Item No.: 7a_supp Meeting Date: August 19, 2014 International Arrivals Facility (IAF) Program Update Second Quarter, 2014 IAF Program International Arrivals on South Satellite and Concourse A Qtr 2, 2014 2 IAF Budget Outlook Program Performance Current Budget Authorized Expended to Date Phase 1 $316,000,000 $8,500,000 $1,691,000 Phase 2 $28,000,000 0 0 Schedule % Planned 10% Actual 9% Complete Q2 Planned values for the Budget and Schedule were slightly ahead of Actual for the Q2 period. Encumbered Authorizations total $7.9M and spend rate has increased significantly during the second quarter. Q3, anticipated Budget Validation (June October): Scope, schedule and cost will be analyzed by 3 independent teams. Final budget report will be reconciled. Will report to Commission in October 2014 briefing. 3 Qtr 2, 2014 IAF Reporting Authorization to publish RFQ, procure as single design-build contract, and program funding 08/05/2014 Commission update 08/19/2014 Authorization to publish RFP 10/28/2014 Commission update 11/25/2014 Authorization to award to selected DB Team Q1 2015 Commission update Q1 2015 Presentation of conceptual designs Q2 2015 Presentation of DB validation Q3 2015 Authorization of NTP and program funding Q3 2015 Authorization to execute GMP Q3 2016 Qtr 2, 2014 4 IAF Accomplishments To Date Completion of Aviation's Connector design Planning and selected Programming effort Risk and opportunity Advertised RFQ for analysis complete Design-Build Team Development of design Commission review process complete Authorization to combine Restroom standards bridge and building workshop held procurements Sustainability US CBP Project Manager recommendations assigned workshops held Qtr 2, 2014 5 IAF In Progress Project Notebook Performance Team Program specifications Management Plan Review of Planning's Internal cost and Programming schedule validation documents effort to set target Program scope extent budget confirmation RFP for DB teams Update of general specs Progressive Design-Build for Progressive Design- contract and terms Build Prepare for MII ballot, if Selection of team co- needed location offices Qtr 2, 2014 6 IAF Issues Updated budget will be higher than preliminary budget due to refinement of scope and higher than earlier anticipated connector costs Challenges connecting with CBP's assigned Project Manager Compressed schedule for MII vote, if necessary, prior to advertisement of RFP Qtr 2, 2014 7 Next Commission Briefings/Actions October 14, 2014 Q3 2014 Briefing October 28, 2014 Scope, schedule and cost validation report Update PDB budget Authorization to advertise RFP to DB Finalists Qtr 2, 2014 8 Thank you Qtr 2, 2014 9
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.