7a Supp

Item No.:                    7a_supp 
Meeting Date:            June 10, 2014 
International Arrivals Facility 
IAF Functional Performance Criteria 
Commission Engagement Plan 
Program Success Factors 
Quarter 1, 2014, Program Update 


6/4/2014                                                                        1

IAF Functional Performance
Criteria 


6/4/2014                                                                        2

IAF Performance Objectives 
Efficient layout that optimizes airline operations
and IAF processes 
Reduced connect time for passengers and baggage
to 75 minutes 
All terminating passengers clear IAF process in no
more than 45 minutes 


6/4/2014                                                           3

IAF Planning 
Defining space program to meet regulatory
requirements and performance objectives 
Matching program scope to processing goal 
Primary inspection (1900 pax/hr in Phase 1, 2600
pax/hr in Phase 2) 
Bag claim (6 large devices in Phase 1, 8 large devices
in Phase 2) 
Increase checkpoint lanes for 15 minute wait for
transfer passengers 
Program defines minimum facility requirements
for design 
6/4/2014                                                           4

IAF Performance Opportunities 
Automated Passport Control (APC) 
kiosks for passengers from 
countries beyond U.S. and Canada 
Baggage system efficiencies 
Security checkpoint improvements for connecting
and originating passengers 
Minimize cost and maximize flexibility of future
Phase 2 improvements 

6/4/2014                                                           5

Commission Engagement Plan 
Briefings 
Communications 
Meetings 


6/4/2014                                                                        6

Commission Briefings/Communication 
Quarterly Briefings 
Design/Construction Status 
Ongoing Activities 
Budget Status 
Schedule Status 
Guaranteed Maximum Price (GMP) Status 
Other communications 
Establish Commission Liaison 
Extensive individual briefings 
Visit other Airport projects 

6/4/2014                                                           7

Commission Meetings 
July 22, 2014 
Bridge/Tunnel Recommendation 
July 29, 2014 
Authorization to procure as single contract 
Authorization to publish RFQ 
Additional funding request 
August 12, 2014 
Quarter 2, 2014 Briefing 
September 9, 2014 
Final IAF Program Definition 
Final Cost Validation 
Final Schedule Validation 
6/4/2014                                                           8

Commission Meetings (cont.) 
October 2014 
Authorization to publish RFP 
November 25, 2014 
Quarter 3, 2014 Briefing 
February 2015 
Quarter 4, 2014 Briefing 
May 2015 
Authorization to Award 
Request funding for validation phase 
Quarter 1, 2015, Briefing 
6/4/2014                                                           9

Commission Meetings (cont.) 
August 2015 
IAF Conceptual Design Review 
Quarter 2, 2015 Briefing 
October 2015 
Authorization to proceed with Design & Construction 
Authorize full Program Funding 
November 2015  November 2018 Quarterly
Briefings 
August 2016 
GMP Execution 
6/4/2014                                                          10

6/4/2014                                                          11

Success Factors for 
Progressive Design Build 
Lessons Learned 
Action Plans 


6/4/2014                                                                        12

Success Factors 
1. Organizational Adaptations 
2. Timely Decision Making 
3. Detailed and Comprehensive Program Definition 
4. Stakeholder Engagement 
5. Right Partner 
6. Design Review and Control 
7. Open Book Accounting 

6/4/2014                                                          13

Success Factor: 
Organizational Adaptations 
Lessons Learned 
Create stand-alone, integrated implementation team and
empower them 
Formal and informal partnering throughout the program 
Streamline decision-making process at the working staff level 
Involve Finance and Accounting Departments 
Action Plan 
PM-CM-DB role definition 
Confirm alignment of existing CDD procedures per Res.
3605/3628 for PDB 
Implement co-location for PM/CM/DB team 

6/4/2014                                                          14

Success Factor: 
Timely Decision Making 
Lessons Learned 
Program buy-in from the top down 
Regular reporting to Commission and stakeholders 
Efficient decision making process 
Structured stakeholder engagement process 
Co-Location of Team 
Action Plan 
Commission Engagement Plan 
Establish Senior Management Decision Making Committee (DMC) 
Define DMC forum, responsibilities and composition 
Establish decision hierarchy and priorities 
Push decisions according to priority and to lowest level possible on
hierarchy 
Maintain and monitor decision turnaround 

6/4/2014                                                          15

Success Factor: 
Detailed and Comprehensive 
Program Definition 
Lessons Learned 
Develop complete and well crafted program definition documents 
Share ownership of the Program Definition 
Importance of DB validation process 
Action Plan 
Preparation of Program Definition currently in progress 
Identification of ancillary and/or enabling projects currently in
progress 
Comprehensive DB Validation first DB deliverable 

6/4/2014                                                          16

Success Factor: 
Stakeholder Engagement 
Lessons Learned 
Shared ownership throughout organization / team 
Structured stakeholder engagement process 
Stakeholder involvement key to making timely decisions 
Focused management of stakeholder engagement 
Action Plan 
Commission Engagement Plan 
Stakeholder Engagement Plan  in progress 
Stakeholder interviews and visioning completed, workshops ongoing 
Senior Management Decision Making Committee 
Airline Technical Rep engaged 

6/4/2014                                                          17

Success Factor: 
Design Builder Selection 
Lessons Learned 
Team selection single most important success factor 
"It's all about the people" 
Partnering and collaborative process yields the best results 
Action Plan 
Qualifications based selection process 
Organizational commitment to support selection process 
Interactive work-sessions with shortlisted teams 
Relevant experience of proposed teams key differentiator 

6/4/2014                                                          18

Success Factor: 
Design Review and Control 
Lessons Learned 
Structured stakeholder engagement 
Embrace new technologies for efficiency 
Early planning of permits and inspections 
Action Plan 
Ongoing collaborative reviews / DMC reviews 
Ongoing cost estimating and reconciliations 
Extensive use of Building Information Modeling 
Extensive use of electronic collaboration tools 
Rigorous requirements for design QA/QC 
Peer reviews 

6/4/2014                                                          19

Success Factor: 
Open Book Accounting 
Lessons Learned 
No surprises mentality 
Transparency 
Establish an affordable budget 
GMP collaboration 
Select DB team with open book 
"culture" 
Trust but verify 
Action Plan 
Experience with open book included in qualifications based DB
selection 
Contract will spell out open book requirements / practices 
GMP fully transparent process 
GMP will further clarify definitions for costs, reserves, etc. 
6/4/2014                                                          20

IAF Program 
International arrivals
on South Satellite
and Concourse A 
Bridge or tunnel
connection from
South Satellite to
Concourse A IAF 

Qtr 1, 2014                                                                     21

IAF Budget Status 
Financial data as of end of Q1, 2014 

International    Current Estimate        Current       Expended to     Estimate at
Arrivals Facility                       Authorizations         Date         Completion 
Phase 1      $316,000,000     $8,500,000     $281,000    $316,000,000 
Phase 1 (2014-2018) to provide the entire building envelope, sterile corridors, a connector (bridge or tunnel)
between the South Satellite and FIS, and interior improvements to accommodate short term growth projections.
Anticipated completion during 4th quarter of 2018. 
Phase 2      $28,000,000         $0          $0      $28,000,000 
Phase 2 (2019-2023) expands the FIS facility in time to accommodate long term growth and completes
improvements in the International Arrivals Facility to expand throughput capacity. 



Qtr 1, 2014                                                                 22

IAF Metrics 
Financial data as of end of Q1, 2014 

Program Performance     Current Budget        Authorized        Expended to Date 
Phase 1 & 2          $344,000,000       $8,500,000         $281,000 
Schedule %
Planned 4%                     Actual 4% 
Complete 
Planned values for the Budget and Schedule reflect early programming targets and assumed earlier resource
availability than has occurred. Spending rate has increased significantly during the second quarter. 



23     23

IAF Schedule 
2014    2015   2016    2017    20182018
Q1 Q2 Q3  Q4  Q1 Q2  Q3  Q4 Q1 Q2  Q3  Q4  Q1  Q2 Q3 Q4
Executive Summary           Program Definition
Planning
Cost/Schedule Validation & Project Notebook
Design Standards, Requirements & Visioning
DB Firm Procurement
RFQ Auth. Schedule                         DB Firm Selected
Auth. RFP
DB Contract Negotiationon
DB Award Authorization             DB Concept Design & Cost/ Schedule Validation
Time Now
Design (to budget)
Subcontractor Procurement
Design/Construction Authorization
Construction
IAF Open
Commissioning & Closeout
Final Completion


Qtr 1, 2014                                                                 24

IAF Accomplishments 
(Narrative for 01/2014  05/2014) 
Hired a new IAF Program  Finalized staffing plan for
Leader               project management staff 
Obtained Commission    Held 21 stakeholder
Authorization to allow the   interviews for program
Sustainable Master Plan    definition development 
consultant to complete    Developed risk and trend
planning and project      registers, regular trend
definition               meetings established 
Three IAF Port staff team  Selected Airline Technical
members passed Design   Rep 
Build Institute of America  Presented Project Delivery
(DBIA) certification exams   Briefing for Port Commission 

Qtr 1, 2014                                                                     25

IAF In Progress 
(Narrative for 01/2014  05/2014) 
Stakeholder kick-off meeting 
Construction management
staffing plan 
Workshops with stakeholders for
further program definition 
Enabling projects identification;
interior and exterior           Coordination meetings with
Project Notebook development    CBP, TSA and other
Request for Qualifications (RFQ)   regulatory stakeholders 
for the Design-Build team       Program budget conversion
Tunnel or bridge decision        from design-bid-build
template to PDB template 
Planning/ programming analysis
with Sustainable Master Plan
Qtr 1, 2014                                                                     26 
consultant

IAF Issues 
Additional technical analysis of the South
Satellite to Concourse A connector will
delay bridge or tunnel decision and
advertisement of RFQ 
Program budget may increase due to new
scope being added to the IAF, such as airline
moves 

Qtr 1, 2014                                                                 27

New International Service 
(insert photo of turret salute) 


June 2, 2014 
Delta Air Lines -Seattle to Seoul 


6/4/2014                                                          28

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.