6d Fire Pump Replacement Presentation

Item No. 6d_supp
Meeting Date: December 10, 2019
Fire Pump Replacement
CIP C800794
Tyler Salisbury
AV PMG - Infrastructure

Project Scope and Location
Replace four (4) emergency
fire pumps
Originally installed in 1970's
Install isolation valves
Single pump isolation for
maintenance
Install a flow meter system
Annual in-house certification

2

Fire Pump Replacement
Wat er Tower Fill
Supply Loop


Bo osted supply


Original Building  1970s (Green)
Building expansion and Pump Upgrade  2000's (Yellow)
Isolate and Replace
High Flow needs
19,000 GPM at 110 PSI (Hanger fire)
Minimum of 5 pumps needed to sustain the need

3

Fire Pump Replacement
Equipment to be replaced:
Diesel engine
Battery bank
Pump head and shaft
Controller panel
Check valve
Pressure relief valve
Install of new equipment:
Isolation valve


4

Flow Measurement
Wa ter Tower Fill


Boosted
supply

Annual Flow Ce rtification
Bypass line
Linear requirements
Inline flow meter system (Direct pressure measurement)
Fill reservoir when testing

5

Schedule
Commission for Design and Construction  4 Quarter 2019
Alternate Procurement  Building Engineering Systems
Advertise for Bid  1st Quarter 2020
Contract Award  2nd Quarter 2020
Design Complete  4th Quarter 2020
Construction Start  4th Quarter 2021
Substantial Completion  3rd Quarter 2021
6

Project Risks
1.  Pump Failure  This project will remove 4 pumps from the 10
existing used as fire protection. If one of the 6 remaining pumps
has a significant failure event that takes it out of service the
system will only have 5 pumps available.
Mitigation  The system is periodically checked to ensure the pumps will
operate as needed. Peak load will only require 5 pumps at a minimum to
maintain coverage.
2.  Competitive market  This project is small in comparison to other
projects being advertised.
Mitigation  Additional steps are being taken to advertise the solicitation to
entice additional

7

Appendix
Alternatives




8

Alternative 1
Defer replacing the pumps until they are no longer operable.
Cost Estimate: $75,000 would need to be expensed.
Pros
This defers the expense to a later date.
Cons
This alternative may result in additional costs if the pumps need to be replaced on an emergency
need.
This alternative removes the additional capacity if multiple pumps are out of service.
This alternative does not address the need for an inline measurement for annual flow testing.
This alternative does not resolve the isolation issue on the pumps if one in the bank of four needs
service.
This alternative will result in an increased maintenance cost to keep underperforming pumps in
operation.
This is not the recommended alternative.
9

Alternative 2
Replace 4 pumps only.
Cost Estimate: $4,500,000
Pros
The replacement pumps will have a new service life.
Common equipment for all four pumps.
Reduced maintenance costs.
Cons
This alternative requires an outside contractor to certify the pumps annually.
This does not allow for individual isolation of each pump.
This is not the recommended alternative.
10

Alternative 3 - Recomended
Replace four fire pumps, install isolation valves, and install a flow
metering system.
Cost Estimate: $5,000,000
Pros
This alternative provides the most reliable means to fight a fire.
The alternative replaces four pumps, reducing costs as compared to performing two
projects replacing two pumps.
This allows for each pump to be isolated for maintenance.
This will allow the boiler shop employees the ability to re-certify the pumps annually.
Cons
This is the highest capital investment
11

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.