6a

PORT OF SEATTLE 
MEMORANDUM 
REVISED COPY 
COMMISSION AGENDA               Item No.       6a 
ACTION ITEM             Date of Meeting   March 26, 2013 

DATE:    March 22, 2013 
TO:      Tay Yoshitani, Chief Executive Officer 
FROM:   Michael Ehl, Director, Airport Operations 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  2013 Airfield Apron Pavement and Joint Seal Replacement (CIP#102573)
Construction 
Amount of This Request:  $8,967,000    Source of Funds:  Existing Revenue Bond 
Proceeds 
Est. State and Local Taxes:   $683,000    Est. Jobs Created:  38 
Est. Total Project Cost:  $9,377,000 
ACTION REQUESTED: 
Request Commission authorization for the Chief Executive Officer to advertise and execute a
single construction contract comprised of Airfield Panel Replacement and Joint Seal
Replacement (CIP #102573) and Runway 16C/34C Panel Replacement. This authorization
request is for $8,967,000, and the estimated total cost of the complete project is $9,377,000. 
Authorization is also requested to perform this contract under a project labor agreement (PLA). 
SYNOPSIS: 
Multiple projects to be constructed on the airfield in 2013 have been combined into a single
construction contract in order to minimize disruption to the airlines and Airport patrons.
Advertising these contracts as one project is advisable due to the coordination requirements for
multiple jobs affecting the airfield movement area in multiple locations. 
This year's pavement and joint seal replacement project is part of a comprehensive plan to
replace the most damaged, aged, and travelled concrete on the airfield as well as replacing failed
pavement joint seal. 
Runway 16C/34C Panel Replacement includes replacement of deteriorating concrete pavement
panels and joint seal. Runway 16C/34C is scheduled to be replaced in 2016. Replacement of
these panels will be paid for as an expense project because it does not meet the requirements for
capitalization. 
Estimated total project cost includes $200,000 previously authorized for design of the panel and
joint seal replacement and $210,000 of expense funds for panel replacement on Runway
16C/34C.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
March 22, 2013 
Page 2 of 6 
In return for the Port's promise to require in its bid specifications that all successful bidders
agree to be covered by a PLA, unions promise labor peace through the life of the contract. The
provisions of a PLA will help ensure that this project is completed during one summer
construction season, minimizing the impact on international and domestic travelers and carriers. 
Funding for this project is included in the 2013-2017 capital budget and plan of finance. 
BACKGROUND: 
Starting in 2009, Airport staff conducted visual surveys of pavement on the airfield to determine
which pavement needed replacing, and in what priority. Work in 2013 will focus on replacing
deteriorated panels on non-runway areas. Pavement joint seals will be replaced in both taxilane 
and taxiway areas. 
Many of the concrete pavements that are currently failing were originally installed as early as
1970 with a design life of 20 years. Typical degradation of the concrete is occurring. The
concrete and joint seal work must occur in phases to minimize impacts to airline operations.
The airfield pavement replacement is part of a multi-year program to replace some of the worst
pavement and joint seal on the airfield in non-runway areas. The project will replace areas of
concrete most susceptible to deterioration due to repeated aircraft loading and age and current
condition of the pavement. Additional non-runway panels may be replaced if they become
unserviceable. 
It is necessary to use expense funds for the 16C/34C runway panel replacement due to the
planned total replacement of the runway in 2016. There are currently six panels on runway
16C/34C identified for replacement and another 34 that are being monitored. Given that
pavement distress will continue to occur between now and construction, additional panels will
likely be added. Staff believes that the $210,000 should be enough to cover the costs, should a
small number of additional panels require replacement this year. 
PROJECT JUSTIFICATION: 
Much of the concrete pavement on the airfield has exceeded its service life and deteriorated to
the point of needing replacement. Concrete debris resulting from the deteriorating pavement can
become a hazard for aircraft and personnel. The replacement of pavement panels requires
phasing by area. Replacing joint seal is the primary method for extending the life of concrete
pavement. 
Project Objectives: 
Maintain the structural integrity of the pavements by the replacement of deteriorated
and aged pavement panels and joint sealant on runway and non-runway areas. 
Replace joint sealant between existing concrete panels on non-runway areas in an effort
to prolong the life of the existing concrete.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
March 22, 2013 
Page 3 of 6 
PROJECT SCOPE OF WORK AND SCHEDULE: 
Scope of Work: This request includes the following elements: 
Approximately 126,000 square feet of panel replacement on Taxilane W. 
Replace approximately 104,000 linear feet of joint seal on Taxiway B and Taxilane W. 
Runway panel replacement of approximately six panels. 
Utility repair or removal of IWS, sewer, and/or waterlines if within the footprint of the 
panel replacement 
Schedule: 
Design Start                      September 2012 
Design Complete                 February 2013 
Commission Authorization to Bid Work   March 2013 
Construction Start                   June 2013 
Construction Complete              October 2013 
FINANCIAL IMPLICATIONS: 
Budget/Authorization Summary:         Capital      Expense    Total Project 
Original Budget                      $30,800,000    $210,000    $31,010,000 
Budget Decreases (2012)                $(537,965)        $0     $(537,965) 
Revised Budget                     $30,262,035    $210,000    $30,472,035 
Previous Authorizations                 $12,378,035         $0    $12,378,035 
Current request for authorization             $8,967,000    $210,000     $9,177,000 
Total Authorizations, including this request    $21,345,035    $210,000    $21,555,035 
Remaining budget to be authorized          $8,917,000        $0     $8,917,000 
Project Cost Breakdown:                   Total Project 
Construction                              $7,185,000 
Construction Management                   $1,109,000 
Design                                  $200,000 
Project Management                        $200,000
Permitting                                     $0 
State & Local Taxes (estimated)                  $683,000 
Total                                    $9,377,000 
Budget Status and Source of Funds: 
Airfield Pavement and Joint Seal: 
The airfield panel and joint seal replacement is included in the 2013-2017 capital budget and
plan of finance. The airfield panel and joint seal replacement project, CIP #102573, is part of a
multi-year program to replace deteriorating pavement panels and joint seal. The funding source
for this authorization will be existing revenue bond proceeds.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
March 22, 2013 
Page 4 of 6 
Runway Pavement: 
The funding source for the $210,000 budgeted for the replacement of panels on Runway
16C/34C will be transferred from the Aviation Division Contingency Budget. 
Financial Analysis and Summary: 
CIP Category             New/Enhancement 
Project Type              Renewal & Replacement 
Risk adjusted discount rate     N/A 
Key risk factors             N/A 
Project cost for analysis        $9,377,000 
Business Unit (BU)          Airfield 
Effect on business performance  NOI after depreciation will occur 
IRR/NPV             N/A 
CPE Impact             $0.05 in 2013, no change from business plan forecast 
Lifecycle Cost and Savings: 
Annual Operating and Maintenance costs are not anticipated to change appreciably. The replacement
of concrete panels and joint seal will result in cost avoidance for maintaining them. 
STRATEGIC OBJECTIVES: 
This project supports the Century Agenda objective to "meet the region's air transportation needs at
Sea-Tac Airport for the next 25 years" by maintaining a safe operating environment as well as
maximizing asset utilization. 
ENVIRONMENTAL SUSTAINABILITY: 
During repair and maintenance activities, various sustainable practices will be considered and
implemented when practicable. These include, but are not limited to, performing a lifecycle analysis
of materials used to ensure that resources being used and/or recycled are environmentally and
economically practical; utilizing onsite water for dust control and irrigation; the reuse of materials
such as concrete and soil; and employing low emission construction equipment. 
BUSINESS PLAN OBJECTIVES: 
This project furthers the Airport's business plan objectives to operate a world-class international
airport by ensuring safe and secure operations and by managing our assets to minimize the total longterm
cost of ownership. 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
1.  Do nothing. This alternative would result in an increasing risk of aircraft ingesting concrete
debris into aircraft engines on non-runway areas and Runway 16C/34C resulting in the
potential need for closure of ramp areas or the center runway. This alternative is not
recommended. 
2.  Replacement of pavement and joint seal material in non-runway areas. Replacement of the
most distressed concrete panels on Runway 16C/34C. This is the recommended
alternative.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
March 22, 2013 
Page 5 of 6 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
None. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
On July 24, 2012, the Commission authorized $200,000 and for the Chief Executive
Officer to complete the design and perform any advance preparatory work for the 2013
Airfield Apron Pavement Replacement project. 
On January 24, 2012, the Commission authorized $5,172,000 and for the Chief Executive
Officer to advertise and execute a construction contract for the replacement of airfield
pavement and joint seal replacement. 
On July 26, 2011, the Commission authorized $465,000 and for the Chief Executive
Officer to complete the design and perform any advance work in support of the 2012
Pavement and Joint Sealant Project for non-runway concrete pavement panels, joint seal
replacement, spall repair, and associated or temporary facilities, such as striping, lighting,
etc., on the Aircraft Operations Area. 
On March 1, 2011, the Commission authorized $6,235,000 and for the Chief Executive
Officer to advertise and execute a construction contract that included slot drain,
pavement, and joint seal replacement at the South Satellite and perform installation of
temporary common use podiums and minor removal of hazardous materials through Port
Construction Services. 
On August 10, 2010, the Commission authorized $394,000 and for the Chief Executive
Officer to direct staff to: 1) proceed with project management, design, environmental
support, and preparation of 100 percent design level construction documents for the
replacement of slot drains, pavement and joint seal at the South Satellite at Seattle-
Tacoma International Airport; 2) execute and award outside professional service
agreements; 3) pre-purchase common-use gate equipment; and 4) allow Port Construction
Services to self-perform, advertise for bids, and execute and award small works
construction contracts for common use equipment installation. 
On September 22, 2009, senior Aviation staff briefed the Commission on Seattle-Tacoma
International Airport Facility Functionality and Readiness. 
C800112  Runway 16C/34C Panel Replacement 
On July 26, 2011, the Commission authorized the Chief Executive Officer to modify the
Scope of Work for the Runway 16C/34C Surface Panel Replacement project by
extending the project period through the end of 2012, and approval of the use of
$200,000 of the previously authorized funds to prepare design documents for surface
panel replacement construction contract to be advertised and constructed in 2012. 
On February 9, 2010, the Commission authorized $5,650,000 for the design,
advertisement, and award of a construction contract for the 2010 Airfield Improvement
Projects  Contract 1, consisting of panel replacements on Runway 16C/34C. 
On February 26, 2008, the Commission authorized $450,000 for joint seal replacement
on runway 16C/34C (CIP 800112).

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
March 22, 2013 
Page 6 of 6 
Note: On October 30, 2003, runway 16 Right/34 Left (16R/34L) was renamed runway
16C/34C, in preparation for the Third Runway to assume the runway 16R/34L
designation. 
On January 14, 2003, the Commission authorized $5,000,000 for a multi-year program of
panel replacement on runway 16R/34L (CIP 102037). 
On November 26, 1996, the Commission authorized $2,000,000 for a multi-year program
of panel replacement on runway 16R/34L (CIP 100663). 
On June 13, 1993, the Commission authorized $10,422,000 for runway 16R/34L
rehabilitation and other airfield improvements (CIP 100663).

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.