9a CIP Report

Item No:      9a_Attach
Meeting Date: December 11, 2018




Capital Improvement Projects
Third Quarter Report 2018

ii  Port of Seattle 3Q 2018 Report

Port of Seattle
Capital Improvement Project Report
Third Quarter 2018
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic 
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the 
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high 
level information on the status of the Port's capital projects.
Background
During 2018, the Port plans to invest $895,100,000 to expand and upgrade the infrastructure that supports marine and
aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping companies,
airlines, rental car companies, concessionaires and public parking. About 2 percent of the Port's capital budget comes
from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in transportation
facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means 
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule, 
budget, change orders, risks, budget transfers, and cost growth of construction if it exceeds 10% of contract. The
report may include graphics that report project costs compared to authorization, construction costs (including change
orders (CO)) compared to the construction contract, location maps, and photographs. The Port implements a number
of different types of projects and not all information may be relevant to a specific project; as such, the reports may vary
in detail and content. Project types may range from construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase, 
and estimated completion date (substantial completion). This section also includes "Project Status" illustrating at a 
glance if the project is on schedule, and within budget, and the date Construction authorization received.
Significant Developments covers items such as accomplishments, significant events or milestones, contract 
advertisements and awards, upcoming activities, and environmental issues.
Schedule includes information on the project schedule, the total schedule variance and variance since the last 
report, contract extensions, and information on critical dates.
Budget addresses the total project budget and includes information on the overall budget status, recent
Commission  authorizations, forecasted overruns or savings, and scope changes.
Change Orders provides information on current quarter's COs and total project Cos, including justification for CO's for
the reporting period and information on any CO over $200,000 or 10% of the contract value.
Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
Budget Transfers reports any transfers between authorized projects during the reporting period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These 
reports intend to meet the reporting requirements of Port of Seattle General Delegation of Authority and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page on the Port of Seattle web site to ask a question, make a comment or
request a copy of the State Audit Reports Response and Action Plan.


Port of Seattle 3Q 2018 Report  1

Charts from PowerPoint
Project Title                        Page
CDD Projects by Status Chart.....................................................................6
CDD Projects by Dollar Value Chart...........................................................7
Aviation
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C101107 ................160th GT Lot ..........................................................8 ........... ...............
C102112 ................Service Tunnel Renewal Rep ................................9 ...........
C102162 ................Air Cargo Road Safety Improvements..................10 ......................... 
C800061 ...............Main Terminal South Low Voltage ........................11 ..........
C800335 ...............EGSE Electrical Charging Stations ......................12 .........................
C800483 ...............Aireld Pavement Program ............................... 13-14 ........
C800556 ...............NorthSTAR North Satellite Lobbies ......................15 ..........
C800583 ...............International Arrivals Facility ................................16 ..........
C800585 ...............Wi-Fi Enhancement for Ramp and Terminal ........17 ............................................ 
C800605 ...............Security Exit Lane Breach Control Phase II .........18 .........................
C800612 ...............Checked Baggage Recap/Optimzation .............19-20.......................
C800638 ...............Dining and Retail Infrastructure Modernization ....21 ..........
C800642 ...............CCTV Camera Data Improvements ....................22 ..........
C800655 ...............IWS Segregation Improvements ..........................23 ......................... ..................
C800658 ...............Mechanical Energy Conservation ........................24 ..........
C800688 ...............Construction Logistics Expansion ........................25 .........................
C800695 ...............C3 Holdroom Expansion ......................................26 .........................
C800697 ...............Concourse B, C and D Restroom Upgrades ........27 ..........
C800699 ...............Electric Utility SCADA Utility .................................28 ......................... ..................
C800702 ...............2015-2016 C Concourse Roof Repl .....................29 .........................
C800717................N. Terminal Utilities Upgrade ................................30 .........................
C800722 ...............CTE Infrastructure Upgrades ...............................31 ......................... 
C800724 ...............Concourse C New Power Center .........................32 .........................
C800760 ...............Auburn Mitigation Rd Removal.............................33 .........................
C800761 ...............Concourse B Ramp Level Holdroom ....................34 ......................... 
C800762 ...............Telecommunications Meet Me Room ...................35 ......................... .................... 
C800769 ...............Concourse D Hardstand Terminal ........................36 .........................
C800779 ...............Safedock Upgrade and Expansion .......................37 ......................... 
C800781 ...............SSAT Narrow Body Conguration ........................38 ..........



2  Port of Seattle 3Q 2018 Report

Aviation, cont.
Overall Project      Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C800784 ...............Emergency Generator ..........................................39 ........................ ..................
C800789 ...............Garage Plazas and Elevators...............................40 ..........
C800793 ...............PLB Renew and Replace Phase 2 .......................41 .................................................. 
C800798 ...............SSAT HVAC Infrastructure Upgrade ....................42 ..........
C800801 ...............Variable Frequency Drive .....................................43 ..........
C800811 ...............Chiller Panel Upgrade ..........................................44 ..........
C800818 ...............SSAT Structural Improvements ............................45 .........................
C800826 ...............ARC Flash Hazard Mitigation ...............................46 ......................... 
C800833 ...............Holdroom Seating For Concourses B and C ........47 ..........
C800834 ...............Ground Based Augmentation System Upgrade ...48 .........................
C800841 ...............Tenant Telecommunications DEMARC Upgrade .49 ..........
C800842 ...............AOA Perimeter Fence Line Standards Comp ......50 ..........
C800845 ...............C1 Building Expansion .........................................51 ..........
C800846 ...............ADR Kiosk Program Expansion 1 ........................52 .........................
C800862 ...............Terminal Security Enhancements ........................53 .........................
C800870 ...............Parking Revenue Infrastructure ............................54 ......................... 
C800873 ...............Concourse B Gate Reconguration .....................55 ..........
C800876 ...............Fire Station Westside............................................56 ..........
C800880 ...............Employee Security Screening ..............................57 ..........
C800883.................Delta Inflight Services Tenant Reimb Agmt .........58..........................
C800886 ...............Central Terminal Enhancements ..........................59 .........................
C800898 ...............Airport Signage Phase 1 ......................................60 ..........
C800914 ...............Taxiways ABLQ Improvements ............................61 ..........
C800920 ...............ASL Converstion at Checkpoints ..........................62 .........................
C800925 ...............Zone 3 Common Use Counters ............................63 ..........
C800950 ...............FedEx TRA ...........................................................64 .......... 
C800977 ...............RCF Pavement Remediation ................................65 ......................... 
C800980 ...............SD Pond Bird Deterrent Improvement ..................66 ..........
C800982 ...............CDD and CPO Oce Relocations .......................67 .........................
C800986 ...............Concourse C Space Ramp Renovation ...............68 ..........
E104395-6 ............Lora Lake ..............................................................69 .......... ............... 
E105827 ................STIA Emergency Water Main ...............................70 ..........
U00225 .................Flight Corridor Safety Prog Ph 1 ..........................71 .........................
U00239 .................NERA Program .....................................................72 .......... ...............
U00356 .................Flight Corridor Safety Program Phase 2 and 3 ....73 .........................




Port of Seattle 3Q 2018 Report  3

Other Aviation
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C200007................. Highline School Noise Insulation........................... 74 .........................
C200094 ...............Single Family Sound Insulation ............................75 ..........
C200095 ...............Condominium Sound Insulation ...........................76 ..........
C800154 ...............Tenant Reimbursement ........................................77 ..........

Maritime
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C800355 ...............Shilshole Bay Marina Paving................................78 ......................... ..................
C800356 ...............Shilshole Tenant Service Buildings .....................79 ......................... ..................
C800445 ...............SBM Site Pad Redevelopment .............................80 ..........
C800525 ...............FT Redevelopment Phase I ..................................81 .........................
C800526 ...............FT Net Sheds 3, 4, 5 & 6 Roof Replacement .......82 .........................
C800531 ...............FT Docks 3, 4, 5 & 6 Fixed Pier Impr ...................83 ..........
C800675 ...............P91 South End Fender .........................................84 ..........
C800895 ...............T-18 Stormwater Outall Renewal & Repl ..............85 ..........
C800910 ...............T-91 StandoBarges ............................................86 ..........
E104324 ................Viaduct Construction Coordination ......................87 ..........
U00218 .................P66 Alaskan Way Street Improvements ...............88 ..........
Economic Development
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C800887 ...............P69 Commission Chamber Refresh .....................89 ..........
C800888 ...............P69 Solar Panel System .......................................90 ......................... 
C800889 ...............BHICC Interior Modernization ........................... 91-92........
Joint Venture
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C102858 et al ....... Street Vacations T-5/18/105 .................................93 .........................
C800546 ...............Argo Yard Truck Roadway ....................................94 .........................
C800620-U00064 T-46 Permit Mitigation ..........................................95 .........................
E102007 ............... East Marginal Way Grade Separation..................96 .........................
U00289 .................T-5 Pile Removal ..................................................97 .......... 

4  Port of Seattle 3Q 2018 Report

Corporate
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C800728 ...............Parking System Replacement ..............................98 .........................
C800729 ...............Vessel Moorage System .......................................99 .........................
C800747................Project Delivery System ......................................100 ........................ 
C800748 ...............Remote Data Ctr Business Continuity .................101 ........................
C800782 ...............Airport Subway System Information Displays .....102 .........
C800788 ...............Airport Data Network Switch Upgrade ................103 ........................
C800790 ...............Checkpoint Wait Time..........................................104 ........................
C800800 ...............SEA Smartphone App .........................................105 ........................
C800907 ...............Supplier Outreach and Procurement System .....106 .........
C800909 ...............PeopleSoft Financials Upgrade ..........................107 .........
C800929 ...............Rental Car Facility Fleet Tracking System ..........108 .........
C801012 ................Radio System Upgrade .......................................109 .........
C801027 ...............Airport Building Controls System Upgrade .........110 .........

Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are o
Both target schedule & budget are o
Negative Variance Status
New Variance
Previously Reported
Schedule Completion on the Project Reports refers to:
Benecial Occupancy or Last Asset In-Use date








Port of Seattle 3Q 2018 Report  5

6  Port of Seattle 3Q 2018 Report

Port of Seattle 3Q 2018 Report  7

THIRD  QUARTER REPORT, 2018
So. 160th  GT Lot Expansion
Project : C101107                      Improve lot drainage and complete      Project Status:
Budget:  $4,326,533                 site fencing and landscaping,           Schedule:  Delayed
Phase:  Construction                 rehabilitate the Ground Transportation   Budget:  On or Under
Start:  2/1/2013                         (GT) Lot building, underground          Status Reset: 9/26/2017
Schedule Completion: 9/30/2018       existing overhead utility lines            (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Substantial completion was achieved by Colvos Construction (100% SBE) in
5      4.3
late September. The GT Lot building received new restrooms, kitchenette,
interior refresh, electrical, HVAC and roof. This is the final quarterly report for     Dollars in Millions  4               3.4
2.8
this project.                                                                                  3
2
Schedule                                                           1
GT Lot building rehabilitation was removed from the project scope in 2015 and      0
restored by the Commission on September 26, 2017. Delays occurred during           Authorized  Forecasted    Costs
final permitting. Work was completed in Q3 2018.                                                       Incurred
Budget                                                      Construction Costs
Project is under budget with savings of $800,000 to be returned in Q4.                 1
0.8
0.7
Change Order                                                  0.8
Current Quarter       Project Total
0.6
Number of COs                7                   10                   0.4
Amount of COs            $15,987.47           $32,607.45             Dollars in Millions  0.2           0.0
Justification for COs: Varying site conditions (roof framing), errors &                  0
Initial     Change     Spent
omissions, regulatory requirements (building insulation), and scope change                        Orders
(toilet partitions).
Photo
Risks
None identified.
Budget Transfers
Amount            From              To
$0

Completed restroom improvements

AIRPORT
8  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT,                                                                            THIRD  QUARTER REPORT, 2018
So. 160th  GT Lot Expansion                                                                           Service Tunnel Renewal/Replace
Project : C101107                      Improve lot drainage and complete      Project Status:                       Project : C102112                      Project will seismically retrofit and      Project Status:
Budget:                            site fencing and landscaping,           Schedule:  Delayed                 Budget:  $39,505,000                structurally strengthen the airport        Schedule:  Within or Ahead 
Phase:  Construction                 rehabilitate the Ground Transportation         t:  On or Under              Phase:  Construction                 Service Tunnel located between the      Budget:  On or Under
Start:  2/1/2013                         (GT) Lot building, underground           tatus Reset: 9/26/2017               Start:  11/4/2012                        Main Terminal and Airport Garage.      Status Reset: 7/25/2017
Schedule Completion: 9/30/2018      existing overhead utility lines            Commission Construction Auth.)         Schedule Completion: 9/3/2020                                            (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred           Significant Developments                                           Budget/Costs Incurred
Substantial completion was achieved by Colvos Construction (100% SBE) in                                           Construction continues within the southern portion of the Service Tunnel and
late September. The GT Lot building received new restrooms, kitchenette,                                                                                                                                   50
along the south portion of the Courtesy Van Plaza located in the Main Garage.             39.5      39.5
interior refresh, electrical, HVAC and roof. This is the final quarterly report for                                              At the end of Q3, construction was 40% completed with 12% of the work             40
this project.                                                                                                                          accomplished in the quarter.                                                               30
16.5
20
Schedule                                                          Dollars in Millions                              Schedule                                                          Dollars in Millions  10
GT Lot building rehabilitation was removed from the project scope in 2015 and                                          Schedule delay may occur due in part to a lack of access to Air Cargo Rd. S.          0
restored by the Commission on September 26, 2017. Delays occurred during           Authorized  Forecasted    Costs          Various strategies are being reviewed for schedule recovery; however project           Authorized  Forecasted    Costs
final permitting. Work was completed in Q3 2018.                                                      Incurred         completion in Q2 2020 is in jeopardy.                                                                  Incurred
Budget                                                      Construction Costs             Budget                                                      Construction Costs
Project is under budget with savings of $800,000 to be returned in Q4.                                                    Project is forecasted to be completed within budget.                                   30
24.0
Change Order                                                Dollars in Millions                            Change Order                                                Dollars in Millions  25
20
Current Quarter       Project Total                                                                    Current Quarter       Project Total              15                  10.5
Number of COs                                    10                                                  Number of COs                5                   25                    10
Amount of COs                                                                                       Amount of COs            $300,779.26          $525,539.36               5           0.5
Justification for COs: Varying site conditions (roof framing), errors &
Initial     Change     Spent            Justification for COs: errors and omissions (electrical).                                       0
omissions, regulatory requirements (building insulation), and scope change                                                                                                                                          Initial    Change    Spent
Orders
Orders
(toilet partitions).                                                                                                                         Risks
Photo                           Providing back-up power routing in the Loading Dock area has taken far
Risks                                                                                                                                                              Photo
more time and effort than anticipated, leading to delay and cost.
None identified.                                                                                                            Inability to access Air Cargo Rd. S. due to International Arrivals Facility
schedule delay will impact Loading Dock and North Tunnel construction,
Budget Transfers                                                                                    leading to schedule delay and cost.
Amount           From             To
$0                                                                                        Budget Transfers
Amount            From              To
$0
pleted restroom improvements
West Wall Seismic Reinforcement

AIRPORT                                                            AIRPORT
Port of Seattle 3Q 2018 Report  9

THIRD  QUARTER REPORT, 2018
Air Cargo Rd Safety Improvements
Project : C102162                       Improvements along Air Cargo Rd   Project Status:
Budget: $8,819,590                   and S 170th St to support Cell         Schedule:  Delayed
Phase:   Design                        Phone Lot and roadway operations,    Budget: On or Under
Start:   10/2/2013                        and meet current safety standards.     Status Reset: 7/11/2017
Schedule Completion: 11/2/2020                                           (Commission Design Auth.)
Significant Developments                                           Budget/Costs Incurred
Completed stakeholder outreach meetings with employee parking and rental car
10                  8.8
busing, commercial ground transportation operators, and adjacent facilities and
tenants. Design consultant completed analysis of existing and future conditions,      8
including a range of capacity improvements. Planned review and approval of       Dollars in Millions  6
3.6
recommended improvements with Port and City staff in October.                    4
2                            0.4
Schedule
0
Project restarted Q2 2017 and design is currently on schedule. Forecast                 Authorized  Forecasted    Costs
construction duration has increased.                                                                        Incurred
Budget                                                      Construction Costs
Project is currently within budget. Overall project budget includes $450,000 of      1.0
additional project contingency to address risks.
0.8
Change Order                                                 0.6
Current Quarter       Project Total            0.4
Number of Cos                  0                    0                 Dollars in Millions 0.2
0.00       0.00       0.00
Amount of Cos                 $0                    $0                 0.0
Justification for COs: None.                                                               Initial     Change     Spent
Orders
Risks
Traffic Growth T !"#$%&' ()* +,-. /01
additional intersection improvements to accommodate growth.
Unknown Utilities U 23456789 :;< =>?@ABCD EFGHIJKLMNOP QRSVWXY Z[\
relocation of a number of unknown utilities.
Budget Transfers
Amount            From              To
$0

AIRPORT
10  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Main Terminal Low Voltage
Project : C800061                    Renewal and replacement of low          Project Status:
Budget:  100,300,000              voltage (600 volts and below) electrical    Schedule:  Within or Ahead 
Phase:  Design                     distribution equipment in the Main        Budget:  On or Under
Start:  6/28/2007                     Terminal.                                 Status Reset: 7/10/2018
Schedule Completion: 5/9/2025                                             (Commission Design Auth.)
Significant Developments                                           Budget/Costs Incurred
Procurement for the Design Consultant and General Contractor Construction
Manager are in progress and will be completed within schedule.                    120             100.3
100
Schedule                                                          80
60
On Schedule.                                                                     30.7
40
20
Budget                                                        Dollars in Millions                   2.6
0
Within Budget.                                                                   Authorized  Forecasted    Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
Not Applicable
Number of COs                0                   0
Amount of Cos                 $0                    $0                 Photo
Justification for COs: None
Risks
None.
Budget Transfers
Amount            From              To
$0




AIRPORT
Port of Seattle 3Q 2018 Report  11

THIRD  QUARTER REPORT, 2018
Electrical Ground Support Equipment (EGSE) Electrical Charge Stations
Project : C800335                      Airport-wide electrical charging       Project Status:
Budget: $30,700,000                 system for electrical ground support    Schedule:  Delayed
Phase:   Construction                 equipment at the Concourses and the   Budget: On or Under
Start:   10/26/2010                     North and South Satellites.             Status Reset: N/A
Schedule Completion: 6/4/2021                                            (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
B6 GSE Coral is currently in construction to expand from GSE charging
capacity from 4-Ports to 6-Ports. Design is remobilized to complete                 35              30.7
construction documents for four locations on Concourse A and five locations        30     25.6
for Concourse. Steel protection frame for Concourse A Gates A2 and A3 is        Dollars in Millions 25                       18.6
scheduled for completion latter part of Q4 2018.                                     20
15
10
Schedule                                                           5
Schedule for Phase 2 is now broken into various deliverable components to          0
Authorized   Forecasted     Costs
accommodate construction schedules for other major projects.                                            Incurred
Budget                                                      Construction Costs
Concourse B and South Satellite Currently under budget but ee]^_` abcdfg   Not Applicable
increase when design is completed for new major Power Centers Concourse.
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                    $0
Justification for COs: None
Risks
Time delays due to construction in areas that impact the GSE project.
Budget Transfers
Amount            From               To
$0

AIRPORT
12  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Airfield Pavement Program 2016-2020
Project : C800483                       This is a multi-year program to       Project Status:
Budget: $25,800,000                  replace distressed pavement and       Schedule:  Within or Ahead 
Phase:   Construction                  joint seal on the airfield starting in     Budget: On or Under
Start:   5/5/2011                          2016 through 2020.                   Status Reset: 10/9/2018
Schedule Completion: 9/30/2021                                           (Commission Design Auth.)
Significant Developments                                           Budget/Costs Incurred
2018 Airfield Pavement Replacement Project - In 2018 replaced sections of
30.000
asphalt pavement located north and west of the South Satellite with concrete                        25.8
25.000
pavement to provide sufficient support to aircrafts. Replaced 47 distressed
20.000
individual concrete panels and damaged joint seal at the touch down zones of
15.000
RW16L/34R. All work was successfully completed in early September 2018.
10.000
2.9
2019 Airfield Pavement Replacement Project - Replace sections of distressed   5.000   Dollars in Millions                        0.9
asphalt pavements located at Hardstand 7, Concourse D Terminal, Cargo 4 and    0.000
Authorized  Forecasted     Costs
South Satellite. This project is currently in design phase and is scheduled to be                              Incurred
advertised for construction bids in mid-March of 2019.
2019 Construction Costs
2020 Airfield Pavement Replacement - Replace sections of portland cement
concrete pavement that are distressed/damaged on TW B (south end), Cargo 2         1
and distressed asphalt pavement at Concourse C Terminal, Airport fire station        0.8
and Cargo 2. Scheduled for Commission Authorization for design in
November 27, 2018.                                                        Dollars in Millions  0.6
0.4
Schedule                                                           0.2
0.0     0.0     0.0
Substantial Completion of the 2018 contract Q4 2018.                                0
Anticipated date of Substantial Completion of the 2019 contract is Q4 2019.              Initial  Change  Spent
Orders
Anticipated date of Substantial Completion of the 2020 contract is Q4 2020.
Budget                                                      2018 Individual Panel
Replacement  Early High
These projects are currently within budget.
Strength Concrete
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                    $0
Justification for COs: None at this time.


Port of Seattle 3Q 2018 Report  13

Risks
Poor weather conditions will impact both the schedule and budget for the
project delivery. Close coordination with CM team to monitor weather and
develop mitigation plans, if poor weather conditions last during construction.
Budget Transfers
Amount            From              To
$0











AIRPORT

14  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
NorthSTAR North Satellite Renovation and NSTS Lobbies
Project : C800556                    Renovation and expansion of the North    Project Status:
Budget:  $672,125,232             Satellite (NSAT), including NSAT        Schedule:  Within or Ahead 
Phase:  Construction               Satellite Transit System (STS) stations     Budget:  On or Under
Start:  7/24/2012                     "refresh", ramp level, Concourse level,     Status Reset: 8/15/2017
Schedule Completion: Q3 2021    and new rooftop airline lounge.           (Commission Construction Auth.) 
Significant Developments                                           Budget/Costs Incurred
Phase 1 Taxiway A/B Reconfiguration, east taxiway vehicle service road                     TOTAL
striping and building expansion "dry-in" completed. Emergency generator            800    672.1    672.1
delivered and placed, five tenant spaces turned over for tenant construction,
passenger loading bridge delivery dates set and Phase 1 Activation plan being
600
established.                                                                             400
220.8
Schedule                                                          Dollars in Millions  200
Project remains on schedule for January 2019 Phase 1A opening                       0
Authorized  Forecasted    Costs
Budget                                                                         Incurred
Budget increased this quarter to include transfer of "savings" from C800555
Construction Costs
into NorthSTAR Management Reserve within C800556. Project currently
remains within budget.                                                                  457.7
500
Change Order                                                  400
Current Quarter       Project Total              300
Number of Cos                88                    340                  200                  144.7
Amount of Cos             $4,703,331           $10,567,416             Dollars in Millions 100           10.5
Justification for COs: holdroom casework; baggage system revisions; increase         0
MACC   Change   Spent
to contractor design development allowance; revisions to restrooms;                               Orders
Risks
Photo
Maintaining budget and schedule; complex central core phasing; exceeding
contractor design development allowance; labor shortage in critical trades;
dining and retail projects completing on time for Phase 1 opening.
Budget Transfers
Amount            hijk             lm
$1,109,600             C800555              C800556
Transfer of savings from NS Refurbish Baggage System to NSAT Management
Reserve.

AIRPnop
Port of Seattle 3Q 2018 Report  15

THIRD  QUARTER REPORT, 2018
International Arrivals Facility (IAF)
Project : C800583                    Planning, design, and construction of a     Project Status:
Budget:  $931,445,000             new          Schedule:  Within or Ahead 
Phase:  Construction               facility including a pedestrian walkway     Budget:  On or Under
Start:  6/25/2013                     connecting the South Satellite and seven     Status Reset: 9/26/2018
Schedule Completion: 5/31/2020    Concourse A gates to the new IA        (Commission Authorization of GMP)
Significant Developments                                           Budget/Costs Incurred
qrs tuvwxyz{ |}~       
931.4      931.4
1000
Schedule                                                           800
Project is currently on schedule and in support of IA  "   Dollars in Millions 600
Budget                                                         400               304.8
Project is currently within budget                                                     200
0
Change Orders                                                     Authorized Forecasted   Costs
Incurred
Current Quarter       Project Total
Number of COs                0                   4               Construction Costs
Amount of COs                $0                   $0
Justification for COs: None this quarter                                              1000    836.0
800
Risks                                                               Dollars in Millions 600
Potential cost and schedule impacts from forecasted shortages of materials and       400                     262.9
skill labor in the current robust Seattle construction market remains a risk. 
200
0.0
Budget Transfers                                                     0
Initial     Change     Spent
Amount                                                          Orders
$2,000,000             C800583               Expense




AIRP"
16  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Wi-Fi Enhancement
Project : C800585                      Upgrade Wi-U      Project Status:
Budget:  $10,676,000                and ramp operational areas of the        Schedule:  Delayed
Phase:  Construction                 Airport. Provide micro-distribution      Budget:   !"#$%
Start:  11/4/2012                        cabinets on the ramp of each             Status Reset: 8/8/2017
Schedule Completion: 9/27/2019       concourse to extend communications     (Commission Construction Auth.)
infrastructure.
Significant Developments                                           Budget/Costs Incurred
Construction for Baggage Claim, Bagwell,     
12      10.68
Satellite Transit System Stations is complete. Passenger loading bridge design                      10.68
Dollars in Millions 10
is 60               7.04
8
Schedule                                                           6
4
Passenger loading bridge delivery method evaluation has delayed the final           2
completion date of the project.                                                        0
Authorized   Forecasted     Costs
Budget                                                                         Incurred
Evaluation of passenger loading bridge proposed solution indicates a budget
Construction Costs
issue. Evaluating options to reduce cost and remain within budget.
3.29
3.5                           3.16
Change Order                                                 3.0
Current Quarter       Project Total            2.5
Number of COs                15                   37                  2.0
1.5
Amount of COs             ($3,467)              $75,454              1.0
Justification for COs: Existing infrastructure was able to be used resulting in        Dollars in Millions 0.5              0.08
reduced cost.                                                                      0.0
Initial     Change     Spent
Orders
Risks
The proposed passenger loading bridge solution is projected to cost more than
originally anticipated. Project team evaluating options.
Budget Transfers
Amount            F              T 
$0



AIRPA 
Port of Seattle 3Q 2018 Report  17

THIRD  QUARTER REPORT, 2018
Security Exit Lane Breach Control  Phase 2
Project : C800605                       Installation of automated security     Project Status:
Budget: $11,100,000                  breach control equipment at exits to   Schedule:  Delayed
Phase:   Design                        Concoursee> ?@ B CDE GHIJK LMN      Budget: On or Under
Start:   10/15/2015                      South Satellite Transit System         Status Reset: 7/12/2016
Schedule Completion: 7/27/2020       exits.                                (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Team changes have been completed to bring relevant experience to bear on the            11.1      11.1
12
development of the proposal documents.
10
Schedule                                                           8
6
Project has been delayed pending resource availability.                                                       3.2
4
Budget                                                        Dollars in Millions 2
0
No change in budget status.                                                           Authorized  Forecasted    Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
Number of COs                 0                   0               None at this time
Amount of COs                $0                   $0
Photo
Justification for COs: None
Risks
Risk remains that there may be limited response to the RR& '()* +,-./01234
Budget Transfers
Amount            5678             9:
$0




AIRP;<=
18  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Checked Baggage Recapitalization/Optimization
Project : C800612                    TSA approached the Airport in 2012      Project Status:
Budget:  $445,050,000             with plan to replace all federally owned    Schedule:  Delayed
Phase:  Construction               and operated baggage scanning           Budget:  On or Under
Start:  2/26/2013                     equipment. In addition the project          Status Reset: N/A
Baseline Schedule Completion:     replaces the remainder of the outbound     (Commission Construction Auth.)
2/28/2025                          baggage system.
Significant Developments                                           Budget/Costs Incurred
Phase 1 - completed the new central terminal ramp and Maintenance
500               445.1
breakrooms in concourse B. The contractor has mechanically installed 218
conveyor sections and continues to construct utilities and infrastructure to          Dollars in Millions 400
support the conveyor install. The Contractor failed the controls sOPQSVW        300
Acceptance Test (XYZ[ \]^_ `ab cdfg hi jklmno pqr tuv wxy z{ |}~   200 136.3
currently rescheduled to start on November 26. The Project Team continues to                              61.7
100
attend weekly meeting in Detroit to monitor controls progress leading up to
0
rescheduled                    Authorized Forecasted Costs
Incurred
Phase 2 - designers have completed the 100      
on the permit set submittal.                                                         Construction Costs
Schedule                                                            60    52.0
Phase 1 - the Contractor is reporting a 77 day schedule delay (extending the           50
final substantial completion date for Phase 1 from 8/10/2019 to 10/26/2019, and       40
the overall program to 5/16/2025). The delay is due to a failure of the initial           30                       22.2
" "                Dollars in Millions   20
to the previously reported 3 month delay for a total estimated delay of 6               10              1.0
months.                                                                      0
Initial     Change     Spent
Actions taken by the team to mitigate and correct the delays include:                               Orders
- Additional design review meetings and on-site reviews.
- Staff travelling to Detroit weekly to oversee pretesting prior to    
- Port Managers, Department Directors, and Prime Contractor    
met quarterly on-site to discuss ways to mitigate scheduled delays.
- Port has secured warehouse space to free area of stored conveyor and speed
installation.
- Three additional BHS installation crews have been added for a total of five
crews.
Phase 2 - Design has been finali   P 
advertised to time Phase 2 start with Phase 1 completion.
Budget
The project forecast is currently within budget. Phase 1 Design/Construction
and Phase 2 Design have been authoria 
Port of Seattle 3Q 2018 Report  19

Change Order
Current Quarter       Project Total
Number of COs                3                   19
Amount of COs             $112,404             $995,175
Justification for COs: Varying site conditions and owner requested changes.
Risks
Contractor delays  Affecting overall completion date
BHS upper level controls and network architecture  As proposed by
Contractor, does not meet specification. Port requiring increased levels of
redundancy. Cost disputed.
Potential budget increase  High market demand for BHS contractors, steel
prices, small business percentage, PLA
Budget Transfers
Amount            From              To
0









AIRPORT
20  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Dining and Retail Infrastructure Modernization
Project : C800638                    Project is to provide infrastructure        Project Status:
Budget:  $15,088,000              modifications, and re-demising of        Schedule:  Within or Ahead 
Phase:  Construction               spaces in support of the Airport Dining    Budget:  On or Under
Start:  10/28/2014                   and Retail concessions plan.               Status Reset: 6/28/2016
Schedule Completion: 6/30/2020                                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Started construction on two spaces on Concourse A and D that will support
20
Lease Group #4. Completed construction to support two Lease Group #3 spaces          15.09     15.08
on Concourse D. A second children's play area has proven infeasible and will      Dollars in Millions 15
not be completed.
10
5.37
Schedule                                                           5
Capital work is driven by leasing and tenant activities. Schedule developments       0
have now brought the project within its scheduled completion.                          Authorized  Forecasted    Costs
Incurred
Budget
Construction Costs
On budget.
Not applicable
Change Order
Current Quarter       Project Total
Number of COs                0                   0
Amount of COs                $0                   $0
Justification for COs: None
Risks
Tenant delays can cause construction delays and leave project open to budget
escalation.
Budget Transfers
Amount            F              T 
$0



AIRPA 
Port of Seattle 3Q 2018 Report  21

THIRD  QUARTER REPORT, 2018
CCTV Camera and System Enhancement
Project : C800642                    Add cameras and improve the video      Project Status:
Budget:  $13,000,000              management system at the Airport.       Schedule:  Within or Ahead 
Phase:  Construction               Project funded by a TSA Other           Budget:  On or Under
Start:  11/4/2012                     Transaction Agreement (OTA) grant.      Status Reset: 5/23/2017
Schedule Completion: 12/29/2018                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Continue with camera installation; anticipated to be complete in December.
Will review remaining project budget against TSA OTA grant funding to                 13.00     13.00
14
ensure its full utilie !"#$%                       12         9.84
10
Schedule                                                          Dollars in Millions  8
6
Project remains on current schedule though should additional work be proposed      4
in order to fully utilii& '() *+, -./0 1 23456789 :;<=>?@BCD EGHIJ KL MNOQRSUVW 2
Budget                                                         0
Authorized   Forecasted     Costs
No change to budget.                                                                                 Incurred
Change Order                                               Construction Costs
Current Quarter       Project Total               6
Number of COs                4                   19                        4.88
4.50
5
Amount of COs             $40,234             $209,820                4
Justification for COs: Click here to enter text.                                            3
2
Risks                                                               Dollars in Millions   1          0.21
No change to risks. Project is advancing toward the TSA funding deadline of          0
Initial     Change     Spent
July 2019.                                                                                      Orders
Budget Transfers
Amount            From              To
$0



AIRPORT
22  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
IWS Segregation Improvements
Project : C800655                      Install  Total  Organic  Carbon  (TOC)  Project Status:
Budget: $1,142,000                   analyzers  into  the  exisiting  Industrial   Schedule:  Delayed
Phase:   Design                        Wastewaster conveyance system serving   Budget: Forecast Overrun
Start:   8/1/2016                          the Terminal Areas of the Airport.           Status Reset: 7/31/2018
Schedule Completion: 10/8/2019                                                (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Decision made to deliver project via major works construction contract.                             2.4
Dollars in Millions 2.5
Schedule                                                           2
1.5      1.1
Schedule delayed due to limited staff resources, change in delivery method, and
the need to align the construction schedule with the summer "dry" season.            1
0.5                           0.26
Budget                                                         0
Authorized   Forecasted     Costs
Budget overrun due to a necessary change in delivery method from small works                          Incurred
self-performance to major works construction low bid.
Construction Costs
Change Order                                               Not Applicable
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                    $0
Justification for COs: None
Risks
None
Budget Transfers
Amount            XYZ[ \]
$0



AIRP^_`
Port of Seattle 3Q 2018 Report  23

THIRD  QUARTER REPORT, 2018
Mechanical Energy Conservation
Project : C800658                       Perform ESCO audit, identify and    Project Status:
Budget: $7,121,000                   prove savings, design and construct    Schedule:  Within or Ahead 
Phase:   Construction                  project.                            Budget: On or Under
Start:   6/24/2014                                                               Status Reset: 7/25/2017
Schedule Completion: 9/30/2019                                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
ESCO contractor has struggled to complete the 100% design set required for
8      7.1        7.1
permitting. Construction start has been delayed due to permit and acceptance of
preconstruction submittals.                                                           6
Schedule                                                           4
Project risks falling behind schedule.                                                Dollars in Millions  2                        0.5
0
Budget                                                           Authorized  Forecasted   Costs
Incurred
Project is on budget.
Change Order                                               Construction Contract Costs
Current Quarter       Project Total               4    3.6
Number of COs                 0                   0
3
Amount of COs                $0                   $0
Justification for COs: None                                                             2
Risks                                                               Dollars in Millions   1
0.2
0.0
None.                                                                    0
Initial     Change     Spent
Orders
Budget Transfers
Amount            bcdf             gh
$0
Cost of Construction Growth
Not Applicable.


AIRPjkl
24  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Construction mnopqrstu vwxyz{|}~
Project : C800688                      The expansion and reconfiguration of     Project Status:
Budget:                    the existing construction logistics         Schedule:  Delayed
Phase:   Closeout                    facilities (including the contractor         Budget:  On or Under
Start:   8/1/2014                         parking lot and associated bus stops)       Status Reset: 2/23/201
Schedule Completion: 12/31/2018     and the renovation of Port field offices.     (Commission Construction Auth.) 
Significant De          Budget/Costs Incurred
Construction is complete and completion memos have been issued for the
10.0
Contractor Parking Lot (CPL), Logistics Lots, Field Office Renovation, and                9.6
CPL Bus Stops. CPL, Logistics Lots, and CPL Bus Stops are closed out. Field        9.5
Office is in closeout. Warranty items were addressed with the replacement field      9.0
8.5
office (changed scope) and final payment will be made Q4. This is the final          8.5                     8.2
quarterly report for this project.                                                        Dollars in Millions  8.0
Schedule                                                           7.5
Authorized  Forecasted    Costs
The overall project schedule was delayed with completion dates of Q1 2017 for                           Incurred
CPL Bus Stops (delays due to weather and errors and omissions), and Q4 2017
for the replacement field office (delay due to scope change and procurement).     Construction Costs
Budget                                                          6
4.9
Dollars in Millions    5                          4.4
Project forecast is within the revised budget. Anticipate additional final
4
closeout savings with Field Office Renovations in Q2 2019.
3
Change Order                                                   2
1                0.1
Current Quarter       Project Total               0
Number of COs                0                   69                        Initial   Change   Spent
Amount of COs                $0                 $99,533                           Orders
Justification for COs: None this quarter.
Photo
Risks
None.
Budget Transfers
Amount                         
$0                                                        Replacement Field Office
Cost of Construction Growth
CPL Bus Stops: Additional project contingency was included within the project
budget for unknown substandard pavement risk. Two change orders were
issued representing 13.8% of the original contract value.
AIRP
Port of Seattle 3Q 2018 Report  25

THIRD  QUARTER REPORT, 2018
C3   "
Project : C800695                       Provide a 1,500 sf building addition  Project Status:
Budget: $6,300,000                   to increase the size of          Schedule:  Delayed
Phase:   Design                        passenger holdroom. Provide 1    Budget: On or Under
Start:   4/4/2016                          sf renovation of existing holdroom.    Status Reset: 7/11/2017
Schedule Completion: 3/15/2020                                           (Commission Construction Auth.)
Significant De          Budget/Costs Incurred
Evaluating options to complete project using alternate means.
7.0      6.30        6.30
Schedule                                                          6.0
5.0
Project is on hold.                                                                      4.0
3.0
Budget                                                        Dollars in Millions 2.0                 0.86
On budget.                                                                   1.0
0.0
Authorized   Forecasted      Costs
Change Order                                                                  Incurred
Current Quarter       Project Total
Number of COs                 0                   0               Construction Costs
Amount of COs                $0                   $0                None currently.
Justification for COs: None
Risks
None currently.
Budget Transfers
Amount            "             
$0




AIRP
26  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Concourse B, C, and D Restroom 
Project : C800697                       Renovate eight sets of public         Project Status:
Budget:     restrooms on Concourses Br  Schedule:Within or Ahead 
Phase:   Design                        D. Increase the size of a portion of    Budget: On or Under
Start:   7/12/2016                        the existing restroomst !"# %&'      Status Reset: CDEGHIJKL
Schedule Completion: 3/31/2022       restrooms( )*+,- ./012 345 6789:;<=>   (Commission Construction Auth.)
existing tenant functionse ?@B
enlarge the building to add one
additional new set of restrooms.
Significant De          Budget/Costs Incurred
This is a five-phase project:
50
Phase one complete. Phase two design complete and advertisement imminent.      Dollars in Millions               38.4
Phase three design complete and FAA review underway. Advertisement now       40
anticipated Q2 2019. Phase four design anticipated to start imminently. Phase 5      30
will start later.                                                                                   20
7.6
10                             3.7
Schedule
0
Overall project remains on schedule.                                                   Authorized  Forecasted    Costs
Incurred
Budget
Commission authorized $       m   Construction Costs
Change Order                                                  2.0
1.5                  1.6
Current Quarter       Project Total              1.5
Number of COs                0                    7                  1.0
Amount of COs                $0                 $ 
Justification for COs: None                                                         Dollars in Millions  0.5
0.02
0.0
Risks                                                                     Initial   Change   Spent
Orders
FAA reviews may take longer than anticipated and delay the project.
Budget Transfers
Amount            F              T 
$0

AIRPA 


Port of Seattle 3Q 2018 Report  27

THIRD  QUARTER REPORT, 2018
MNOPQRSU VWXYZ[\ ]^_`a
Project : C800699                       Install a Supervisory Control and     Project Status:
Budget: $9,600,000                   Data Ac      Schedule:  Delayed
Phase:   Design                        for the Airport's 12.47 kV Medium    Budget: Forecast Overrun
Start:   8/5/2015                          Voltage (MV) power distribution      Status Reset: 8/4/2015
Schedule Completion: 5/22/2020       network.                            Commission Construction Auth.)
Significant Debcdfghijkl          Budget/Costs Incurred
Working to incorporate 100n opqsuv wxyz{|}~    
12
review feedback    "   "        9.6
10
Schedule                                                           8
6
Turnover in staff and consultant resources has created project delays. Project is       4
scheduled to return to Commission for construction authorization in Q2 201     Dollars in Millions      1.6             1.57
2
0
Budget                                                           Authorized  Forecasted   Costs
Incurred
Team conducting value engineering effort to find cost reductions.
Change Order                                               Construction Costs
Not Applicable
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                    $0
Justification for COs: None at this time 
Risks
The project budget is based on the ability to perform construction work without
power shutdowns to each Power Center. 
Budget Transfers
Amount                         
$0



AIRP

28  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT,                                                                                THIRD  QUARTER REPORT, 2018
Concourse B    
Project : C800699                          tall a Supervisory Control and     Project Status:                             Project :  C800770 ,C800702         Overlay the existing roof system         Project Status:
Budget:                            Data Ac                          Schedule:  Delayed                      Budget: $13,183,000              (approx. 86,500 Sa      Schedule:  Delayed
Phase:  Design                           he Airport's 12.47 kV Medium         t: Forecast Overrun                Phase:   Construction               and 83,000 S ! "#$        Budget: On or Under
Start:   8/5/2015                          Voltage (MV) power distribution        tatus Reset: 8/4/2015                      Start:   3/1/2010                       install a new elastomeric roofing         Status Reset: 1/24/2017
Schedule Completion:  5/22/2020       network.                           Commission Construction Auth.)               Schedule Completion: 9/30/2018    system; ladders and fall protection;      (Commission Construction Auth.)
and replace and refurbish the existing
Significant De                                                         Budget/Costs Incurred                                                 skylight window/walls.
Working to incorporate 100                                                                                             Significant De                                                  Budget/Costs Incurred
12
review feedback                                                                                                     Substantial Completion issued on September 30 S                                  13.18
10                                                                                                                                                        14
Schedule                                                          Dollars in Millions                                                                                                   12
Schedule                                                          Dollars in Millions             9.26
10                            7.45
Turnover in staff and consultant resources has created project delays. Project is                                                  Contractor working to complete last items remaining after substantial                 8
scheduled to return to Commission for construction authorization in Q2 201                                                  completion.                                                                        6
4
Budget                                                                                                                                                     2
Authorized   Forecasted     Costs                  Budget                                                                                              0
Incurred
Team conducting value engineering effort to find cost reductions.                                                             On budget.                                                                             Authorized  Forecasted    Costs
Incurred
Change Order                                               Construction Costs                Change Order
Not Applicable                                                                                                      Construction Costs
Current Quarter       Project Total                                                                       Current Quarter       Project Total
Number of COs                 0                   0                                                     Number of COs                12                   37                       5.7
6                            5.0
Amount of Cos                 $0                   $0                                                      Amount of COs              $19,934              $189,012                5
Justification for COs: None at this time                                                                                          Justification for COs: Varying site conditions and design issues.                    Dollars in Millions  4
3
Risks                                                                                                 Risks                                                                2
The project budget is based on the ability to perform construction work without                                                Last items remaining add a risk of leaks during the wet season.                       1              0.2
er shutdowns to each Power Center.                                                                                                                                                                    0
Initial     Change     Spent
Budget Transfers                                                              Orders
Budget Transfers
Amount            F              T 
Amount                                                                             $0
$0



AIRP
AIRPA 
Port of Seattle 3Q 2018 Report  29

THIRD  QUARTER REPORT, 2018
N%&'( )*+,-./0 123456789 :;<=>?@ BCDEGHI
Project : C800717                       Replace and extend the steam,        Project Status:
Budget: $21,335,000                  condensate and chilled water          Schedule:  Delayed
Phase:   Construction                  supply and return piping from the     Budget: On or Under
Start:   9/21/2010                        Central Mechanical Plant to the end    Status Reset: 6/28/2016
Schedule Completion: 6/30/2021       of mechanical room four and to the    (Commission Design & Construction
ends of the South and West Loops`   Auth.)
Significant DeJKLMOPQRUV          Budget/Costs Incurred
Design contract amended. Service Directive scope of work and level of effort
25
approved by Project Management. Pending review and approval by Central                       21.3
Procurement Office.                                                           Dollars in Millions 20
15
Schedule                                                                9.3
10
90 percent design review completed                                               5                      2.6
0
Budget                                                           Authorized  Forecasted   Costs
Incurred
Project remains within budget for design. Pending 100 percent design cost
estimate for future construction authorization.
Construction Costs
Change Order                                                  2.0
Current Quarter       Project Total
Number of COs                 0                   0                  1.5
Amount of Cos                 $0                    $0                  Dollars in Millions  1.0
Justification for COs: N/A                                                              0.5
0.0        0.0        0.0
Risks                                                                0.0
Initial     Change     Spent
Significant construction schedule delays could result in the North Star program                     Orders
utilizing alternate methods to heat and cool the North Satellite 
Photo
Budget Transfers
Amount            WXYZ             [\
$0



AIRP]^_
30  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Central Terminal Infrastructure Upgrade
Project : C800722                       Install H  "   Project Status:
Budget: "   for me     Schedule: Delayed
Phase:   Construction                  terminal. Reconfigure tenant spaces   Budget: On or Under
Start:   5/8/2015                          on the Concourse level of the          Status Reset: 6/27/2017
Schedule Completion: 2/14/2020       central terminal in order to improve    (Commission Construction Auth.)
customer service and experience.
Significant Debcdefghijk          Budget/Costs Incurred
Safety netting installed for contractor during construction of the mezzanine
access stairways. Added light pole relocation/removal and granite tile                20     16.8      16.8
replacement to the scope.                                                          Dollars in Millions 15
Schedule                                                          10
4.9
At this time the project is 90 days behind the original schedule which may            5
cause a schedule delay in the future.                                                   0
Authorized   Forecasted     Costs
Budget                                                                         Incurred
Project remains within budget
Construction Costs
Change Order                                                 
9.3
Current Quarter       Project Total             
Number of COs                8                   26
Amount of COs             $91,391             $240,422               
Justification for COs: Changes in field conditions                                   Dollars in Millions                       2.3
0.2
Risks                                                                 
Initial     Change     Spent
Delayed closure of the CT1 (Anthonylmn opqrs tuvwxy z{|}~      Orders
schedule
Photo
Budget Transfers
Amount                         
$6,190,000             C800638               C800722



AIRP 
Port of Seattle 3Q 2018 Report  31

THIRD  QUARTER REPORT, 2018
Concourse C New Power Center
Project : C800724                     Add new z{|}~          Project Status:
Budget: $nopqrtuvwxy   substation on Ramp level at column Schedule: Delayed
Phase:   Design                     line F/40            Budget: On or Under
Start:   10/26/2014                   ourse  " "        Status Reset: 9/22/2015
Schedule Completion: 11/3/2020     panels will be re           (Commission Construction Auth.)
power center   
and branch circuit panels will be added. 
Significant De          Budget/Costs Incurred
Resolved design issues with Medium     
equipment, Data Communication for electrical metering and coordination with      12              10.5
SCADA and Arc S            10
8
Schedule                                                           6
Expect to secure Commission Approvals for project construction funding and      Dollars in Millions  4     2.0
1.1
authorization to advertise during Q2 2019.                                           2
0
Budget                                                           Authorized  Forecasted   Costs
Incurred
Within approved design budget and currently completing detailed review oW 
9 sign and do not s ! "#$%&'()*+,- ./0123 45678:;               Construction Costs
Not Applicable
Change Order
Current Quarter       Project Total
Number oN <=>    0     0
Amount oA ?@B     CD     EF
JGHIKLMOPQRTU VXY Z[\] None
Risks
Time delays due to construction in areas that impact this pro^_`ab
Budget Transfers
Amount            cdef             gh
ij
AIRPklm

32  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Au   
Project : C800C                       Wetland mitigation site              Project Status:
Budget: $7      enhancements, including installing Schedule: Delayed
Phase:   Construction                  perimeter chain-link fence and        Budget: On or Under
Start:   8/1/2018                        converting interior paths/roads to      Status Reset: 6/28/2016
Schedule Completion: 12/15/2018     forest.                               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Project is substantially complete. Waiting for final invoices to close-out project.
0.8      0 
This will be the final report.
0.6
Schedule                                                                              0.4
0.4
Project is scheduled for close-out in December 2018.
0.2
Budget                                                        Dollars in Millions
0
Project is under budget.                                                                  Authorized  Forecasted    Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
Not Applicable
Number of COs                 0                   0
Amount of Cos                 $0                    $0
Justification for COs: None
Ris
N/A
Budget Transfers
Amount            F              T 
$0




AIRPA 
Port of Seattle 3Q 2018 Report  33

THIRD  QUARTER REPORT, 2018
Concourse B Ramp Level Holdroom
Project : C800761                       Construct a ramp level holdroom on  Project Status:
Budget: $5,548,000                   Concourse B to serve airline          Schedule:  Delayed
Phase:   Construction                  passengers bussed to and from        Budget: On or Under
Start:   4/12/2015                        remotely parked flights at             Status Reset: 3/27/2018
Schedule Completion: 11/3/2017       hardstands.                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Progressing with installation efforts for remaining scope of signage and
6.2
monitor.                                                                              5.99      5.98
6
Schedule                                                          Dollars in Millions 5.8
Continued progress though is taking longer than anticipated.                        5.6                       5.49
5.4
Budget
5.2
No changes to budget                                                              Authorized  Forecasted    Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
Number of COs                1                   28
3.5                           3.09
Amount of COs             $11,784             $344,602                   2.79
3
Justification for COs: Changed site conditions and design issues.                   Dollars in Millions 2.5
2
Risks                                                               1.5
1
Resource availability may continue to hinder schedule.                                             0.34
0.5
0
Budget Transfers                                                        Initial    Change    Spent
Orders
Amount
$0




AIRP 
34  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Telecommunications Meet Me Room
Project : C800762                       The Telecommunications "Meet      Project Status:
Budget: $3,978,000                   Me Room" is a gateway to the         Schedule:  Delayed
Phase:   Design                        internet and allows quick, reliable,    Budget: tXYZ[\]^ _`abdef
Start:  11/20/2016                       and cost-effective network             Status Reset: N/A
Schedule Completion: 4/22/2021        connections for all of the airportcW     (Commission Construction Auth.)
tenants
Significant DeS !"          Budget/Costs Incurred
Project in design (60% stage).
7.0                 5.99
Schedule                                                          6.0
Dollars in Millions 5.0      3.98
Coordinating the project with IAF. Access to the site is limited until Q2 2020.       4.0
3.0
Budget                                                        2.0
Current 60% estimate shows a forecast overrun. Project team is evaluating the       1.0                        0.26
estimate given current delays.                                                       0.0
Authorized   Forecasted      Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0               None at this time
Amount of COs                $0                   $0
Justification for COs: None at this time
Risks
Project will go to 100P #$%&'( )*+ ,-./ 1234 569 :;< => ?@BDEGHIJ
Budget Transfers
Amount            KLMN             OQ
$0




AIRPRUV
Port of Seattle 3Q 2018 Report  35

THIRD  QUARTER REPORT, 2018
Concourse D ghijklmno pqrsuvwx
Project : C800769                       Construct a 32         Project Status:
Budget: $38,400,000                  using the alternative public works     Schedule:  Delayed
Phase:   Closeout                     design/build method to support       Budget: On or Under
Start:   2/28/2016                        passengers bused to and from          Status Reset: N/A
Schedule Completion: 10/11/2018     airline flights parked at remote        (Commission Construction Auth.)
hardstands.
Significant Deyz{|}~          Budget/Costs Incurred
Substantial completion for the Concourse D Hardstand Holdroom (now known
50
as the Concourse D Annex) achieved on October 11, 2018 and opened for                38.4
operations October 31, 2018.                                                      40              33.6
30.1
30
Schedule                                                          Dollars in Millions 20
Project is in close out.                                                                    10
0
Budget                                                           Authorized  Forecasted   Costs
Incurred
Project is within budget.
Change Order                                               Construction Costs
Current Quarter       Project Total             30
24.28
Number of COs                 3                   49
Dollars in Millions 25
Amount of COs            $516,654.49          $1,932,132.49                                17.57
20
Justification for COs: Varying site conditions contributed to the changes.            15
10
Risks                                                                5           1.19
None                                                            0
Initial     Change     Spent
Orders
Budget Transfers
Amount                                     Photos
$0




AIRP

36  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Safedock Upgrade and Expansion
Project : C800779                       Install Safedock units at 90 gates.     Project Status:
Budget: $28,218,250                  Connect all existing Safedock units    Schedule:  Delayed
Phase:   Design                        to communications. Install           Budget: On or Under
Start:   9/6/2017                          Safedock  "       Status Reset: 2/13/2018
Schedule Completion: 6/5/2020                                            (Commission Design Auth.)
Significant Developments                                           Budget/Costs Incurred
Proceed with 90% design.                                                                    28.2
30
Schedule                                                          25
Ninety percent design complete by November 2018.                              20
Final Design complete by December 2018.                                     Dollars in Millions 15
Request for construction authori  "        10
3.6
5                            0.3
Budget                                                         0
Authorized   Forecasted     Costs
On budget                                                                                   Incurred
Change Order                                               Construction Contract Costs
Current Quarter       Project Total
1.0
Number of COs                 0                   0
Amount of COs                $0                   $0                   0.8
Justification for COs: N/A                                                             0.6
0.4
Risks                                                               Dollars in Millions  0.2
0.0        0.0        0.0
None                                                             0.0
Initial     Change     Spent
Budget Transfers                                                               Orders
Amount                         
$0
Cost of Construction Growth
None


AIRP
Port of Seattle 3Q 2018 Report  37

THIRD QUARTER REPORT, 2018
South Satellite Narrow Body Configuration
Project : C800781                       Planning       Project Status:
Budget: $5,500,000                   of three new narrow body positions    Schedule:  Within or Ahead 
Phase:   Construction                  at the S. Satellite. Scope includes      Budget: On or Under
Start:   2/23/2016                        new: 1 passenger loading bridge       Status Reset: 2/2
Schedule Completion: 1/13/2020       (P      "     (Commission Construction Auth.)
at S10  " 
pavement marking.
Significant Developments                                           Budget/Costs Incurred
Design is now 100            5.5 5.5
6
Pro P 
Dollars in Millions  5
4
Schedule                                                           3
1.7
Pro !"# $% &'()*+, -. /01 234 56789:; <=>?@ABCDEF 2
1
0
Budget                                                           Authorized  Forecasted   Costs
ProGHIJ KL MNOQRSTUV WXYZ[\ ]^_`ab          Incurred
Change Order                                               Construction Costs
Current Quarter       Project Total               6
Number of COs                 0                   0                        4.8
5
Amount of Cos                 $0                    $0                     4
cdefghijklmno pqr stuv None                                                                     Dollars in Millions    3
1.6
2
Risks                                                                 1          0.0
Potential cost and schedule impacts from forecasted shortages of materials and         0
skill labor in the current robust Seattle construction market remains a risk.                   Initial    Change    Spent
Orders
Budget Transfers
Amount            wxyz             {|
$0



AIRP}~
38  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Emergency Generator Control Renewal and Replacement
Project : C800784                    Replace and re-program generator        Project Status:
Budget:  $2,640,000               programmable logic controllers          Schedule:  Delayed
Phase:  Design                     (PLCs). Install load bank with controls    Budget:  Forecast Overrun
Start:  12/28/2015                   for "L             Status Reset: N/A
Schedule Completion: 2/26/2021    generator load testing.                   (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Issued new MODs to SD9 to update scope based on modifications made to the
design, and to redo the 90          4   3.0
3
3
Schedule                                                           2
Anticipate 90     nd Quarter 2019    Dollars in Millions 2
0.8
1                             0.4
Budget                                                         1
0
Sixty percent design review currently shows forecast greater than current                Authorized   Forecasted     Costs
budget due to added scope items, including addition of Load Banks.                                        Incurred
Change Orders                                               Construction Costs
Current Quarter       Project Total          Not applicable
Number of COs                0                   0
Amount of Cos                 $0                    $0
Justification for COs: None at this time
Risks
Added scope changes and inclusion of Load Banks make it necessary to re-visit
90% design effort. Potential budget increase request shall be evaluated during
90% design review.
Budget Transfers
Amount            F              T 
$0



AIRPA 
Port of Seattle 3Q 2018 Report  39

THIRD  QUARTER REPORT, 2018
Parking Garage Elevator Modernization
Project : C800789                       All work is in the $%&' ()*+,-.      Project Status:
Budget: $23,516,000                  Phase 1- weatherize the elevator       Schedule:  Within or Ahead 
Phase:   Design                        cores (Sections B and C), and         Budget: On or Under
Start:   5/8/2018                          provide lobby floor treatments.        Status Reset: 5/8/2018
Schedule Completion: 1/25/2023       Phase 2 - replace the elevators in      (Commission Design Auth. Phase 1)
Sections B and C and modernize
the elevator cabs and replace motor
drives in Sections D and E.
Significant Developments                                           Budget/Costs Incurred
Started Phase 1 and completed the 15% design package. Presented Phase 2 at                      23.5
25
the Acquisition Planning and the Investment Committee. Presentation
documents are being prepared for the January 22, 2019 Commission Meeting.       20
15
Schedule                                                          Dollars in Millions 10
Overall project remains on schedule. Phase 1 design completion anticipated in       5     0.7                0.1
Q2 2019.                                                                  0
Authorized   Forecasted     Costs
Budget                                                                         Incurred
Currently under budget.
Construction Contract Costs
Change Order                                                   1
Current Quarter       Project Total              0.8
Number of COs                 0                   0
Amount of COs                $0                   $0
0.6
Justification for COs: None.                                                          Dollars in Millions  0.4
0.2
0.0        0.0        0.0
Risks                                                                 0
Initial     Change     Spent
Coordination of work between Phase 1 and Phase 2 construction contracts.                        Orders
Minimizing impacts to parking and ground transportation operations during
construction.
Budget Transfers
Amount
$0


AIRP!"#
40  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
PLB Renew & Replace Phase 2
Project : C800793                       Replace nine passenger loading       Project Status:
Budget: $10,000,000                  bridges (Ps89:;                     Schedule:  Within or Ahead 
Phase:   Construction                                                   Budget: Forecast Overrun
Start:   12/17/2015                                                            Status Reset: 2/28/2017
Schedule Completion: 12/12/2020                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Work is complete on the S11 PLB. Working on finishing design for S6 and C15
14
PLBs.                                                                             12.0
12      10.0
Dollars in Millions 10
Schedule                                                           8
Scheduled to replace six PLBs in 2019.                                             6
4                            1.6
Budget                                                         2
0
Projected to be over budget because of multiple in ground utilities requiring             Authorized  Forecasted    Costs
extensive modifications to expand and/or fully replace PLB foundations.                                  Incurred
Additional PLB has been identified as needing replacement in near term.
Construction Contract Cost
Change Order
1
Current Quarter       Project Total
0.8
Number of COs                 0                   0
Amount of COs                $0                   $0                 Dollars in Millions  0.6
Justification for COs: None                                                            0.4
0.2
0.00       0.00       0.00
Risks                                                                 0
None                                                                 Initial   Change   Spent
Orders
Budget Transfers
Amount            /012             34
$0



AIRP567
Port of Seattle 3Q 2018 Report  41

THIRD  QUARTER REPORT, 2018
SSAT Infrastructure Upgrades
Project : C800798                       Replace hot and cold deck fans,      Project Status:
Budget: $52,232,000                  coils and controls with energy         Schedule:  Within or Ahead 
Phase:   Permitting                    efficient new air handler, coils and    Budget: On or Under
Start:   9/19/2016                        controls. New scope will replace      Status Reset: 8/8/2017
Schedule Completion: 9/6/2021        ceiling, lights, fire sprinklers,         (Commission Construction Auth.)
signage, and carpet.
Significant DeS<=>?@BCDE          Budget/Costs Incurred
Project is out for bid with bid opening scheduled for December 18, 2018.            60              52.2
Dollars in Millions 50
Schedule                                                          40
Project is on schedule                                                                30
20      13.9
Budget                                                        10                 0.9
Project is within budget                                                               0
Authorized   Forecasted     Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Contract Costs
Number of COs                 0                   0               Not Applicable
Amount of COs                $0                   $0
Justification for COs: None
Risks
Irregular Bid.
Budget Transfers
Amount            GHIJ             KM
$0




AIRPNOP
42  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Variable Frequency Drive
Project : C800801                       Yeplace 47 of the oldest Variable  Project Status: Design
Budget: $3,995,000                   Frequency Drives (VFDs) installed   Schedule:  Within or Ahead 
Phase:   Construction                  at  Seattle  Tacoma  International   Budget: On or Under
Start:   7/10/2017                        Airport.                               Status Reset: 9/25/2018
Schedule Completion: 3/18/2020                                           (Commission Design Auth.)
Significant Developments                                           Budget/Costs Incurred
Project budget reduced due to scope refinement.
5
4.0        4.0
Schedule                                                          Dollars in Millions  4
Ninety Percent design completed on schedule.                                      3
2
Budget                                                         1                 0.3
Within Budget                                                               0
Authorized   Forecasted     Costs
Change Order                                                                 Incurred
Current Quarter       Project Total          Construction Contract Costs
Number of COs                0                   0
Amount of COs                $0                   $0                    1
Justification for COs: None at this time                                               0.8
Risks
0.6
0.4
None at this time                                                                   Dollars in Millions  0.2
0.0        0.0        0.0
Budget Transfers                                                     0
Initial     Change     Spent
Amount            QRUV             WX                       Orders
$0
VFD powering a 350 HP motor




AIRPORT
Port of Seattle 3Q 2018 Report  43

THIRD  QUARTER REPORT, 2018
Chiller Panel Upgrade
Project : C800811                       Convert integrated control panels     Project Status:
Budget: $900,000                     for 3 central mechanical plant         Schedule:  Within or Ahead 
Phase:   Construction                  chillers                            Budget: On or Under
Start:   9/20/2017                                                               Status Reset: 1/9/2018
Schedule Completion: 6/28/2019                                           (Commission Construction Auth.)
Significant DeZ[\]^_`abc          Budget/Costs Incurred
Project is out for bid; expect bid opening to occur on November 28, 2018.
1      0.9
Schedule                                                          0.8           0.7
On schedule to complete all work before summer of 2019.                         0.6
Budget                                                        Dollars in Millions 0.4
0.2                            0.1
Budget is likely to be $100,000 under at completion.
0
Authorized   Forecasted     Costs
Change Order                                                                 Incurred
Current Quarter       Project Total
Number of COs                 0                   0               Construction Contract Costs
Amount of COs                $0                   $0                N/A
Justification for COs: N/A
Risks
None
Budget Transfers
Amount            defg             hi
$0
Cost of Construction Growth
N/A



AIRPjkl
44  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
SSAT Structural Impromnopqrt
Project : C800818                       Improvements to the South Satellite  Project Status:
Budget: $4,050,000                   (SSAT) building to address           Schedule:  Delayed
Phase:   Construction                  structural deficiencies. Work         Budget: On or Under
Start:   12/28/2015                      includes abatement of regulated        Status Reset: 8/8/2017
Schedule Completion: 11/13/2018     materials.                            (Commission Construction Auth.)
Significant Deuvwxyz{|}~          Budget/Costs Incurred
Phase 1 of the Concourse level work is complete. Construction work is
5.0
underway on the Ramp and International Corridor levels with 94% complete                4.2      4.1
overall at the end of Q3. Remaining work includes fireproofing and restoration        4.0
2.8
on the International Corridor level.                                                   Dollars in Millions    3.0
2.0
Schedule                                                            1.0
Phase 2 Concourse level work has been delayed until Q1 2019 due to                 0.0
operational and tenant coordination requirements.                                         Authorized Forecasted   Costs
Incurred
Budget
Construction Contract Costs
Overall project budget impacted by regulated materials abatement. Project
remains within authorized budget.                                                  2.0    1.8
1.6
Change Order                                                  1.5
Current Quarter       Project Total              1.0
Number of COs                10                  15
Amount of COs             $99,224             $104,683              Dollars in Millions  0.5
0.10
Justification for COs: Varying site conditions, regulatory requirements, scope         0.0
change.                                                                             Initial    Change    Spent
Orders
Risks
Photo
Phase 2 Concourse level work may impact tenant operations
Budget Transfers
Amount                        
$0


Corridor Level Fireproofing
AIRP
Port of Seattle 3Q 2018 Report  45

THIRD  QUARTER REPORT, 2018
Arc Flash Mitigation
Project : C800826                       Replace medium voltage fused       Project Status:
Budget: $7,533,000                   switches with medium voltage        Schedule:  Delayed
Phase:   Design                        circuit breakers at six power          Budget: On or Under
Start:   9/21/2016                        centers.                               Status Reset: 9/26/2017
Schedule Completion: 6/22/2020                                           (Commission Construction Auth.)
Significant De          Budget/Costs Incurred
Finalizing design documents.                                                            7.53      7.53
8.0
7.0
Schedule                                                          6.0
Schedule might be delayed due to resource constraints.                            Dollars in Millions 5.0
4.0
Budget                                                        3.0
2.0
On budget.                                                                   1.0                      0.23
0.0
Authorized   Forecasted      Costs
Change Order                                                                  Incurred
Current Quarter       Project Total
Number of COs                 0                   0               Construction Costs
Amount of COs                $0                   $0                None at this time
Justification for COs: None
Risks
None
Budget Transfers
Amount                         
$0




AIRP
46  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Holdroom Seating for Concourses B & C
Project : C800833                       Replace existing passenger           Project Status:
Budget: $9,300,000                   holdroom seating in Concourses B     Schedule:  Within or Ahead 
Phase:   Construction                  and C. Provide electrical             Budget: On or Under
Start:   9/25/2016                        improvements to support required      Status Reset: 4/11/2017
Schedule Completion: 6/15/2019       power for new seating.               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Construction was started on electrical power for passenger seating. Manufacture           9.3
10                  8.8
of passenger seating continued prior to shipment.
8
Schedule
5.9
6
Schedule is less than 30 days behind and contractor may be able to make up the    Dollars in Millions  4
time during the next 6 months.                                                      2
0
Budget                                                           Authorized  Forecasted   Costs
Incurred
Project is within current budget, $471,000 to be returned as saving due to a
lower than estimated construction bid.
Construction Contract Costs
Change Order                                                  2.0
Current Quarter       Project Total
Number of COs                 0                   0                  1.5    1.2
Amount of COs                $0                   $0                   1.0
Justification for COs: None                                                         Dollars in Millions  0.5
0.0        0.0
Risks                                                                0.0
None at this time                                                                          Initial    Change    Spent
Orders
Budget Transfers
Amount                         
$0



AIRP
Port of Seattle 3Q 2018 Report  47

THIRD  QUARTER REPORT, 2018
Ground Based Augmentation System (GBAS) Upgrade
Project : C800834                       Upgrade Sea-Tac's Ground Based    Project Status:
Budget: $4,588,000                   Augmentation System (        Schedule:  Delayed
Phase:   Design                        from a beta system to a fully          Budget: On or Under
Start:   1/5/2017                          functioning navigational aid.          Status Reset: 9/12/2017
Schedule Completion: 9/10/2019                                           (Commission Const Auth.)
Significant Developments                                           Budget/Costs Incurred
Contract with Honeywell is still in review. Additional meetings scheduled                          4.6
5
Q4 2018.
Dollars in Millions  4      3.5
Schedule                                                           3
Delay in schedule due to negotiations taking additional time.                         2
1                            0.1
Budget                                                         0
Project is within budget.                                                                  Authorized  Forecasted    Costs
Incurred
Change Order
Construction Contract Costs
Current Quarter       Project Total
Number of COs                 0                   0                   1
Amount of COs                $0                   $0
Dollars in Millions   0.8
Justification for COs: None.                                                          0.6
0.4
Risks
0.2
None at this time.                                                                            0.0       0.0       0.0
0
Initial     Change     Spent
Budget Transfers                                                               Orders
Amount                         
$0




AIRP"
48  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Tenant Telecommunications D "
Project : C800841                       Standardize tenant network demark   Project Status:
Budget: $2,815,000                   packages for many existing legacy     Schedule:  Within or Ahead 
Phase:   Design                        installations and vacant properties     Budget: On or Under
Start:   2/27/2017                                                               Status Reset: N/A
Schedule Completion: 6/30/2021                                           (Commission Construction Auth.)
Significant De          Budget/Costs Incurred
Working towards 90% design.                                                               2.82
3.0
Schedule                                                          2.5
On schedule.                                                                  2.0
1.5
Budget                                                        Dollars in Millions 1.0   0.72
0.18
On budget.                                                                   0.5
0.0
Authorized   Forecasted      Costs
Change Order                                                                  Incurred
Current Quarter         Project Total
Number of COs                   0                     0                 Construction Costs
Amount of COs                  $0                     $0                 None at this time
Justification for COs: None
Risks
N/A
Budget Transfers
Amount                           
$0




AIRP
Port of Seattle 3Q 2018 Report  49

THIRD  QUARTER REPORT, 2018
AOA Perimeter Fence  
Compliance
Project : C800842                       This project will replace the old 7    Project Status:
Budget: $6,935,000                   foot AOA fence line with the new     Schedule:  Within or Ahead 
Phase:   Design                        standard height of 12      Budget: On or Under
Start:   1/29/2017                        foot barbed wire at the top.            Status Reset: 7/10/2018
Schedule Completion: 9/30/2019                                           (Commission Construction Auth.)
Significant De          Budget/Costs Incurred
The final design was completed; working on final review to prepare for the
advertisement starting in November 2018. The FAA completed their review for      8     6.9       6.9
the design set and the Draft Engineer's Design Report and issued an approval      Dollars in Millions  6
letter for advertisement.
4
Schedule
2
0.5
On Schedule
0
Budget                                                           Authorized  Forecasted   Costs
Incurred
Project is currently on budget.
Construction Contract Costs
Change Order
1
Current Quarter       Project Total
Number of COs                 0                   0                  0.8
Amount of COs                $0                   $0                   0.6
Justification for COs: None at this time.                                             Dollars in Millions  0.4
0.2
Risks                                                                     0.0     0.0     0.0
0
TSA requirement changes to the perimeter fence height and/or mesh size has               Initial    Change    Spent
Orders
increased the cost of material and caused delays in project delivery. Close
coordination with Port Security to ensure compliance with the most current
Photo
TSA standards.
Budget Transfers
Amount                         
$0

AIRP

50  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
C1 Building Expansion

Project : C800845                      Define a project to expand the C1    Project Status:
Budget: $50,000,000                  building with up to four additional     Schedule:  Within or Ahead 
Phase:   Planning                     floors.                             Budget: On or Under
Start:   9/10/2018                                                               Status Reset: N/A
Schedule Completion: 7/9/2025                                            (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Starting Project definition process. Once this is complete, the project scope and
1
budget will be established.                                                                  0.8
0.8
Schedule                                                          0.6
Planning to return to Commission in Q3 2019.                                    Dollars in Millions 0.4
0.2
0.2
Budget                                                                    0.0
0
On budget.                                                                      Authorized  Forecasted    Costs
Incurred
Change Order
Construction Contract Costs
Current Quarter       Project Total
Number of COs                 0                   0               Not Applicable
Amount of COs                $0                   $0
Justification for COs: None
Risks
Timeliness of planning efforts could delay completion.
Budget Transfers
Amount            F              T 
$0
Cost of Construction Growth
N/A



AIRPA 
Port of Seattle 3Q 2018 Report  51

THIRD  QUARTER REPORT, 2018
ADR Kiosk Program Expansion
Project :  C800846                   Install utilities to support (8) new       Project Status:
Budget: V1,240,000            ADR WXYZ[ \]^_`abcde             Schedule: Delayed
Phase:   Design                     fgh ijkermediate lmnpqr stu            Budget: On or Under
Start:   3/26/2017                      (2) Introductory vwxyz{|                  Status Reset: N/A
Schedule Completion: 8/17/2019                                           (Commission Constr. Auth.)
Significant Developments                                           Budget/Costs Incurred
Started construction on Intermediate S !"#$% &'
1.4     1.24       1.24
1()* +omplete. Anticipate starting construction of the Introductory o,-./0 23        1.2
Q1Q 45678            1
0.8
Schedule                                                          0.6
Site selection issues delayed the design completion schedule.                       Dollars in Millions 0.4
0.11
0.2
0
Budget                                                           Authorized  Forecasted   Costs
Incurred
On budget.
Change Order                                               Construction Costs Incurred
Current Quarter       Project Total          Not Applicable
Number of COs                0                    0
Amount of COs                $0                   $0
J9:;<=>?@BCDE GHI KLMN OPRU
Risks
Risk that other operational needs will take the areas designated for the kiosks.
Space is short and operational needs are at a premium.
Budget Transfers
Amount            From              To
$0




52  Port of Seattle 3Q 2018 Report
AIRPORT

THIRD  QUARTER REPORT, 2018
Terminal Security Enhancements (TSE)
Project : C800862                     The project includes shatter proofing     Project Status:
Budget: $12,216,000                the windows (Phase I) and security and    Schedule:  Delayed
Phase:   Construction               accessibility improvements (Phase II)     Budget: On or Under
Start:   4/28/2017                      for the Main Terminal and Sky bridge      Status Reset: 1/1 
Schedule Completion: 2/4/2020      entrances.                             (Phase II Commission Design Auth.)
Significant Developments                                           Budget/Costs Incurred 
Phase I } ~         " 
14.0                12.2
bridges "          12.0
construction is 20      c        10.0
Phase II P ! "#$ %&'()*+,- ./012 345 67
7.8
8.0
Arrivals structural limitations that require more bollards to be installed.             Dollars in Millions  6.0
4.0
1.1
Schedule                                                           2.0
0.0
Phase I schedule is delayed and has been further impacted by contractor                 Authorized  Forecasted    Costs
productivity and additional regulated material remediation. The current forecast                            Incurred
for substantial completion remains in Q1 2019. Phase II remains behind
schedule and the current forecast for design completion is Q2 2019.               Construction Contract Costs 
Budget                                                         15.0
Project is within budget. Savings from Phase I bid results was incorporated into
10.0
the revised Phase II budget (scope increase) with an overall budget reduction of
89:;<=>?@                                                                   Dollars in Millions  5.0
2.2
Change Order                                                            0.1    0.5
0.0
Phase I               Current Quarter       Project Total                 Initial   Change   Spent
Orders
Number of COs                 1                   1
truction costs for Phase I only.
Amount of COs             ABCDEFG              HIJKLMN
OQRSTUVWXYZ[\ ]^_ `abd efghijk lmno pqrstuvwx                                      Photo
Risks
Phase I y z{|}~        "  
from manufacturer.
Phase II  "       
curbside operations along the Arrivals curbside.
Budget Transfers
Phase I Windows  Phase II Security
Amount                        
$0
AIRP

Port of Seattle 3Q 2018 Report  53

THIRD  QUARTER REPORT, 2018
Parking ReP 
Project : C800870                       Design/construct within Parking      Project Status:
Budget: $22,898,000                                Schedule:  Delayed
Phase:   Design                        guidance system "      Budget: On or Under
Start:   11/1/2017                        stations                                Status Reset: 10/2018
Schedule Completion: 8/8/2022                                            (Commission Design Auth.)
Significant DeS           Budget/Costs Incurred
Selection of Design consultant for infrastructure design.
22.9
25
Schedule                                                          20
The project is behind schedule by approximately ten weeks. The Automated        15     11.2
Parking !"#$% &'()*+ ,-. /02345678 9:;<=>?@ AB CDEFG HIJKL   10
review/development. The associated schedule slip will be evaluated in
5
December to determine if the lost time can be recovered.                           Dollars in Millions                         0.27
0
Budget                                                           Authorized  Forecasted   Costs
Incurred
Project is on budget
Construction Contract Costs
Change Order
1
Current Quarter       Project Total
Number of COs                 0                   0                  0.8
Amount of COs                $0                   $0                 Dollars in Millions  0.6
MNOQRTUVWXYZ[ \]^ _`ab N/A                                                               0.4
0.2
0.00       0.00       0.00
Risks                                                                 0
The primary goal is the installation of an automated parking guidance system              Initial    Change    Spent
Orders
that is integrated with the ParkingSoft parking revenue control system and the
reservations system to bring in additional parking revenue. Integrating these
three parking products to reservet cdefgh ijk lmnopq rsuvwxyz{|} ~  
accomplished in the industry yet.
Budget Transfers
Amount                         
$0
Cost of Construction Growth
N/A

AIRP
54  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Concourse B Gate Reconfiguration
Project : C800873                       Tenant reimbursement project by     Project Status:
Budget:     Delta Air Lines to add two new  Schedule:Within or Ahead 
Phase:   Closeout                     gates and reconfigure four others at    Budget: On or Under
Start:   1/16/2017                        Concourse B.                         Status Reset: N/A
Schedule Completion: 5/26/2017                                           (Commission Construction Auth.)
Significant De"          Budget/Costs Incurred
Project complete and in-use. Failing potable water cabinets are being replaced
12
at Gate B5A and Gate B7.                                                            9.9
Dollars in Millions 10                  7.9        7.9
Schedule                                                           8
6
The water cabinet work will be completed by Q1 2019.                             4
2
Budget                                                         0
The project is under budget.                                                            Authorized  Forecasted    Costs
Incurred
Change Order
Construction Contract Costs
Current Quarter       Project Total          Not Applicable
Number of COs                 0                   0
Amount of COs                $0                   $0
Justification for COs: N/A
Risks
N/A
Budget Transfers
Amount                         
$0




AIRP
Port of Seattle 3Q 2018 Report  55

THIRD  QUARTER REPORT, 2018
Fire Station-West Side
Project : C800876                       Install a modular type building and   Project Status:
Budget: $5,500,000                   truck shelter to facilitate an interim    Schedule:  Within or Ahead 
Phase:   Design                        Fire Station on the west side of the    Budget: On or Under
Start:   5/12/2017                        airport.                                Status Reset: N/A
Schedule Completion: 11/15/2019                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Design is progressing to 90% complete.
5.5        5.5
6
Schedule                                                           5
Design development took slightly longer than anticipated. Project remains            4
within schedule. Investigating an early completion of the truck shelter to              3
facilitate heated storage of fire trucks before inclement weather.                     Dollars in Millions  2
0.5
1
Budget                                                         0
Authorized   Forecasted     Costs
Project on budget.                                                                                        Incurred
Change Order                                               Construction Contract Costs
Current Quarter       Project Total          N/A
Number of COs                 0                   0
Amount of COs                $0                   $0                Photos
Justification for COs: None
Risks
Site space constraints, utility runs, and existing conditions.
Budget Transfers
Amount                         
$0
Cost of Construction Growth
NA



AIRP
56  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Employee Security Screening
Project : C800880                       Add security screening checkpoints   Project Status:
Budget: $2,950,000                   for employees entering the secure     Schedule:  Within or Ahead 
Phase:   Closeout                     areas of the airport.                 Budget: On or Under
Start:   7/3/2016                                                                Status Reset: 11/28/2017
Schedule Completion: 7/31/2017                                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
The two screening rooms in operation are proving to be sufficient for employee
3.5
screening. Therefore, the last phase of the project's scope, the North Employee             3.0
3
Screening Room, has been canceled. The project is now in close-out. This is the     2.5
final report.                                                                                Dollars in Millions  2
1.5                 1.1        1.1
Schedule                                                           1
0.5
Further work on the project has been canceled.                                      0
Authorized   Forecasted     Costs
Budget                                                                         Incurred
The current project budget will be decreased per the reduced scope.
Construction Costs
Change Order                                               Not Applicable
Current Quarter       Project Total          Photos
Number of COs                $0                   $0
Amount of COs                $0                   $0
Justification for COs: None
Risks
None
Budget Transfers
Amount                         
$0



AIRP
Port of Seattle 3Q 2018 Report  57

THIRD  QUARTER REPORT, 2018
Delta Inflight Services Tenant Reim 
Project : C800883                       Prepare for occupancy               Project Status:
Budget: $1,196,000                   approa      Schedule:  Delayed
Phase:   Construction                  space for Delta Air s !"#$     Budget: On or Under
Start:   1/12/2017                        Services facility using a Tenant        Status Reset: N/A
Schedule Completion: 12/31/2018     Reimbursement Agreement.          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Construction underway. Anticipate completion in December.
1.4      1.2        1.2
1.2
Schedule                                                            1
Schedule is delayed due to late construction start by Delta's contractor.               0.8
0.6
Budget                                                        Dollars in Millions 0.4                0.2
0.2
Delta has submitted their first reimbursement request for this project, which is         0
currently in the review and approval process.                                            Authorized  Forecasted    Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total          N/A
Number of COs                 0                   0
Amount of COs                $0                   $0
Justification for COs: N/A
Ris
The project team is working to mitigate construction impacts to adjacent
spaces.
Budget Transfers
Amount                         T 
$0



AIRPA 
58  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Central Terminal C%&'()*+,-./
Project : C800886                       Provide new passenger charging      Project Status:
Budget: $4,800,000                   station counters, furniture, music      Schedule:  Delayed
Phase:   Construction                  performance area, waste receptacles   Budget: On or Under
Start:   8/8/2017                          and electrical floor outlets in the       Status Reset: N/A
Schedule Completion: 8/18/2020       Central Terminal                    (Commission Construction Auth.)
Significant DeS012345678          Budget/Costs Incurred
Construction contract has been executed.
6
4.8        4.8
Schedule                                                           5
4
While the overall project has been delayed, its schedule meets the requirements      3
for the opening of new food services in the Central Terminal as well as aligning    Dollars in Millions  2
with other projects in the space.                                                        1                        0.4
0
Budget                                                           Authorized  Forecasted   Costs
Incurred
On budget
Change Order                                               Construction Contract Costs
Not Applicable
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                   $0
Justification for COs: None
Risks
None at this time
Budget Transfers
Amount            F9:;             <=
$0




AIRP>?@
Port of Seattle 3Q 2018 Report  59

THIRD  QUARTER REPORT, 2018
Airport Signage Phase 1
Project : C800898                       Provide short-term improvements    Project Status:
Budget: $8,000,000                   to airport signage and wayfinding     Schedule:  Within or Ahead 
Phase:   Design                                                         Budget: On or Under
Start:   4/4/2016                                                                Status Reset: N/A
Schedule Completion: 10/26/2020                                         (Commission Construction Auth.)
Significant DeBDEGHIJKLM          Budget/Costs Incurred
Consultant continued work on recommendations for signage and wayfinding
short-term improvements.                                                      10.0
8.0
8.0
Schedule                                                          6.0
Dynamic signage has been installed. As authorizedN OPQRUVWXY Z[\]^_` bcdefghi  4.0
will be defined with the remaining short-term improvements.                      Dollars in Millions        2.0
2.0                             0.7
Budget                                                        0.0
Authorized   Forecasted      Costs
On budget                                                                                     Incurred
Change Order                                               Construction Costs
Current Quarter       Project Total          None at this time
Number of COs                 0                   0
Amount of COs                $0                   $0
jklmnopqrtuvw xyz {|}~ 
Risks
None at this time
Budget Transfers
Amount                         
$0




AIRP
60  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Ta   
Project : C800HIJ                      TaYZ[\]^_ `ab cdefghijklmnopq rs   Project Status:
Budget: $KLMNPQRSTUVWX   transition and SMtuv wxyz{|}  Schedule:Within or Ahead 
Phase:   Construction                  Ta~       Budget: On or Under
Start:   10/11/2016                      Q partial hot spot mitigation.          Status Reset: 11/14/2017
Schedule Completion: 12/10/2018                                         (Commission Const Auth.)
Signi "       Budget/Costs Incurred
Labor strike delayed the start of the 90 day Runway 16L/34R closure until                4
September 10. Portions of Taxiway L demolition and relocation adjacent to the     50
runway were completed and work transitioned to Taxiway B on September 28.      ! 40
Reconfigured Runway 16L/34R and is being used as taxiway during Taxiway B     30
closure to complete Taxiway L demo and relocation. Project is approximately                              1 
80% complete. Light can installation and paving are on going. Targeted
20
10
acceleration utilized where appropriate and acceptable. During construction        D
Taxiway S was found to be damaged, distressed and determined to be Critical        0
AuthoriA F  Costs
Work. Grinding and overlay of new asphalt added to contract, no impact to                                Incurred
schedule or budget, taking advantage of the current runway closure.
Construction Contract Costs
Schedule
Project is currently on schedule. There is a possibility of early completion but it       30     2"#$
is weather dependent.                                                            EG  25
BC
>?@   20
=
Budget                                                        ;<  15                '()*
9:
Project is currently on budget.                                                        78   10
56
3    5                0%&
Change "            0
Initial     Change     Spent
Current   Project Total      O+,-./
Number of COs                 3                   19
Amount of COs            $35,000.00           $230,300.00           Photo
Justification for COs: 1)Additional Panel Replacement Work Areas E1-E6; 2).
Grind and Re          

Adverse weather is current major risk as we continue moving toward finish
through major paving. Close coordination with Operations and communication
with airlines is top priority in completing the project as soon as practicle and
possible. 
Budget Trans
Amount            From              To
$0
AIRPORT                                              Port of Seattle 3Q 2018 Report  61

THIRD  QUARTER REPORT, 2018
Automated Screening Lanes Checkpoint Conversions
Project : C800920                       Procurement of Automated           Project Status:
Budget: $17,000,000                  Screening Lanes for Security          Schedule:  Delayed
Phase:   Construction                  Checkpoints 2    "       Budget: On or Under
Start:   5/21/2017                        installation at Security Checkpoints    Status Reset: 12/12/2017
Schedule Completion: 8/9/2019          nd 5.                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
The first phase of Checkpoint 2 is complete, and three lanes are operational.
20.0
Checkpoint 3 design is 90% complete.                                                   17.0     17.0
Dollars in Millions   15.0
Schedule
10.0
Construction at Checkpoint 2 was delayed due in part to a TSA request to audit
the performance of the previously installed Automated Screening Lanes before        5.0                    2.4
proceeding further (which has since been satisfactorily completed). Checkpoint        0.0
2 is now set to be completed in Q1 2019 with Checkpoint 3 installation set to              Authorized Forecasted   Costs
begin Q2.                                                                                          Incurred
Budget                                                      Construction Contract Costs
Project is within budget                                                           Not applicable
Change Order                                               Photo
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                   $0
Justification for COs: None
Risks
Infrastructure installation is taking longer and has been difficult due to the tight
space. Space constraints are requiring equipment changes. Installations are                                   CP5
impacted by continued high traffic.
Budget Transfers
Amount                         
$0
Cost of Construction Growth
N/A
CP2
AIRP
62  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
" 
Project : C800925                       Convert existing standard check-in   Project Status:
Budget: $1,700,000                   counter arrangement at the north      Schedule:  Within or Ahead 
Phase:   Construction                  end of          Budget: On or Under
Start:   11/7/2017                        the Main Terminal to create 10        Status Reset: 1/10/2018
Schedule Completion: 6/20/2018       common-use check-in positions.       (Commission Construction Auth.)
Significant De          Budget/Costs Incurred
Reached substantial completion in June. Project is in close out phase.
This will be the final report.                                                              2.0     1.70
Dollars in Millions 1.5
Schedule
The project is on schedule.                                                          1.0              0.72
0.54
0.5
Budget
The project is under budget.                                                         0.0
Authorized   Forecasted      Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0
Amount of COs                $0                   $0                   0.1
Justification for COs: None                                                         Dollars in Millions  0.1
0.1
Risks
0.0
None                                                             0.0   0.01          0.01
0.00
Budget Transfers                                                    0.0
Initial     Change     Spent
Amount            From              To                        Orders
$0
Photo




AIRPORT
Port of Seattle 3Q 2018 Report  63

THIRD  QUARTER REPORT, 2018
F 
Project : C800YZ[                      Renovate a vacant cargo building     Project Status:
Budget: $4,612,000                   for lease by FedEx.                  Schedule:  Within or Ahead 
Phase:   Design                                                         Budget: On or Under
Start:   4/2/2018                                                                Status Reset: 9/25/2018
Schedule Completion: 11/14/\]^_                    (Commission Construction Auth.)
SigniS       Budget/Costs Incurred
The first phase design is currently in permit review.                                         =>?       @AD
5
Schedule                                                           4
Construction of the first phase is on schedule to begin Q1 2019. Design for the
3
second phase has fallen slightly behind schedule though the overall project         Dollars in Millions  2
remains on schedule.                                                              1                      EGH
0
Budget                                                           Authorized  IJKLMNOPQU  Costs
Incurred
The project is currently on budget.
Construction Contract Costs
Change Order
Not Applicable
Current C   Project Total
Number of COs                 0                   0
Amount of COs                $0                   $0
Justification for COs: N/A
R !
Unknown site conditions may impact the project.
Budget TransB"#$
Amount            %&'( T)
$0
Cost o* +,-./0123456 789:;<
N/A


AIRPVWX
64  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
RCF Pa`abcde fghijklmnop
Project : C800977                       The project addresses pavement      Project Status:
Budget: $10,637,000                  performance issues at the             Schedule:  Delayed
Phase:   Design                        Consolidated Rental Car Facility      Budget: On or Under
Start:   5/23/2017                        (6789:;<=                            Status Reset: 7/10/2018
Schedule Completion: 12/24/2019                                         (Commission Design Auth.)
Significant Deqrstuvwxyz          Budget/Costs Incurred
On {|}~          "
12                 10.6
work. Reached agreement to share costs for the Bridge 2 improvements with
10
the Designer of Record "       
8
Record began construction and plans to be completed in Q4. Design underway
for early work     a th Floor Topping Slab
6
improvements in Q4. Design underway on remaining scope and i    Dollars in Millions 4
0.0
2
submittal planned for Q4.                                                                                  0.1
0
Authorized   Forecasted     Costs
Schedule                                                                            Incurred
Early work construction on schedule and planned to be completed in Q4 2018.
Design delayed but planned to be complete in Q1 2019.                          Construction Contract Costs
Not Applicable at this time
Budget
Photo
Project is currently on budget.
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                   $0
J    !"# $%&' ()*+,-./
Risks
Operational and phasing impacts due to construction.
Budget Transfers
Amount            F012             T3
$0
Cost of Construction Growth
None.

AIRPA45
Port of Seattle 3Q 2018 Report  65

THIRD  QUARTER REPORT, 2018
SD Pond Bird Deterrent ImproS>?@BCD
Project : C800980                       The project implements a long term   Project Status:
Budget: $10,492,000                  solution to improve the bird           Schedule:  Within or Ahead 
Phase:   Design                        deterrent system. A total of 1|        Budget: On or Under
Start:   6/1/2017                          ponds are included.                   Status Reset: }~
Schedule Completion: 10/14/2020                                         (Commission Design Auth.)
Significant DeEGHIKLMNOP           Budget/Costs Incurred
Environmental group is conducting testing to evaluate water quality impacts of
12                 10.5
bird-ball use as a deterrent to water fowl. Sixty percent design was completed
with 90% design planned to be completed in December 2018.
10
8
Schedule                                                          Dollars in Millions  6
4
Request construction authorization from Commission in February 2019.
2      0.3
The on-site construction is planned to start in QQ RUVWX                             0.1
0
Authorized   Forecasted     Costs
Budget                                                                         Incurred
On Budget
Construction Contract Costs
Change Order
1
Current Quarter       Project Total
Dollars in Millions   0.8
Number of COs                 0                   0
Amount of COs                $0                   $0                   0.6
YZ[\]^_`bcdef ghj klmn opqr                                                        0.4
0.2
0.0        0.0        0.0
Risks                                                                 0
Initial     Change     Spent
None                                                                       Orders
Budget Transfers                                                 Photo
Amount            stuv             wx
$0
Cost of Construction Growth
None


66  Port of Seattle 3Q 2018 Report
AIRPyz{

THIRD  QUARTER REPORT, 2018
CDD       
Project : C800                      Design communications              Project Status:
Budget: $     infrastructure, purchase and install Schedule: Delayed
Phase:   Design                        furniture and communications to      Budget: On or Under
Start:   6/30/2017                        support the relocation of staff to       Status Reset: N/A
Schedule Completion: 9   SeaTac Office Center.     (Commission Construction Auth.)
Signi"       Budget/Costs Incurred
Construction complete. Staff have now relocated.                                              
Schedule                                                           2
Schedule delayed due to delayed access to the new space.

1
Budget                                                        Dollars in Millions                  
Project is within budget.                                                               0
Authorized  Costs
Incurred
Change Order
Current Quarter       Project Total
Construction Costs Incurred
Number of COs                 0                   0
Amount of COs                $0                   $0                Not Applicable
Justification for COs: None
"
No risks at this time
Budget Trans
Amount                         
$0
Cost o  
N/A



AIRP
Port of Seattle 3Q 2018 Report  67

THIRD  QUARTER REPORT, 2018
Concourse C Ramp Space RenoC 
Project : C800986                       Create Leasable Space on the Ramp  Project Status:
Budget: $2,100,000                   Level of Concourse C                Schedule:  Within or Ahead 
Phase:   Construction                                                   Budget: On or Under
Start:   1/26/2018                                                               Status Reset: N/A
Schedule Completion: 3/22/2019                                           (Commission Construction Auth.)
Significant DeS           Budget/Costs Incurred
The construction contract for this project has been advertised and awarded.
2.5     2.10
Schedule                                                           2          1.70
Project is on schedule.                                                               Dollars in Millions 1.5
1
Budget
0.5                           0.14
Project is within budget.
0
Authorized   Forecasted     Costs
Change Order                                                                 Incurred
Current Quarter       Project Total
Number of COs                 0                   0               Construction Contract Costs
Amount of COs                $0                   $0
1
Justification for COs: None
Dollars in Millions   0.8
Risks                                                                0.6
0.4
Contractor not being able to make scheduled NTP date could delay project.
0.2
0.00       0.00       0.00
Budget Transfers                                                     0
Initial     Change     Spent
Amount            F              T                        Orders
$0
Cost of Construction Growth
N/A



AIRPA !
68  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT,                                                                              THIRD  QUARTER REPORT, 2018
Concourse C Ramp Space Reno                                                           L"#% &'() *+, -./0 12345678:;<
Project : 104395, 104396               Remediation of contaminated soils   Project Status:
Project : C800986                           ate Leasable Space on the Ramp  Project Status:                             Budget: $24,300,000                   at aVWXYZ[\]^_`bcdefghijklmno     Schedule:  Delayed
Budget:                            Level of Concourse C               Schedule:  Within or Ahead              Phase:   Construction                 Capping and filling of the pqrs       Budget: On or Under
Phase:  Construction                                                         t: On or Under                    Start:   9/26/2010                      tuvw xyz{|}~         Status Reset: 9/1
Start:   1/26/2018                                                                tatus Reset: N/A                           Schedule Completion: 7/28/2019        adjoining Miller Creek.                (Commission Construction Auth.)
Schedule Completion:  3/22/2019                                         Commission Construction Auth.)
Significant De=>?@BDEGHI          Budget/Costs Incurred
Significant De                                                         Budget/Costs Incurred               The re-design of Phase/Season 2 work on Lora Lake has been submitted and
The construction contract for this project has been advertised and awarded.                                                                                                                                         30
approved by Ecology and Corp. Upon approval, rather than start so late in the            24.3
25                 21.4
season, it was decided to postpone Phase 2 until the summer of 2019. Phase 1
Schedule                                                                                                                                                            20
Watering Plan was carried out through October 2018.
Project is on schedule.                                                               Dollars in Millions                                                                                                                                   15
8.2
Schedule                                                          10
Budget                                                                                                                                                    Dollars in Millions 5
Phase 2 will begin in July 2019                                                      0
Project is within budget.                                                                                                                                                                                                    Authorized  Forecasted    Costs
Incurred
Authorized   Forecasted     Costs                 Budget
Change Order                                                                 Incurred          Project is within budget.
Construction Costs
Current Quarter       Project Total
Number of COs                 0                   0               Construction Contract Costs        Change Order                                                         10    8.9
Amount of COs                $0                  $0                                                                           Current Quarter       Project Total              8             6.8
Justification for COs: None                                                                                                      Number of COs                     0                        8
Amount of COs                $0               $106,776.16               6
Risks                                                                                                Justification for COs: N/A                                                 4
ractor not being able to make scheduled NTP date could delay project.         Dollars in Millions                                                                                                                            Dollars in Millions   2
0.1
Risks                                                                 0
Budget Transfers                                                                                    NSTR                                                                    Initial Change Spent
Orders
Initial     Change     Spent
Amount                                                     Orders
$0                                                                                            Budget Transfers
Photo
Amount            JKMN             OP
Cost of Construction Growth                                                                                    $0
N/A


AIRPQRU
AIRP
Port of Seattle 3Q 2018 Report  69

THIRD  QUARTER REPORT, 2018
SeaTac International Airport Emergency 16 Inch Water Main
Project : 105827                        Emergency project to repair the 16   Project Status:
Budget: $800,000                     inch water main line at Sea-Tac       Schedule:  Within or Ahead 
Phase:   Closeout                     International Airport.                Budget: On or Under
Start:   7/2CDEGHI                                                             Status Reset: 7/30/2018
Schedule Completion: 12/31/2018                                         (Executive Direct Auth.)
Signi       Budget/Costs Incurred
On July 30, 2018 a declaration of emergency was issued due to failure of the
1
water main located under the Airport roadway system. A contract was executed            
on July 31st and work began on August 3rd. On August 13th permanent water                            0 
service was restored. Airport roadway system was back in use by August 16th
and the storm drainage system by August 27th . This is the first and final            Dollars in Millions                                                                                 quarterly report for this project.

Schedule                                                           0
Authorized   F     Costs
Work was completed within 27 days of contract execution.                                              Incurred
Budget                                                      Construction Costs
This is an e"" 567
Operational Budget.                                                                                     !
234
./1
Change Order                                                 +,-
Current Quarter       Project Total            ()*
Number of Cos                  1                    1                 Dollars in Millions %&'
Amount of Cos                 $0                    $0                 "#$
Justification for COs: Contract time e                                            Initial     Change     Spent
Orders
Photo
None, work is complete.
Budget Trans
Amount                         
$0

Lane Closure - Utility EL89:;<=>?

AIRPA@B
70  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Flight Corridor Safety Program  Phase 1 Port Property
Project : U00225                        Removal of obstructions to           Project Status:
Budget: $5,806,000                   navigable airspace on Port of          Schedule:  Delayed
Phase:   Construction                  Seattle property at Seattle-Tacoma    Budget: On or Under
Start:   5/31/2015                        International Airportu vwxyz{|}~        Status Reset: 11/14/2017
Schedule Completion: 4/3/2019        e                (Commission Construction Auth.)
revegetating on-site.
Significant Developments                                           Budget/Costs Incurred
The remaining work of Phase 1 includes the removal of invasive species and
7
Re-planting at Port site P-4, P-5 and Off-site Mitigation Areas (OMA). The                5.8       5.8
6
contract has been awarded and the work began in November 2018. Prior to the       5
work start, Port Public Affairs conducted community outreach.                    Dollars in Millions                         3.5
4
3
Schedule                                                           2
1
Invasive species removal and replanting began November 2018 and will be          0
completed within the Spring 2019 planting season.                                     Authorized  Forecasted    Costs
Incurred
Budget
Phase 1A Construction Costs
The project is currently within budget.
2.5                          2.1
Change Order                                                   2   1.7
Current Quarter       Project Total              1.5
Number of COs                 1                   24                Dollars in Millions              0.9
1
Amount of COs            $(15,562.86)          $889,438.57
Justification for COs: Reconciliation of Bid Item R J KMNO PQSTU VWXYZ[\ ]^_       0.5
Bid Item ` abcde fghijk           0
Initial     Change     Spent
Orders
Risks
None.                                                                Photo
Budget Transfers
Amount            lmno             pq
$0



AIRPrst
Port of Seattle 3Q 2018 Report  71

THIRD  QUARTER REPORT, 2018
" 
Project :     This is an FAA funded project with Project Status:
Budget: $5,000,000                   participation from the City of         Schedule:  Delayed
Phase:   Closeout                     Burien but led by Port. The project    Budget: On or Under
Start:   8/16/2015                        is to redevelop the Area north of the   Status Reset: 10/14/2014
Schedule Completion: 12/31/2018     airport in the City of Burien.
Signi "      Budget/Costs Incurred
Final Design Management Team meeting held October 5  
6.0
deliverables for the project were completed as scoped. The FAA Close Out                5.0       5.0
5.0
Report will be submitted in December. This is the final quarterly report for this
4.0
project.
3.0
Schedule                                                          Dollars in Millions 2.0                  1.1
1.0
Project schedule was e         0.0
October 2018 and closeout by December 2018.                                      Authorized  yz{|}~   Costs
Incurred
Budget
Construction Costs
Project is within budget. The project is funded by a $ P 
G   !"#$%&'()*+, -./0 123 4567 89 :;<=>? @ABCDEF HIJ KLM NOQR  N/A Design Only
($750k).
Photo
Change Order
Current Quarter       Project Total
Number of COs               N/A                   N/A
Amount of COs               N/A                  N/A
STUVWXYZ[\]^_ `ab cdef ghi
jklmn
None identified.
Budget Transopqr
Amount            stuv             wx
$0



AIRP
72  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Flight Corridor Safet       
Project : U00356                        Multi-year program to manage       Project Status:
Budget: $7,227,000                   obstructions consisting of trees and    Schedule:  Delayed
Phase:   Design                        other vegetation off Port property     Budget: On or Under
Start:   1/8/2017                          around Seattle Tacoma                Status Reset: 2/28/2017
Schedule Completion: 9/25/2020       International Airport, and             (Commission Design Auth.)
replanting lower-height vegetation.
Significant De"           Budget/Costs Incurred
Phase 2 and 3 of the program will include managing obstructions on public and
8                 7.2
private properties around the airport and replanting. Consultants are evaluating
data that will determine the specific number and locations of the obstructions.        6
The Port is in discussions with the FAA regarding their interpretation of FAA
4
rules to determine the possibility that some obstructions in Phase 2 and 3 can be            2.6
left in place.  "         2
0.4
environmental review process, compensation approach and public outreach.        Dollars in Millions
0
Authorized   Forecasted     Costs
Schedule                                                                            Incurred
Complete obstruction analysis Q4 2018. Begin environmental review and
design in Q1 2019.                                                            Construction Contract Costs
Not Applicable
Budget
The project is currently under budget.
Change Order
Current Quarter       Project Total
Number of Cos/                  0                     0
Amount of COs                $0                   $0
Justification for COs: None.
Risks
Any delay in the approval process will impact the budget and schedule for
project delivery. Close coordination with stakeholders including the Public,
WSDOT, other public agency property owners, Operations, Environmental, and
FAA is very important for the successful delivery of the project.
Budget Transfers
Amount                         
$0

AIRP          Port of Seattle 3Q 2018 Report  73

THIRD  QUARTER REPORT, 2018
H 
Project : C200007                      Highline School Insulation Agreement  Project Status:
Budget:  =>?@BCDEGIKL               was intended to provide funding for     Schedule:  Delayed
Phase:  Construction                 sound insulation for 15 schools that      Budget:  On or Under
Start:  3/23/1999                        are impacted by aircraft noise from       Status Reset: N/A
Schedule Completion: 11/30/2021     Sea-Tac Airport                       (Commission Construction Auth.)
Significant DeS           Budget/Costs Incurred
Port funds authorized for availability when the FAAP !"#
120
and the Highline School District (HSD) provide matching funds. HSD passed a           102.1     101.8
100
bond for the construction of Des Moines Elementary and Highline High School.
80                           63.4
FAA funding mechanism was provided in Q1 through the National Defense
60
Authorization Act. Construction commenced at Des Moines Elementary in Q2.
40
Construction at Highline High will commence in 2019.                           Dollars in Millions  20
Schedule                                                            0
Authorized  Forecasted     Costs
Port funding for Des Moines Elementary is anticipated to begin in Q4 2018.                               Incurred
Budget                                                      Construction Costs
Not Applicable
The budget forecast is within the approved budget and authorization.
Change Order
Current Quarter       Project Total
Number of COs                0                   0
Amount of Cos                 $0                    $0
J$%&'()*+,-./ 012 3456 N/A
Risks
The current risk is the availability of FAA AIP funding.
Budget Transfers
Amount            F789             T:
$0



AIRPA;<
74  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
SingleMNOQRUV WXYZ[ \]^_`abcde
Project : C2000                      The Single-Family Sound            Project Status:
Budget: $7,855,000                   Insulation Program provides sound    Schedule:  Within or Ahead 
Phase:   Testing                       insulation improvements to           Budget: On or Under
Start:   3/1/2018                          appro           Status Reset: 10/11/
Schedule Completion: 12/31/2020     eligible homes located within the      (Commission Construction Auth.)
Noise Remedy Boundary for Sea-
Tac Airport.
Significant Defghijklmno          Budget/Costs Incurred
The Noise Office received 48 completed applications to date. C&S Engineers
10
completed FAA required noise testing at 41 homes in Q2. Thirty sip qrstu        7.855   7.855
were found to have interior noise levels of at least 45 dB and continued in the         8
process. Eleven homeowners delayed or dropped out of the program and 25         6
remain in process. It is anticipated that a small number of additional potentially      4
eligible homeowners may come forward during the process.                      Dollars in Millions  2                    0.17016
Schedule                                                           0
Authorized       Costs
The design process and the ordering of materials is taking place in Q4v wxyz                     Incurred
construction starting also in Q4 2018.
Construction Contract Costs
Budget                                                      Not Applicable
The project is within the approved budget and authorization.
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                   $0
{|}~   
Ris
The program is subject to homeowners being available during key stages of the
process. Homes may have e     "  "
time for the availability of sound-rated materials can be substantial.
Budget Transfers
Amount                         
$0
Cost of Construction 
N/A
AIRP
Port of Seattle 3Q 2018 Report  75

THIRD  QUARTER REPORT, 2018
Condominium Sound Insulation
Project : C200095                       The Condominium Sound            Project Status:
Budget: $20,000,000             Insulation Program provides sound   Schedule: Within or Ahead 
Phase:   Planning                     insulation improvements to i         Budget: On or Under
Start:   7/10/2018                        potentially eligible condo              Status Reset: 7/10/2018
Schedule Completion: 12/31/2021     complec !" #%&'()*         (Commission Construction Auth.)
within the Noise Remedy Boundary
for Sea-Tac Airport.
Significant De          Budget/Costs Incurred
After receiving Commission approval in July, we are in the process of               25
procuring a design and construction management firm.                                   20.0      20.0
20
Schedule                                                          Dollars in Millions 15
A design and construction management firm will be procured in Q2 2019.          10
Program design and homeowner outreach will begin in Q3 2019. Construction      5
0.0
to start in 2019.                                                                            0
Authorized   Forecasted     Costs
Budget                                                                         Incurred
The project is within the approved budget and authorization.
Construction Contract Costs
Change Order                                               Unknown until the Port and AU 
consulting firm can gain access to
Current Quarter       Project Total          the buildings and assess the
Number of COs                 0                   0               conditions.
Amount of COs                $0                   $0
Justification for COs: N/A
Risks
The program may be subject to the approval of applicable condominium
associations. Lead-time for the availability of sound-rated materials can be
substantial. Structural conditions of the buildings are unknown. The buildings
are subject to an FAA required noise audit of 45 dB or higher interior noise
level and must be located within the current  l 
grant funding is not guaranteed.
Budget Transfers
Amount            From              To
$0

AIRPORT
76  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Tenant ReimT+,-./012
Project : C800154                      Allows Port to reimburse tenants for     Project Status:
Budget:  DEGHIJKLMN                 costs that are normally a landlord        Schedule:  Within or Ahead 
Phase:  Construction                 responsibility, ex: upgrade unleasable    Budget:  On or Under
Start:  8/14/2007                        space to leasable condition, or correct     Status Reset: N/A
Schedule Completion: TBD         code deficiencies when a tenant         (Commission Construction Auth.)
encounters them on a tenant
construction project.
Significant DeS3456789:;          Budget/Costs Incurred
None
8                 6.7
Schedule                                                          Dollars in Millions  6    5.0
On schedule.                                                                                         3.6
4
Budget                                                         2
On budget.                                                                   0
Authorized   Forecasted     Costs
Change Order                                                                 Incurred
Current Quarter       Project Total          Construction Costs
Number of COs                0                   0               Not Applicable
Amount of Cos                 $0                    $0
Justification for COs: None
Risks
None
Budget Transfers
Amount            F<=>             ?@
Click here to enter text.




AIRPABC
Port of Seattle 3Q 2018 Report  77

THIRD  QUARTER REPORT, 2018
Shilshole Bay Marina Paving
Project : C800355                       Repave areas of Shilshole Bay        Project Status:
Budget:                    Marina not rehabilitated in the 2004   Schedule:  Delayed
Phase:  Design                        major capital redevelopment. Full     Budget:  Forecast Overrun
Start:  1/1/2016                          depth replacement in some failed      Status Reset: 11/14/2017
Schedule Completion: 6/30/2019       areas and e          (Commission Construction Auth.)
grinding and overlay.
Significant Developments                                           Budget/Costs Incurred
Contract for restrooms and paving advertised and bids opened July 2018.
Apparent low bidder substantially over Engineer's estimate ($10.8M vs              3             2.50
$8.1M). Currently developing reduced scope alternative to return to              Dollars in Millions 2.5    2.00
2
Commission Q1 2019O                                         1.5
1
Schedule                                                                             0.29
0.5
The overall schedule will be delayed by the high bids received and subsequent       0
return to Commission. Target was to have the new facilities to be online by mid         Authorized  Forecasted    Costs
Incurred
to late 2019t PQRVWXY Z[\]^_`a bdef ghjkmn op qrsuvwxyz{| }~  
Budget                                                      Construction Costs
Project is within the approved budget      "    1
authorization to complete construction.
0.8
Change Order                                                Dollars in Millions  0.6
Current Quarter       Project Total              0.4
Number of COs                0                   0                   0.2
0.0        0.0        0.0
Amount of Cos                 $0                    $0                     0
"                                                                    Initial    Change    Spent
Orders
Risks
Work tied with Restroom schedule. Phasing and coordination will be critical
on active marina parking areas. Contract includes phasing requirements to limit
parking impacts.
Budget Transfers
Amount            From              To
$0


MARITIME
78  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Shilshole Tenant Ser 
Project : C800356                       Replacement/rehabilitation of five    Project Status:
Budget:  uvwxyz{|}~                 restrooms and laundry facilities at     Schedule:  Delayed
Phase:  Design                        Shilshole Bay Marina by     Budget:  Forecast Overrun
Start:  1/6/2015                          for $10.1M.                           Status Reset: 11/14/2017
Schedule Completion: 6/30/2019                                           (Commission Construction Auth.)
Significant De          Budget/Costs Incurred
Contract for restrooms and paving advertised and bids opened July 2018.
14                 12.60
Apparent low bidder substantially over Engineer's estimate ($10.8M vs
12      10.10
$8.1M). Currently developing reduced scope alternative to return to               10
Commission Q1 2019.                                                    Dollars in Millions  8
6
Schedule                                                           4
1.35
2
The overall schedule will be delayed by the high bids received and subsequent       0
return to Commission. Target was to have the new facilities to be online by            Authorized  Forecasted    Costs
mid-2019  m ! "# $%&'()*+    Incurred
Budget                                                      Construction Costs
Project is forecasted over budget for current scopeP ,-. /0123456 78 9:;<=> ?@A None at this time
additional authorization to complete construction.
Photo
Change Order
Current Quarter       Project Total
Number of COs                0                   0
Amount of Cos                 $0                    $0
JBCDEFGHIKLMN OQR STUV WXY
Risks
Schedule and phasing the work in an active site continue to be the primary
risks. Construction costs in Seattle continue to be increasing and volatile which
may lead to higher than eZ[\]^_` abcde
Budget Transfers
Amount            fghi             jk
$0
lnopqrst
Port of Seattle 3Q 2018 Report  79

THIRD  QUARTER REPORT, 2018
SBM Pad Site De
Project : C800445                       Provide utility extensions to          Project Status:
Budget: $500,000                     support tenant development of new    Schedule:  Within or Ahead 
Phase:   Planning                     restaurant on pad site by Duke's      Budget: On or Under
Start:   1/1/2018                                                                Status Reset: N/A
Schedule Completion: 9/30/2019                                           (Commission Construction Auth.)
Significant De          Budget/Costs Incurred
Site utilities have been identified. Coordinating initial schedule with Dukes.
0.6      0.5        0.5
Schedule                                                          0.5
Schedule dependent on tenant development and is currently at 30% design          0.4
level.                                                                                       0.3
0.2
Budget                                                        Dollars in Millions                   0.1
0.1
0
Within budget                                                                   Authorized  Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Contract Costs
Number of COs                 0                   0
1
Amount of COs                $0                   $0
Justification for COs: None this quarter                                             Dollars in Millions  0.8
0.6
Risks                                                                0.4
Existing utility extensions must be closely coordinated with tenant construction       0.2
0.0        0.0        0.0
schedule and surrounding work.                                                    0
Initial     Change     Spent
Budget Transfers                                                               Orders
Amount                         
$0
Cost of Construction Growth
None

80  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
FT Rede"  
Project : C800525                       Demolition of net sheds        Project Status:
Budget: $4,300,000                   the C-12 Bank Building              Schedule:  Delayed
Phase:   Design                        construction of 2 light industrial      Budget: On or Under
Start:   12/1/2009                        buildings              Status Reset: N/A
Schedule Completion: 12/30/2022     Supply Building "      (Commission Construction Auth.)
improvements "  
infrastructure improvements. 
Significant De"          Budget/Costs Incurred
Project Phase I scope reduced to Bank and Net Sheds 7    
5
G               3.99      3.99
Maritime Innovation Center). Previously proposed West Wall 1 BuildingM     4
Wall gear storage improvements deferred to future Phase 2.                        Dollars in Millions  3
2                           1.50
Schedule                                                           1
Project currently ON HOP ! "# $%&' ()* +,- ./012 3 4 56 789 0
completion of design of new c:;<=>? @ABCDEFH IJK LNOQ RSTUVW XYZ[\]^_  Authorized Forecasted Costs
renovation.                                                                                              Incurred
Budget                                                      Construction Contract Costs
Project currently within authorized budget.                                             1
Change Order                                                  0.8
Current Quarter       Project Total
0.6
Number of COs                 0                   0                  0.4
Amount of Cos                 $0                    $0                  Dollars in Millions  0.2
0.0        0.0        0.0
`abdefghijklm nop qrst uvwx yz{| }~                                               0
Initial     Change     Spent
Risks                                                                           Orders
None at this time.
Budget Transfers
Amount                         
$0
Cost of Construction Growth
None

Port of Seattle 3Q 2018 Report  81

THIRD  QUARTER REPORT, 2018
FT Net Sheds 3,4,5,    
Project : C800526                       Replace the eROPQSUV WXYZ[\] ^_`abc  Project Status:
Budget: $3,259,000                   on all four Net sheds with new        Schedule:  Delayed
Phase:   Construction                  security ladderss defghijk lmn opqr      Budget: On or Under
Start:   11/16/2014                      protection system. Install 44          Status Reset: 12/tuvwxyz
Schedule Completion: 11/30/2017     crystalline solar panels at NS 5.       (Commission Construction Auth.)
Significant De          Budget/Costs Incurred
Construction is complete for Net Sheds 3, 4, 5 and 6. The final piece of this                3.25
pilot project is to provide WiFi access to the Fronius Data Manager so the data      3.5              3.00
Dollars in Millions  3                           2.52
can be downloaded. ICT and PCS installed the Wireless Access Point (WAP)      2.5
on Net Shed            2
1.5
Schedule                                                           1
The project is complete. WiFi connections are also complete will take place        0.5
0
shortly.                                                                                      Authorized  Forecasted    Costs
Incurred
Budget
Construction Contract Costs
No budget issues anticipated.
2
Change Order                                                      1.56          1.61
Current Quarter       Project Total              1.5
Number of COs                 2                   10                Dollars in Millions   1
Amount of Cos               $
0.5
J !"#% &' ()*+,- ./01234 56 789:;<=>?@                                0.07
0
Risks                                                                     Initial   Change   Spent
Orders
None
Budget Transfers                                                 Photo
Amount            FABC             TD
$0
MEGHIKLN
82  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
FT Docks 3, 4, and 5 Fixed Pier Improvements
Project : C800531                      The project will wrap the e    Project Status:
Budget: 6,400,000             steel piling with      Schedule: Within or Ahead 
Phase:   Design                        Cathodic corrosion protection on all   Budget: On or Under
Start:   10/10/2017                      piling from Docks               Status Reset: 5/15/2018
Schedule Completion: 4/15/2019                                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Design and permitting are currently underway.                                                    6.40
7
6
Schedule                                                           5
The project schedule has been revised to accommodate installation of the Piling      4
Wraps and protections in 2019 and is awaiting permitting details. Commission     Dollars in Millions  3
Authorization to Advertise and Bid will be requested in Q1 2019.                    2    0.80
1                           0.15
0
Budget                                                           Authorized  Forecasted   Costs
Incurred
On budget
Change Order                                               Construction Contract Costs
Current Quarter       Project Total               1
Number of COs                 0                   0                  0.8
Amount of COs                $0                   $0                 Dollars in Millions  0.6
{|}~     
0.4
Risks                                                                0.2
0.0        0.0        0.0
Permit conditions   "  "      0
Initial     Change     Spent
Orders
Budget Transfers
Amount            From              To
$0
Cost of Construction Growth
None


MARITIME
Port of Seattle 3Q 2018 Report  83

THIRD  QUARTER REPORT, 2018
T  
Project : C800675                       Upgrade/replace e "      Project Status:
Budget:  "                  fender system at the South end of     Schedule:  Within or Ahead 
Phase:  Closeout                      Pier 91                            Budget:  On or Under
Start:  1/31/2016                                                               Status Reset: 8/8/2017
Schedule Completion: 3/31/2018                                           (Commission Construction Auth.)
Significant DeS           Budget/Costs Incurred
Construction completed by American Construction Co., substantial completion
issued April 17i         5 4.10
4
Schedule                                                           3          2.20     2.18
All in-water workA  !" #$%& '()*+,-. /01 23456789:;<= >? @BCDEFGH IJK    2
2018 to comply with permit fish window. Construction completed prior to start       1
of cruise operations.                                                                  Dollars in Millions
0
Authorized   Forecasted     Costs
Budget                                                                         Incurred
Project is forecast to complete under authorization.
Construction Costs
Change Order                                               Not applicable at this time
Current Quarter       Project Total
Photo
Number of Cos                 2                    2
Amount of Cos              LMNOPQRTU             VWXYZ[\]^
_`abcdefghjkl mno pqrs tuvwxy z{ |}~    
obstructions
Risks
All work complete.
Budget Transfers
Amount                         
$0

84  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
T     
Project : C8008C                       Remove and replace the 13 outfall    Project Status:
Budget: $4,000,000                   pipes and tides gate from the last      Schedule:  Within or Ahead 
Phase:   Design                        downstream manhole to the outlet     Budget: On or Under
Start:   9                                                              Status Reset: 4/25/2017
Schedule Completion: 12/31/2020                                         (Commission Design Auth.)
Significant De          Budget/Costs Incurred
Construction started in August and completed in September. Three outfalls had
voids filled around the exterior joints with high density polyurethane foam           5
4.00
(HDPF) and were relined with cure in place pipe (CIPP). After the lining was      Dollars in Millions 4    4.00
installed new tide gates were measured, ordered and installed. A fourth outfall,       3
not needing any additional repairs, had a tide gate installed.                           2
1                           0.43
Schedule
0
Phase 1 of the project was completed as planned. The team is currently                 Authorized  F    Costs
developing the plans for Phase 2 construction for 2019                                                    Incurred
Budget                                                      Construction Contract Costs
Project is within authorization                                                           1
Change Order                                                  0.8
0.6
Current Quarter       Project Total
Number of COs                 5                   5                   0.4
Amount of COs             $48,094              $48,094              Dollars in Millions  0.2
0.0        .0         0.0
Justification for COs: unforeseen conditions requiring additional foam required        0
to fill void                                                                                             Initial    Change     Spent
Orders
Ris
Photo
Major project risk remain the unknown condition of the outfall that have not
been videoed yet as well as the unknown voids that may be encounted
Budget Transfers
Amount                         
$0
M
Port of Seattle 3Q 2018 Report  85

THIRD  QUARTER REPORT, 2018
TT !
Project : C800910                       Procure five additional cruise         Project Status:
Budget: $1,100,000                   standoff barges to replace the         Schedule:  Within or Ahead 
Phase:   Closeout                     e "  "     Budget: On or Under
Start:   3/17/2017                        the e          Status Reset: 9/12/2017
Schedule Completion: 4/15/2018       in 2012-14 currently in use           (Commission Construction Auth.)
Terminal 91
Significant DeS"#$%&'()*          Budget/Costs Incurred
Five barges fabricated and deployed for 2018 cruise season. Project in closeout.
Schedule                                                          1.15   1.10     1.10
1.1
Barges delivered June 2018 and used for 2018 Cruise season (One season          1.05
earlier than originally planned in the capital budget).                                   1
0.93
0.95
Budget                                                        Dollars in Millions 0.9
Five barges procured under current authorization. Evaluated the possibility of      0.85
procuring one additional barge within one year and within the current                   Authorized  Forecasted    Costs
Incurred
authoria+,-./ 0123456 78: ;<=>?@ABDE GHIJKL NOP QRUVWXYZ [\]^_ `bcdefg hijklmnopq
however budget not sufficient for additional procurement.                        Construction Contract Costs
Not Applicable at this time
Change Order
Current Quarter       Project Total          Photo
Number of COs                 0                   0
Amount of COs                $0                   $0
Justification for COs: None this quarter
Risks
Addition of sixth barge to procurement order would use all of existing
authorizationr stuv wxyz {|}~  
Budget Transfers
Amount                         
$0

86  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018

Project : E104324, E104535-38         Participate in the design p           Project Status:
Budget:  $2,900,000                  construction of the bored tunnelq rs   Schedule:  Within or Ahead 
Phase:  Implementation                u vw xyz{|}~          Budget:  On or Under
Start:  1/1/2009                          Central Waterfront surface streets     Status Reset: N/A
Schedule Completion: 9/30/2019                      (Commission Construction Auth.)
adequate connection to port
facilities.
Significant DeS           Budget/Costs Incurred
Tunnel construction is complete and final system testing is wrapping up.            3.5
Month-to-month lease of P46 continued to allow repairs to underdock sprinkler           2.90
3.0
system. WSF is using P48 for ferry queue during Colman Dock construction.       2.5
1.75
Construction continued on Pier t !"#  2.0    1.45
1.5
Schedule                                                          Dollars in Millions 1.0
0.5
Tunnel opening and Viaduct closure are scheduled for Early 2019. Central          0.0
Waterfront construction is eW$%&'() *+ ,-./0 12 3456 789:;<=>? @ABCDEF   Authorized Forecasted Costs
Incurred
demolition. Colman Dock construction to continue through 202dG
Budget                                                      Construction Costs
Not Applicable
Costs were within anticipated 2018 spending.
Photos
Change Order                                               Tunnel Vehicles (TV) & cross-section
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                    $0
JHIKLMNOPQRTU VXY Z[\] ^_`
Risks
Project delays due to unforeseen construction issues.
Budget Transfers                                                 4-wheeler TV's are 9.5 ft long
Amount            abce             fg
$0
hijklmno
Port of Seattle 3Q 2018 Report  87

THIRD  QUARTER REPORT, 2018
P66 Alas"   "
Project :     Widen a segment of Alaskan Way Project Status:
Budget: $1,657,000                   in the vicinity of the Bell Street       Schedule:  Within or Ahead 
Phase:   Closeout                     Cruise Terminal to improve traffic    Budget: On or Under
Start:   4/1/2015                          flow and safety during cruise days.     Status Reset: 8/23/2016
Schedule Completion: 4/13/2018                                           (Commission Construction Auth.)
Significant De          Budget/Costs Incurred
The project is in the close-out phase. Staff is working with Seattle City Light       1.7     1.66
and SDOT on invoice backups and payments.                                                 1.65
1.65
Schedule                                                          1.6
1.54
Construction is complete and the project is being closed out.                        1.55   Dollars in Millions 1.5
Budget                                                       1.45

Overall expenditure is expected to stay within the authorized budget at the end          Authorized             Costs
Incurred
of the close-out phase.
Construction Contract Costs
Change Order                                               In house Construction
Current Quarter       Project Total          Photo
Number of COs                 0                   0
Amount of Cos                 $0                    $0
Justification for COs: None this quarter
Ris
Risks not anticipated since construction is complete and project is being closedout.
Budget Transfers
Amount                         
$0

88  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2019
P69 Commission Chamber Refresh
Project : C800887                       Replace acoustic ceiling. Retrofit     Project Status:
Budget: $394,000                     existing light fixtures with new        Schedule:  Within or Ahead 
Phase:   Design                        LED Luminairs. Replace carpet and   Budget: On or Under
Start:   4/17/2018                        misc. aesthetic improvements may     Status Reset: 10/9/2018
Schedule Completion: 3/31/2019        include painting columns and         (Commission Construction Auth.)
replacing entry doors.
Significant Developments                                           Budget/Costs Incurred
Design is 100% complete and in internal review. This is a slight delay from
0.5
what we had anticipated. Permit application and engagement with JOC                   0.39      0.39
contractor for schedule and estimate will occur before the end of November.        0.4
0.3
Schedule                                                          0.2
Design completion delayed due to the need to conduct a test and balance (TAB)    Dollars in Millions 0.1                      0.02
of the HVAC system in Chambers. Although TAB and 100% Design
0
completed, it did cause a delay in permit application and engagement with JOC         Authorized  Forecasted    Costs
contractor. However, the overall project status remains on schedule.                                        Incurred
Budget                                                      Construction Contract Costs
Project is on budget.                                                               Not Applicable
Change Order                                               Photo
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                   $0
Justification for COs: None
Risks
Schedule delay may result in a need to reschedule the March 12th Commission
meeting and will make the room unavailable for other uses.
Budget Transfers
Amount                         
$0
Cost of Construction Growth
None
E
Port of Seattle 3Q 2018 Report  89

THIRD  QUARTER REPORT, 2018
P69 Solar Panel System
Project : C800888                       Design and build a roof-mounted     Project Status:
Budget: $515,000                     1()* kWh/yr photovoltaic (PV)      Schedule:  Delayed
Phase:   Construction                  solar system at Pier s+ ,- ./0         Budget: On or Under
Start:   12/12/2017                      sloped2 3456789:;<=>?@ABC DG HIJ       Status Reset: 12/12/2017
Schedule Completion: 12/31/2018     roof.                               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
During building permit review by the City of Seattle, it was discovered that the
0.6
project needs a Shoreline Master Use Permit variancee    0.52  0.52
the shoreline development code. Port is working with the City on the variance
0.5
process. The contract with Puget Sound Solar has been put in suspension (no
0.4
cost change order) to minimize cost impact. Solar panels have been delivered
0.3                           0.21
and stored in Port warehouse. The costs for the panels will be reflected in the
0.2
Q4 2018 costs.                                                                 Dollars in Millions 0.1
0.0
Authorized   Forecasted     Costs
Schedule                                                                            Incurred
Project is delayed by 3-5 months, due to the Shoreline Master Use Permit
variance requirement by the City.                                                Construction Contract Costs
0.36
Budget                                                         0.4
0.4
On budget                                                                 0.3
0.3
Change Order
0.2
0.2
Current Quarter       Project Total            Dollars in Millions  0.1                  0.03
0.1               0.00
Number of COs                 1                   1                  0.0
Amount of COs                $0                   $0                        Initial   Change   Spent
Orders
Justification for COs: put contract under suspension and add 20 days due to
permit delays
Photo
Risks
Permit delays put more risks on meeting grant deadlines.
Budget Transfers
Amount            F              T 
$0
Cost of Construction Growth
None
!"#$%&'
90  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
P66 Interior and Exterior Modernization
Project :  C800889, C800820         Modernize the interior and            Project Status:
Budget: $20,000,000                ee<=>?@ABCDEFGH IJ KLM NOP QRSTUVWX YZ    Schedule:  Within or Ahead 
Phase:   Design                     better support the needs of our         Budget: On or Under
Start:   10/11/2016                   customers for the foreseeable future.    Status Reset: 10/11/[\]^
Schedule Completion: 6/30/2020                                         (Commission Design Auth.)
Significant Developments                                           Budget/Costs Incurred
With the focus of the project on the Interior Modernization onlyW KLM NOPQ
5
refined the interior concepts and completed preliminary design documents.                3.8
Final design began in August and RSU VXYZ[\]^_`abcdfghijkl mnopqrtuv wxy Dollars in Millions 4
z{| }~sign         "               3
1.8
completed late October                     2
0.8
1
Schedule
0
Overall schedule remains unchanged from the last update and we anticipate             Authorized  Forecasted    Costs
building permit submission around early 2019. Forecasting construction to start                            Incurred
late 4th  Quarter " 
Construction Contract Costs
Budget
1
In October 201 c 
0.8
phase of both the Interior and Es !"# $%&'()*+,-./0 12345678 9:; <=>? @AB
decision to only move forward with the Interior Modernization Projectd CDE        0.6
design phase budget allocations were redistributed and $290FGHI JKLMNOPQRST   Dollars in Millions 0.4
from the EUVWXYZ[ \]^_`abefghij klmn opqrtuvw xy z{| }~  0.2
0.0        0.0        0.0
(CIP C800889) project budget. Current total project budget is based on the             0
preliminary design and will be further validated through additional efforts                  Initial    Change    Spent
during the final design phase of the project.                                                          Orders
Change Order                                               Photos
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                    $0

Risks
"  "         
budget during the final design phase. Potential budget impacts associated with
the robust economy    t 
together with other risk factors ! "# $% &'()*+,-./ 012 3456789:;
monitored as the project progresses through final design.

Port of Seattle 3Q 2018 Report  91

Budget Transfers
Amount            From              To
$290,000            P66 Exterior           P66 Interior
Modernization (CIP     Modernization (CIP
C800820)            C800889)













ECON. DEVELOPMENT
92  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Street _`abcdfgh ijk lmn opqr
Project : C102858, C102875           Street vacation related real estate     Project Status:
Budget:                   negotiations and agreements         Schedule:  Delayed
Phase:  Implementation               Terminal 5             Budget:  On or Under
Start:  6/1/2010                                                                Status Reset: N/A
Schedule Completion:                      (Commission Construction Auth.)
Significant De            
T-18 Work Completed:                                                         5.3      5.3
City is working on legislation to vacate the streets to the Port "              5.1
5.00
completion of early 2019.
4.00
T-5 Street Vacation work includes:                                               3.00
Drafted several easement agreements for power  "  
utilities in T-5 property area. Finalizing utility locates and establishing draft
2.00
documents and legal descriptions for utility easements for PSE   Dollars in Millions 1.00
0.00
K            Authorized      Costs
with Port and Port Stormwater District to resolve approach to negotiating                                Incurred
terms for the t ! "#$%& '()*+,-. /012 3456 789:;<=>?@ ABCDEFGH IJ
" 
Schedule                                                       Not Applicable
City is scheduled to vacate streets on Harbor Island in late 2018 or early
P
LMNOP QRpending on the legislative calendar at City Council. T-5 Street
vacation is planned for completion at end of year 2019
Budget
Overall budget between T-18 and T-5 projects is good.
Change Order
Current Quarter       Project Total
Number of COs                0                   2
Amount of COs                $0                STUVWXYZ[\
]^_`abcdefghi jkl mnop qrsu vwxy z{|}~
Ris
None
Budget Transfers
Amount            From              To
$0
suvwx yz{|}~
Port of Seattle 3Q 2018 Report  93

THIRD  QUARTER REPORT, 2018
Argo  " 
Project : C800546, E104751,           New Port of Seattle owned truck     Project Status:
E104754                         roadway between East Marginal      Schedule:  Delayed
Budget:  IKLMNOQSVW                  Way and Colorado Avenue South     Budget:  On or Under
Phase:  Construction                  right-of-way.                       Status Reset: 4/22/2014
Start:  3/11/2012                                                               (Commission Construction Auth.)
Schedule Completion: 6/28/201X
Significant De          Budget/Costs Incurred
UPRR's Element III Argo      
10
to administer FMSIB funding) under construction.                                       7.75      7.75
8
6.10
Schedule                                                           6
UPRR Element III Argo freight yard Automated  U   4
anticipated to be completed in Q1 2019.                                           Dollars in Millions  2
0
Budget                                                           Authorized  12456789:;  Costs
Incurred
Project is currently within the budget authorized by Commission on April 22P
2014.
Construction Costs
Change Order                                                   6  5.05
Current Quarter       Project Total                             4.50
5
Number of COs                0                   3                    4
Amount of COs                $0                 $                 3
J   !"# %&'( )*+                                                               Dollars in Millions    2
1           0.41
RisR,                0
Initial  Change  Spent
No significant known risks at this time.                                                          Orders
Budget Transfers
Amount           F-./             T0
$0
<=>?@ ABCDEGH
94  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
T-46 Permit Mitigation
Project : C800620              Construct overwater public access    Project Status:
Budget: $1,250,000                   pedestrian pier to comply with        Schedule:  Delayed
Phase:   Design                        permit requirement in operation of    Budget: On or Under
Start:   3/26/2013                        T-4                                 Status Reset: N/A
Schedule Completion: 4/21/2021                                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
No change from previous reporting. Continue to wait for Trustee approval.         1.4             1.25
Authorization for construction funds will be requested in Q2 2020.                  1.2
1.0
Schedule                                                          0.8   0.65
0.6
Project is delayed due to Port/Trustee NRD negotiation of the Sites 2YZ[\        0.4
Restoration project. Schedule to commence construction on October 2020.         Dollars in Millions                          0.11
0.2
0.0
Budget                                                           Authorized  Forecasted   Costs
Incurred
Currently within budget
Construction Contract Costs
Change Order                                               Not Applicable
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                    $0
]^_`abcdefghi jkl mnop qrst uvwx yz{|}~
Risks
Potential risk of T-4         "
compliance.
Budget Transfers
Amount                         
$0
"
Port of Seattle 3Q 2018 Report  95

THIRD  QUARTER REPORT, 2018
East Marginal Way  
Project : E102007                      FAST Corridor funded project       Project Status:
Budget:                   FHWA             Schedule:  Delayed
Phase:  Closeout                      commitment of $22    Budget:  On or Under
Start:  5/1/2006                          is to construct grade separation in      Status Reset: 4/22/2014
Schedule Completion: 3/2  vicinity of T5 and T18 to minimize  (Commission Construction Auth.)
truck traffic/rail conflicts.
Significant Developments                                           Budget/Costs Incurred
T102 Lot Boundary Adjustment documents amended   
56     56.25     56.25
by City of Seattle     t  56
finalization of environmental indemnity languagef  !"#$%&'( )*+ ,-./0      56
sewer easements documentss 12 345 678 9:;< => ?@ABCDE FGHIJ KLMNOP   Dollars in Millions 56
56
55.30
Schedule                                                            55
55
Final (revised per City review) documents to be submitted to City in Q4 2018          55
and final approval by City Council and Port Commission to be completed by             Authorized "  Costs
Q2 2019.                                                                                     Incurred
Budget                                                      Construction Costs
Project is on track within the April 22Q RSTU VWXYZ[\]^_ `abcdeghijklmn   25 22.0  22.0
Change Order
20
Current Quarter       Project Total            Dollars in Millions  15
10
Number of COs                 0                   97
Amount of COs                $0                opqruvwxyz                5        2.0
{|}~                                                    0
Initial  Change  Spent
Orders
Ris
No risks at this time.
Budget Transfers
Amount                         
0
"
96  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Terminal 5 Pile Removal
Project : U00289                        Demolition of existing timber piers   Project Status:
Budget: $6,800,000.00                 23, 24, 25, and 26 and Shipway       Schedule:  Within or Ahead 
Phase:   Construction                  north of the Inner Harbor Line.       Budget: On or Under
Start:   5/19/2016                        Demolition of existing steel sheet      Status Reset: 6/13/2017
Schedule Completion: 7/31/2018       pile to the existing mud line,          (Commission Construction Auth.)
regrade site and install rip-rap.
Significant Developments                                           Budget/Costs Incurred
All work is complete with exception of the four steel piles required by tribes.
7
Pile installation is pending completion of Lockheed superfund cleanup. Due to                      5.3
6
clean up by Lockheed in shipway area, a section of the sheet pile wall failed in             6.8
5                            3.8
October. Lockheed is working on remedy.                                        4
3
Schedule                                                           2
Project is on schedule.                                                               Dollars in Millions  1
0
Authorized   Forecasted     Costs
Budget                                                                         Incurred
Project is within budgeted authorization.
Construction Contract Costs
Change Order
3                          2.8
Current Quarter       Project Total                   2.3
Dollars in Millions   2.5
Number of COs                 0                   7                   2
Amount of COs                $0                 $573,730               1.5
Justification for COs: Discretionary: Grading change, additional clear/grub,            1             0.6
additional top soil, and 90 tons of drain rock. Varying Site Conditions: Crane         0.5
rail treated wood support piling, underwater template pile removal, and                0
additional pile length                                                                         Initial    Change    Spent
Orders
Discretionary: Grading change, additional clear/grub, additional top soil, and 90
tons of drain rock. Varying Site Conditions: Crane rail treated wood support
piling, underwater template pile removal, and additional pile length
Risks
Delays to installing four steel piles due to Lockheed cleanup project.
Budget Transfers
Amount                         
$0

JOI 
Port of Seattle 3Q 2018 Report  97

THIRD  QUARTER REPORT, 2018
Parking System Replacement
Project : C800728                       Replacement of the Airport Main        Project Status:
Budget:  $5,500,000                  Garage Parking System               Schedule:  Delayed
Phase:  Implementation                                                 Budget:  On or Under
Start:  1/6/2015                                                                Status Reset: N/A
Scheduled Completion: 6/30/2019                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
New system was deployed on original schedule in Q4 2017. Additional features           5.50      5.50
6
such as reducing impacts of bank outages and expansion to North Employee lot
will be delivered in 2018 and 2019.                                                Dollars in Millions  5
4
2.83
3
Schedule                                                           2
Additional features will be delivered throughout 2018 and 2019.                     1
0
Budget                                                           Authorized  Forecasted   Costs
Incurred
On budget
Construction Costs
Change Order                                               Not Applicable
Current Quarter       Project Total
Number of COs                 0                   3
Amount of Cos                 $0                 $232,632
Justification for COs: None this quarter
Risks
Original vendor, ParkingSoft, purchased by T2. After delays to incorporate
product and processes, T2 is recommending a move to a merged
ParkingSoft/T2 product in 2019 to provide new features with less risk.
Significant testing and analysis is in progress.
Budget Transfers
Amount            F              T 
$0



CC 
98  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
V 
Project : C800723                      Implementation of a vessel           Project Status:
Budget:  456789:;                   moorage system to support marina    Schedule:  Delayed
Phase:  Implementation                and terminal operations.              Budget:  On or Under
Start:  1/12/2016                                                               Status Reset: N/A
Schedule Completion: 6/30/201<                                 (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Implementation is in progress for a planned 2nd quarter 2019 deployment.                  0.55      0.55
0.6
Schedule                                                          0.5
Project implementation was delayed due to a lack of response to original
0.4
procurement. A new procurement was advertised and a vendor selected.
0.3
0.2                            0.10
Budget                                                        Dollars in Millions 0.1
0
On budget                                                                   Authorized !"#$%&'()*   Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total          Not Applicable
Number of COs                 0                   0
Amount of Cos                 $0                    $0
Justification for COs: N/A
RisR 
Vendor could delay implementation schedule due to resource constraints.
Budget Transfers
Amount                               To
$0




C+,-./012
Port of Seattle 3Q 2018 Report  99

THIRD  QUARTER REPORT, 2018
Project Delivery System
Project : C800747                       Development of a project delivery    Project Status:
Budget:  $1,000,000                  system initially for construction      Schedule:  Delayed
Phase:  Implementation                projects. System will replace two      Budget:  On or Under
Start:  12/14/2016                       legacy systems.                       Status Reset: N/A
Schedule Completion: 4/1/2019                                            (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
First planned deliverable completed in August 2018. Development is currently in
1.2
progress on remaining features.                                                           1.00      1.00
1
Schedule                                                          Dollars in Millions 0.8
0.57
0.6
Project is delivering functionality every few months starting in Q3 2018 but         0.4
features for optimum business value will not be completed until Q1 2019,           0.2
which is a 3 month delay on original schedule estimate.                              0
Authorized   Forecasted     Costs
Budget                                                                         Incurred
On budget
Construction Costs
Change Order                                               Not Applicable
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                    $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount            =>?@             AB
$0



CDEGHIJKL
100  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Data Center Operations/Business Continuity
Project : C800748                       Build out of the remote data center   Project Status:
Budget:  $1,200,000                  to support automated backup and     Schedule:  Delayed
Phase:  Implementation                recovery                           Budget:  On or Under
Start:  1/12/2016                                                               Status Reset: N/A
Schedule Completion: 8/1/2018                                            (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Infrastructure procurement and deployment has been completed to support
1.2
automated backup and recovery. Completing application migration to the new             1.20      1.20
infrastructure.                                                                            1.2
1.2
Schedule                                                          1.2                 1.15
During the design process, complexities were identified that delayed the final       Dollars in Millions 1.1
deployment.                                                                 1.1
Authorized   Forecasted     Costs
Budget                                                                         Incurred
On budget
Construction Costs
Change Order                                               Not Applicable
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                    $0
Justification for COs: N/A
Risks
Competing priorities from other projects may further delay project completion.
Budget Transfers
Amount            MNOP             QS
$0



CUWXYZ[\]
Port of Seattle 3Q 2018 Report  101

THIRD  QUARTER REPORT, 2018
Airport Su^_`a bcdefg hijklmnopqr stuvwxyz
Project : C800782                       Procurement and implementation of  Project Status:
Budget:                     an upgraded informational display    Schedule:  Within or Ahead 
Phase:  Implementation                system for the Airport trains and      Budget:  On or Under
Start:  8/                         stations.                               Status Reset: N/A
Schedule Completion: 12/31/2018                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Implementation is in progress for deployment throughout Q3 and Q4.              3.5          
3                           2.47
Schedule                                                          2.5
On schedule                                                                 2
1.5
Budget                                                        Dollars in Millions 1
0.5
On budget                                                                 0
Authorized  Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0               Not Applicable
Amount of Cos                 $0                    $0
Justification for COs: N/A
Ris{|
No significant risks at this time.
Budget Transfers
Amount             }~              To
$50,000              C800782              C80556





C
102  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Airport Data Network Switch Upgrade
Project : C800788                       Equipment and software upgrade     Project Status:
Budget:                    for the network supporting Airport    Schedule:  Delayed
Phase:  Closeout                      Operations systems.                 Budget:  On or Under
Start:  2/23/2016                                                               Status Reset: N/A
Schedule Completion: 12/30/2018                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Failure of some of the new equipment required a product change that will delay
3.5
the final implementation until early Q4 2018. There will be no significant                  2.98      2.98
3.0
budget impact from this development.                                           Dollars in Millions 2.5                     2.10
2.0
Schedule                                                          1.5
Remaining deployments impacting critical airline operations have been             1.0
0.5
scheduled to minimize disruption causing a small delay to the overall project        0.0
completion.                                                                       Authorized  Forecasted    Costs
Prior Report: System deployment was delayed due to an une"             Incurred
procurement requirement and opportunity. By completing a competitive
procurement during this project we are able to set a standard that will reduce      Construction Costs
maintenance costs and ma"        Not Applicable
Budget
On budget
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                    $0

Risks
No significant risks at this time.
Budget Transfers
Amount             From                To
$0

C

Port of Seattle 3Q 2018 Report  103

THIRD  QUARTER REPORT, 2018
Checkpoint Wait Time
Project : C800790                       Procure and implement an            Project Status:
Budget:  $1,215,000                  automated system to track           Schedule:  Delayed
Phase:  Implementation                movement and estimate wait times    Budget:  On or Under
Start:  7/12/2016                         for checkpoints 2 through 5.           Status Reset: N/A
Schedule Completion: 4/30/2019                                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Checkpoint 3 construction will be coordinated with other construction in the
same area, likely in Q1 2019. TSA adjustments of queue lines are hampering       1.4    1.22      1.22
automated wait time usage.                                                      1.2
Dollars in Millions  1
Schedule                                                          0.8                 0.56
0.6
Prior Report: Schedule is delayed due to competing priorities for construction       0.4
resources and Security Checkpoint  r       0.2
0
Budget                                                           Authorized  Forecasted   Costs
Incurred
On budget
Construction Costs
Change Order
0.7     0.63       0.63
Current Quarter       Project Total            0.6
Number of COs                 0                   1                 0.5
Amount of Cos                 $0                  $73,370               0.4
0.27
Justification for COs: None this quarter                                              0.3
0.2
Risks                                                              Dollars in Millions 0.1
0
Required construction costs are significantly higher than originally                Authorized  Forecasted    Costs
Incurred
estimated prior to procurement of the selected system. This may require
additional funding to complete all planned checkpoints.
Coordination with other projects at Checkpoint 3 may delay schedule.
TSA queue reconfigurations are making it difficult to program wait time system.
Budget Transfers
Amount             From                To
$0


CORPORATE
104  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
SeaTac Smartphone App
Project : C800800                       Development of a Mobile app with   Project Status:
Budget:  $500,000                   SeaTac S !"#$% &'()*+, -./     Schedule:  Delayed
Phase:  Implementation                Service Options, and other           Budget:  On or Under
Start:  2/23/2016                         important customer service            Status Reset: N/A
Schedule Completion: 3/1/2019        features.                             (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
iOS mobile application was deployed in Q3 2018 and has been downloaded by     0.52    0.50      0.50
approximately 16,000 individuals. Android development is in progress for an       0.5
estimated Q1 2019 deployment.                                               0.48
0.46
Schedule                                                                             0.43
0.44
Prior Report: The team has re-evaluated solution and the Port development         0.42   Dollars in Millions
team will partner with a design firm to deliver mobile application. . The first         0.4
phase deployment was delayed by four months and completed in Q4 2017.             Authorized  Forecasted    Costs
Incurred
Budget
Construction Costs
On budget                                                              Not Applicable
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                    $0
Justification for COs: N/A
Risks
No significant risks at this time.
Budget Transfers
Amount            F              T 
$0



CC 
Port of Seattle 3Q 2018 Report  105

THIRD  QUARTER REPORT, 2018
Supplier Outreach and Procurement System
Project : C800907                       This project will provide an          Project Status:
Budget:  $800,000                   integrated supplier outreach and      Schedule:  Within or Ahead 
Phase:  Implementation                procurement solution that utilizes     Budget:  On or Under
Start:  7/11/2017                         vendor provided systems for           Status Reset: N/A
Schedule Completion: 3/31/2019       outreach with a Port-developed        (Commission Construction Auth.)
solution for procurement
management.
Significant Developments                                           Budget/Costs Incurred
Development is currently in progress.                                                  1
0.80        0.80
Schedule                                                          0.8
On schedule
0.6
0.32
0.4
Budget                                                        Dollars in Millions 0.2
On budget                                                                 0
Authorized   Forecasted     Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0               Not Applicable
Amount of Cos                 $0                    $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount            0123             45
$0




C6789:;<=
106  Port of Seattle 3Q 2018 Report

THIRD  >UARTER REPORT, 2018
PeopleSoft Financials Upgrade
Project : C800909                       Upgrade of the Port's PeopleSoft     Project Status:
Budget:  $3,600,000                  Financials System.                 Schedule:  Within or Ahead 
Phase:  Implementation                                                 Budget:  On or Under
Start:  12/12/2017                                                             Status Reset: N/A
Schedule Completion: 3/31/2019                                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Implementation is in progress for a Q1 2019 Deployment. Due to stability            4    3.60     3.60
issues with last planned test pass, the upgrade deployment has been moved
from Q4 2018 to 201? @A BDEGHI JK LMNOPQRUVWX YZ[\]^_ `abc defghijk lmnopqstuv. Dollars in Millions 3
2                        1.59
Schedule
1
On Schedule
0
Budget                                                           Authorized Forecasted  Costs
Incurred
On budget
Construction Costs
Change Order                                               Not Applicable
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                    $0
Justification for COs: N/A
Risks
If stability issues continue, schedule could be delayed past original estimate.
Budget Transfers
Amount             From                To
$0




Cwxyz{|}~
Port of Seattle 3Q 2018 Report  107

THIRD  QUARTER REPORT, 2018
Rental Car Facility Fleet Tracking System
Project : C800929                       Procure a fleet tracking system and   Project Status:
Budget:  $1,055,000                  provide next bus displays for         Schedule:  Within or Ahead 
Phase:  Implementation                passengers, voice paging, wireless     Budget:  On or Under
Start:  6/27/2017                         access, and music at all pick up        Status Reset: N/A
Schedule Completion: 3/31/2019       locations.                            (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Fleet tracking system has been deployed and is operational in Port buses.            1.2    1.06      1.06
Operational processes are being developed to fully utilize the new features.           1
Signage implementation is in progress.                                             0.8
0.6
Schedule                                                           0.4                 0.26
On Schedule                                                             Dollars in Millions 0.2
0
Budget                                                           Authorized Forecasted   Costs
Incurred
On budget
Construction Costs
Change Order                                               Not Applicable
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                    $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount                         
$0




C
108  Port of Seattle 3Q 2018 Report

THIRD  QUARTER REPORT, 2018
Radio System 
Project : C801012                       Upgrade key components of the      Project Status:
Budget:                   Port's Radio System including       Schedule:  Within or Ahead 
Phase:  Design                        subscriber equipment, tower site      Budget:  On or Under
Start:  4/24/2018                         equipment, hardware and software.    Status Reset: N/A
Schedule Completion: 3/31/2020                                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
End user equipment has been purchased. Design is in progress for core system       20
upgrades.                                                                            14.80     14.80
15
Schedule                                                           10
On Schedule                                                             Dollars in Millions  5
0.37
Budget                                                         0
On Budget                                                                 Authorized      Costs
Incurred
Change Order                                               Construction Costs
Current Quarter       Project Total          Not Applicable
Number of COs                 0                   0
Amount of Cos                 $0                    $0
Justification for COs: N/A
Ris
No significant risks at this time
Budget Transfers
Amount                         
$0




C"
Port of Seattle 3Q 2018 Report  109

THIRD  QUARTER REPORT, 2018
Airport Building Controls System "
Project : C801027                       Upgrade of the airport-wide central   Project Status:
Budget:                     building controls software           Schedule:  Within or Ahead 
Phase:  Planning                                                        Budget:  On or Under
Start:  7/24/2018                                                               Status Reset: N/A
Schedule Completion: 3/31/2020                                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Contract ready for signature.                                                          1          
Schedule                                                          Dollars in Millions 0.8
0.6
On Schedule
0.4
Budget                                                        0.2
0.00
On Budget                                                              0
Authorized      Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0               Not Applicable
Amount of Cos                 $0                    $0
Justification for COs: N/A
Ris
No significant risks at this time
Budget Transfers
Amount                         
$0





C
110  Port of Seattle 3Q 2018 Report

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.