5c

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      5c 
ACTION ITEM          Date of Meeting    February 5, 2013 

DATE:    January 25, 2013 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    David Soike, Director, Aviation Facilities and Capital Program 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  Airport-wide HVAC Controls Upgrade (CIP # C800497) 
Amount of This Request:   $274,000     Source of Funds: Airport Development Fund 
Est. State and Local Taxes: $148,000      Est. Jobs Created: N/A 
Est. Total Project Cost:    $2,157,000 
ACTION REQUESTED: 
Request Commission authorization for the Chief Executive Officer to proceed with the Airportwide
Heating Ventilation & Air Conditioning (HVAC) Controls Upgrade project, and direct staff
to prepare design documents. The total amount of this request is $274,000 and the total
projected cost is $2,157,000. 
SYNOPSIS: 
Commission authorization is requested to proceed with design of the Airport-wide HVAC
Controls System. The existing system controls and/or monitors a very large and spread out
system that serves the Airport terminal campus. The controls system includes the heating and
cooling, water pumping and distribution, ventilation, cooling towers, central plant, smoke
control, natural gas and water metering, and waste pumping demands of the Airport. 
The current system suffers from significant performance issues due to obsolescence and the mix
of network types and the overall number of aging devices on the serial communications network.
The existing Airport-wide HVAC Controls System network will be upgraded to a modern
ethernet based communications network that can provide sufficient bandwidth and speed to
allow operations and maintenance personnel to better manage the Airport-wide systems.
The control systems in the building facilities located at the South Logistic Center (SLC) are not
currently connected to the Airport-wide HVAC Control System. The existing serial network
does not allow for the addition of a stand-alone system such as the one controlling the SLC. The
new system will add a wireless connection to enable addition of existing facilities such as the
South Logistic Center (SLC), and it will allow the addition of stand-alone systems with separate
servers. This will include future projects in the North and South Satellite Concourses.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
January 25, 2013 
Page 2 of 6 
The existing system components and software are a Siemens proprietary system. An existing
Competition Waiver is in place that covers the Siemens system. The project specifications will
include the proprietary system and be included in the bid package. 
The design will be developed using the Mechanical-Electrical Indefinite Delivery/Indefinite
Quantity Service Agreement, which has an ordering period end date of April 26, 2014.
This project was included in the 2013  2017 capital budget and plan of finance. 
BACKGROUND: 
The existing Airport-wide mechanical system control network has been evolving over the years
and has been modified as larger mechanical system projects have been executed. The current
network consists of a mix of serial and ethernet communications that connect the servers to the
mechanical systems' field controllers. As a result, the current system suffers from significant
performance issues due to the mix of network types, obsolescence of some components, and the
overall number of devices on the serial communications network.
The existing system currently runs on a local area network which limits the flexibility in adding
stand-alone systems to the airport wide network. The system will be upgraded to an ethernet
based wide area network (WAN). The WAN allows the Airport to add separate stand-alone
systems such as the SLC control system or future systems that may be required, e.g. at the North
and South Satellites. 
In addition to the mix of systems, there are two components of the mechanical control network
that slow down processing of important data. The first component is the existing system copper
"backbone" in Concourse A. This existing copper "backbone" transmits data slowly, creating a
bottleneck. The new ethernet system will replace the copper system to provide a "backbone"
that can transmit at 100 times faster than copper. The second component is the network
hardware and switches. These also need to be replaced to increase data transmission.
The current server and a large portion of the network hardware are at the end of their
useful/supportable life (5-7 years). Technical support is no longer available for the existing
system hardware and software. The server and hardware must be replaced. 
A good faith survey will be completed. Port Construction Services (PCS) will manage the
survey. The areas in question are located in Concourse A, we don't anticipate the need for
regulated materials abatement; however, a good faith survey is required.
PROJECT JUSTIFICATION: 
This request will authorize design services to replace the existing Airport-wide HVAC Control
System with an up-to-date data delivery system that includes a new Ethernet fiber optics
"backbone," up to date hardware, new server, and updated software. The new system will
provide the needed speed and flexibility for current and future needs as well as facilitating the
addition of stand-alone systems such as the existing facilities in the SLC.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
January 25, 2013 
Page 3 of 6 
Project Objectives: 
Minimize system downtime and associated operational disruption to tenants. 
Ethernet network expansion to include Concourse A mechanical systems. The upgrade
will include major communications links over fiber optic cables. Existing 100
megabit/sec network switches will be replaced with 1 gigabit/sec network switches. 
Upgrade existing Concourse A mechanical systems field panels from serial to ethernet
communications. 
Update the current system network hardware major infrastructure.
Update system infrastructure hardware (servers and workstations) to replace old unsupported
equipment.
Replace existing server infrastructure in boiler control room, provide new racks and
environmentally conditioned space for new system server and communications
hardware. 
Update system visualization, data collection, and aging software to the latest version
and update respective support agreements as required. 
Create a new network connection to the SLC in order to incorporate the building's
mechanical equipment into the existing control and monitoring software. 
Integrate cooling tower chemical feed pumps into existing mechanical systems control
and monitoring software. 
Update or create mechanical system documentation to reflect system changes including
network record drawings. 
Complete project on time and within budget. 
PROJECT SCOPE OF WORK AND SCHEDULE: 
Scope of Work: 
The Scope of Work includes the following elements: 
Field Investigation to support design. 
Provide Good Faith regulated materials survey - design for asbestos removal 
Provide design of the Airport-wide HVAC Control Upgrade: 
o Replace the existing copper "backbone" with fiber optics. 
o  Replace the existing hardware, server, and software. 
o  Add a wireless connection to the SLC. 
Schedule: 
Commission Design Authorization           February 2013 
Commission Construction Authorization        October 2013 
Issue Notice to Proceed                    December 2013 
Construction Substantial Completion          June 2014

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
January 25, 2013 
Page 4 of 6 
FINANCIAL IMPLICATIONS: 
Budget/Authorization Summary:               Capital       Expense    Total Project 
Original Budget                         $1,800,000           $0     $1,800,000 
Budget Increase                          $357,000           $0       $357,000 
Revised Budget                        $2,157,000          $0     $2,157,000 
Previous Authorizations                         $0           $0           $0 
Current request for authorization                $274,000            $0       $274,000 
Total Authorizations, including this request         $274,000            $0       $274,000 
Remaining budget to be authorized            $1,883,000           $0     $1,883,000 
Total Estimated Project Cost                $2,157,000           $0     $2,157,000 
Project Cost Breakdown:                   This Request       Total Project 
Construction                                   $0         $1,560,000 
Construction Management                        $0          $86,000 
Design                                  $125,000         $125,000 
Project Management                        $130,000        $219,000
Permitting                                  $19,000           $19,000 
State & Local Taxes (estimated)                       $0          $148,000 
Total                                     $274,000         $2,157,000 
Budget Status and Source of Funds: 
This project, CIP #C800497, was included in the 2013  2017 capital budget and plan of finance
with a budget of $1,800,000. The original budget was developed based on a range of magnitude
and since has increased due escalation, soft cost recalculation, and addition of scope such as the
addition of the wireless connection to SLC. The budget increase will be transferred from the
Aeronautical Allowance, CIP C800404, resulting in no net change to the Aviation Division's
capital budget. The source of funds is the Airport Development Fund.
Financial Analysis and Summary: 
CIP Category             Renewal/Enhancement 
Project Type              Airport Infrastructure 
Risk adjusted discount rate     N/A 
Key risk factors             N/A 
Project cost for analysis        $2,157,000 
Business Unit (BU)          Terminal 
Effect on business performance  NOI after depreciation will increase 
IRR/NPV             N/A 
CPE Impact             $0.01 increase in 2015 
Lifecycle Cost and Savings: 
The project replaces existing electrical and communication infrastructure. By itself, this project
does not provide energy efficiency; rather the project provides better monitoring data in real

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
January 25, 2013 
Page 5 of 6 
time, which allows the maintenance staff to diagnose operational problems quicker and therefore
to remedy them quicker. Operational costs will remain the same and are factored into existing
Aviation Maintenance budgets. 
STRATEGIC OBJECTIVES: 
This project will support our Century Agenda Strategic Objective to meet the region's air
transportation needs at the Airport for the next 25 years by ensuring that the infrastructure is
operationally reliable and well controlled. 
ENVIRONMENTAL SUSTAINABILITY: 
This project demonstrates environmental sustainability by improving existing Port assets and
better utilizing existing resources. This project will replace existing equipment with new more
efficient systems. A large portion of the existing materials will be recycled. 
BUSINESS PLAN OBJECTIVES: 
The project will provide a stable, reliable infrastructure that supports the Aviation Division's
strategic goal of operating a world-class international Airport by anticipating and meeting the
growing needs of our tenants, passengers, and the region's economy. 
TRIPLE BOTTOM LINE SUMMARY: 
This project supports: 
The Airport customers by improving response time to mechanical problems which
might otherwise impact travelers comfort (air temperature, water temperature, etc.).
Operational efficiency can be improved with better control and monitoring data mined
from the various mechanical systems at the Airport. 
The environment by recycling a portion of the materials to be removed and by
installing new more efficient HVAC Control System equipment. 
The community by ensuring that the Airport is effective and efficient and therefore can
remain a financially healthy neighbor and good steward of energy among local cities.
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
Alternative 1  Leave the equipment in place and live with the slow response time, lack of real
time data. This alternative represents growing risk to the Port. If an aging component of the
system fails, then the remote monitoring and controlling function fails. HVAC systems would
still operate at the local thermostats and controllers using either the manufacturers or recent set 
points. Equipment malfunctions would not be visible to maintenance staff until customers call in
with problems such as being too hot or cold. This is not the recommended Alternative. 
Alternative 2  Replace the existing HVAC Control System with an up to date data delivery
system that includes a new fiber optics "backbone," up-to-date hardware, new server, and
updated software. The new system will provide the needed speed and flexibility for current and
future needs as well as facilitate the addition of stand-alone systems such as the facilities in the
SLC. This is the recommended alternative.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
January 25, 2013 
Page 6 of 6 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
N/A 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
N/A

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.