9b. CIP Briefing presentation
Item No.: 9b_Supp Meeting Date: March 12, 2019 CORRECTED March 13, 2019 Capital Improvement Projects Fourth Quarter Report 2018 Agenda Challenged Projects Featured Projects Future Dashboard Handout Revised Briefing 2 Exception Report of Capital Project Variances Exception Report of Capital Project Variances: Out of 93 projects, 55 are in construction or implementation phase of which 6 have new variances in Q4 36M Variance - 3 in Aviation - 0 in Maritime & Economic Development 2.54 B - 3 in Information Technology Budget Out of 55 Construction Projects 6 new Variances 3 Three new Aviation Schedule Variances Holdroom Seating for Concourse B and C added 170 days (zero cost) Charging capabilities delayed by old electrical panels Video System Improvements final component (South Satellite) delayed due to field condition issues. All work will be completed within the grant funding window by May 2019 AOA Perimeter Fence Delayed due to additional requirements from Security and TSA. Delayed by 90 days to September 2019 Three new variances 4 Information & Communication Technology Two new Schedule and one new Budget variances PeopleSoft Financials Upgrade Delay due to additional testing needs. Upgrade scheduled in June 2019. Project Delivery System Resource constraints delay optimum deployment of features until Q2 2019 Additional system features will ensure a more successful cutover . Airport Subway Information Displays System complete in most locations but unanticipated complexity requires budget increase of $285,000. Scheduled Q2 2019 completion. Three new variances 5 Featured Project: Main Terminal Low Voltage Purpose: Ensures reliable electric power, safe operations, maintenance Scope: Renewal and replacement of low voltage (600 volts and below) electrical distribution equipment in the Main Terminal. Delivery: General Contractor/Construction Manager Budget: $100.3M Schedule: Design Complete Q1 2022; Construction: Q3 2021 Q3 2025 Significant Developments: Procurement for the Design Consultant and Contractor are in progress and will be completed within schedule. Risks/Challenges: Limited times for shutdowns require coordination with Operations Aviation - Sustain airport electrical infrastructure 6 Featured Project: SSAT Infrastructure Upgrades Purpose: Improve the effectiveness of the heating, ventilation, and air conditioning system Scope: Replace hot/cold deck fans, energy efficient air handlers, coils, ceiling, lights, fire sprinklers, signage, and carpet. Delivery: Design-Bid-Build Budget: $52.2M Schedule: Design completed; Construction: Q1 2019 Q1 2022 Significant Developments: Two bids received, both below the Engineer's Estimate Risks/Challenges: Unforeseen site conditions Aviation - Meeting need to provide reliable SSAT climate control 7 Featured Project - Blue Carbon Pilot Project Maritime Division is conducting a pilot project to evaluate the ability to enhance blue carbon processes at Smith Cove. The project team includes staff from the Port, Puget Sound Restoration Fund, NOAA, City of Seattle, UW, and Grette Associates Plant and install blue carbon elements (Kelp, eelgrass, shellfish beds, marsh plants, and riparian vegetation) Monitor project over time Report results Pilot Budget $300,000 Schedule events: Installation April 2018 May 2019 Maritime environmental pilot project 8 Featured Project - P69 Solar Panel System Working with Puget Sound Solar to install solar panels at P69 Headquarters Photovoltaic system is designed to generate approximately 100,000 kWh annually Budget $515,000 Schedule events : Installation Feb 2019 Economic Development - Work proceeding rapidly after receiving permit 9 Aviation Projects completed Concourse D Hardstand Hold Room Passenger Loading Bridge S11 Two Significant Projects Completed in Q4 10 Information & Communication Technology Projects Completed Sea-Tac Mobile Apps Data Center Fail Over Two Significant Projects Completed in Q4 11 Maritime Projects Underway Aerial Photo of Salmon Bay location of dredging Docks D-E replacement location, new docks and lighting panels in plan The steel piles supporting FiT Docks 3, 4, and 5 were installed in the early 1980s. The piling consists of thin steel hollow pipes filled with unreinforced concrete. The pile system provided reliable service for the past 35 years, but corrosion is manifesting within the splash zones and near the mud line of some piling, compromising the integrity of the system and requiring the prevention of future corrosion. Both projects in design 12
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.