Terminal 91 Substation Upgrade Item #: 6a_Supp Date: March 11, 2014 Commission Memo TERMINAL 91 SUBSTATION UPGRADE Sub 15 Sub 14 Sub 9 Sub 12 Subs 6 & 7 Main Sub 8 Sub 13 Substation Subs 10 MMS-2 & 11 Sub 5 Sub 1 Subs 2 & 3 Sub 4 Main Substation MMS-1 2 Preliminary Project Schedule Design Funding Authorization: March, 2014 Construction Funding Authorization: November, 2014 Construction Contract Advertisement Award: November 2014 February 2015 Construction Complete: 4th Quarter, 2015 3