Q4 NorthSTAR Program and North Satellite Briefing Presentation

Item No.          9b_supp 
Sea-Tac International Airport       Date of Meeting  February 26, 2019 
NorthSTAR Program
Fourth Quarter 2018
Program and North Satellite 
Project Update

2018 Q4 Brief News 
At budget & schedule.                   Opened 5 gates on Jan 23, 2019 
ADR tenants opening mid February and early March, 2019. Alaska TI, Alaska
Lounge are tracking progress to their openings 
Concourse C train station closed January 2, 2019 for duration of
construction, about 11 months 
Q4 project worker peak: 250 workers; safety scorecard 
Opened escalator NS2 
Small Business Apprenticeship/Utilization on track to meet or exceed goals 
Looking ahead to opening 5 more gates, remaining ADR spaces and
transitioning to Phase 2 

Within contracted budget and Schedule                                                            2

New Building 
Existing Building                             Phase 1A Opening 

3

4 

North Holdroom

5

AGENDA 
Project Overview 
2018 Quarter 4 News 
Budget 
Schedule 
Challenges 
Accomplishments 
Look Ahead 

North Satellite Modernization                                                                             6

PROJECT OVERVIEW 
12 to 20 contact gate positions 
263,000 sf to 428,000 sf 


Key elements: 
Infrastructure     Marketplace 
Gate additions    Station lobbies 
Clerestory "river" Technology 
Airline services    Seismic reinforcement 
North Satellite Modernization                                                                        7

2018 Q4 News 
At budget & schedule.                   Opened Phase 1A of 5 gates on Jan 23, 2019 
Tenant spaces (Alaska TI, Alaska Lounge) under construction by tenant;
tracking their progress to openings 
ADR tenants opening mid February and early March, 2019 
Concourse C train station closed January 2, 2019 for duration of
construction, about 11 months 
Q4 project worker peak: 250 workers; safety scorecard 
Collaborated with procurement and deployment of Port furnished items:
Passenger Loading Bridges, load dock equipment, recycle containers 
Opened escalator NS2 
Performed simulation and successfully activated Phase 1A 
Within contracted budget and Schedule                                                            8

FINANCIAL PROGRESS REPORT 
Authorization Summary       Capital    Expense     Total 
Current Budget                $659.8M    $12.3M     $672.1M 
Millions
$700
Current Authorization          $659.8M    $12.3M     $672.1M 
$600
Remaining to be Authorized       $0.0M     $0.0M       $0.0M 
$500                                                                               Total Project (Capital + Expense) 
$400
Prior         Period        Current     Spent to Date     Forecast at      Variance 
Budget       Changes       Budget                    Completion 
$300
Soft Cost          $94.2M      $0.0M     $94.2M      $60.7M     $103.2M        $9.0M 
$200
Construction    $545.9M      $5.8M    $551.7M    $217.8M     $568.9M      $17.2M 
$100
Construction
$15.3M   <$5.0M>    $10.3M                 $0.0M   <$10.3M> 
Contingency 
$-
Management Reserve Remaining           Project
$1.1M   <$0.2M>      $0.9M                  $0.0M    <$0.9M> 
Construction Remaining                    Contingency 
Construction Spent                         Management
$15.6M   <$0.6M>    $15.0M                 $0.0M   <$15.0M> 
Soft Cost Remaining                        Reserve 
Soft Cost Spent                                           $672.1M     $0.0M   $672.1M   $278.5M    $672.1M        $0M 
Financial Breakdown  Project Tracking forecast At Authorized Budget                               9

FINANCIAL PROGRESS REPORT 
Value   Deducts from Management Reserve 
<$648,900>   Tenant Improvements (1) 

<$648,900>   TOTAL DEDUCT FROM MANAGEMENT RESERVE 
Management Reserve was reduced by $643,900 during Q4 2018 for addition of Phase 2 Service Corridor 
Management Reserve will be further reduced to cover the forecasted $3.5M overage to reconcile the final
contractual Design Development Allowance 
Forecasting the remaining $10.3M Construction Contingency will be spent on current trends ($11.4M), risks
in retrofitting the existing building and additional unforeseen underground items (utilities, contaminated
soil) 
Forecasting future reductions in the $15.9M Project Contingency and Management Reserve for additional
discretionary changes, risks in retrofitting the existing building, unforeseen items, retaining staff (soft
costs) and to replenish construction contingency 
$351.1M in construction remain to be spent 


Management Reserve Utilization Last Quarter                                                      10

SCHEDULE 
Phase 1A                       Phase 1B
Building                                              Occupancy                       Occupancy 
Steel Superstructure                                                Enclosed                                              1/23/2019                       May/2019 
(12/17 thru 2/18)                                                 Aug 2018 
Phase 1 Escalators and Elevators 
(2/18 thru 4/19) 
Phase 2A
Ramp Concrete                                                                                                                         Occupancy 
Systems Install / Commission & Activation 
(4/18 thru 6/18)                                                                                                                         Q2/2021 
Roof Insulation 
Phase 2B
(3/18 thru 8/18) 
Occupancy 
Exterior Skin                                                                                                                      Q3/2021 
(4/18 thru 8/18) 
Mech / Elect / Plumbing 
(3/18 thru 11/18) 
Penthouse Rough-in 
(4/18 thru 10/18) 
Exterior Stairs 
(7/18 thru 9/18) 
Apron Paving & Utilities 
(4/18 thru 11/18) 
Emergency Generator 
(8/18 thru 10/18) 
PLBs / Finishes
(9/18 thru 5/19) 


<> 

Critical Path on track through Phase 1 opening                                                        11

SMALL BUSINESS/APPRENTICESHIP UTILIZATION 
SCS/SBE/WMBE                                APPRENTICESHIP 
WMBE Const                                                              Overall
(3.6%)                                                                                (15%)

SBE Const
(16%)                                                                       Women
(10%)
SCS Const
(5.5%)
Minority
(15%)
SCS Design
(10%)
0.0%     50.0%    100.0%    150.0%    200.0%    250.0%
0.0%     20.0%     40.0%     60.0%     80.0%    100.0%    120.0%
Goal   Actual                                                Goal   Actual
On track to meet or exceed 2014 goals by completion 

Tracking close to or exceeding goals                                                                   12

CHALLENGES 
Construction Schedule  Remains on track, Opened Phase 1A January 23, 2019; tracking Phase 1B
opening May 6, 2019 
Central Core phasing - Complex; Minimize passenger and operational level of service impacts 
On budget; but need to cover scope changes during construction 
Completing work in an Operational Area 
Contractor Design Development forecast exceeds contract allowance; using Management Reserve to
cover excess 
Shortages of workers in critical trades are being mitigated by working additional days per week on
overtime 


North Satellite - CHALLENGES                                                                   13

ACCOMPLISHMENTS 
Phase 1A successful opening on schedule 
Performed full-scale passenger experience simulation (ORAT) of Phase 1A facilities 
Started construction in existing NSAT building 
Passenger Loading Bridge procurement and installation lessons learned will inform next phase
opening 
Conducted joint Commissioning and Activation meetings to develop Phase 1 Activation Plans
Finalized Port furnished Phase 1 A & B items including deployment, commissioning and activation
(ICT electronics, load dock equipment, recycle containers) 
Emergency Generator placed into service for NSAT 
On track to complete 5 tenant spaces for Airport Dining & Retail (ADR) tenant construction 
Closed Concourse C STS and vertical circulation to Concourse area for construction. Demolished
escalators 
North Satellite - ACCOMPLISHMENTS                                                                                        14

Look Ahead 
Open Expansion west side restrooms in March 
Open remaining ADR tenants and deploy temporary Grab and Go concession in expansion area in
February 
Activate new load dock with better accessibility and improved amenities in March 
NS2 escalator nearly complete 
Phase 1 Expansion 
o Ramp concrete placement on west in March 
o Ramp area progressing for new gates in May 
o Baggage expansion progressing 
o Third floor areas on track 
o Remaining expansion holdrooms and gate activation 
o Concourse C vertical circulation demolition and construction underway 
Continuing construction in Alaska Lounge 
Final LEED design submittal review by US Green Building Council anticipated February 
North Satellite - PROGRESS                                                                       15

Oct 2018 
Feb 2019 





View of the New Expansion from Fire Station                                                         16

Oct 2018 
Feb 2019 




View of the New Expansion from Concourse C                                                      17

Rendering of NSAT - 2016 



View from Air Cargo Road  February 2019 



View from Air Cargo Road                                                                          18

Construction Photos                                                                              19

20 

Full-scale Passenger Experience Simulation

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.