Item No.       7b_attach
Date of Meeting    June 25, 2013 


SeaTac International Airport 
NorthSTAR Program 
Program Quarterly Commission Update 
June 2013 

Program  NSAT  C-Vert   Main   BHS   C/D-Stairs

NorthSTAR Program 
C800544  NS NorthSTAR Program  George England, Program Manager 
Overall management of the NorthSTAR program including program controls. 
C800556  NS NSAT Renov NSTS Lobbies  Greg Vouros, Project Manager 
Renovation of the North Satellite, all levels, interior and infrastructure, including seismic reinforcement, gate relocation
and penthouse shell. 
C800547  NS Conc C Vertical Circulation  Joe Nessel, Project Manager 
Exterior vertical circulation at Concourse C gates C-2/4, C-10/12 and C-14 to improve efficiency and customer service. 
C800545  NS Main Terminal Improvements  Joe Nessel, Project Manager 
Curbside revisions, ticket lobby upgrades, demolition of Zone 7 ticket counters, and reconfiguration of Main Terminal
north checkpoint (#5). 
C800555  NS Refurbish Baggage System  Ken Warren, Project Manager 
Baggage system refurbishment in support of Alaska Air Group (AAG) operations in the North Satellite and Concourse D. 
C800554  NS Concourse C&D Exterior Stairs  Not Yet Approved 
New exterior stairs at Concourses C & D to enable aft loading of aircraft. (Project is currently Status 1.) 


Program  NSAT  C-Vert   Main   BHS   C/D-Stairs 
2

NorthSTAR Program 
Estimated : $315.6M                             Overall Budget 
FINANCIAL STATUS: NorthSTAR Program
Original        Approved        Current         Current        Pending       Remaining       Expended        Forecast
Budget    Transfers / Trends    Budget     Authorization  Transfers / Trends   Contingency      To Date      At Complete
$          $          $          $          $          $          $          $
C800544
NS NorthSTAR      $ 13,000,000  $ 3,300,000  $ 16,300,000  $ 3,600,000  $ (5,850,000) $ 109,000  $ 949,774  $ 10,450,000
Program
C800545
NS Main Terminal    $ 30,000,000  $ 100,000  $ 30,100,000  $ 100,000  $ (900,000) $ 2,606,000                $ 29,200,000
Improvements
C800547
NS Conc C Vertical    $ 19,300,000  $ -   $ 19,300,000  $ 3,155,000  $ -   $ 1,995,000  $ 427,009  $ 19,300,000
Circulation
C800555
NS Refurbish Baggage $ 22,000,000  $ -   $ 22,000,000  $ 3,760,000  $ -   $ 1,315,000  $ 71,049  $ 22,000,000
System
C800556
NS NSAT Renov NSTS  $ 194,300,000  $ 12,246,357  $ 206,546,357  $ 32,718,056  $ 1,800,000  $ 19,479,000  $ 492,435  $ 208,346,357
Lobbies
MANAGEMENT
$ - $ - $ - $ - $ 4,950,000 $ - $ - $ 4,950,000
RESERVE
Subtotal          $ 278,600,000  $ 15,646,357  $ 294,246,357  $ 43,333,056   $ -   $ 25,504,000  $ 1,940,267  $ 294,246,357

C800554
NS Exterior Stairs     $ 21,400,000  $ -   $ 21,400,000  $ -   $ -   $ 2,123,700  $ -   $ 21,400,000
Conc C&D
Total             $ 300,000,000  $ 15,646,357  $ 315,646,357  $ 43,333,056   $ -   $ 27,627,700  $ 1,940,267  $ 315,646,357


Program  NSAT  C-Vert   Main   BHS   C/D-Stairs 
3

NorthSTAR Program 
Overall Schedule 







Program  NSAT  C-Vert   Main   BHS   C/D-Stairs 
4

NorthSTAR Program 
Program Status 
CIP: C800544 - NS NorthSTAR Program 
Accomplishments: 
Developed process for Tri-Taxilane scope refinement. 
Established Monthly Program Status Reviews with AAG attendance. 
Issued Final Project Controls Plan (Version 1.0). 
Established baseline start date for North Main Terminal project. 
Commission authorized programmatic Project Labor Agreement. 
Progress: 
Coordinating integrated Program-wide Northwest Sense of Place development. 
Refining process to capture Aeronautical vs. Non-Aeronautical scope transfers as part of budget reporting. 
Risks: 
Communication & Coordination across multiple teams, stakeholders & people. 
Assure baseline schedule alignment of all stakeholders. 

Program  NSAT  C-Vert   Main   BHS   C/D-Stairs 
5

NS NSAT Renovation & NSTS Lobbies 
CIP: C800556 - NS NSAT Renovation & NSTS Lobbies 
Accomplishments: 
Design workshops conducted with follow-up meetings in place. 
Preliminary conceptual layouts submitted and reviewed. 
Construction schedules developed to reflect impact of 2, 3 and 4 phase options. 
Completed and submitted Gate Analysis Study to AAG. 
Progress: 
Design Team conducting site investigations of existing building conditions. 
Enhanced as-built photogrammetry for increased definition of existing conditions. 
Construction gate phasing options being reviewed by AAG. 
IATA Level of Service study underway. 
Port workshops held defining "Northwest Sense of Place."AAG workshops to follow. 
Risks: 
Maximize maintaining Airport operations (AAG & concessions) during renovations. 
Level of Services (IATA) rating for passengers may be lower than what would be deemed acceptable. 
Program  NSAT  C-Vert   Main   BHS   C/D-Stairs 
6

NS Concourse C Vertical Circulation 
CIP: C800547 - NS Concourse C Vertical Circulation 
Accomplishments: 
Completed project notebook, reduced budget by $2.7M. 
Received investment committee, MII and Commission approval of $3.07M for design. 
30% design approved by AAG. 
60% design completed. 
Progress: 
90% design underway. 
Issues: 
Maintaining an aggressive schedule. 
Risk: 
Utility conflicts for placement of walkway structures. 


Program  NSAT  C-Vert   Main   BHS   C/D-Stairs 
7

Main Terminal Improvements 

CIP: C800545 - NS Main Terminal Improvements 
Progress: 
Established budget for Project Notebook development. 
Project team concurred in placing project on-hold until July 2013. 
Issues: 
Coordination with the NSAT design concept to ensure a cohesive look/feel. 
Use Northwest Sense of Place developed for NSAT design. 
Coordination with AAG & TSA on Checkpoint 5 reconfiguration. 
Risk: 
Least defined scope relative to the program budget. 


Program  NSAT  C-Vert   Main   BHS   C/D-Stairs 
8

NS Refurbish Baggage System 

CIP: C800555 - NS Refurbish Baggage System 
Accomplishments: 
Obtained 30% design concurrence from AAG 4/24 & POS 4/25. 
C88 Section Report/Conditions assessment completed. 
Progress: 
60% design underway. 
Baggage metrics definition underway. 
Speed investigation underway. 
Issues: 
Refurbishment scope accelerated in the schedule. 
Risk: 
IATA Level of Service study results may impact scope of project. 

Program  NSAT  C-Vert   Main   BHS   C/D-Stairs 
9

NS Concourse C&D Exterior Stairs 
CIP: C800554 - NS Concourse C&D Exterior Stairs 
Accomplishments: 
This is a Status 1 prospective project. A decision whether to include in the program will
be made in the future. 






Program  NSAT  C-Vert   Main   BHS   C/D-Stairs 
10

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.