10e. Memo

T91 Berths 6 and 8 Redevelopment

COMMISSION 
AGENDA MEMORANDUM                        Item No.          10e 
ACTION ITEM                            Date of Meeting     February 13, 2024 

DATE :     January 4, 2024 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Kenneth R. Lyles, Director, Maritime Operations and Security 
Kelli Goodwin, Senior Manager, Maritime Operations 
Mark Longridge, Capital Project Manager, Seaport Project Management 
SUBJECT:  Terminal 91 Berths 6 & 8 Redevelopment Additional Construction Funding 
(CIP#s C102475, C801350) 
Amount of this request:              $22,000,000 
Total estimated project cost:         $98,000,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to approve additional funding in
the amount of $22,000,000 for construction of the Terminal 91 Berths 6 & 8 redevelopment and 
to award and execute a contract with the lowest responsible bidder. 
EXECUTIVE SUMMARY 
Higher than expected bids for the Terminal 91 Berths 6&8 redevelopment require additional
funds to proceed with the work. The project redevelops the condemned vessel berths and
adjoining apron areas of Berths 6 & 8 along the northeast side of Pier 90 at Terminal 91 to help
ensure the long-term viability of the Port of Seattle (Port) as the home to the North Pacific fishing
fleet.
The major works contract was advertised on November 1, 2023, and bids were opened for the
construction contract on December 20, 2023.  Three bids were received in response to the
construction advertisement.  However, acceptance of any of these bids would exceed the
previously authorized total project budget of $76,000,000. The   Engineer’s estimate of
construction cost for this contract was $49,615,105. The lowest bid received was from Pacific Pile
& Marine for a total of $72,636,235 which is $23,021,129 or 46% over the estimate.
This overage is chiefly attributed to very high escalation and volatility in the current construction
market, federal permit requirements, schedule constraints, and the specialized nature of the
work. In reviewing the bids there is no single item or class of work items that is driving the cost
increase, but rather an escalation across the board of all project elements. The Washington State
Department of Fish and Wildlife permit requirement to complete all impact pile driving within a
shorter in-water construction window (Sep 1 - Jan 15) is two months shorter than for similar work 

Template revised January 10, 2019.

             COMMISSION AGENDA – Action Item No. 10e                                 Page 2 of 9 
Meeting Date: February 13, 2024 
in previous years. The need to expedite the work to comply with the permit may have also
contributed to additional labor costs from extended and off-shift hours. The primary driver of
the increase remains underestimating construction cost escalation which has continued to
exceed the Port’s most conservative expectations in the current market which is not expected to
abate. The low bid and second bid differed by less than $60,000 or under one tenth of one
percent which signals that the bids reflect actual market rates for the work as currently scoped. 
The additional funds requested in this action will be used to cover the difference of the bid
amount including Washington state sales tax and to ensure funds are available for project
contingencies (project contingency has been maintained at 10% in the revised project estimate). 
The staff recommendation is to accept the low bid of Pacific Pile & Marine. Their bid has been
reviewed and confirmed that they are the lowest and responsible bidder. Acceptance of the low
bid would also meet the project goal of 5% WMBE participation. 
The project scope has been carefully developed over the past several years to restore the full 
utility of the existing berths, include sustainability features and minimize operational impacts to
Port and tenant operations, and to conduct the work as an interim action under Ecology oversight
because the project is within an active clean-up site. The project has gone through a long and 
complex permitting process for this work. As a result, limited opportunities exist to modify the
scope or contract packaging of the project without the risk of significant delay. Rejecting the 
current bids would delay completion of the berths and pier structure at least one to two years 
and could incur significant additional costs required to rescope and readvertise the project.
While scope reductions would be possible in this rebidding scenario, it could not make the project
fit within the original budget without significantly impacting the utility of the facility (halving the
berths for example) and undermining the purpose of the capital work. Given the current market,
even with significant scope reductions, rebidding may not result in any additional bids or in lower
project cost. 
Approval of this funding request will allow construction to begin with minimal delay to the
original construction schedule. 
JUSTIFICATION 
The redevelopment of Berths 6 & 8 supports the following Maritime Division goals toward
achieving Century Agenda objectives: 
1.  Continue to grow the economic value of the fishing and maritime cluster including the
number of local jobs and regional business revenue. 
2.  Prioritize uses that support the commercial fishing industry, with a focus on anchoring the
North Pacific fishing fleet in Seattle. 
3.  Supports the Port’s strategy to “be the greenest and most energy-efficient port in North
America” by installing solar array infrastructure, stormwater treatment infrastructure,

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10e                                 Page 3 of 9 
Meeting Date: February 13, 2024 
direct connection for vessel sanitary sewer, and replacing existing creosote piling with
cement and recycled steel materials.
Diversity in Contracting 
The project team has coordinated with the Diversity in Contracting Department to determine
appropriate Women and Minority Business Enterprise aspirational goals for this project and
identified a 5% contracting goal for the major works contract advertisement. 
DETAILS 
Berths 6 & 8 are the last remaining original timber pier berths at Terminal 91 and are at the end
of their service life. Approximately 30% of the apron is condemned, and the remaining sections
are posted with severe load limits. Originally built in the 1910s, this section of Pier 90 was most
recently  rehabilitated  in  1985,  and  little  has  been  done  to  the  structure  since  then.
Redevelopment of Berths 6 & 8 is critical to ensuring the long-term viability of the port as the
home to the North Pacific fishing fleet.
Planned redevelopment includes demolition of approximately 62,250 square feet of condemned
existing timber apron and replacement of approximately 780 linear feet of seawall (northerly
portion of Berth 6 and entire Berth 8), removal and relocation of existing gangway, floats and
boathouse, removal/replacement of existing small office structures, and reconstruction of a
concrete apron structure at 600 pounds per square foot along the current alignment. The project
includes the removal of over 2,200 failing creosote piles, installation of approximately 320
concrete and steel piles, with an overall decrease in overwater coverage. The project work also
includes stormwater improvements, upgraded shore power connections, renewable energy
through new solar panel arrays, and a direct connection for vessel sanitary sewer. 
In January of 2020 the Port Commission authorized staff to proceed with the design and
permitting phase of the project, and in August of 2023 authorized construction funding and the
advertisement of the major works contract. Staff has since completed the design and submitted
application packages for all required environmental permits and engaged important stakeholders
such as the Suquamish and Muckleshoot Tribes, City of Seattle’s Department of Construction and
Inspection, the Army Corps of Engineers, U.S. and Washington State Fish and Wildlife, NOAA
Fisheries, Washington State Department of Ecology, the Port's Neighbors Advisory Committee,
Port operations staff and current tenants in the design development. Demand for moorage at
Terminal 91 is strong. Several times during the shoulder seasons the load-limited and condemned
berth space at Terminal 91 impeded the facility’s ability to accommodate the needs of the North
Pacific fleet and other commercial vessels, research vessels and ships of state. This project will
also allow the Port  to remain ready to respond to future business opportunities. This project
responds to the sustained demand and will alleviate some of the shoulder season pressure by
providing space for three 250-foot-plus catcher processors. 
As noted in the 2017 Fishing Vessel Moorage Analysis for the Port by S2 Strategy, “fishing and
seafood processing sector of the maritime industry, has by far the largest revenue impact to the
state of any maritime sector.  And is at least equal in job production to the other sectors.…”

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10e                                 Page 4 of 9 
Meeting Date: February 13, 2024 
Recommendations included providing an additional three to four 200-400-foot berths by 2020
and to plan for berths to accommodate another ten to twelve boats of 175-400-feet over the
next decade. Restoring existing load limited and partially condemned moorage facilities to their
full capacity is the first step to meeting these future capacity needs. 
The Washington Maritime Federation recently completed a 2023 Economic Impact Assessment
of Washington’s Maritime Industry.  The Assessment identifies that “In total, the Washington
fishing and seafood production sector generated approximately $825 million in labor income in
2022. An estimated 780 businesses generated $3.8 billion in revenue.” This sector represents
8,300 jobs in the state. 
Scope of Work 
This project provides significant waterside and landside improvements, including the following: 
 Dock demolition and replacement, relocation of boat house and removal of existing small
boat floats. Demolition of the existing pier deck and structure, including removal or cutoff
of approximately 2,200 existing creosote piles.  Removal and regrading of the existing
under pier slope and replacement of the upland sheet pile wall.
 Placement of approximately 240 prestressed concrete structural piles and approximately
80 steel fender and guide piles, placement of 4 feet of riprap rock and habitat fish mix,
placement of the new concrete precast deck panels, bullrail, utilities, bollards, upgraded
shore power connection points and appurtenances. 
 Removal of the existing buildings A-310 building (currently leased by American Seafoods),
A-300, A-400, A-301, A-500, A-501 (occupied by Port Operations and police), removal of
existing pavement and installation of deep soil mixing soil amendments, stormwater
treatment system, and surface regrading.
 Replacement of the six existing buildings with two new modular buildings for tenant and
Port use, paving and striping, installation of electric vehicle charging infrastructure, and
installation of modernized electrical substation to service the buildings and vessels at the
pier. 
While there could be the possibility of reducing some of these scope elements to reduce costs if
the current bids were rejected, such as removing sustainability elements or one of the new
modular buildings, the maximum amount that could be expected to be reduced would be
approximately 10-12% of the cost without significantly reducing the core utility of the berths 
overall. Rejecting the bids to make these scope reductions and rebid again later would expose
the project again to further escalation and market volatility however. Given current escalation
rates it is entirely possible that even with significant scope reductions there might be no
appreciable savings. 


Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10e                                 Page 5 of 9 
Meeting Date: February 13, 2024 
Sustainability/Community Outreach 
This project will replace the existing creosote timber pier with a more environmentally
responsible concrete apron.  It is expected that all the existing creosote timber piles will be
removed from the water column, resulting in a significant reduction in the number of piles
overall. The plans also include a vessel sanitary sewer connection point to eliminate the use of
on-dock collection tanks and resulting truck transport of waste with its associated fuel use and
greenhouse gas emissions. 
The design collects and treats all stormwater collected on the new construction areas using a
cartridge filter vault, plus includes additional stormwater treatment elements to treat another
approximately 100,000 square feet of additional pier area outside the project limits.  This
additional scope will be funded by the Marine Stormwater Utility as a separate work project
included in this authorization.  Completing this work concurrently provides efficiency in both
design and construction and allows us to treat twice the impervious surface area before
discharging to the Sound. 
The new office structures are planned to be modular construction to reduce site construction
time and construction waste, with energy efficient heating, ventilation, and air conditioning
(HVAC) systems. Solar photovoltaic panels will be installed on the larger of the two buildings and
sized to produce sufficient power for all that building’s energy use. Both buildings will include EV
charging parking, which is being coordinated with the Port’s fleet management, and covered bike
racks to encourage alternate commuting methods. 
Port staff have been working with terminal users throughout the design to mitigate operational
impacts and have kept the Port’s Neighbors Advisory Committee (NAC) informed about the
project and potential neighborhood impacts. Outreach included regular updates at the NAC
monthly meetings which includes community leaders from Magnolia and Queen Anne. During
construction, staff will implement a communication plan to provide specific details to Queen
Anne and Magnolia neighbors, adjacent businesses and T91 tenants with a focus on noise from
the pile driving work. 
Schedule 
All in-water work associated with the work must be completed within the fish window from
August 1 to February 15 of each construction season, with pile driving for steel pile limited to 
September 1 to January 15, a two-month reduction from previous typical fish window permit
work. This presents another constraint to the project that will need to be closely monitored and
will likely require more than one full fish window construction period to complete the work. Both
federal and local permits are in process and expected to be issued in Q1 of 2024, but if delayed
still have the potential to affect the construction schedule. 


Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10e                                 Page 6 of 9 
Meeting Date: February 13, 2024 
Activity 
Commission design authorization               2020 Q1 
Design start                                       2020 Q3 
Commission Construction auth                 2023 Q3 
Commission Additional Construction auth       2024 Q1 
Construction start                                2024 Q2 
In-use date                                       2025 Q4 
Previous request estimates reflected the Engineer’s estimate of construction cost, escalated to
the construction period, including potential project risks. The project team performed a full risk
analysis of the project at both 30% and 90% design milestones to evaluate potential cost and
schedule risks and quantify them using a Monte Carlo probabilistic analysis. The project total of
the previous requests represented the 50th percentile estimate from the latest risk analysis
update.  Unfortunately,  this approach still significantly underestimated the total cost of
construction as evidenced by the bids received. 
Cost Breakdown                                     This Request           Total Project 
Design                                                           $0             $4,175,000 
Construction                                           $22,000,000            $93,825,000 
Total                                                        $22,000,000             $98,000,000 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1 – Maintain the status quo and cancel the redevelopment work for Berths 6 & 8.
Continue to enable limited operations of the berths for workboat moorage and keep the load
restrictions and condemnation of dock sections in place. 
Cost Implications: This alternative carries significant uncertainty and risk and accordingly much
variability in cost potential.  Maintenance costs for the berth are not currently high but would
expand greatly if a deck failure occurred, for example. 
Pros: 
(1) Lower initial capital cost 
Cons: 
(1) Significant risk to the existing creosote structure if kept in use 
Deterioration will continue, with larger failures possible 
(2) Current berth space demand from the Pacific fishing fleet not met 
(3) Revenue for these berths would remain minimal 
This is not the recommended alternative. 
Alternative 2 – Reject the current bids, look for potential scope reductions and/or grant
opportunities and rebid the work. 
Cost Implications: This alternative carries significant uncertainty and risk and accordingly much 

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10e                                 Page 7 of 9 
Meeting Date: February 13, 2024 
variability in cost potential. Anticipated federal grant award could be in the $5M-$20M range, if
successful. However, this type of grant would also carry significant cost increases due to typical
grant requirements (Build America/Buy American requirements would be anticipated to add
10%-15% to the total project cost for example). Total project cost range $90-120M 
Pros: 
(1) Potential for lower capital cost, or cost sharing with grant agencies 
Cons: 
(1) No guarantee of grant award. Cost savings may not be realized, even with
significant scope reductions and grant award 
(2) 1 to 2 year delay in project implementation 
(3) Reduced utility of berth and facility due to scope reductions 
This is not the recommended alternative. 
Alternative 3– Award the major works contract to the lowest bidder and implement the current
design, proceed with replacement of the deteriorated timber apron with a concrete apron
structure and associated improvements. 
Cost Implications: Total project cost $98 million 
Pros: 
(1)    Brings the berth back to full operation, replacing the deteriorated facility 
(2)    Provides much needed berth and staging space for the North Pacific fishing fleet 
(3)    Replacement  of  existing  creosote  pilings  and  apron,  with  far  fewer  concrete
elements. Significant environmental benefits 
Cons: 
(1)    Higher initial capital cost 
This is the recommended alternative. 
FINANCIAL IMPLICATIONS 
The current total project estimate has significantly increased from initial planning level estimates 
due to required additional scope, including upland soil improvements to meet current seismic
code and resultant building replacements, increased permitting mitigation costs, and historically
high construction escalation over the last several years. Cost increases  have been further
aggravated due to the pandemic and resultant manufacturing and supply chain issues, especially
for long lead items such as electrical equipment.
The current estimate includes pricing for the construction work obtained on a competitive low
bid basis. The low bid and second bid received were separated by less than 0.08%, which does
give confidence that this is the actual market price for the work as currently scoped. 
The summary below also includes a breakout of anticipated Environmental Remediation Liability
(ERL) costs for expenses incurred above regular construction costs due to historic contamination
of sites. In this case the estimate is for the cost of upland disposal of slope dredge spoils above

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10e                                 Page 8 of 9 
Meeting Date: February 13, 2024 
what in water disposal would cost.  These costs were not previously broken out in prior
authorizations. Final ERL costs will be determined based on actual construction costs. 
Cost                               Berth        Additional   Anticipated ERL         Total 
Estimate /Authorization    Redevelopment       Stormwater          funding 
Summary                  (U00554)       Treatment
(U00704) 
COST ESTIMATE 
Original estimate              $40,000,000                  $0                  $0   $40,000,000 
Previous changes – net       $35,600,000          $400,000                 $0   $36,000,000 
Current change              $19,900,000          $100,000        $2,000,000   $22,000,000 
Revised estimate             $95,500,000          $500,000         $2,000,000   $98,000,000 
AUTHORIZATION 
Previous authorizations       $75,600,000           $400,000                  $0   $76,000,000 
Current request for           $19,900,000          $100,000        $2,000,000   $22,000,000 
authorization 
Total authorizations,          $95,500,000           $500,000         $2,000,000   $98,000,000 
including this request 
Remaining amount to                $0               $0               $0           $0 
be authorized
Annual Budget Status and Source of Funds 
This project is part of the 2024 Capital Plan under C102475 Terminal 91 Berths  6 & 8
Redevelopment with a total project cost of $75,600,000. 
The redevelopment of the berths is being funded by the Tax Levy.  Additional stormwater
treatment work is being funded by the Stormwater Utility. 
Financial Analysis and Summary 
Project cost for analysis              $98,000,000 
Business Unit (BU)                  Elliott Bay Fishing and Commercial Operations 
Effect on business performance    The redeveloped berths are expected to increase annual
(NOI after depreciation)             moorage revenue by approximately $977,000 in the first
full year of operation. 
Annual depreciation expense is estimated to increase by
approximately $2 million based on an expected useful life
of 50 years. 

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10e                                 Page 9 of 9 
Meeting Date: February 13, 2024 
IRR/NPV (if relevant)                NPV: ($70 million) 
Payback Period: 44 years (assuming 5% annual dockage
rate increase) 
ATTACHMENTS TO THIS REQUEST 
(1)   Presentation slides 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
August 8, 2023 – The Commission authorized Construction funding of $71,825,000. 
January 7, 2020 – The Commission authorized Design and Permitting funding of $4,000,000. 














Template revised June 27, 2019 (Diversity in Contracting).



Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.