4g

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA               Item No.      4g 
ACTION ITEM                  Date of Meeting     July 1, 2014 
DATE:    June 24, 2014 
TO:      Tay Yoshitani, Chief Executive Officer 
FROM:   Michael Ehl, Director, Airport Operations 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  2014 Airfield Improvement Project (CIP #C102573) 
Amount of This Request: $0              Source of Funds: Airport Development
Fund and future revenue bonds 
Est. Total Project Cost: $1,500,000 
Est. State and Local Taxes: $80,000 
ACTION REQUESTED 
Request Commission authorization for the Chief Executive Officer to reject all bids for the
previously advertised contract for the Airfield Apron Pavement Replacement (CIP #102573) and
NSAT-STS Ceiling Leak Long Term Repair (CIP #C800609) and to re-advertise and execute a 
construction contract for a revised Airfield Apron Pavement Replacement project (CIP #C102573). 
SYNOPSIS 
On April 1, 2014, the Commission authorized the CEO to advertise and execute a single
construction contract for three projects consisting of two CIPs and one expense project to be
constructed on the airfield in 2014. A single bid was received for the contract, which was 29.45% 
over the Engineer's Estimate. The single bid was deemed to be irregular and subsequently rejected.
The requested authorization is to re-advertise a subset of the previous contract in order to address
the most critical items that could impact airport operations. The revised contract will include: 
Distressed concrete pavement on Runway 16C/34C. 
Distressed concrete pavement in three areas surrounding the North Satellite. 
No additional fund authorization is being requested. The estimated total cost of the revised project
is $1,500,000. 
BACKGROUND 
The 2014 Airfield Improvement Project is part of an ongoing pavement management program to
replace aged and distressed concrete pavement and joint sealant in non-runway areas. 
Concrete pavement panels and joint sealant typically have respective design lives of 20 and 10
years. Currently, there is a significant amount of airfield pavement and joint sealant that have far
exceeded their expected service lives. Concrete debris resulting from the deteriorating pavement can

Template revised May 30, 2013.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
June 25, 2014 
Page 2 of 6 
become a hazard for aircraft and personnel. The replacement of the distressed panels is necessary
for the safe operation of aircraft. 
The revised 2014 Airfield Improvement Project will replace approximately 12 deteriorated panels
surrounding the North Satellite and approximately 15 deteriorated panels located on Runway
16C/34C. 
Replacement of pavement joint seal on portions of Taxiways B and W and the North Satellite  
Satellite Transit System (STS) Ceiling Leak Long-Term Repair will be deferred. Taxiways B and
W are located west of the North Satellite and their joint seal replacement is a component of CIP
#C102573. The North Satellite  STS ceiling repair to eliminate leaks is a component of CIP
#C800609. Performing work for these items is weather-sensitive and the schedule for the readvertised
project would likely affect the ability to perform the work. The interior of the STS lobby
would be exposed to weather during replacement of exterior components. 
Replacement of the distressed panels on Runway 16C/34C will be paid for using $300,000 of
expense funds because they will not meet the longevity requirements for capitalization with the
scheduled reconstruction of the runway in 2015. The 2014 operating budget includes $160,000 for
the Runway 16C/34C maintenance. 
The Commission previously authorized use of a project labor agreement for this project.
PROJECT JUSTIFICATION AND DETAILS 
Project Objectives 
Provide structurally sound pavements for current and future customers. 
Provide reliable and appropriate-sized infrastructure systems. 
Minimize total lifecycle cost (capital and expense). 
Minimize operational impacts. 
Scope of Work 
This request includes the following elements: 
Apron panel replacement of approximately twelve panels. 
Runway panel replacement (for RW 16C/34C) of approximately fifteen panels. 
Schedule 
Commission Authorization to Advertise and Execute a Contract                July 2014 
Advertisement                                           July 2014 
Notice to Proceed                                        September 2014 
Begin Construction                                      September 2014 
Construction Complete                                   October 2014

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
June 25, 2014 
Page 3 of 6 
FINANCIAL IMPLICATIONS 
CIP C102573 Budget/Authorization Summary   Capital     Expense     Total Project 
Original Budget                    $30,800,000   $0          $30,800,000 
Budget Decrease                   $903,505     $0         $903,505 
Revised Budget                    $29,896,495   $0         $29,896,495 
Previous Authorizations               $27,679,495   $0          $27,679,495 
Current request for authorization          $0          $0          $0 
Total Authorizations, including this request   $0          $0          $0 
Remaining budget to be authorized        $2,217,000    $0          $2,217,000 
Total Estimated Project Cost            $29,896,495   $0          $29,896,495 
Project Cost Breakdown                              This Request                Total Project 
Construction                       $0                $950,000 
Construction Management             $0               $190,000 
Design                          $0               $100,000 
Project Management                $0              $60,000 
Central Procurement Office             $0                $50,000 
Administration                     $0                $40,000 
Environmental& Permitting            $0               $30,000 
State & Local Taxes (estimated)          $0                $80,000 
Total                             $0                 $1,500,000 
The total Project cost includes expense cost of $300,000. 
Budget Status and Source of Funds 
CIP C102573 is included in the 2014  2018 capital budget and plan of finance. The Runway
16C/34C expense work was included in the 2014 operating budget for $160,000. The Airport will
seek to absorb the increase through savings or use of contingency. The funding sources for these
projects include the Airport Development Fund and future bonds. The Port plans to issue bonds in
2014 to fund a number of projects. 
Financial Analysis and Summary 
CIP Category             Renewal/Enhancement 
Project Type              Renewal & Replacement 
Risk adjusted discount rate     N/A 
Key risk factors             N/A 
Project cost for analysis        $1,500,000 
Business Unit (BU)          Airfield Movement Area and Airfield Apron Area 
Effect on business performance  NOI after depreciation will increase 
IRR/NPV             N/A 
CPE Impact             $.02 in 2014 due to expense work, $.02 in 2015 and
beyond due to capital costs.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
June 25, 2014 
Page 4 of 6 
Lifecycle Cost and Savings 
The replacement of concrete panels will result in cost avoidance for maintaining them. Geometric
constraints limit the depth of the pavement that can be constructed at the North Satellite and may
reduce the life of those particular concrete panels.
STRATEGIES AND OBJECTIVES 
This project supports the Port's Century Agenda objective of meeting the region's air transportation
needs at Seattle-Tacoma International Airport for the next 25 years. Ensuring safe and secure
operations and managing assets to minimize the long-term total cost of ownership assist in meeting
this objective. 
TRIPLE BOTTOM LINE 
Economic Development 
Generally, there are no economic impacts related to renewal/enhancement projects since they are
primarily related to preservation of existing business activity. 
Environmental Responsibility 
The project contains appropriate environmental controls to prevent sediments from entering
stormwater systems. Removed concrete panels are anticipated to be crushed and recycled as has
occurred on previous, similar projects.
Community Benefits 
Maintaining runway and airfield apron pavement benefits both our airline customers and travelers.
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
1) Do nothing: This alternative would result in an increasing risk of aircraft ingesting concrete
debris into aircraft engines from distressed pavement, adversely affecting Airport operations. This
is not the recommended alternative. 
2) Replace the deteriorated and aged pavement panels on runway and non-runway areas during the
2014 construction season. This allows for the programmatic replacement of aged and distressed
pavement and avoids operational risk from panels with known distress. This is the recommended
alternative. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
2014 Airfield Improvement Project: 
On April 1, 2014, Commission authorized the Chief Executive Officer to advertise and
execute a contract which included pavement and joint seal replacement in the amount of
$2,500,000 combined with another CIP and a total project cost of $4,470,000. 
On August 6, 2013, the Commission authorized the use of a project labor agreement for the
project.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
June 25, 2014 
Page 5 of 6 
On April 2, 2013, the Commission authorized $300,000 and for the Chief Executive Officer
to complete the design and perform any advance preparatory work for the 2014 Airfield
Apron Pavement Replacement project. 
On March 26, 2013, the Commission authorized for the Chief Executive Officer to advertise
and execute a single construction contract comprised of Airfield Panel Replacement and
Joint Seal Replacement (CIP #102573) and Runway 16C/34C Panel Replacement. This
authorization request is for $8,967,000, and the estimated total cost of the complete project
is $9,377,000.
On July 24, 2012, the Commission authorized $200,000 and for the Chief Executive Officer
to complete the design and perform any advance preparatory work for the 2013 Airfield
Apron Pavement Replacement project. 
On April 10, 2012, the Commission authorized an additional $1,467,000 because the bids
exceeded the Engineer's Estimate by greater than 10 percent; and authorized the Chief
Executive Officer to execute a contract in the amount of $6,553,964 with the low responsive
and responsible bidder for the 2012 Exterior Gates and Airfield Improvement Projects. This
authorization increased the budget by $1,467,000 due to the higher than expected bids, for a
total project cost of $10,500,000. 
On January 24, 2012, the Commission authorized $4,707,000 and for the Chief Executive
Officer to advertise and execute a construction contract that included Apron Pavement
Replacement, Exterior Gate Improvements, Runway 16C/34C Panel Replacement, and
South Snow Dump Pavement Expansion 
On July 26, 2011, the Commission authorized $465,000 and for the Chief Executive Officer
to complete the design and perform any advance work in support of the 2012 Pavement and
Joint Replacement and Sealant Project for non-runway concrete pavement panels, joint seal
replacement, spall repair, and associated or temporary facilities, such as striping, lighting,
etc., on the Aircraft Operations Area. 
On March 1, 2011, the Commission authorized $6,235,000 and for the Chief Executive
Officer to advertise and execute a construction contract that included slot drain, pavement,
and joint seal replacement at the South Satellite and perform installation of temporary
facilities in concourses. 
On August 10, 2010, the Commission authorized $394,000 and for the Chief Executive
Officer to direct staff to: 1) proceed with project management, design, environmental
support, and preparation of 100 percent design level construction documents for the
replacement of slot drains, pavement and joint seal at the South Satellite at Seattle-Tacoma
International Airport; 2) execute and award outside professional service agreements; 3) prepurchase
common-use gate equipment; and 4) allow Port Construction Services to selfperform
, advertise for bids, and execute and award small works construction contracts for
common use equipment installation. 
On February 9, 2010, the Commission authorized $5,650,000 for the design, advertisement,
and award of a construction contract for the 2010 Airfield Improvement Projects  Contract
1, consisting of panel replacements on Runway 16C/34C. 
On September 22, 2009, senior Aviation staff briefed the Commission on Seattle-Tacoma
International Airport Facility Functionality and Readiness.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
June 25, 2014 
Page 6 of 6 
On February 26, 2008, the Commission authorized $450,000 for joint seal replacement on
Runway 16C/34C (CIP 800112). 
Note: On October 30, 2003, Runway 16 Right/34 Left (16R/34L) was renamed runway
16C/34C, in preparation for the Third Runway to assume the runway 16R/34L designation. 
On January 14, 2003, the Commission authorized $5,000,000 for a multi-year program of
panel replacement on Runway 16R/34L (CIP 102037). 
On November 26, 1996, the Commission authorized $2,000,000 for a multi-year program of
panel replacement on Runway6R/34L (CIP 100663). 
On June 13, 1993, the Commission authorized $10,422,000 for Runway 16R/34L
rehabilitation and other airfield improvements (CIP 100663).

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.