5f

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA               Item No.       5f 
ACTION ITEM             Date of Meeting    April 23, 2013 

DATE:    April 12, 2013 
TO:      Tay Yoshitani, Chief Executive Officer 
FROM:   Beth Britz, Project Manager, Marine Maintenance 
Rebecca Schwan, Real Estate Manager 
SUBJECT: Fishermen's Terminal Building C-15 Exterior Paint Project 

Amount of This Request:  $ 458,000        Source of Funds:    General Fund 
Est. State and Local Taxes: $  3,000        Est. Jobs Created:   4 
Est. Total Project Cost:    $ 458,000 
ACTION REQUESTED: 
Request Commission authorization for the Chief Executive Officer to proceed with deferred
maintenance at Fishermen's Terminal Building C15 (Fishermen's Center) to hand wash and
paint the exterior of the building (Paint Exterior project), including authorization for Marine
Maintenance to self-perform the work required to clean the exterior, prep, and repaint, for a total
cost not to exceed $458,000. 
SYNOPSIS: 
Commission has approved this project as part of the 2013 Deferred Maintenance Program. The
project will include hand washing the siding on the exterior of the entire Fishermen's Terminal
C15 Building (Fishermen's Center), using a method compliant with stormwater regulations, as
well as preparation for and repainting of the areas identified in the scope of work. The building is
visibly dirty from years of exposure to the elements and becoming an eyesore. 
The C15 Building is at the center of Fishermen's Terminal. It is home to anchor tenant
Chinook's at Salmon Bay, which is part of the Anthony's Homeport restaurant chain and is a
popular local seafood restaurant. The building also houses two other restaurants, a tavern, a 
seafood market, a brand-new grocery store and deli along with several other retail and office
tenants. It is the newest building at the facility. The combined annual revenues from the tenants
are estimated at just over $1,200,000. Due to the public nature of the building's operations, this 
request includes authorization for the Port to self-perform the work utilizing Maintenance
personnel. This decision was reached after careful analysis of the costs/benefits of performing
the work by Marine Maintenance or contracting it out. Self-performing this work is preferable 
because it allows work to be scheduled and coordinated to provide minimal impact and

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
April 12, 2013 
Page 2 of 5 
disruption to the tenants' businesses. Working partial days and working around peak use hours
will be required. A large portion of this work is exposed to the weather, which requires
additional flexibility in scheduling. The cost of this project was included in the 2013 Real Estate
Operating Budget. 
BACKGROUND: 
The Fishermen's Terminal C15 Building was constructed in 1988. It is a popular and well-
known destination frequented by the boating, fishing, tourist and dining public. In addition to the
public venues (three restaurants and a tavern), the entire second floor is 100% occupied by office
tenants. The combined annual revenues from these tenants are estimated at just over $1,200,000 
per year. 
The exterior of the C15 Building needs to be thoroughly cleaned and repainted. The siding has a
great deal of built-up oily grime and dirt from having been in the local elements for many years
without being washed. The build-up leads to pitting of the baked coating, which in turn flakes
and peels. This leaves the metal siding exposed and subject to rust. The area referred to as the
plaza is especially susceptible to the elements due to the wind blowing off the water. This area is
peeling and needs to be repainted. The steel supports, posts, trusses and exposed framing are
also very dirty, peeling and in need of repainting. Recently, peeling of the coating on the siding
has been observed. In short, with each year, the building gets dirtier, more degraded and in
greater need of an exterior paint job.
Annual preventive maintenance of C15 has been deferred for a number of years because of
budget constraints, but this work was identified several years ago as one of the Deferred
Maintenance projects that should be funded to safeguard a Port asset to ensure the Port realizes
the full useful life of the building. 
PROJECT JUSTIFICATION: 
The C15 Building exterior is visibly dirty from many years of exposure to the elements. The 
coating of the siding in the plaza area is peeling and rust is forming. The undersides of the plaza
and covered walkways have started to rust in the places where the paint has peeled. The building
is very visible to the public and to customers. 
The decision to have Maintenance self-perform the work was based on the scheduling flexibility
required, and the challenge of pre-identifying all of the areas to be repainted. The nature of the 
building's business operations makes it essential to schedule and coordinate the work to provide
minimal impact and disruption. Starting and stopping of the work would require a contactor to
have multiple mobilizations and demobilizations and challenges in scheduling workers. Working
partial days, working around peak-use hours and delays for inclement weather will be required.
The areas to be repainted are identified in the scope of work, but additional areas may be
exposed as the cleaning process is conducted.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
April 12, 2013 
Page 3 of 5 
The cleaning and repainting has been deferred for several years due to budget constraints. With
each year, the building deteriorates further. 
Project Objectives: 
Preserve and maintain a Port asset. 
Improve building appearance. 
Perform work with minimal disruption to patrons and tenants during project. 
Complete project prior to the inclement fall weather. 
PROJECT SCOPE OF WORK AND SCHEDULE: 
Scope of Work: 
Hand wash the entire exterior siding of the C15 building, ensuring all run-off is captured
and appropriately disposed of.
Prepare and repaint the exposed posts, girders, rafters, trusses and all areas that are
currently blue, green or similar colors to match the building standard trim color. 
Prepare and repaint the exterior walls inside of the plaza area. 
Remove, store, then re-install the bird barrier/netting. 
Prepare and repaint the underside of the plaza area and covered walkways. 
Coordinate all work with tenant schedules to minimize adverse impact to the facility's 
operations. 
Comply with stormwater regulations. 
Schedule: Perform the work between June 2013 and September 2013 as weather and tenant
schedules permit. 
FINANCIAL IMPLICATIONS: 
Budget/Authorization Summary: 
Original Budget                                          $458,000 
Previous Authorizations                                          $0 
Current request for authorization                                 $458,000 
Total Authorizations, including this request                          $458,000 
Remaining budget to be authorized                                 $0 
Total Estimated Project Cost                                  $458,000 
Project Cost Breakdown:                                Total Project 
Construction                                             $435,000 
Construction Management                                     $0 
Design                                                    $0 
Project Management                                     $20,000
Permitting                                                   $0 
State & Local Taxes (estimated)                                  $3,000 
Total                                                    $458,000

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
April 12, 2013 
Page 4 of 5 
Budget Status and Source of Funds: 
The cost to paint the exterior of the Fishermen's Terminal C15 Building was included in the
2013 Real Estate Operating Budget in the amount of $458,000. 
This project will be funded from the General Fund. 
Financial Analysis and Summary: 
CIP Category  Not applicable  Expense project. 
Project Type   Deferred Maintenance Expense project. 
Risk adjusted  N/A 
discount rate 
Key risk       Delays due to weather and tenant operations. This risk is
factors           mitigated by utilizing Port Maintenance personnel for the
work. 
Costs might increase if required work is more extensive than
currently known. 
Project cost   $458,000 
for analysis 
Business Unit  Commercial Properties, Real Estate. 
(BU) 
Effect on     The estimated cost of this project of $458,000 will be an expense in
business     2013 and thus will reduce Net Operating Income (NOI) by a
performance   corresponding amount. The cost of the project is in line with the 
amount included in the 2013 Operating Budget, so no unfavorable
variance from Budget is anticipated. 
IRR/NPV    The NPV of this project is equal to ($458,000) or the project cost. 
Lifecycle Cost and Savings: 
This expense work is ordinary preventive maintenance required to properly care for the asset.
This type of preventive maintenance will ensure that the Port realizes the full useful life of the
asset. Annual preventive maintenance was deferred due to previous budget constraints. 
STRATEGIC OBJECTIVES: 
Cleaning and repainting the exterior of the Fishermen's Terminal C15 Building supports the
Port's strategies to "Exhibit Environmental Stewardship through our actions." This project
refreshes the aesthetics of this popular tourist destination and improves the longevity of the
existing exterior.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
April 12, 2013 
Page 5 of 5 
ENVIRONMENTAL SUSTAINABILITY: 
The work will be conducted in compliance with stormwater regulations, which require collection
and proper disposal of all run-off. This project will prolong the life of the siding and remove
loose or peeling paint. 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
Alternative 1: Do nothing. Doing nothing would limit the life of the siding and reduce the public
appeal. This is not recommended. 
Alternative 2: Authorize to procure a Public Works contract to do this work and authorizations of
$600,000 for a combined authorization that would include project design, advertisement and
execution of a major construction contract, and construction management. This is not the
recommended alternative. 
Alternative 3: Authorize $458,000 for the Port to self-perform the cleaning and repainting of the
Fishermen's Terminal C15 Building's exterior. This is the recommended alternative. 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
None 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
November 27, 2012: Approval of 2013 Deferred Maintenance program.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.