9b. CIP Briefing presentation

Item No.: 9b_Supp
Meeting Date: March 12, 2019
CORRECTED March 13, 2019
Capital Improvement Projects
Fourth Quarter
Report 2018

Agenda
Challenged Projects
Featured Projects
Future Dashboard Handout

Revised Briefing
2

Exception Report of Capital Project Variances
Exception Report of Capital Project Variances:
Out of 93 projects, 55 are in construction or implementation phase of
which 6 have new variances in Q4                       36M Variance
- 3 in Aviation
- 0 in Maritime & Economic Development
2.54 B
- 3 in Information Technology                                Budget

Out of 55 Construction Projects  6 new Variances
3

Three new Aviation Schedule Variances
Holdroom Seating for Concourse B and C  added 170
days (zero cost)
Charging capabilities delayed by old electrical panels
Video System Improvements final component (South
Satellite) delayed due to field condition issues.
All work will be completed within the grant funding
window by May 2019
AOA Perimeter Fence  Delayed due to additional
requirements from Security and TSA.
Delayed by 90 days to September 2019
Three new variances
4

Information & Communication Technology Two new
Schedule and one new Budget variances
PeopleSoft Financials Upgrade  Delay due to additional testing needs.
Upgrade scheduled in June 2019.
Project Delivery System  Resource constraints delay optimum deployment of
features until Q2 2019
Additional system features will ensure a more successful cutover .
Airport Subway Information Displays  System complete in most locations but
unanticipated complexity requires budget increase of $285,000.
Scheduled Q2 2019 completion.
Three new variances
5

Featured Project: Main Terminal Low Voltage
Purpose: Ensures reliable electric power, safe operations,
maintenance
Scope: Renewal and replacement of low voltage (600 volts and
below) electrical distribution equipment in the Main Terminal.
Delivery: General Contractor/Construction Manager
Budget: $100.3M
Schedule: Design Complete Q1 2022; Construction: Q3 2021 
Q3 2025
Significant Developments: Procurement for the Design
Consultant and Contractor are in progress and will be
completed within schedule.
Risks/Challenges: Limited times for shutdowns require
coordination with Operations
Aviation - Sustain airport electrical infrastructure
6

Featured Project: SSAT Infrastructure Upgrades
Purpose: Improve the effectiveness of the heating, ventilation,
and air conditioning system
Scope: Replace hot/cold deck fans, energy efficient air
handlers,
coils, ceiling, lights, fire sprinklers, signage, and carpet.
Delivery: Design-Bid-Build
Budget: $52.2M
Schedule: Design completed; Construction: Q1 2019  Q1
2022
Significant Developments: Two bids received, both below the
Engineer's Estimate
Risks/Challenges: Unforeseen site conditions

Aviation - Meeting need to provide reliable SSAT climate control
7

Featured Project - Blue Carbon Pilot Project
Maritime Division is conducting a pilot project to evaluate the ability to enhance blue carbon processes at Smith
Cove. The project team includes staff from the Port, Puget Sound Restoration Fund, NOAA, City of Seattle, UW, and
Grette Associates
Plant and install blue
carbon elements
(Kelp, eelgrass, shellfish
beds, marsh plants, and
riparian vegetation)
Monitor project over
time
Report results

Pilot Budget $300,000
Schedule events:
Installation  April 2018
May 2019
Maritime environmental pilot project
8

Featured Project - P69 Solar Panel System
Working with Puget Sound Solar to install solar panels at P69 Headquarters

Photovoltaic
system is designed
to generate
approximately
100,000 kWh
annually

Budget $515,000
Schedule events :
Installation Feb
2019

Economic Development - Work proceeding rapidly after receiving permit
9

Aviation Projects completed


Concourse D Hardstand Hold Room            Passenger Loading Bridge  S11

Two Significant Projects Completed in Q4
10

Information & Communication Technology
Projects Completed



Sea-Tac Mobile Apps                        Data Center Fail Over

Two Significant Projects Completed in Q4
11

Maritime Projects Underway
Aerial Photo of Salmon Bay
location of dredging Docks
D-E replacement location,
new docks and lighting
panels in plan

The steel piles supporting FiT Docks 3, 4, and 5 were installed in the
early 1980s. The piling consists of thin steel hollow pipes filled with
unreinforced concrete. The pile system provided reliable service for
the past 35 years, but corrosion is manifesting within the splash zones
and near the mud line of some piling, compromising the integrity of
the system and requiring the prevention of future corrosion.
Both projects in design
12

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.