6d Rental Car Pavement memo

COMMISSION 
AGENDA MEMORANDUM                        Item No.          6d 
ACTION ITEM                            Date of Meeting       April 23, 2019 
DATE:     April 16, 2019 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Mike Tasker, Sr Manager - AV Facility & Infrastructure 
Wayne Grotheer, Director Aviation Project Management 
SUBJECT:  Rental Car Facility (RCF) Pavement Remediation (CIP #C800977) 
Amount of this request:              $ 6,845,000 
Total estimated project cost:          $ 8,303,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to advertise and execute a major
works construction contract for the Rental Car Facility  Pavement Remediation project at
Seattle-Tacoma International Airport. The amount being requested under this authorization is
$6,845,000 of a total estimated project cost of $8,303,000. 
EXECUTIVE SUMMARY 
Several RCF assets need renewal or replacement sooner than anticipated due to greater usage
and potential design errors and omissions or construction latent defects. The assets that will be
addressed include the floor expansion joints and topping slab, the helices, S. 160th St. driveway,
and the weatherproofing membranes in the car wash areas. Since the previous authorization 
for design, the scope of the project has increased to include the replacement of the existing
perimeter fence and resealing the employee and visitor parking. 
The RCF Lease Agreement between the Port and the Rental Car Operators ("Operators")
includes provisions for major maintenance improvements during the life of the facility.
According  to  the  Lease,  the  Port  is  responsible  for  completing  major  maintenance
improvements, which are to be funded from a major maintenance fund supported by Customer
Facility Charges (CFCs).  Major maintenance is generally classified as the full replacement of
certain assets, as defined in the Lease Agreement, or for repairs and replacements exceeding
$341,087.37, which is adjusted annually. CFCs are collected from rental car customers and the
funds are restricted for capital and operating costs that support the RCF and rental car
operations at the airport. This project is included in the 2019  2023 capital budget and plan of
finance. The current estimated project cost will result in budget savings of $2,184,000 from the
previously identified budget of $10,487,000.

Template revised January 10, 2019.

COMMISSION AGENDA  Action Item No. ____                                Page 2 of 5 
Meeting Date: April 23, 2019 
The parallel effort that is looking into whether the need for remediation of any of the assets
being renewed could be attributed to design (Error and Omission) or construction (Latent
Defect) is still ongoing. Additional information on the progress of this effort is provided in the
"Additional Background" section of the memo. 
JUSTIFICATION 
The project scope includes several major maintenance improvements for the facility that the
Port has the responsibility to complete under the terms of the RCF Lease Agreement. The
Operators have requested that the Port complete these improvements as expeditiously as
possible since many are essential to their operations. Completing the perimeter fence in a
timely manner is also essential to ensure the safe and secure operations of the facility. This
project supports the Port's Century Agenda strategy of advancing this region as a leading
tourism destination and business gateway by meeting the region's air transportation needs at
Sea-Tac Airport for the next 25 years. 
DETAILS 
The project will be completed in two phases. Phase one consisted of the early replacement of
critical portions of the fifth floor topping slab in support the Operators' request for expeditious
action and was completed in October 2018 by Port Construction Services (PCS). Phase two
includes the remaining scope. 
The project scope has been modified during the design phase. The scope decreased with the
reduction in area for the replacement of the fifth floor topping slab since testing proved it was
not as damaged as originally thought. The scope  increased to include the replacement of
existing perimeter site fencing with a 10-foot no-climb fence to address site security concerns 
and resealing the fifth floor employee and visitor parking areas to address weather proofing
and safety concerns at these locations. 
Diversity in Contracting 
Project staff worked  with the Economic Development Division   Diversity in Contracting
Department and determined this contract will have an eight percent WMBE aspirational goal. 
Scope of Work 
The project will complete the major maintenance improvements described below. 
(1)   Replace and upgrade the fifth floor expansion joints in the bus operation area 
(2)   Replace and upgrade portions of the fifth floor topping slab in the bus operation area
due to excessive cracking and spalling 
(3)   Route and seal cracks in the deck and beams of both Helices 
(4)   Complete pavement rehabilitation on the existing S. 160th St. driveway 
(5)   Replace the weatherproofing membrane at carwash areas at the RCF located on the
second and fourth floors of the facility 
(6)   Replace existing perimeter fence with a 10-foot no-climb fence 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. ____                                Page 3 of 5 
Meeting Date: April 23, 2019 
(7)   Reseal the employee and visitor parking areas 
Schedule 
Construction start                                2019 Quarter 3 
In-use date                                       2020 Quarter 3 
Cost Breakdown                                     This Request           Total Project 
Design                                                    $887,000             $2,217,000 
Construction                                             $5,958,000             $6,086,000 
Total                                                         $6,845,000              $8,303,000 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1  No major maintenance improvements are completed for the RCF. 
Cost Implications: $0 
Pros: 
(1)   Capital investment not required. 
Cons: 
(1)   The Port does not meet its obligations under the terms of the RCF Lease Agreement. 
(2)   The facility could suffer further damage that could make portions of it unusable by the
Operators and significantly reduce its asset life. 
(3)   A key security concern at the RCF would continue without being addressed. 
This is not the recommended alternative. 
Alternative 2  This alternative includes the original project scope that was authorized by the
Commission. 
Cost Implications: $3,000,000 
Pros: 
(1)   The Port meets its obligations under the terms of the RCF Lease Agreement. 
(2)   The improvements are completed that maintain or prolong the asset life of the facility. 
Cons: 
(1)   Requires significant capital investment by the Port funded by CFC revenues. 
(2)   Significant impacts to facility operations during construction. 
(3)   A key security concern at the RCF would continue without being addressed. 
(4)   Does not reseal the employee and visitor parking areas to address weatherproofing
and safety concerns. 
This is not the recommended alternative. 


Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. ____                                Page 4 of 5 
Meeting Date: April 23, 2019 
Alternative 3  This alternative includes the original project scope that was authorized by the
Commission plus the two scope additions (no-climb site fencing, resealing of employee and
visitor parking). 
Cost Implications:  $8,303,000  ($2,184,000 less than the 2018 total project estimate of
$10,487,000) 
Pros: 
(1)   The Port meets its obligations under the terms of the RCF Lease Agreement. 
(2)   Most cost-effective approach to complete the improvements that maintain or prolong
the asset life of the facility. 
(3)   Includes the replacement of existing perimeter site fencing with a 10-foot no-climb
fence to address site security concerns, and the resealing of the fifth floor employee
and visitor parking areas to address weather proofing and safety concerns. 
Cons: 
(1)   Requires capital investment by the Port funded by CFC revenues. 
(2)   Significant impacts to facility operations during construction. 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
Cost Estimate/Authorization Summary              Capital        Expense           Total 
COST ESTIMATE 
Original estimate                                $10,487,000        $100,000     $10,587,000 
Current change                               ($2,184,000)         $50,000    ($2,134,000) 
Revised estimate                                $8,303,000        $150,000      $8,453,000 
AUTHORIZATION 
Previous authorizations                          $1,458,000        $150,000      $1,608,000 
Current request for authorization                $6,845,000               $0      $6,845,000 
Total authorizations, including this request       $8,303,000        $150,000      $8,453,000 
Remaining amount to be authorized                    $0             $0             $0 
Annual Budget Status and Source of Funds 
This project #C800977 was included in the 2019-2023 capital budget and plan of finance with a
total budget of $10,487,000. A budget reduction of $2,184,000 will be transferred to #C800754
Non-Aeronautical Allowance. This project will be funded by Customer Facility Charge (CFC)
funds per the terms of the RCF Lease Agreement. 
Financial Analysis and Summary 
Project cost for analysis              $8,303,000 
Business Unit (BU)                  Rental Car 

Template revised September 22, 2016; format updates October 19, 2016.

COMMISSION AGENDA  Action Item No. ____                                Page 5 of 5 
Meeting Date: April 23, 2019 
Effect on business performance     NOI after depreciation will decrease 
(NOI after depreciation) 
IRR/NPV (if relevant)                N/A 
CPE Impact                       None 
Future Revenues and Expenses (Total cost of ownership) 
According to the terms of the RCF Lease Agreement the Operators are responsible for majority of
the on-going operating and maintenance costs of the facility. 
ADDITIONAL BACKGROUND 
Staff is separately investigating whether any of the deterioration of the assets being renewed is 
due to design (errors and omissions) or construction (latent defects) of the facility. To date
discoveries associated with this effort have led to: 1) the completion of the Bridge 2 structural
improvements through a three-party agreement with the Port, Contractor, and Designer of
Record, 2) reductions in scope of the fifth floor topping slab replacement, and 3) reduction of
number of carwash areas requiring replacement of the weather proofing membranes. These
findings reflect a savings of just over $1,000,000 to the project. 
Staff continues to work on determining the root cause of the severity of the helix cracking and
the waffle pattern radiating at the fourth floor carwash area. Both efforts are expected to be
completed by end of second quarter of  2019.   If the Port does ultimately receive
reimbursement by either the Designer of Record or Contractor, those funds will be used to
replenish the CFC Fund to the extent the costs reimbursed were paid for with funds from the
CFC Fund. 
ATTACHMENTS TO THIS REQUEST 
(1)   Presentation slides 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
July 10, 2018  The Commission authorized execution of a professional services contract for
design services, proceeding with the design and preparation of contract bid documents,
and use Port Construction Service (PCS) crews to perform the early construction work. 





Template revised September 22, 2016; format updates October 19, 2016.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.