport     Status Reset: N/A
Schedule Completion: 6/30/2020  Dining and Retail concessions plan.     (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Design Package#1is100% complete. Design Package #2 is60% complete.
15           13.95
Elevator concepts for the Central Terminal have been reviewed and approved.
Job Order Contract has beenexecuted.
10    8.83
Schedule                                      Dollars in Millions 5                                             Project mayexperience adelaydepending on the leasing packages. Working                 1.20
with Sponsor to re-establish leasing schedule.                           0
Authorized Forecasted   Costs
Incurred
Budget
Currently onbudget. ADR to return to Investment Committee to request
Construction Costs
additional funds for utility build out and code compliance in the Ken's Baggage
Not Applicable 
location. This location is an important service to maintain but was not included
in the original scope of work.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of COs          $0            $0
Justification for COs: N/A
Risks
1. Construction is linked with leasing;
2. Projects in the Central Terminal are linked with other projects; delays in
these projects could impact this project.
Budget Transfers
Amount       From         To
$0


AIRPORT 
46  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
CCTV Camera and SystemEnhancement 
Project: C800642            Add cameras and improve the video   Project Status:
Budget: $11,000,000         management system at the Airport.     Schedule: Within or Ahead
Phase: Design             Project funded by a TSA Other       Budget: On or Under
Start: 11/4/2012              Transaction Agreement (OTA)        Status Reset: N/A
Schedule Completion: 7/1/2019                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Thirty percent design is complete for ramp cameras. Sixty percent design
begins. Monthly meetings held with TSA.                           12        11.00
10
Schedule
Project team has re-phased the project to complete high priority locations first.    Dollars in Millions 86   4.07
4
Ramp cameras design is anticipated to complete in April 2016.
2                  0.15
Budget                                      0
Authorized Forecasted   Costs
Project continues to be within approved budget.                                       Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The projectteamis reviewing as-built information and site conditionsin order
to understand variances.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 4Q 2015 Report  47

FOURTHQUARTER REPORT, 2015 
Emergency Phones 
Project: C800648              Overhaul and modernize the      Project Status:
Budget: $536,000              Airport Parking Garage Emergency  Schedule: Delayed
Phase: Design              Phone System.             Budget:On or Under
Start: 7/9/2015                                        Status Reset: N/A
Schedule Completion: 12/31/2015                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The building permit was issued. Electrical contractexecuted.
0.6     0.5      0.5
Schedule                                       0.5
Schedule delayeddue to availability of open order small works electrical         0.4
contract resources.Electricalwork hasto be bid due to the lack of availability
of open order small works contracting. Remaining schedule is dependent on     Dollars in Millions 0.30.2              0.1
0.1
working areas availability in the parking garage.
0
AuthorizedForecasted  Costs
Budget                                                Incurred
Currently within the budget. 
Construction Costs
Change Order                               Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs:None
Risks
Limited availability of PCS crew resourcesmay increase the schedule. The
work is in the Airport parking garage. Need tocoordinateclosely with
Operations to minimize potential delays. 
Budget Transfers
Amount       From         To
$0



AIRPORT
48  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Passenger Loading Bridge Renew 
Project: C800653              Renewal/Replacement of Passenger Project Status:
Budget: $7,250,000             Loading Bridges B6, B8, B14, C3   Schedule: Delayed
Phase: Design              and S15                 Budget:On or Under
Start: 7/18/2014                                       Status Reset: 10/7/2014
Schedule Completion: 12/31/2015                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The new Passenger Loading Bridge(PLB)at B14 began operation on May 20th
8.0    7.25
and PLB at C3 was operational on June 15th.During the fourth quarter of 2015
7.25
new PLB's were installed and are operational at S15 and B8.                6.0
Dollars in Millions 4.0                                                                                 Schedule                                                                                            2.22
Completion schedule required some revision dueto Vendor material supply      2.0
delays. Project completion will be delayed by onemonth.B6 is scheduled for     0.0
replacement in January, 2016.                                      Authorized Forecasted  Costs
Incurred
PLB        Original schedule Revised Schedule
B14 and C3       Complete                          Construction Costs
Not Applicable at this time 
S15           September 21, 2015 November 6, 2015
B6          October 12, 2015  January 22, 2016
B8          November 2, 2015  November 20, 2015
Budget
Estimate cost at completion will be about $5.75million. ($1.5 million under
budget.) 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of COs          $0            $0
Risks
Timely delivery of PLB's to job site. Working close with Vendorto track PLB
fabrication and delivery.
Budget Transfers
Amount       From         To
$0

AIRPORT 
Port of Seattle 4Q 2015 Report  49

FOURTHQUARTER REPORT, 2015 
Domestic Water Piping 
Project: C800657            Replace domestic water piping      Project Status:
Budget: $1,950,000          branches and manifolds including      Schedule: Delayed
Phase: Design             valves.                     Budget: On or Under
Start: 11/4/2012                                         Status Reset: 5/13/2014
Schedule Completion: 4/30/2016                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Project was successfullybid. Notice to proceed(NTP)is expected in Q1 2016.
$3
2.0
Schedule                                       $2
1.5
$2
Substantial completion scheduled for June 7, 2016.Contractor is late with pre-
NTP submittals. NTP was expected in early January, 45 days after execution of   Dollars in Millions $1                                                        contract. NTP is now anticipated in mid-February, whichputs construction       $1
0.1
completion at risk.
$0
Authorized Forecasted   Costs
Incurred
Budget
Project is within budget.
Construction Costs
Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Schedule as noted above.
Budget Transfers
Amount       From         To
$0



AIRPORT
50  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Mech Energy Conservation (CA) 
Project: C800658            Stage 3 Mechanical Energy         Project Status:
Budget: $3,500,000           Conservation to improve the efficiency   Schedule: Within or Ahead
Phase: Audit/Notebook        of portions of the mechanical         Budget: On or Under
Start: 8/25/2014              infrastructure system at the Airport.      Status Reset: N/A
Schedule Completion: 12/31/2016                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Completed evaluation of total project costand project options and financials.
4           3.5
Presented four options to Investment Committee on November 6th..Project is
still under review by Finance and Budget.                             3
Dollars in Millions 2                                                                             Schedule
Schedule delay will be affected by length of time required to complete Finance     1
0.3               0.2
and Budget review, and possible second MII votedue to increased budget.
0
Authorized Forecasted   Costs
Budget                                                Incurred
Schedule future Commissionauthorization for additional funds after
completion of Aviation division approvalswith an updated construction       Construction Costs
schedule.Facilities and Infrastructure is recommending an increase in budget to  Not Applicable 
$5,019,000.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Project is complex due to diversity in scope of work and location of nine
separate energy conservation measures.Project financials are complicated as
they are impacted by assumptions in airport growth and future costs of energy.
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 4Q 2015 Report  51

FOURTHQUARTER REPORT, 2015 
S4 & S6 International Corridor Connection 
Project: C800662            Installation of a fixed bridge and      Project Status:
Budget: 5,092,000            corridor extension to connect gates S6    Schedule: Delayed
Phase: Construction          and S4 to the International Corridor     Budget: On or Under
Start: 11/4/2012                                           Status Reset: 2/25/2014
Schedule Completion: 10/22/2015                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Beneficial Occupancy of major work achieved. Corridor functioning with       6   5.1    5.0
additional widebody gate availability.PC Air unit delivered.This will be the      5
4.0
final report.
Schedule
Major work completed in October 2015. InstallingPC Air unit in January to     Dollars in Millions 4321
complete full functionality.                                        0
Authorized Forecasted   Costs
Incurred
Budget
On budget.                                           Construction Costs
Change Order                                  2        1.8
1.7
Current Quarter     Project Total         1.5
Number of COs           3             15
Amount of COs         $58,038         $122,538           1
Justification for COs: Designer and Owner error/omissions and varyingsite         Dollars in Millions 0.5
0.1
conditions. Scope change to retain S5 gate.
0
Initial Change Spent
Risks                                                Orders
Project is in close-out.
Budget Transfers
Amount       From         To
$0



AIRPORT 
52  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Automated Passport Control 
Project: C800667             Install additional Automated Passport  Project Status:
Budget: $2,197,900          Control (APC) kiosks in the existing   Schedule: Within or Ahead
Phase: Construction          FIS at the South Satellite.         Budget: On or Under
Start: 10/31/2013                                       Status Reset: N/A
Schedule Completion: 6/1/2015                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Project is complete and in use. This will be the final report. 
2
2.2
Schedule                                       2       2.1
Project is complete.                                            Dollars in Millions 22                2.0
Budget
2
Project remains within current budget.                               2
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable 
Amount of Cos           $0             $0
Justification for COs: N/A                                   Photo
Risks
None
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 4Q 2015 Report  53

FOURTHQUARTER REPORT, 2015 
Construction Logistics Expansion 
Project: C800688             The expansion and reconfiguration of   Project Status:
Budget: $7,800,000          the existing construction logistics      Schedule: Within or Ahead
Phase: Design              facilities (including contractor parking)   Budget: On or Under
Start: 8/1/2014                and the renovation of Port field offices.   Status Reset: 7/14/2015
Schedule Completion: 10/31/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Completed construction of the Contractor Parking Lot,and Logistics Lots1and   12.0
2.Received a lowbid for the remainingConstruction Logistics facilities,                  9.6
10.0
resulting in savings.Completed 90% design for the renovation of the Field       8.0   6.9
Offices.A new airport security directive,requiringfull inspection of            6.0
construction workers,willincrease theproject scope and costthatis currently
being defined,to support the ramp up of construction workers anticipated in Q4   Dollars in Millions 4.0              1.6
2.0
2016.Commission authorization is planned for the new scopeinQ1 2016.       0.0
AuthorizedForecasted  Costs
Incurred
Schedule
The project is currently on schedule with completion datesof Q3 2016 for
Construction Costs
Construction Logistics and Q4 2016 for Field Office Renovation.
1
Budget                                         0.8
0.8
Field Office Renovationisforecast to exceed budgetgiven the risks belowbut
0.6                     0.5
savings from the Construction Logistics low bid will cover the increase.
0.4
Authorization for construction of the Field Offices and new security inspection
improvements is planned for Q1 2016.                             Dollars in Millions 0.2        0.0
0
Change Order                                    Initial  Change  Spent
Orders
Current Quarter     Project Total
Number of COs           0             0
Photo
Amount of COs          $0            $0
Justification for COs: None issued this quarter.
Risks
x Construction Logistics: Completionofthe work to support Capital Program
including the new security inspection improvements.
x Field Offices: additional scope due to unknown building conditionsand
additional regulatory requirements.
Budget Transfers
Amount       From         To
$0
AIRPORT
54  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
2016 Fuel System Modifications 
Project: C800692              Airline activity growth at the     Project Status:
Budget: $4,680,000             Airport is requiring the installation   Schedule: Delayed
Phase: Design              of a new fuel pits in 2016.       Budget:On or Under
Start: 11/6/2013                                       Status Reset: 11/11/2014
Schedule Completion: 11/30/2016                           (Commission Design Auth.)
Significant Developments                             Budget/Costs Incurred
Scope has increased by five additional new fuel pits to accommodate the new
5    4.7      4.7
narrow body gate configurations at the South Satellite, bringingthe total to nine
new fuel pits.                                                  4
3
Schedule                                       2
Project is scheduled to advertise for construction inQ12016.Anticipate
1
beginning construction in Q3 2016.                               Dollars in Millions                0.1
0
Authorized Forecasted   Costs
Budget                                                Incurred
Commission Authorization to increase authorizationand scopewas approved
onNovember 10, 2015.                                   Construction Costs
None at this time 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: None at this time
Risks
Not Applicable
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 4Q 2015 Report  55

FOURTHQUARTER REPORT, 2015 
Electric Utility SCADA 
Project: C800699              InstallaSupervisory Control and   Project Status:
Budget: $9,650,000             Data Acquisition (SCADA) system   Schedule: Within or Ahead
Phase: Design              for the Airport's 12.47 kV Medium  Budget:On or Under
Start: 8/5/2015                Voltage (MV) power distribution    Status Reset: 8/4/2015
Schedule Completion: 10/25/2017   network.                   (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Engineerwas selected;rates and scopewerenegotiated.                  12
9.7
10
Schedule
8
Project is on schedule.                                           6
4
Budget                                     Dollars in Millions    1.6
2
0.0
Project is within budget.                                           0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs:None at this point.
Risks
Controls are being added to an existing electricalsystem that includes several
manufacturers' equipment resulting in potential coordination challenges.
Unplanned shutdowns may also occur, but is being mitigated through site
investigations.
Budget Transfers
Amount       From         To
$0



AIRPORT
56  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
2015-2016 Concourse CRoof Replacement 
Project: C800702            Remove and replace the existing roof  Project Status:
Budget: $5,596,000           system(approximately83,000 square   Schedule: Within or Ahead
Phase: Design             feet)on Concourse C; install a new    Budget:On or Under
Start: 5/26/2010              elastomeric roofing system; ladders    Status Reset: N/A
Schedule Completion: 11/30/2016 and fall protection; and replace and     (Commission Construction Auth.)
refurbish the existing skylight
window/walls.
Significant Developments                             Budget/Costs Incurred
Ninety percentdesign completed.
6           5.60
5
Schedule
4
Project is on schedule
Budget                                     Dollars in Millions 32  0.87
1                  0.64
Project is within budget.                                           0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          None at this time
Amount of Cos           $0             $0
Risks
If the project fails to make up time,the bids could be delayed running the risk
of higherthan planned bids.
Budget Transfers
Amount       From         To
$0




AIRPORT
Port of Seattle 4Q 2015 Report  57

FOURTHQUARTER REPORT, 2015 
South Satellite Steam Piping Utility Upgrade 
Project: C800708            Replace expansion joints in the SSAT  Project Status:
Budget: $1,000,000          steam piping supply system.         Schedule: Within or Ahead
Phase: Design                                      Budget: On or Under
Start: 11/1/2015                                         Status Reset: n/a
Schedule Completion: 12/31/2016                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Commission approved funding for design and construction on December 8,
$1
1.0       1.0
2015.
$1
Schedule
Design is schedule to begin in January 2016.                          Dollars in Millions $1$1$0$0               0.0
Budget                                     $0
Authorized Forecasted   Costs
Incurred
Project is within budget.
Change Order                               Construction Costs
Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Schedule as noted above.
Budget Transfers
Amount       From         To
$0




AIRPORT
58  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Central Terminal Stairs 
Project: C800716              This project will build two       Project Status:
Budget: $2,217,000             stairways near the central         Schedule: Within or Ahead
Phase: Design              checkpoint to provide egress      Budget:On or Under
Start: 2/15/2015               capacity from the mezzanine level   Status Reset: n/a
Schedule Completion: 5/21/2017    to the ticketing level on the non-    (Commission Construction Auth.)
secure side of the airport.
Significant Developments                             Budget/Costs Incurred
Service directive for designexecuted.
3
Upcoming activities:                                                   2.6
2.5
x Design concept review
2
x 30% Design Review                             Dollars in Millions 1.51  0.5
Schedule
0.5                     0.0
The project is on schedule.                                    0
AuthorizedForecasted  Costs
Incurred
Budget
Project is within the budget.                                       Construction Costs
Change Order                               None at this time
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Risks
No significant risks at this time.
Budget Transfers
Amount       From         To
$0



AIRPORT

Port of Seattle 4Q 2015 Report  59

)2857+ 48$57(5 5(3257 
7HUPLQDO 8WLOLWLHV 8SJUDGH 3URMHFW 
3URMHFW &               5HSODFH DQG H[WHQG WKH VWHDP      3URMHFW 6WDWXV 
%XGJHW $             FRQGHQVDWH DQG FKLOOHG ZDWHU        6FKHGXOH :LWKLQ RU $KHDG 
3KDVH 'HVLJQ                  VXSSO\ DQG UHWXUQ SLSLQJ IURP WKH     %XGJHW 2Q RU 8QGHU 
6WDUW                 &HQWUDO 0HFKDQLFDO 3ODQW WR WKH HQG 6WDWXV 5HVHW 1 $ 
6FKHGXOH &RPSOHWLRQ    RI PHFKDQLFDO URRP IRXU DQG WR WKH (Commission Construction Auth.) 
HQGV RI WKH 6RXWK DQG :HVW /RRSV. 
6LJQLILFDQW 'HYHORSPHQWV                              %XGJHW &RVWV ,QFXUUHG 
&RQGXFWHG SURMHFW GHVLJQ NLFNRII DQG SURMHFW FRRUGLQDWLRQ PHHWLQJV 
&RQGXFWHG SURMHFW GHVLJQ VLWH ZDONV 
6FKHGXOH                                         'ROODUV LQ 0LOOLRQV                                                3URMHFW LV RQ VFKHGXOH 

%XGJHW 
3URMHFW LV ZLWKLQ EXGJHW                                             $XWKRUL]HG )RUHFDVWHG  &RVWV
,QFXUUHG
&KDQJH 2UGHU 
&RQVWUXFWLRQ &RVWV 
&XUUHQW 4XDUWHU      3URMHFW 7RWDO 
1RW $SSOLFDEOH 
1XPEHU RI &2V 
$PRXQW RI &RV 
5LVNV 
5LVN WR VFKHGXOH DQG EXGJHW URXWLQJ ODUJH VHFWLRQV RI SLSH WKURXJK D YHU\ 
GHQVHO\ GHYHORSHG SDUW RI WKH DLUSRUW 5LVNV WR EH PLQLPL]HG GXULQJ GHVLJQ 
%XGJHW 7UDQVIHUV 
$PRXQW         )URP          7R 




$,53257 
60  Port of Seattle 4Q 2015 Report

)2857+ 48$57(5 5(3257 
&7( +9$& 8SJUDGH 
3URMHFW &               ,QVWDOO WZR QHZ DLU KDQGOLQJ XQLWV   3URMHFW 6WDWXV 
%XGJHW               $+8V RQ WKH URRI DERYH WKH 1     6FKHGXOH :LWKLQ RU $KHDG 
3KDVH 'HVLJQ                  DQG 6 PH]]DQLQH OHYHOV RI WKH       %XGJHW 2Q RU 8QGHU 
6WDUW                  FHQWUDO WHUPLQDO WR SURYLGH KHDWLQJ 6WDWXV 5HVHW Q D 
6FKHGXOH &RPSOHWLRQ YHQWLODWLRQ DQG DLU FRQGLWLRQLQJ      (Commission Construction Auth.) 
LQIUDVWUXFWXUH V\VWHPV 
6LJQLILFDQW 'HYHORSPHQWV                              %XGJHW &RVWV ,QFXUUHG 
)LIWHHQ SHUFHQW GHVLJQ VXEPLWWDO UHFHLYHG 
6FKHGXOH 
3URMHFW LV RQ VFKHGXOH                                           'ROODUV LQ 0LOOLRQV 
%XGJHW 
3URMHFW LV ZLWKLQ EXGJHW 
$XWKRUL]HG )RUHFDVWHG   &RVWV
,QFXUUHG
&KDQJH 2UGHU 
&XUUHQW 4XDUWHU      3URMHFW 7RWDO        &RQVWUXFWLRQ &RVWV 
1XPEHU RI &2V                                     1RW $SSOLFDEOH 
$PRXQW RI &RV 
-XVWLILFDWLRQ IRU &2V 1RQH DW WKLV WLPH 
5LVNV 
5LVN WR SURMHFW EXGJHW LI VLJQLILFDQW VWUXFWXUDO XSJUDGHV WR WKH SHQWKRXVH URRILQJ 
V\VWHPV DUH UHTXLUHG 5LVN WR EH PLWLJDWHG GXULQJ GHVLJQ SURFHVV 
%XGJHW 7UDQVIHUV 
$PRXQW         )URP          7R 





$,53257 
Port of Seattle 4Q 2015 Report  61

FOURTHQUARTER REPORT, 2015 
Concourse C New Power Center 
Project: C800724              Addnew5000Adoubleendedunit  Project Status:
Budget: $10,500,000             substation(powercenter)on Ramp   Schedule: Within or Ahead
Phase: Design               levelatcolumnlineF/40foranew   Budget:On or Under
Start: 10/26/2014              electricalroominConcourseC.     Status Reset: n/a
Schedule Completion: 12/31/2017    Theexistingdistributionpanelswill  (Commission Construction Auth.)
bere-fedfromthenewpower
centerandnewdistributionpanels
andbranchcircuitpanelswillbe
added. 
Significant Developments                             Budget/Costs Incurred
Working with CPO and Consultant to developService Directive scope of work,
12           10.5
level effort.Staff is currently reviewing Consultant submittals.
10
Schedule
Probable completion of 100% design bid documents 3rd Qtr.2016.
Probable construction completion date 4th Qtr.2017.                     Dollars in Millions 864   2.0
2
0.1
0
Authorized Forecasted   Costs
Budget
Incurred
The project cost forecastis within the September 22, 2015Commission
approved budget.                                        Construction Costs
Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
x Airline Gate Realignment programmay affect Concourse Cprojects.
x Budget or schedule maybeaffectedif site conditions differ from record
files.
x Contractor purchasedequipment may not fit in Concourse C allocated space
for this new power center room.

Budget Transfers
Amount       From         To
$0
AIRPORT
62  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Interim Baggage System Program 
Project: C800825            Implement program of individual      Project Status:
Budget: $14,200,000          projects with the objective of increasing   Schedule: Within or Ahead
Phase: Construction          reliability and capacity through the      Budget: On or Under
Start: 12/13/2015             interim period between the upcoming    Status Reset: N/A
Schedule Completion: 10/1/2017  summer and Baggage Optimization     (Commission Construction Auth.)
Project.
Significant Developments                             Budget/Costs Incurred
Status 1, 2, and Notebook were approved on December3rd. The project            14.2    14.2
15
received Commission approval on December 8 for design and partial
construction funds. The project was presented at ACCC on December 16th.
Three service directives were issued to being design. Long lead conveyor
equipment order was placed to meet fast track schedule.                   Dollars in Millions 105
Schedule                                                   0.0
0
All four elements of this project are considered hot and on a fast track schedule.      Authorized Forecasted  Costs
Incurred
The project is on schedule.
Budget                                    Construction Costs
The project forecast is within the approved budget and authorization.         Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Any project on the fast track schedule has potential risks of not meeting
schedule. The team is working together to utilize all resource avenues to get
this completed on time.
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 4Q 2015 Report  63

FOURTHQUARTER REPORT, 2015 
RM Abatement for Tenant Projects 
Project: U00234U00237        Provideregulated materials      Project Status:
Budget: $1,800,000             abatement support as neededin four  Schedule: Within or Ahead
Phase: Construction           locations in the Main Terminal that  Budget:On or Under
Start: 12/1/2015               willbe leased by airline tenants.    Status Reset: 8/4/2015
Schedule Completion: 9/30/2016                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The abatement work under this project has been separated into four Work
2    1.8      1.8
Projects as follows:
U00234 Former US Airways Ticketing and ATO Ticketing Level Zone 3    1.5
U00235 Former Airline Technical RepresentativeOffices North Mezzanine                  0.8
U00236 Former Alaska Airlines Lounge SpaceConcourse D
U00237 Vacant ATO Space Ticketing Level Zone 7                Dollars in Millions 1 0.5
0
Schedule                                        Authorized Forecasted  Costs
Each Work Project has its own schedule that is dependent upon the                          Incurred
requirements of theleasing airline:
U00234 4th Quarter 2015 1st Quarter 2016                      Construction Costs
U00235 4th Quarter 2015
0.5
U00236 4th Quarter 2015 2nd Quarter 2016                           0.4
0.4
U00237 2nd Quarter 2016
Each of theprojects currently under way or in progress ison schedule.         Dollars in Millions 0.30.2                                                          Budget
0.1
0.0    0.0
The abatement work for U00235 was found to be much less extensive than
0
originally expected and was completed by PCSunder their Regulated Materials       Initial Change Spent
Orders
Operations & Maintenance budget. This represents an approximately $40K
savings from the original $65K budget. The remaining projects are on budget
or haven't been started as of this reporting date.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Risks
None at this time.
Budget Transfers
Amount       From         To
$0
AIRPORT
64  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
North East Redevelopment Area Program 
Project: U000239              This is an FAA fundedprojectwith Project Status:
Budget: $5,000,000             participation from the City of      Schedule: Within or Ahead
Phase: Design              Burien but ledby Port (500K each).  Budget:On or Under
Start: 8/16/2015               The project is to redevelop the Area  Status Reset: 10/14/2014
Schedule Completion: 5/12/2019    north of the airport in the City of    (Commission Construction Auth.)
Burien.
Significant Developments                             Budget/Costs Incurred
Professional Service Agreement executedinAugust 2015.
6
Service Directive 1executed September 2015.                            5.0    5.0
5
Project Management Plan (PMP) completed.
Schedule                                      Dollars in Millions 432                                             The project schedule completedand project is currently on schedule.         1
0.0
0
Budget                                       Authorized Forecasted  Costs
Incurred
Commissionauthorizationreceivedon October 14, 2014. 
Construction Costs
Change Order
None at this time
Current Quarter     Project Total
Number of COs           0             0          Photo
Amount of Cos           $0             $0
Risks
None
Budget Transfers
Amount       From         To
$0




AIRPORT
Port of Seattle 4Q 2015 Report  65

FOURTHQUARTER REPORT, 2015 
Highline Schools Noise Insulation 
Project: C200007             Highline School Insulation Agreement Project Status:
Budget: $101,797,000           will provide funding for sound       Schedule: Delayed
Phase: Construction            insulation for 15 schools that are      Budget: On or Under
Start: 3/23/1999                impacted by aircraft noise from Sea-    Status Reset: N/A
Schedule Completion: 11/30/2021   Tac Airport                  (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Port funds authorized for availability when the FAA, the State of Washington,
120
and the Highline School District (HSD) provide matching funds. HSD has been       102.1   101.8
100
unable to pass a school bond vote. Project has an unknown timeframe until a
80                  63.4
bondpasses.
60
40
Schedule                                      Dollars in Millions 20
The schedule for state funds is unknown. The district's schedule is dependent on     0
obtaining general election bonds at various intervals. The district's construction       AuthorizedForecasted  Costs
Incurred
schedule at this point is unknown.
Budget                                    Construction Costs
Not Applicable 
The project forecast is within the approved budget and authorization.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Project delayed due to funding issues with HSD. There is a risk if there are no
bonds passed in the general election, and if FAA Airport Improvement Program
(AIP) Grant funding is not available.
Budget Transfers
Amount       From         To
$0


AIRPORT 
66  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
HomeInsulationRetrofit 
Project: C200048             Storm window retrofit of previously   Project Status:
Budget: $4,060,147            insulated homes.                Schedule: Within or Ahead
Phase: Construction                                     Budget: On or Under
Start: 1/11/2005                                            Status Reset: N/A
Schedule Completion: 12/31/2016                            (Commission Construction Auth.)
Budget/Costs Incurred
Significant Developments
All known eligible homes have been identified and owners have been notified     6   5.3
by certified mail. At this point, no further applications were received for this      5
4.1
project.                                                       4                3.4
3
Schedule                                       2
The project is on hold until new eligible applications are received.            Dollars in Millions 1
0
Authorized Forecasted   Costs
Budget                                                Incurred
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                               Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The ability to accomplish the retrofit is dependent on homeowner's voluntary
participation.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 4Q 2015 Report  67

FOURTHQUARTER REPORT, 2015 
Single Family Home Sound Insulation 
Project: C200093            Sound insulate remaining homes that are Project Status:
Budget: $13,747,395          within the 1998 65 decibel day night     Schedule: Within or Ahead
Phase: Construction          level (DNL) noise contour.           Budget: On or Under
Start: 3/27/2007                                           Status Reset: N/A
Schedule Completion: 6/30/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The final twohomes are in the process of receiving sound insulation.
15    13.7     13.7
Schedule
10
Project is on schedule. Anticipate completion by 2nd quarter 2016.
5.4
5
Budget                                     Dollars in Millions
The project forecast is within approved budget and authorization to complete all    0
homes currently in progress.                                        Authorized Forecasted  Costs
Incurred
Change Order
Construction Costs
Current Quarter     Project Total
Number of COs           0             0                3.8
4
Amount of Cos           $0             $0
3
Justification for COs: N/A
2             1.8
Risks
1
The ability to accomplish the insulation is dependent on the homeowner's       Dollars in Millions         0.0
schedules, willingness to sign an aviation easement, obtain a subordination        0
Initial Change Spent
agreement from their lender, and structural integrity of the home.                     Orders
Budget Transfers
Amount       From         To
$0



AIRPORT 
68  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Tenant Reimbursement 
Project: C800154             Build-out of spaces for new and     Project Status:
Budget: $4,709,577            existing tenants. If more than a "basic   Schedule: Within or Ahead
Phase: Construction            finish", condition space is built for the   Budget: On or Under
Start: 8/14/2007                tenant. Tenant is required to reimburse  Status Reset: N/A
Schedule Completion: TBD      the Port for the cost of the work      (Commission Construction Auth.)
beyond the "basic finish. Reimb
allowed under the guidelines in the
"Tenant Reimb.Policy:
Significant Developments                             Budget/Costs Incurred
In 2016, anticipate reimbursement forsome reimbursable work that tenants
5    4.7      4.7
have done on their project buildouts (Delta, Alaska, and American),whereby
4
the Port's Fire Department has required the tenant to upgrade the fire sprinkler
system in areas they are building out, as well as additional code upgrades.       Dollars in Millions 32                1.3
Schedule
1
Schedules vary to meet the tenant's needs.                             0
Authorized Forecasted   Costs
Incurred
Budget
The project forecast is within the approved budgetand authorization.
Construction Costs
Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 4Q 2015 Report  69

FOURTHQUARTER REPORT, 2015 
T-46 Lease Improvements Stormwater Improvements 
Project: U00050 (C102554)        Construct stormwater treatment    Project Status:
Budget: $8,000,000            system to comply with Ecology     Schedule: Within or Ahead
Phase: Construction            order.                    Budget: On or Under
Start: 4/12/2013                                          Status Reset: 5/7/2015
Schedule Completion: 2020                               (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
With theContainer Dock Apron Upgrade placed on hold, the stormwater
10
project will be packagedas aseparate construction package. Senior Executive        8.00    8.00
8
team approved the inclusion of replacement/rehabilitation of the outfall pipes.
5.51
6
Schedule                                       4
Washington State Department of Transportation (WSDOT) is to extend the      Dollars in Millions 2
lease to December 31, 2016with an option to further extend an additional six      0
months. The construction is currently scheduleto start on January 2017.           Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
Authorized budget for Stormwater Treatment Systemis currently within
budget.                                                      2.5
1.9
2             1.8
Change Order
1.5
Current Quarter     Project Total
1
Number of COs           0             8
0.5          0.3
Amount of Cos           $0           $259,264          Dollars in Millions
Justification for COs:None this quarter                               0
Initial Change Spent
Orders
Risks
Delay of completing the treatment vaultscommission due to terminal operation.
Vaults may not provide level of treatment required by Ecology.
Budget Transfers
Amount       From         To
$0


SEAPORT ALLIANCE 
70  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
T-46 Lease Improvements Container Dock Apron Upgrade 
Project: U00175(C102554)        Upgrade 200 LF at existing T-46   Project Status:
Budget: $10,195,000            dock apron to increase load       Schedule: Within or Ahead
Phase: Design                capacity to accommodate 100-foot   Budget: On or Under
Start: 4/12/2013                 gauge cranes. Upgrade electrical     Status Reset: 5/7/2015
Schedule Completion: TBD       power to support new cranes if     (Commission Construction Auth.)
requested by tenant.
Significant Developments                             Budget/Costs Incurred
Completed 60% design review. Master Use Permit (MUP)has been submitted
12
toCity for review.SubmittedJARPA and Biological Evaluation to Corp of               10.19
10
Engineers forreview.Completed Building Permit set to submit for City
Building Permit reviewand a seismic technical memo to supplement Code
Alternate Request.Senior Executive instructed project team to suspend project
as of December 14, 2015. Proceed to complete permitting process.           Dollars in Millions 864   2.50
2                  0.95
0
Schedule                                        Authorized Forecasted  Costs
Incurred
Schedule has not been set yet.
Budget                                    Construction Costs
Currently project is within budget.                                  None at this time
Change Order                               Photo
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs:N/A
Risks
Permit review timeline uncertain. Meet federal funding procurement
requirements. Contractor's ability to procure long lead items on schedule.
Meet tenant requests due to change in operation.TIGER grant no longer
available due to timing of project.
Budget Transfers
Amount       From         To
$0


SEAPORT ALLIANCE 
Port of Seattle 4Q 2015 Report  71

)2857+ 48$57(5 5(3257 
6WUHHW 9DFDWLRQV 7 7 DQG 7 
3URMHFW & & ( 6WUHHW YDFDWLRQ UHODWHG UHDO HVWDWH    3URMHFW 6WDWXV 
%XGJHW              QHJRWLDWLRQV DQG DJUHHPHQWV  7 6FKHGXOH 'HOD\HG 
3KDVH 3HUPLWWLQJ               7 DQG 7 FRPSOHWH        %XGJHW 2Q RU 8QGHU 
6WDUW                                             6WDWXV 5HVHW 1 $ 
6FKHGXOH &RPSOHWLRQ                                (Commission Construction Auth.) 
%XGJHW &RVWV ,QFXUUHG 
6LJQLILFDQW 'HYHORSPHQWV 
7KH &LW\ SUHSDUHG WKH 7 6WUHHW 9DFDWLRQV (DVHPHQWV DQG 8WLOLW\ WUDQVIHU 
GRFXPHQWV 3RUW /HJDO UHYLHZ FRPSOHWHG 7 0DVWHU (DVHPHQW EHLQJ 
ILQDOL]HG $Q DVVHW WUDQVIHU DJUHHPHQW IRU VWRUP ZDWHU GUDLQV LV EHLQJ ILQDOL]HG 
DV SDUW RI WKH PDVWHU HDVHPHQW 3RUW DQG 1:6$ VWDII PHW ZLWK &HQWXU\ /LQN 
VWDII WR GLVFXVV WKUHH DOWHUQDWLYH SODQV                                 'ROODUV LQ 0LOOLRQV                                                                  0RYH SLSH ZLWK UHTXLUHG FKDQJH LQ HDVHPHQW 
0RYH KXW RU UHFRQILJXUH DQG                                      $XWKRUL]HG)RUHFDVWHG  &RVWV
&UHDWH DOWHUQDWLYH HDVHPHQW WR EH H[HUFLVHG LQ WKH HYHQW RI D VLJQLILFDQW                        ,QFXUUHG
HYHQW VR WKDW D IXWXUH SLSOLQH UXQ FDQ EH LQVWDOOHG WR HOLPLQDWH WKH 
HQFURDFKPHQW                                          &RQVWUXFWLRQ &RVWV 
1RQH DW WKLV WLPH 
&HQWXU\ /LQN VWDII DUH FRPSOHWLQJ GHVLJQ DQG FRVW HVWLPDWHV WR UHFRQILJXUH WKH 
KXW WR UHPRYH LW IURP WKH HQFURDFKPHQW &/ ZLOO FRRUGLQDWH ZLWK 638        3KRWRV 
HQJLQHHULQJ UHJDUGLQJ DQ\ DGGLWLRQDO FRQFHUQV WKDW 638 KDV VXFK DV WKH 
IRXQGDWLRQ SLOLQJV XQGHU WKH KXW 
'LVFXVVLRQ DQG 7LWOH ZRUN KDV VWDUWHG IRU 7HUPLQDO 
7 YDFDWLRQV FRPSOHWHG LQ . 
6FKHGXOH 
&XUUHQW VFKHGXOH KDV 7 FRPSOHWHG E\ HQG RI &LW\ &RXQFLO DFWLRQ E\ 
HQG RI -XQH DQG 7 E\ WKH HQG RI 'HOD\ FDXVHG E\ VKLIWLQJ RI 
ZRUN WR 1:6$ QHZ VWDII JHWWLQJ IDPLOLDU ZLWK WKH ZRUN DQG &LW\ &RXQFLO 
VFKHGXOH GHOD\V GXH WR HOHFWLRQV QHZ FRXQFLO IRUPDW GLVWULFW Y DW ODUJH DQG 
QHZ FRXQFLO PHPEHUV VWDII 
%XGJHW 
7KH EXGJHW UHYLVHG IRU DQG EH\RQG 
&KDQJH 2UGHU 
&XUUHQW 4XDUWHU      3URMHFW 7RWDO 
1XPEHU RI &2V 
$PRXQW RI &RV 
-XVWLILFDWLRQ IRU &2V 1RQH WKLV TXDUWHU 


72  Port of Seattle 4Q 2015 Report

5LVNV 
1RW DSSOLFDEOH 
%XGJHW 7UDQVIHUV 
$PRXQW         )URP          7R 













6($3257 $//,$1&( 
Port of Seattle 4Q 2015 Report  73

FOURTHQUARTER REPORT, 2015 
T-5 Berth Modernization 
Project: C800132              Improvements to support larger    Project Status:
Budget: $210,000,000-$260,000,000  vessels at T5, including crane rail   Schedule: Within or Ahead
Phase: Design                strengthening, berth deepening, and  Budget: On or Under
Start: 6/3/2014                  electrical upgrades.             Status Reset: 11/4/2015
Schedule Completion: 6/30/2019                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
EIS progress includes refinement of alternatives, data collection, and technical
15
analysis. Design suspended sinceOctoberto improve alignment with expanded       12.00   12.00
SEPA environmental reviewand tenant selection/negotiations.
10
5.55
Schedule
5
Test pile program started in Decemberwillcontinue through March/April.      Dollars in Millions
DEIS is expected in April. Expecting 95% Design by May and Building Permit    0
submittal mid-June.Project completion target is mid-2019.                  Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
Authorized budget is now$12,000,000, which is expected tocover 100% level
design, test pile program,and expanded environmental review process.        None at this time
Change Order                               Photos
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs:N/A
Risks
Alignment of tenant negotiations, EIS, design, and permits by end of 2016.
Budget Transfers
Amount       From         To
$0



SEAPORT ALLIANCE 
74  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
FT C15 HVAC Improvement 
Project: C800137              Replace existing HVAC systems    Project Status:
Budget: $4,887,000             within Building C-15 that are at the   Schedule: Delayed
Phase: Closeout             end of their service life.         Budget: On or Under
Start: 5/1/2010                                        Status Reset: 10/8/2013
ScheduledCompletion: 6/30/2014                          (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Construction Substantial Completionwasissued on October 19th.Claims,
5
change ordersand liquidated damagesnegotiation continues. Overall, the           4.9    4.9
4.9
project is expected to stay within budget at the end of project close-out. Staff     4.8
has also been coordinating with the Seattle City Light on energy rebate and      4.7
rebate amount of $49k is expected. This update would be the last report on the    Dollars in Millions 4.6               4.5
project.                                                      4.5
4.4
4.3
Schedule                                        Authorized Forecasted  Costs
Incurred
Substantial completion issued.
Budget                                    Construction Costs
Project is within the October 8, 2013 Commission funding authorizationand
3.5
though claims, change orders,and liquidated damages negotiation is still             3.0
3             2.6
ongoing, staff expects there are adequate budget to close out the project. 
Dollars in Millions 2.52                                                                               Change Order                                                              1.5
1
Current Quarter     Project Total
0.5          0.1
Number of COs           0             16             0
Amount of COs          $0           $61,040             Initial Change Spent
Orders
Justification for COs:None this quarter
Risks                                        Photo
Some significant cost items have been raised by the contractor but Port
disagrees with their merits. These are being negotiated along with Liquidated
Damages from contractor's delays that Port will assess. This negotiation
process is anticipated to be lengthy but should be resolved in 2016.
Budget Transfers
Amount       From         To
$0

MARITIME 
Port of Seattle 4Q 2015 Report  75

FOURTHQUARTER REPORT, 2015 
T-91 Lighting Upgrade 
Project: C800160              Lighting upgrade at Terminal 91   Project Status:
Budget: $1,160,000                                     Schedule: Delayed
Phase: Construction                                    Budget: On or Under
Start: 6/23/2014                                          Status Reset: 1/8/2016
Schedule Completion: 2/26/2016                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The installation of the lighting and controls is complete. Commissioning of the
1.18
controlsand training arescheduled to occur in February2016.                  1.16    1.16
1.16
Schedule                                      1.14
Expectto finish the project in March2016.                          1.12 Dollars in Millions                1.11
1.1
Budget                                     1.08
Authorized Forecasted   Costs
The budget was increased by $125,000; now totaling $1,160,000 total project                    Incurred
cost.The project is expected to complete within the revised project budget. 
Construction Costs
Change Order
Not Applicable
Current Quarter     Project Total
Number of COs           4             2          Photos
Amount of Cos          $18,155         ($24,845)
Justification for COs:Add additional fixtures to meet the goals ofthis project.
Risks
None
Budget Transfers
Amount       From         To
$0




MARITIME 
76  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
T-102 HMCC Roofsand HVACUnits
Replacement 
Project: C800196              Replace Corporate Center building  Project Status:
Budget: $6,350,000          roofs,final group (3rd phase)of    Schedule: Within or Ahead
Phase: Design              rooftop HVAC units, and all      Budget: On or Under
Start: 9/1/2014                 rooftop gas piping.Assets areat the  Status Reset: N/A
ScheduledCompletion: 10/31/2016  end of theirservice lives.        (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Finaldesign completed.
8
6.4
Schedule                                       6
Project on schedule for bid advertisement in January and construction in 2016.
Budget                                     Dollars in Millions 42  0.5        0.3
Project currently within design budget.                                0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not applicable at this time
Amount of COs          $0            $0
Justification for COs:None at this time
Risks
Nothing significant at this time.
Budget Transfers
Amount       From         To
$0




ECON. DEVELOPMENT 
Port of Seattle 4Q 2015 Report  77

FOURTHQUARTER REPORT, 2015 
Shilshole Tenant Service Buildings 
Project: C800356              Replacement/rehabilitationof five  Project Status:
Budget: $5,500,000to $6,500,000    restroomsand laundry facilities at   Schedule: Within or Ahead
Phase: Design                Shilshole Bay Marina by June 2017  Budget: On or Under
Start: 1/6/2015                  for $5.5M.                   Status Reset: N/A
Schedule Completion: 6/30/2017                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Consultant selected, designisunderway.Public outreach for tenant feedback
2
and prioritieswith moorage and business tenants continues.                          1.61
1.5
Schedule                                      Dollars in Millions 1  0.71
Design completion target of September2016.Schedule to complete all work
for boating season in 2017 is tight.                                   0.5
0.13
0
Budget                                       Authorized Forecasted  Costs
Incurred
Project is within theapprovedbudget. 
Change Order                               Construction Costs
None at this time
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs:N/A
Risks
No significant known risks at this time
Budget Transfers
Amount       From         To
$0




MARITIME 
78  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
T-91 Substation Upgrades 
Project: C800439              Upgrade/replace existing        Project Status:
Budget: $2,058,000             substations/equipment at Substation  Schedule: Within or Ahead
Phase: Design                Nos. 1, 14 and 15.             Budget: On or Under
Start: 11/4/2013                                          Status Reset: 3/10/2015
Schedule Completion: 4/30/2016                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
City of Seattle approved electrical permit submitted by the contractor.
2.5
Contractor mobilized to begin work in January 2016. Due to Department of         1.995   1.995
Energy's new requirements, contractor informed the Port that two electrical       2
transformers delivery would be delayed. This nation-wide problem has also      1.5
impacted other transformer manufactures. Contractor has proposed a work      Dollars in Millions 1              0.545
around to address the transformer issue.Port is evaluating their proposal.
0.5
0
Schedule                                        Authorized Forecasted  Costs
Incurred
On Schedule
Budget                                    Construction Costs
Onbudget                                        Not Applicable
Change Order                               Photo
Current Quarter     Project Total
Number of COs           2             2
Amount of Cos           $0             $0
Justification for COs:No cost change orders.
Risks
Department of Energy's new requirements caught major transformer equipment
manufacturers off guard and transformer manufacturing delays will impact the
project and would have cost ramifications, including additional staff labor costs
and assessment of liquidated damages. Project team is working with the
contractor on a contingency plan.
Budget Transfers
Amount       From         To
$0

MARITIME 

Port of Seattle 4Q 2015 Report  79

FOURTHQUARTER REPORT, 2015 
Argo Yard Truck Roadway 
Project: C800546,E104751,       New Port of Seattle owned truck   Project Status:
E104754                   roadway between East Marginal    Schedule: Within or Ahead
Budget: $7,750,000             Way and Colorado Avenue South    Budget: On or Under
Phase: Construction            right-of-way.                Status Reset: 4/22/2014
Start: 3/11/2012                                          (Commission Construction Auth.)
Schedule Completion: 4/15/2015
Significant Developments                             Budget/Costs Incurred
Union Pacific (UP) railroad crossing improvements (POS sharing costs) still to
10
be completed; awaiting finalization of construction agreements and scheduling        7.75    7.75
8
of UP crew. UP Element III Argo Yard improvements (POS administering                     6.10
FMSIB funds) construction start awaiting finalization of FMSIB funding       Dollars in Millions 6
agreements with POS and WSDOT.                            4
2
Schedule
0
UP railroad crossing improvementsanticipated to be completed Q2 2016.UP      Authorized Forecasted  Costs
Incurred
Element III Argo Yard improvements anticipated to be completed in 2017or
2018.
Construction Costs
Budget
6
5.05
Project is currently within the budget authorized by Commission on April 22,       5          4.50
2014.                                               Dollars in Millions  4
3
Change Order                                  2
Current Quarter     Project Total          1     0.41
Number of COs           14            34             0
Initial Change Spent
Amount of COs         $156,932         $408,681                Orders
Justification for COs:Construction requirements not addressed by design
documents.
Risks
No significant known risks at this time.
Budget Transfers
Amount       From         To
$0

MARITIME 
80  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
T-46 Dock Rehabilitation 
Project: C800603              Terminal 46 Dock Rehabilitation   Project Status:
Budget: $32,659,000            Project.                  Schedule: Delayed
Phase: Design                                         Budget: On or Under
Start: 11/6/2012                                          Status Reset: N/A
Schedule Completion: Q3 2020                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Completion of NEPA has been delayeddue to the negotiation of harbor wide
40
tribal agreement. It is currently projected to be completedat the end of Q1                 32.65
2016. It would require re-inspection of the dock,due tothelength of time since   30
the last inspection. The inspection will include the north 200' apron area.
Schedule                                      Dollars in Millions 2010  1.85        0.45
Design work is scheduled to resume Q22016.Construction is anticipated to
0
start in 2018.                                                      Authorized Forecasted  Costs
Incurred
Budget
The project is onbudget.                                      Construction Costs
None at this time
Change Order
Photo
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs:N/A
Risks
Container operation variation which can cause additional construction phasing.
Budget Transfers
Amount       From         To
$0



SEAPORT ALLIANCE 
Port of Seattle 4Q 2015 Report  81

FOURTHQUARTER REPORT, 2015 
HIM E Dock Improvements 
Project: C800678              Dock currently under consideration Project Status:
Budget: $500,000              for improvements ranging from     Schedule: Within or Ahead
Phase: Planning             partial elements (walers, rub strips,   Budget: On or Under
Start: 9/1/2014                cleats,etc.) replacement to        Status Reset: N/A
ScheduledCompletion: TBD      complete floats and pile         (Commission Construction Auth.)
replacements and electrical system
upgrade.
Significant Developments                             Budget/Costs Incurred
No development in 4th quarter toreport as project is currently on hold pending
0.5             0.47
TCO analysisbeing performed by Maritime Finance and Maritime
Management to subsequently decide on final project improvements scope and    0.4
schedule.                                                Dollars in Millions 0.30.2                                                        Schedule
0.1    0.07               0.06
Final schedule to be determined.
0
Authorized Forecasted   Costs
Budget                                                Incurred
Budget dependent on final scope decision. 
Construction Costs
Change Order                               None at this time
Current Quarter     Project Total
Number of COs           0             0
Amount of COs          $0            $0
Justification for COs:N/A
Risks
Nothing significant at this time.
Budget Transfers
Amount       From         To
$0



ECON. DEVELOPMENT 
82  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
P69 Carpet Replacement 
Project: C800691              Replace approximately 10,200 sq.  Project Status:
Budget: $1,200,000            yards of carpeting on the second    Schedule: Delayed
Phase: Construction            and third floors of the Port's       Budget: On or Under
Start: 7/7/2014                  Corporate Headquarters.          Status Reset: 1/8/2016
Schedule Completion: 9/30/2014                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The Contractor has successfully completed 100% of the contract scope. Due to    1.5
an ongoing labor determination, the project close-out has been postponed.The        1.20    1.20
primary concern is inregards toappropriate labor rates and application of small    1               0.77
business involvement. Final closing documents have been received.
0.5
Schedule                                      Dollars in Millions
The Port has submitted final documents to the State for review. Anticipated       0
Authorized Forecasted   Costs
closure of the project is May of 2016.
Incurred
Budget
Construction Costs
We do not anticipate any additional costs to be incurred other than internal     Not Applicable
processing soft costs. 
Change Order
Current Quarter     Project Total
Number of COs           0             3
Amount of Cos           $0           $4,700
Justification for COs:None this quarter
Risks
None at this time
Budget Transfers
Amount       From         To
$0



MARITIME 
Port of Seattle 4Q 2015 Report  83

FOURTHQUARTER REPORT, 2015 
P69 Beam Rehabilitation Project 
Project: C800698              Rehabilitate five rows of concrete   Project Status:
Budget: $3,024,000            roof beams supporting top of      Schedule: Within or Ahead
Phase: Design                clerestory windows at P69.        Budget: On or Under
Start: 7/1/2014                                            Status Reset: 10/27/2015
Schedule Completion: 11/23/2016                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Contract award to Western Ventures in progress. NTPestimate: April 1, 2016.
4
3.02
Schedule                                       3
2.09
Project had a 2-month bid period due to building permit delay, and holiday      Dollars in Millions 2                                                         periods in November / December. Timeline goal remains substantial
1
completion by November2016.                                            0.26
0
Budget                                       Authorized Forecasted  Costs
Incurred
Construction funding authorization approved by Commission October 27thfor
additional $2,694,000. Current approved total budgetis $3,024,000.Contractor  Construction Costs
bid at $896,200 is 49% below Engineers' Estimateof $1,765,250. Bid was
None at this time
validated by bidder. Bid assurance review meeting with Contractor held on
January 21, 2016. Bidder confirmed responsible. Current project estimate is
Photos
$2.091M, reduced from $3.024M. 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs:N/A
Risks
Contractor access during construction will restrict space and create visual
impacts on third floor and second floor atrium for estimated 7.5months.
Need to mitigate environmental impacts due to presence of lead paint / concrete
silica dust / asbestos insulation behind interior flashing.
Need to hire security guard. Contractor expects 4-10 night shifts for typical
work, and weekend (Saturday) for painting.
Budget Transfers
Amount       From         To
$0

MARITIME 
84  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Terminal 18 Rail Spur 
Project: C800721              Remove and replace rail spur that   Project Status:
Budget: $1,000,000            services Westway Feeds         Schedule: Within or Ahead
Phase: Design                                         Budget: On or Under
Start: 6/9/2015                                            Status Reset: 1/19/2016
Schedule Completion: 8/31/2016
Significant Developments                             Budget/Costs Incurred
The project documents are at the 100 percent level. Recent events include
2
receiving construction funding authorization from the Managing Members for a       1.60    1.60
total project funding amount of $1.6M.                              1.5
Schedule
The project is scheduledtoadvertise for constructionbids in February, award in   Dollars in Millions 10.5               0.14
April and substantial completion atthe end of August 2016.
0
Authorized Forecasted   Costs
Budget                                                Incurred
The project is within budget. 
Construction Costs
Change Order                               N/A
Current Quarter     Project Total
Photo
Number of COs           0             0
Amount of Co            $0             $0
Justification for COs:None at this time
Risks
Current risks includeconstruction phasing with coordination of the activities
with two tenants and working on and adjacent to a capped EPA Superfund site.
Budget Transfers
Amount       From         To
$0



SEAPORT ALLIANCE 
Port of Seattle 4Q 2015 Report  85

FOURTHQUARTER REPORT, 2015 
East Marginal Way Grade Separation 
Project: E102007              FAST Corridor funded project;    Project Status:
Budget: $56,256,171            FHWA, State, City with Port      Schedule: Within or Ahead
Phase: Closeout               commitment of $22,480,807. Scope  Budget: On or Under
Start: 5/1/2006                  is to construct grade separation in    Status Reset: 4/22/2014
Schedule Completion: 6/30/2016    vicinity of T5 and T18 to minimize   (Commission Construction Auth.)
truck traffic/rail conflicts.
Significant Developments                             Budget/Costs Incurred
Coordination continuedwith City of Seattle for properties and easements
56.5   56.25    56.25
conveyance to City. Proposed Lot Boundary Adjustment for POS properties
under final review by Seattle DPD. POS preparingproposed easement          56.0
documents for review by SDOT as well as Seattle City Light and Seattle Public
55.5                   55.30
Utilities.                                                          Dollars in Millions 55.0
Schedule
54.5
Anticipate final acceptance by Seattle Department of Transportation (SDOT) in       AuthorizedForecasted  Costs
Incurred
2016.
Budget                                    Construction Costs
Project is on track within the April 22, 2014Commission authorization.          25  22.0      22.0
20
Change Order
15
Current Quarter     Project Total
10
Number of COs           0             97
5        2.0
Amount of COs          $0          $1,922,967         Dollars in Millions
Justification for COs:None this quarter.                               0
Initial Change Spent
Orders
Risks
No risks at this time.
Budget Transfers
Amount       From         To
$380,000         102007       104866 & 104739



MARITIME 
86  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Viaduct Construction Coordination 
Project: E104324, E104535-38      Participate in the design &       Project Status:
Budget: $2,900,000            construction of the bored tunnel, N.  Schedule: Delayed
Phase: Implementation          & S. portals, Holgate to King St,    Budget: On or Under
Start: 1/1/2009                  Central Waterfront surface streets,   Status Reset: N/A
Schedule Completion: 12/31/2018   & related projects to ensure       (Commission Construction Auth.)
adequate connection to port
facilities.
Significant Developments                             Budget/Costs Incurred
Contractor completedrepairstothe SR 99 tunnel boring machine, resumed
4
mining, and then stopped due to barge incident and sinkhole development.
2.90
Seawall and Mercer corridor construction continued.                     3
Dollars in Millions 2            1.75
Schedule                                                   1.18
Tunneling project is delayed by 2 years due to machine failure. Mercer West      1
construction will continue through early 2016. Seawall Phase I construction to
0
be completed in mid-2016. Central Waterfront start/completion depends on        Authorized Forecasted  Costs
Incurred
completion of SR99 tunnel and Viaduct demolition.
Budget                                    Construction Costs
Port staff costs were within anticipated 2015 spending.                   Not Applicable
Change Order                               Photos
Current Quarter     Project Total       North Access to SR99 Tunnel
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs:N/A
Risks
Project delays due to repairs to the tunneling machine.
Budget Transfers
South Access to SR99 Tunnel
Amount       From         To
$0



MARITIME 
Port of Seattle 4Q 2015 Report  87

FOURTHQUARTER REPORT, 2015 
FT Net Shed Code Compliance 
Project: E104838              FT Net Sheds 3-11: Improvements  Project Status:
Budget: $2,950,000             required per City of Seattle building  Schedule: Delayed
Phase: Construction            & fire codes.                Budget: On or Under
Start: 5/1/2012                                            Status Reset: 6/25/2013
Schedule Completion: 6/30/2015                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Port Construction Services completed code compliancerelatedimprovements
4
to all net lockers at the Fishermen's Terminal in December 2015 and began
2.95
demobilizing. The close coordination between Port Construction Services,       3
Dollars in Millions               2.50      2.43
Fishermen's Terminal Operations staff, Maintenance, and Seaport Project
2
Management paid off with many happy net locker tenants despite significant
interruptions and impacts the project had on them.                        1
0
Schedule                                        Authorized Forecasted  Costs
Incurred
All work within the net lockers is complete.
Budget                                    Construction Costs
Projectbudgetis on trackandprojected to come in about $450,000below     Port Self Perform Construction
authorized budget. 
Photo
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs:N/A
Risks
None.
Budget Transfers
Amount       From         To
$0



MARITIME 
88  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
T-5 and T-91 Maintenance Dredging 
Project: E104840, E105038, U00067, Maintenance Dredge at T-5 all     Project Status:
E105050,                    three berths and at T-91 East cruise  Schedule: Delayed
Budget: $4,800,000             berth.                     Budget: On or Under
Phase: Design                                        Status Reset: N/A
Start: 8/14/2012                                          (Commission Construction Auth.)
Schedule Completion: 2/28/2016
Significant Developments                             Budget/Costs Incurred
T-5Maintenance Dredging was completed earlier in 2014.
6
T-91 East Cruise Berth: The Port recently received all permits for the preferred        4.80    4.80
5
under-water regrading alternative.Constructionisplanned for early February
Dollars in Millions 4                    3.53
2016.
3
2
Schedule
1
On schedule for completion in February 2016.                         0
Authorized Forecasted   Costs
Incurred
Budget
Project is onbudget 
Construction Costs
None at this time
Change Order
Current Quarter     Project Total       Photo
Number of COs           0             2
Amount of Cos           $0          $20,390.33
Justification for COs:None this quarter
Risks
Monitor construction for permit compliance.
Budget Transfers
Amount       From         To
$0



MARITIME 
Port of Seattle 4Q 2015 Report  89

FOURTHQUARTER REPORT, 2015 
T-18 Maintenance Dredging 
Project: U00033and U00231       Design,permitting, and        Project Status:
Budget: $3,216,000             construction ofT-18 Maintenance   Schedule: Within or Ahead
Phase: Construction           Dreddging; Advertise and execute   Budget:On or Under
Start: 2/10/2015               an on-call major construction      Status Reset: N/A
Schedule Completion: 2/28/2016    dredging contract             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Designand permitting work is complete.Construction is expected to begin in
4
early February and complete by the end of February.                         3.21    3.21
3
Schedule
2
Project is slightly behind schedule due to a delay in permitting, however, we
still plan to complete construction in February 2016, with a possible extension    Dollars in Millions 1               0.61
to the permit.                                                  0
Authorized Forecasted   Costs
Incurred
Budget
Project is on budget. 
Construction Costs
Change Order                               None at this time
Current Quarter     Project Total       Photo
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs:N/A
Risks
Coordinate with Terminal customers to minimize impact to operations.Monitor
construction for permit compliance.
Budget Transfers
Amount       From         To
$0



MARITIME 
90  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
IHI Crane Removal 
Project: U00099               Remove three IHI Cranes from    Project Status:
Budget: $1,835,000            Terminal 18                Schedule: Delayed
Phase: Construction                                    Budget: On or Under
Start: 9/11/2012                                          Status Reset: 6/23/2015
Schedule Completion: 1/31/2016                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The construction contract has been terminated. Finalizing the remaining costs
2    1.84
and negotiating a final change order amount and details withcontractor.This
will be the last report unless project resumes.                           1.5
Dollars in Millions 1                                                                             Schedule
0.49     0.44
The crane removal has been postponed.                            0.5
0
Budget                                       Authorized Forecasted  Costs
Incurred
The project is within budget. 
Change Order                               Construction Costs
Current Quarter     Project Total         1.4  1.3
Number of COs           0             3            1.2
1
Amount of Cos           $0           $183,628
Justification for COs:None this quarter.                             Dollars in Millions 0.80.60.4           0.3
0.2
Risks                                          0.2
None                                         0
Initial Change Spent
Orders
Budget Transfers
Amount       From         To        Photo
$0




MARITIME 
Port of Seattle 4Q 2015 Report  91

)2857+ 48$57(5 5(3257 
,' %DGJH 6\VWHP 5HSODFHPHQW 
3URMHFW &               3URFXUHPHQW DQG UHSODFHPHQW RI    3URMHFW 6WDWXV 
%XGJHW             WKH 3RUWZLGH ,' %DGJH V\VWHP       6FKHGXOH 'HOD\HG 
3KDVH ,PSOHPHQWDWLRQ          LQFOXGLQJ VRIWZDUH KDUGZDUH DQG    %XGJHW 2Q RU 8QGHU 
6WDUW                  HTXLSPHQW                   6WDWXV 5HVHW 1 $ 
6FKHGXOH &RPSOHWLRQ                             (Commission Construction Auth.) 
6LJQLILFDQW 'HYHORSPHQWV                              %XGJHW &RVWV ,QFXUUHG 
7KH ILUVW SKDVH RI WKH QHZ %DGJH 6\VWHP GHSOR\HG RQ 1RYHPEHU $ 
QG GHSOR\PHQW WR DGG PRELOH IXQFWLRQDOLW\ DQG DXWKRUL]HG VLJQHU HIILFLHQFLHV LV 
LQ WKH LPSOHPHQWDWLRQ VWDJH 
6FKHGXOH 
3ULRU 5HSRUW $ FULWLFDO SURMHFW WR UHSODFH WKH YHQGRU SURYLGLQJ DQ LQWHUIDFH ZLWK   'ROODUV LQ 0LOOLRQV 
76$ IRU WKH EDGJLQJ SURFHVV VHFXULW\ FKHFNV ZLOO UHGLUHFW 3RUW UHVRXUFHV 
$XWKRUL]HG )RUHFDVWHG   &RVWV
UHVXOWLQJ LQ D GHOD\ RI WKH ILQDO FRPSRQHQWV RI WKH ,' %DGJH 6\VWHP 
,QFXUUHG
5HSODFHPHQW SURMHFW E\ IRXU PRQWKV 
&RQVWUXFWLRQ &RVWV 
%XGJHW 
1RW $SSOLFDEOH 
2Q EXGJHW 
&KDQJH 2UGHU 
&XUUHQW 4XDUWHU      3URMHFW 7RWDO 
1XPEHU RI &2V 
$PRXQW RI &RV 
-XVWLILFDWLRQ IRU &2V 1RQH WKLV TXDUWHU 
5LVNV 
5HVRXUFH DYDLODELOLW\ PD\ FRQWLQXH WR GHOD\ WKH VHFRQG SKDVH PRELOH 
GHOLYHUDEOHV 
%XGJHW 7UDQVIHUV 
$PRXQW         )URP          7R 



&25325$7( 
92  Port of Seattle 4Q 2015 Report

)2857+ 48$57(5 5(3257 
&RQWUDFWRU 'DWD 6\VWHP 8SJUDGH 
3URMHFW &               8SJUDGH RI WKH &RQWUDFWRU 'DWD     3URMHFW 6WDWXV 
%XGJHW               6\VWHP XVHG E\ (QJLQHHULQJ DQG     6FKHGXOH 'HOD\HG 
3KDVH ,PSOHPHQWDWLRQ          RWKHU JURXSV WR WUDFN FRQWUDFWV IRU    %XGJHW 2Q RU 8QGHU 
6WDUW                  FRQVWUXFWLRQ SURMHFWV             6WDWXV 5HVHW 1 $ 
6FKHGXOH &RPSOHWLRQ                             (Commission Construction Auth.) 
6LJQLILFDQW 'HYHORSPHQWV                              %XGJHW &RVWV ,QFXUUHG 
'HYHORSPHQW LV LQ SURJUHVV 
6FKHGXOH 
'ROODUV LQ 0LOOLRQV                                                                                *RRG SURJUHVV LV EHLQJ PDGH LQ WKLV GHYHORSPHQW SURMHFW DQG FRQVLVWHQW 
EXVLQHVV UHYLHZ SULRULWL]DWLRQ DQG YDOLGDWLRQ HQVXUHV ZH DUH ZRUNLQJ RQ WKH 
KLJKHVW SULRULW\ IHDWXUHV 5HVRXUFH DYDLODELOLW\ GXH WR FRPSHWLQJ SULRULWLHV ZLOO 
GHOD\ WKH ILQDO GHSOR\PHQW IRXU PRQWKV. 
$XWKRUL]HG )RUHFDVWHG   &RVWV
,QFXUUHG
%XGJHW 
2Q EXGJHW                                            &RQVWUXFWLRQ &RVWV 
1RW $SSOLFDEOH 
&KDQJH 2UGHU 
&XUUHQW 4XDUWHU      3URMHFW 7RWDO 
1XPEHU RI &2V 
$PRXQW RI &RV 
-XVWLILFDWLRQ IRU &2V 1 $ 
5LVNV 
1R VLJQLILFDQW ULVNV DW WKLV WLPH 
%XGJHW 7UDQVIHUV 
$PRXQW         )URP          7R 




&25325$7( 
Port of Seattle 4Q 2015 Report  93

)2857+ 48$57(5 5(3257 
&RQVWUXFWLRQ 'RFXPHQW 0DQDJHPHQW 
3URMHFW &               5HSODFHPHQW RI WKH &RQVWUXFWLRQ    3URMHFW 6WDWXV 
%XGJHW               'RFXPHQW 0DQDJHPHQW 6\VWHP     6FKHGXOH 'HOD\HG 
3KDVH ,PSOHPHQWDWLRQ          XVHG E\ &RQVWUXFWLRQ 0DQDJHPHQW %XGJHW 2Q RU 8QGHU 
6WDUW                 WR DFFHSW UHYLHZ DQG GLVWULEXWH      6WDWXV 5HVHW 1 $ 
6FKHGXOH &RPSOHWLRQ    FULWLFDO GRFXPHQWDWLRQ           (Commission Construction Auth.) 
6LJQLILFDQW 'HYHORSPHQWV                              %XGJHW &RVWV ,QFXUUHG 
'HVLJQ DQG FRQILJXUDWLRQ LQ SURJUHVV 
6FKHGXOH 
3ULRU 5HSRUW ,PSOHPHQWDWLRQ LV LQ SURJUHVV EXW YHQGRU KDV VLJQLILFDQWO\ 
XQGHUHVWLPDWHG ZRUN LQ FRQWUDFW UHVXOWLQJ LQ D VFKHGXOH GHOD\ WR VHFRQG TXDUWHU    'ROODUV LQ 0LOOLRQV 

%XGJHW                                           $XWKRUL]HG )RUHFDVWHG  &RVWV
,QFXUUHG
2Q EXGJHW 
&RQVWUXFWLRQ &RVWV 
&KDQJH 2UGHU                                 1RW $SSOLFDEOH 
&XUUHQW 4XDUWHU      3URMHFW 7RWDO 
1XPEHU RI &2V 
$PRXQW RI &RV 
-XVWLILFDWLRQ IRU &2V 2ULJLQDO VRIWZDUH UHFRPPHQGDWLRQ LQ 5)3 IRU OLFHQVH 
W\SH GLG QRW PHHW DOO UHTXLUHPHQWV &2 LQLWLDWHG WR SXUFKDVH IXOO OLFHQVHV &UHGLW 
JLYHQ IRU RULJLQDO SXUFKDVH $GGLWLRQDO UHTXLUHPHQWV ZHUH LGHQWLILHG GXULQJ 
UHTXLUHPHQWV ZRUNVKRSV 
5LVNV 
9HQGRU KDV VLJQLILFDQWO\ XQGHUHVWLPDWHG ZRUN LQ FRQWUDFW DQG PD\ IXUWKHU GHOD\ 
LPSOHPHQWDWLRQ LQ FRQWUDFW GLVSXWHV 
%XGJHW 7UDQVIHUV 
$PRXQW         )URP          7R 



&25325$7( 
94  Port of Seattle 4Q 2015 Report

)2857+ 48$57(5 5(3257 
3DUNLQJ 6\VWHP 5HSODFHPHQW 
3URMHFW &               5HSODFHPHQW RI WKH $LUSRUW 0DLQ     3URMHFW 6WDWXV 
%XGJHW             *DUDJH 3DUNLQJ 6\VWHP             6FKHGXOH :LWKLQ RU $KHDG 
3KDVH 3ODQQLQJ                                          %XGJHW 2Q RU 8QGHU 
6WDUW                                             6WDWXV 5HVHW 1 $ 
6FKHGXOHG &RPSOHWLRQ                            (Commission Construction Auth.) 
6LJQLILFDQW 'HYHORSPHQWV                              %XGJHW &RVWV ,QFXUUHG 
9HQGRU VHOHFWHG YLD FRPSHWLWLYH SURFXUHPHQW LQ 'HFHPEHU 1HJRWLDWLRQV 
LQ SURJUHVV 
6FKHGXOH 
2Q VFKHGXOH                                              'ROODUV LQ 0LOOLRQV 
%XGJHW 
$XWKRUL]HG )RUHFDVWHG   &RVWV
2Q EXGJHW                                                           ,QFXUUHG
&KDQJH 2UGHU                                 &RQVWUXFWLRQ &RVWV 
&XUUHQW 4XDUWHU      3URMHFW 7RWDO        1RW $SSOLFDEOH 
1XPEHU RI &2V 
$PRXQW RI &RV 
-XVWLILFDWLRQ IRU &2V 1 $ 
5LVNV 
1R VLJQLILFDQW ULVNV DW WKLV WLPH 
%XGJHW 7UDQVIHUV 
$PRXQW         )URP          7R 





&25325$7( 
Port of Seattle 4Q 2015 Report  95

)2857+ 48$57(5 5(3257 
0D[LPR 8SJUDGH 
3URMHFW &               8SJUDGH 0D[LPR 6\VWHP XVHG E\   3URMHFW 6WDWXV 
%XGJHW             $YLDWLRQ DQG 0DULWLPH            6FKHGXOH :LWKLQ RU $KHDG 
3KDVH ,PSOHPHQWDWLRQ          0DLQWHQDQFH DQG ,QIRUPDWLRQ     %XGJHW 2Q RU 8QGHU 
6WDUW                 &RPPXQLFDWLRQ 7HFKQRORJ\        6WDWXV 5HVHW 1 $ 
6FKHGXOH &RPSOHWLRQ                             (Commission Construction Auth.) 
6LJQLILFDQW 'HYHORSPHQWV                              %XGJHW &RVWV ,QFXUUHG 
3URFXUHPHQW FRPSOHWH IRU LPSOHPHQWDWLRQ YHQGRU 3URMHFW NLFNRII VFKHGXOHG 
IRU -DQXDU\ . 
6FKHGXOH 
2Q VFKHGXOH                                            'ROODUV LQ 0LOOLRQV 
%XGJHW 
$XWKRUL]HG )RUHFDVWHG   &RVWV
2Q EXGJHW                                                           ,QFXUUHG
&KDQJH 2UGHU                                 &RQVWUXFWLRQ &RVWV 
&XUUHQW 4XDUWHU      3URMHFW 7RWDO        1RW $SSOLFDEOH 
1XPEHU RI &2V 
$PRXQW RI &RV 
-XVWLILFDWLRQ IRU &2V 1 $ 
5LVNV 
1R VLJQLILFDQW ULVNV DW WKLV WLPH 
%XGJHW 7UDQVIHUV 
$PRXQW         )URP          7R 




&25325$7( 
96  Port of Seattle 4Q 2015 Report

FOURTHQUARTER REPORT, 2015 
Employee Performance Management System 
Project: C800763              Implement the PeopleSoft       Project Status:
Budget: $400,000              e-Performance Management system  Schedule: Within or Ahead
Phase: Implementation          to support the Port Performance     Budget: On or Under
Start: 5/17/2015                 Management Program.           Status Reset: N/A
ScheduleCompletion: 5/31/2016                           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Procurement is complete.Implementationplanning is in process.            0.5
0.40     0.40
0.4
Schedule
On schedule
Budget                                     Dollars in Millions 0.30.2           0.10
0.1
Onbudget                                          0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          NotApplicable
Amount of Cos           $0             $0
Justification for COs:N/A
Risks
No significant risks at this time
Budget Transfers
Amount       From         To
$0




CORPORATE 
Port of Seattle 4Q 2015 Report  97

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.