2. Attachment

Minutes for approval

P.O. Box 1209 
Seattle, Washington 98111 
www.portseattle.org; 206.787.3000 
APPROVED MINUTES 
AUDIT COMMITTEE SPECIAL MEETING
December 14, 2023
The Port of Seattle Commission Audit Committee met in a special meeting Thursday, December 14, 2023.
The meeting was held in the Commission Chambers located at the Port of Seattle Headquarters Building,
2711 Alaskan Way, Seattle, WA, and virtually via Microsoft Teams.  Committee   members   present
included Commissioners Cho and Mohamed and Public Member Sarah Holmstrom (non-voting). 
1.    Call to Order: 
The committee special meeting was called to order at 10:00 a.m. by Commissioner Mohamed. The agenda
was approved without objection.

*Internal Audit Department presentation is found here and contains information for Agenda Items 5 through
10 and 12. 
2.    Approval of Audit Committee Meeting Minutes of September 7, 2023
The minutes of the Audit Committee special meeting of September 7, 2023, were approved without 
objection. 
EXTERNAL AUDITS 
3.    Moss Adams – 2023 Financial Statements Audit Engagement Service (Presentation)

Presenters: 
Olga Darlington, Partner 
Anna Waldren, Senior Manager 
Connor McCauley, Senior Manager 
The Office of the Washington State Auditor presented regarding the opening of the 2023 financial
statements audit.
The opening audit addressed: 
• scope of services; 
• auditor and management responsibilities;

            PORT COMMISSION AUDIT COMMITTEE MEETING MINUTES             Page 2 of 2 
THURSDAY, DECEMBER 14, 2023 
• audit procedures; 
• accessing financial statements from management to make sure they are free of misstatements; 
• areas of audit emphasis; 
• audit timeline; and 
• recent and upcoming accounting developments. 
Members of the Committee thanked the Moss Adams team for their presentation. 
4.    R.L. Townsend & Associates – Construction Audit Services Annual Report (Presentation)

Presenters: 
Debbie Townsend, President and Executive Construction Cost Control Consultant 
Patricia Farrell-Shear, Project Executive 
Rachel Smith, Senior Professional Associate 
RL Townsend & Associates presented regarding the construction audit services annual report.
The presentation addressed: 
• EC/CM monthly pre-construction and construction invoices and confirmation that billings are in
accordance with the contract; 
• review of pre-construction pay applications; 
• review of construction pay applications; 
• issues identified including billings for individuals not identified in the subcontract; individuals billed
at labor rates that exceed the subcontract rates; and minimal backup documentation on change
orders. 
Identified issues were presented to the Port and to Turner Construction. 
Members of the Committee and audit staff discussed the turnaround time to solve these issues and
receiving a follow-up report on the status of this audit at the March 2024 Audit Committee meeting. 
Members of the Committee thanked the RL Townsend staff for their audit and presentation. 
UPDATES AND APPROVALS 
5. Outreach Project Update 
Presenters: 
Glenn Fernandes, Director, Internal Audit 
The presentation addressed: 
• assisting small businesses to build controls to avoid phishing scams and ACH fraud; 
• resources available on the internal audit website; 
• in-house training conducted at the Port; 
• next steps to include control training for newly hired Port managers and staff, and separately, the
2024 concession audit plan will touch several small businesses and the Port will be integrating
controls training into opening meetings with smaller concessionaires.

            PORT COMMISSION AUDIT COMMITTEE MEETING MINUTES             Page 3 of 3 
THURSDAY, DECEMBER 14, 2023 
Members of the Committee thanked the audit staff for their continued work to make this information and
resources available. 
6.     2023 Audit Plan Update 
Presenters: 
Glenn Fernandes, Director, Internal Audit 
Mr. Fernandes overviewed the status of the approved 2023 Audit Plan, including Limited Contract
Compliance; Performance Audits; and Information Technology Audits.
The presentation addressed: 
• audits pushed back, including the Post IAF airline realignment and equity policy directive audits; 
• identified risks for management action; 
• looking at audits with an equity lens; 
• increases in GC/CM projects at the port in the next seven years; 
• suggested capital recoveries; and 
• controllable cost recommendations. 
Members of the Committee thanked Mr. Fernandes for the update. 
7. Approval of Proposed 2024 Internal Audit Plan 
Presenters: 
Glenn Fernandes, Director, Internal Audit 
The presentation addressed: 
• 2024 performance audit plan approach; 
• mandated audits; 
• 27 projects currently scheduled for review; 
• risk considerations; 
• required GC/CM independent audits; 
• lease and concession audit plan approach; 
• proposed 2024 lease and concession audits scheduled; 
• 2024 information technology audit plan approach and audit plan; 
• 2024 limited contract compliance, performance, and information technology audits planned; and 
• contingency audits proposed. 
Commissioner Mohamed requested that the delegation of authority process audit come back to the
Commission and be reported out to the Audit Committee. 
The motion, to recommend approval of the 2024 audit plan, carried by the following vote: 
In favor: Cho and Mohamed (2) 
Opposed: (0)



PORT COMMISSION AUDIT COMMITTEE MEETING MINUTES             Page 4 of 4 
THURSDAY, DECEMBER 14, 2023 
8.  Open Issue Status 

Presenters: 
Glenn Fernandes, Director, Internal Audit 
Mr. Fernandes overviewed the status of Open Issues, reporting as of November 29, 2023. 
The presentation addressed five issues outstanding for over one year from the target date of completion;
and three information technology issues that do not currently have target dates assigned. 
Discussion ensued regarding:
• difficulty in understanding the graphs and what the target date means; 
• teams give the Audit staff action plans and target dates for resolving issues;
• length of time that open issues remain open; and 
• follow-up process for items that remain open. 
PERFORMANCE AUDITS 
9.  Airport Parking Garage (See Report) 
Presenters: 
Glenn Fernandes, Director, Internal Audit 
Dan Chase, Manager, Internal Audit 

The presentation addressed: 
• the airport parking garage scope and description; 
• public parking toll booth operations; 
• employee parking; 
• parking systems; 
• five issues identified in the audit regarding revenue lost as a result of improper billing and misuse
of parking cards, audit recommendations, and management’s response.
Discussion ensued regarding if the Port has considered going cashless and determining that not all
customers are in the position to utilize a cashless solution. 
Members of the Committee thanked the Internal Audit Department staff for their work on the audit, and
management for their responses. 
10. Police Department Seizures and Evidence Room (See Report) 
Presenters: 
Glenn Fernandes, Director, Internal Audit 
Dan Chase, Manager, Internal Audit


PORT COMMISSION AUDIT COMMITTEE MEETING MINUTES             Page 5 of 5 
THURSDAY, DECEMBER 14, 2023 
The presentation addressed: 
• composition and organization of the Port of Seattle Police Department; 
• the process for seizures and forfeitures of contraband that aligns with state regulations; 
• seized property and cash stored in the evidence room; 
• quarterly seizure reports prepared and provided to the Washington State Department of Revenue; 
• disposal process for items in this category in the evidence room; and 
• Internal Audit’s recommendation that management should adopt a formal policy regarding the
timely disposal of items on an annual basis; and 
• management’s concurrence with the audit recommendations. 
Members of the Committee thanked the Internal Audit Department staff for their work on the audit, and
management for their responses. 
INFORMATION TECHNOLOGY AUDITS 
11. Network Infrastructure Management (Aviation Maintenance) 
Presenters: 
Glenn Fernandes, Director, Internal Audit 
Ritika Marwaha, Manager, Internal Audit – IT 
(Item 11 is security sensitive and were discussed in non-public session.) 
LIMITED CONTRACT COMPLIANCE AUDITS 
12. Seattle Air Ventures (See Report) 
Presenters: 
Glenn Fernandes, Director, Internal Audit 
The presentation addressed: 
• the joint venture operated under the Hudson Group; 
• audit of two contracts representing 15 stores; 
• timeline of the audit; 
• 2021 and 2022 revenue reviewed; 
• differences between point-of-sale revenue and the general ledger; 
• Internal Audit’s recommendation for the dining retail group, in partnership with Internal Audit, to
continue discussions and seek documentation from Seattle Air Ventures to validate that accounting
records agree to verbal assertions; and 
• management’s response in agreeance with the audit findings, noting they will engage with Seattle
Air  Ventures  to  determine  what  is  causing  the  variance,  and  supporting  variances  with
documentation. 
Members of the Committee thanked the Internal Audit Department staff for their work on this audit.

            PORT COMMISSION AUDIT COMMITTEE MEETING MINUTES             Page 6 of 6 
THURSDAY, DECEMBER 14, 2023 
13. Committee Comments 
Internal Audit Director Glenn Fernandes thanked the committee for a great year and for their work. 
14. Adjournment 
There being no further business, the special meeting recessed at 11:50 a.m. and re-convened in a nonpublic
session to address security-sensitive information technology audit information for Agenda Item 11 for
approximately 30 mins.  The meeting adjourned immediately at the conclusion of the discussion and no
further action was taken. 
Prepared:                                         Attest: 
__________________________________          __________________________________ 
Michelle M. Hart, MMC, Commission Clerk            Toshiko Hasegawa, Audit Committee Chair
Minutes approved: March 28, 2024.



Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.