4g memo

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA               Item No.      4g 
ACTION ITEM 
Date of Meeting     August 5, 2014 
DATE:    July 29 2014 
TO:      Tay Yoshitani, Chief Executive Officer 
FROM:   Michael Ehl, Director, Airport Operations 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  2014 Airfield Improvement Project (CIP #C102573) 
ACTION REQUESTED 
Request Commission authorization for the Chief Executive Officer to execute a major public
works construction contract with the sole responsive and responsible bidder to perform the 2014
Airfield Improvement Project at Seattle-Tacoma International Airport. 
SYNOPSIS 
On July 1, 2014, the Commission authorized rejection of all bids for the earlier advertised 2014
Airfield Improvement Project that contained more scope and was combined with the North
Satellite Ceiling Leaks project. The Commission also authorized the advertisement of the 2014
Airfield Improvement Project with a subset of the previous contract. Outreach occurred to the
contractor community prior to advertisement and the contract contained provisions intended to
attract more bidders. Bids were opened on July 22, 2014 and found to be irregular as there was
only a single bidder and the bid was more than ten percent (10%) over the engineer's estimate.
The single bid is in the amount of $969,100, which is thirty-four percent (34%) over the
engineer's estimate of $723,860. Staff recommends accepting the bid and authorizing execution
of the major works contract with the sole bidder as the work is considered essential to airport
operations and the work needs to occur prior to the approaching seasonal, inclement weather. 
BACKGROUND 
The current 2014 Airfield Improvement Program is part of an ongoing program to replace
distressed pavement on the airfield. The revised 2014 Airfield Improvement project will replace
approximately twelve deteriorated panels surrounding the North Satellite and approximately
fifteen deteriorated panels located on Runway 16C/34C. One additional panel that recently
became distressed will also be replaced and others may be necessary if encountered during the
duration of the contract work. 
Staff has determined that the funds previously authorized by the Commission for the 2014
Airfield Improvement project are sufficient for the completion of this project. No additional
fund authorization is being requested. 

Template revised May 30, 2013.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 29, 2014 
Page 2 of 3 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1)  Cancel the bid and re-bid under the assumption that additional contractor
interest can be achieved. This alternative assumes that future contractor outreach might have
better results than the previous effort. Although there was some evidence of other contractor
interest in performing the work, the time involved in re-advertising the project would result in
the timing of the work coinciding with the seasonal inclement weather. This could result in the
work not being able to be performed and significant impact to airfield operations. This is not the
recommended alternative. 
Alternative 2)  Accept the bid and authorize the execution of the major public works contract
with the sole responsible bidder. This alternative will prevent impact to airfield operations and
allow the work to be completed before the seasonal inclement weather.  This is the
recommended alternative. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
On July 1, 2014, Commission authorized the Chief Executive Officer to reject all bids for
the previously advertised project for the 2014 Airfield Improvement p the Airfield Apron
Pavement Replacement (CIP #102573) and NSAT-STS Ceiling Leak Long Term Repair
(CIP #C800609) and to re-advertise and execute a construction contract for a revised
Airfield Apron Pavement Replacement project (CIP #C102573). 
On April 1, 2014, Commission authorized the Chief Executive Officer to advertise and
execute a contract which included pavement and joint seal replacement in the amount of
$2,500,000 combined with another CIP and a total project cost of $4,470,000. 
On August 6, 2013, the Commission authorized the use of a project labor agreement for
the project. 
On April 2, 2013, the Commission authorized $300,000 and for the Chief Executive
Officer to complete the design and perform any advance preparatory work for the 2014 
Airfield Apron Pavement Replacement project. 
On March 26, 2013, the Commission authorized for the Chief Executive Officer to
advertise and execute a single construction contract comprised of Airfield Panel
Replacement and Joint Seal Replacement (CIP #102573) and Runway 16C/34C Panel
Replacement. This authorization request is for $8,967,000, and the estimated total cost of
the complete project is $9,377,000.
On July 24, 2012, the Commission authorized $200,000 and for the Chief Executive
Officer to complete the design and perform any advance preparatory work for the 2013
Airfield Apron Pavement Replacement project. 
On April 10, 2012, the Commission authorized an additional $1,467,000 because the bids
exceeded the Engineer's Estimate by greater than 10 percent; and authorized the Chief
Executive Officer to execute a contract in the amount of $6,553,964 with the low
responsive and responsible bidder for the 2012 Exterior Gates and Airfield Improvement
Projects. This authorization increased the budget by $1,467,000 due to the higher than
expected bids, for a total project cost of $10,500,000.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 29, 2014 
Page 3 of 3 
On January 24, 2012, the Commission authorized $4,707,000 and for the Chief Executive
Officer to advertise and execute a construction contract that included Apron Pavement
Replacement, Exterior Gate Improvements, Runway 16C/34C Panel Replacement, and
South Snow Dump Pavement Expansion 
On July 26, 2011, the Commission authorized $465,000 and for the Chief Executive
Officer to complete the design and perform any advance work in support of the 2012
Pavement and Joint Replacement and Sealant Project for non-runway concrete pavement
panels, joint seal replacement, spall repair, and associated or temporary facilities, such as
striping, lighting, etc., on the Aircraft Operations Area. 
On March 1, 2011, the Commission authorized $6,235,000 and for the Chief Executive
Officer to advertise and execute a construction contract that included slot drain,
pavement, and joint seal replacement at the South Satellite and perform installation of
temporary facilities in concourses. 
On August 10, 2010, the Commission authorized $394,000 and for the Chief Executive
Officer to direct staff to: 1) proceed with project management, design, environmental
support, and preparation of 100 percent design level construction documents for the
replacement of slot drains, pavement and joint seal at the South Satellite at Seattle-
Tacoma International Airport; 2) execute and award outside professional service
agreements; 3) pre-purchase common-use gate equipment; and 4) allow Port Construction
Services to self-perform, advertise for bids, and execute and award small works 
construction contracts for common use equipment installation. 
On February 9, 2010, the Commission authorized $5,650,000 for the design,
advertisement, and award of a construction contract for the 2010 Airfield Improvement
Projects  Contract 1, consisting of panel replacements on Runway 16C/34C. 
On September 22, 2009, senior Aviation staff briefed the Commission on Seattle-Tacoma
International Airport Facility Functionality and Readiness. 
On February 26, 2008, the Commission authorized $450,000 for joint seal replacement
on Runway 16C/34C (CIP 800112). 
Note: On October 30, 2003, Runway 16 Right/34 Left (16R/34L) was renamed runway
16C/34C, in preparation for the Third Runway to assume the runway 16R/34L
designation. 
On January 14, 2003, the Commission authorized $5,000,000 for a multi-year program of
panel replacement on Runway 16R/34L (CIP 102037). 
On November 26, 1996, the Commission authorized $2,000,000 for a multi-year program
of panel replacement on Runway6R/34L (CIP 100663). 
On June 13, 1993, the Commission authorized $10,422,000 for Runway 16R/34L
rehabilitation and other airfield improvements (CIP 100663).

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.