8e. Memo

Access Control in Communication Rooms

COMMISSION 
AGENDA MEMORANDUM                        Item No.          8e 
ACTION ITEM                            Date of Meeting       May 14, 2024 

DATE:     May 3, 2024 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Keri Stephens, Director, Aviation Facilities and Capital Programs 
Eileen Francisco, Director, Aviation Project Management 
SUBJECT:  Access  Control  in  Communication  Rooms  (CIP#  C800935)–Construction
Authorization 
Amount of this request:              $ 6,000,000 
Total estimated project cost:          $ 8,100,000 
ACTION REQUESTED 
Request Commission authorization for the Executive Director to (1) Advertise, bid, and execute a
major publics works construction contract, execute related project change orders, amendments,
work authorizations, purchases, contracts, and take other actions necessary to support and
deliver the Access Control in Communication Rooms Project within the approved budget; (2)
Authorize use of Port of Seattle crews to support construction activities, and any possible
abatement work for Access Control in Comm Rooms project at Seattle-Tacoma International
Airport.  Total request for this action is $6,000,000 for a total project cost not to exceed
$8,100,000. 
EXECUTIVE SUMMARY 
Communication rooms at Seattle-Tacoma International Airport (STIA) house telecommunications
and data processing equipment that are critical for airport operations.  The Port of Seattle
updated the security requirements for communications rooms and a subsequent security audit
identified deficiencies in communications rooms in need of correction. This project will bring all
STIA terminal communications rooms up to the latest Port of Seattle security standards by
installing (details intentionally omitted) enhanced security measures.
JUSTIFICATION 
This project is designed to comply with findings from an internal audit of the communication
rooms at STIA. The locations were identified in the audit, several have since been updated as
part of other projects, the remaining rooms will be addressed with this project. These sensitive
rooms contain vital communication equipment and cable interconnection infrastructure. The
findings from the audit revealed the requirement for increased security and access control for

Template revised January 10, 2019.

             COMMISSION AGENDA – Action Item No. 8e                                  Page 2 of 4 
Meeting Date: May 14, 2024 
these rooms. Existing key or cipher lock access does not meet the latest heightened security
requirements and access controls. The scope of this project will increase security measures to
meet current Port standards. 
Diversity in Contracting 
The project team, in coordination with the Diversity in Contracting Department, have set a 10%
woman and minority-owned business enterprise (WMBE) goal for this construction contract.
DETAILS 
This project will install the necessary access control devices and supporting infrastructure
equipment to communication rooms throughout the main terminal, to meet compliance with
audit findings and bring these locations to current Port standards. 
Scope of Work 
For security purposes, key details of the Access Control in Communication Room project have
been intentionally omitted: 
(1)   Construction services: 
a.  Modify room walls to accommodate infrastructure equipment. 
b.  Modify wall around door to accommodate access control devices. 
c.   Modify and/or replace doors as required. 
d.  Install associated wiring and interconnections for access control devices. 
e.  Installation of infrastructure equipment, access control devices, and surveillance
equipment. 
f.   Connection to current STIA Access Control System and surveillance system. 
g.   Set-up and removal of barricades for securing the rooms during construction. 
Schedule 
Activity 
Construction start                                2024 Quarter 3 
In-use date                                       2025 Quarter 4 
Cost Breakdown                                     This Request           Total Project 
Design                                                    $793,000             $2,893,000 
Construction                                             $5,207,000             $5,207,000 
Total                                                         $6,000,000              $8,100,000 



Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 8e                                  Page 3 of 4 
Meeting Date: May 14, 2024 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1 – Do not proceed with the project. 
Cost Implications:   Expense approximately $700,000 for Notebook and Design development
costs. 
Pros: 
(1)   Delays or defers capital investment. 
Cons: 
(1)   Audit findings remain unaddressed. 
(2)   Security of the communication rooms remain at current levels with no reduction in risk 
of unauthorized access. 
(3)   Change in software/hardware may happen during deferment. 
(4)   Potential for additional increase in costs for materials, labor, and/or inflation. … 
This is not the recommended alternative. 
Alternative 2 – Comply with Audit and secure STIA communication rooms. 
Cost Implications: $8,100,000 in capital cost. 
Pros: 
(1)   Complies with the Audit and brings the security access of these highly sensitive rooms
to current Port standards. 
(2)   Reduces the potential risk of unauthorized access onto critical STIA networks. 
(3)   Provides the owners of these rooms the ability to remotely monitor room and door
status. 
(4)   Provides better flexibility to control who has access to these very sensitive rooms. 
Cons: 
(1)   Capital Cost. 
This is the recommended alternative. 





Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 8e                                  Page 4 of 4 
Meeting Date: May 14, 2024 

FINANCIAL IMPLICATIONS 
Cost Estimate/Authorization Summary              Capital        Expense           Total 
COST ESTIMATE 
Original estimate                                 $2,893,000               $0      $2,893,000 
Previous changes – net                           5,207,000                0       5,207,000 
Revised estimate                                 8,100,000                0       8,100,000 
AUTHORIZATION 
Previous authorizations                           2,100,000                0       2,100,000 
Current request for authorization                  6,000,000                0       6,000,000 
Total authorizations, including this request         8,100,000                0       8,100,000 
Remaining amount to be authorized                    $0             $0             $0 
Annual Budget Status and Source of Funds 
This project C800935 is included in the 2024-2028 capital budget and plan of finance with a
budget of $8,100,000. The funding sources will be the Airport Development Fund and future
revenue bonds. 
Financial Analysis and Summary 
Project cost for analysis              $8,100,000 
Business Unit (BU)                  Terminal Building 
Effect on business performance     NOI after depreciation will increase due to inclusion of
(NOI after depreciation)             capital (and operating) costs in airline rate base 
IRR/NPV (if relevant)                N/A 
CPE Impact                       $0.02 in 2026 
Future Revenues and Expenses (Total cost of ownership) 
N/A 
ATTACHMENTS TO THIS REQUEST 
(1)   Presentation slides 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
December 13, 2022 – Design Authorization.


Template revised June 27, 2019 (Diversity in Contracting).



Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.