6a
COMMISSION AGENDA MEMORANDUM Item No. 6a ACTION ITEM Date of Meeting August 8, 2017 DATE: July 31, 2017 TO: Dave Soike, Interim Executive Director FROM: Jeffrey Brown, Director, Aviation Facilities and Capital Programs Mike Tasker, Senior Manager, Aviation Facilities and Infrastructure Wayne Grotheer, Director, Aviation Project Management Group SUBJECT: South Satellite Structural Improvements (CIP #C800818) Amount of this request: $550,000 Total estimated project cost: $4,150,000 ACTION REQUESTED Request Commission authorization for the Executive Director to (1) authorize an additional $550,000 for the South Satellite Structural Improvements project at Seattle-Tacoma International Airport for a total estimated project cost of $4,150,000, (2) advertise and execute a major works construction contract, and (3) utilize Port crews to assist with the project. EXECUTIVE SUMMARY This project will address existing structural overload conditions at the South Satellite (SSAT) building. The SSAT was built in 1970 and expanded in 1984. Recent structural analyses have shown that the existing building dead load (i.e., weight of the built facilities) and live load (i.e., weight of the people in the building) exceed the capacity of the existing SSAT structure per current building codes. The project has experienced some cost growth due to the construction market, additional costs to address unknown utilities and systems, and a scope increase to support another project in the SSAT building. JUSTIFICATION This project addresses a structural overload condition in the SSAT building as identified by current building codes. This project contributes to the Port's Century Agenda strategic objective to advance this region as a leading tourism destination and business gateway. The fifteen international gates at the SSAT are fundamental to the Port's goals to double the number of international flights and destinations and meet the region's air transportation need at Seattle- Tacoma International Airport (STIA) for the next 25 years. Template revised September 22, 2016. COMMISSION AGENDA Action Item No. 6a Page 2 of 5 Meeting Date: August 8, 2017 DETAILS The SSAT Structural Improvements project will address the existing dead and live load structural overload conditions in the SSAT building by completing a number of structural improvements to columns and beams on the concourse, international corridor, and ramp levels of the building. The project will not address lateral load (i.e., wind and seismic) structural requirements. In November 2016, the Commission authorized a total of $3,600,000 for the design and construction of the project. At that time, two significant risks were identified and additional project contingency was included in the estimated project cost for these risks. The two risks were the existing construction market and the need to relocate unknown utilities and systems to support the work. On August 8, 2017 the Commission will also be requested to authorize the construction of the South Satellite Heating Venting and Air Conditioning (HVAC) Upgrade project. That project will replace key components of the SSAT HVAC system including the air handlers and distribution boxes serving the concourse level. In order to support the construction phasing required to maintain existing building operations, temporary HVAC units need to be brought in for several months and placed on the roof of the SSAT building. This additional equipment on the roof will increase the dead load of the building. The two project teams coordinated on the location of the units and as a result only one additional column location on the concourse level needs to be strengthened to support the temporary HVAC units. Given the nature of the construction work involved, this additional structural upgrade is most efficiently accomplished by this SSAT Structural Improvements project. The estimated project cost has increased by $550,000 to $4,150,000 which is attributed to three issues: 1) the existing construction market, 2) relocation of unknown utilities and systems to support the work, and 3) a scope increase. Activity in the construction market continues to rise and subcontractors to support the work are in limited supply. The market impact has increased beyond staff expectations and represents 64% of the project cost increase. As the project team began identifying the unknown utilities and systems to be relocated, it became apparent that the impacted HVAC systems were more complex than anticipated. These costs have increased beyond the original identified project contingency and represent 9% of the project cost increase. The additional column strengthening to support the temporary HVAC units represents the remaining 27% of the project cost increase. Scope of Work The scope of work includes beam to column strengthening at 26 locations, column strengthening at 13 locations, and haunch to column strengthening at four locations. A number of other systems will need to be relocated to support the construction effort and include Wi-Fi antennas, conveyer controls, tug charging stations, door optical sensors, 400Hz electrical power conduits, mechanical piping, heating and ventilation ductwork, and other electrical and communication conduits. Asbestos abatement will also be required in Template revised September 22, 2016; format updates October 19, 2016. COMMISSION AGENDA Action Item No. 6a Page 3 of 5 Meeting Date: August 8, 2017 support of the work. The majority of the work will be completed through a major works construction contract. The portion of work on the concourse level will be completed by Port Construction Services (PCS) and small works contracts since this work needs to be coordinated with the Airport Dining and Retail tenant construction effort. In June, Port PM staff, along with the Small Business Group , and the Central Procurement Office, had conducted an outreach and training effort through PortGen. This early effort was to maximize small business knowledge and the promotion of those potential opportunities within the scope of work. Additional outreach efforts will be conducted to continue small business interest and preparation in anticipation of this project. Schedule Due to the increase in project costs, the project now requires approval from the airlines through the majority-in-interest vote. This effort is currently underway and assuming approval by the airlines, the anticipated schedule is summarized below. Activity Construction start 2018 Quarter 1 Construction complete 2018 Quarter 3 Cost Breakdown This Request Total Project Design $0 $795,000 Construction $550,000 $3,355,000 Total $550,000 $4,150,000 FINANCIAL IMPLICATIONS Cost Estimate/Authorization Summary Capital Expense Total COST ESTIMATE Original estimate $1,000,000 $0 $1,000,000 Previous changes net $1,880,000 $720,000 $2,600,000 Current change $720,000 ($170,000) $550,000 Revised estimate $3,600,000 $550,000 $4,150,000 AUTHORIZATION Previous authorizations $3,050,000 $550,000 $3,600,000 Current request for authorization $550,000 $0 $550,000 Total authorizations, including this request $3,600,000 $550,000 $4,150,000 Remaining amount to be authorized $0 $0 $0 Template revised September 22, 2016; format updates October 19, 2016. COMMISSION AGENDA Action Item No. 6a Page 4 of 5 Meeting Date: August 8, 2017 Annual Budget Status and Source of Funds The SSAT Structural Improvements project (CIP #C800818) was included in the 2017-2021 capital budget and plan of finance with a total capital budget of $2,880,000. The cost increase is attributed to continued growth in activity in the construction market, additional costs for the relocation of unknown utilities and systems, and additional column strengthening scope. Additional capital budget of $720,000 was transferred from the Aeronautical Allowance (CIP #C800753), resulting in no net change to the capital budget. The expense budget savings of $170,000 is attributed to the reduction in asbestos abatement scope and is considered an environmental remediation liability. Both the capital and expense portions of this project will be funded by the Airport Development Fund. Financial Analysis and Summary Project cost for analysis $4,150,000 Business Unit (BU) Terminal Building Effect on business performance NOI after depreciation will increase (NOI after depreciation) IRR/NPV (if relevant) N/A CPE Impact $0.03 in 2018 (RMM) and $0.01 in 2019 Future Revenues and Expenses (Total cost of ownership) No future revenues or expenses are anticipated as a result of the completion of this project. ADDITIONAL BACKGROUND The SSAT Renovations project is currently exploring alternatives for the complete renovation of the SSAT building to meet long-range capacity and customer experience goals. The SSAT Renovation project will also address the lateral load structural requirements since they are integral to the renovated building structure. There is limited risk that the structural improvements completed by the SSAT Structural Improvements project would be demolished by this future renovation effort. Airport Dining and Retail has completed the competitive solicitation process for units in the SSAT. This includes unit SS-7 an upscale bar with food, unit SS-2A a gourmet coffee unit, units SS-2B and SS-2C quick service restaurants, food court seating, and optional food services in the SSAT. The structural improvements on the concourse level that are the subject of this request are located within three of the dining units (SS-2A, SS-2B, and SS-2C) and adjacent to the public restrooms. This work is planned to be completed by PCS and small works contractors and will be coordinated with the planned tenant build-out of these areas to minimize disruption to public areas. These structural improvements are anticipated to be complete by second quarter 2018. Template revised September 22, 2016; format updates October 19, 2016. COMMISSION AGENDA Action Item No. 6a Page 5 of 5 Meeting Date: August 8, 2017 ATTACHMENTS TO THIS REQUEST None PREVIOUS COMMISSION ACTIONS OR BRIEFINGS November 8, 2016 The Commission authorized the Chief Executive Officer to (1) prepare design and construction bid documents for the South Satellite Structural Improvements project at Seattle-Tacoma International Airport, (2) advertise and execute a major works construction contract, and (3) utilize Port crews for an estimated $3,450,000 Template revised September 22, 2016; format updates October 19, 2016.
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.