10c. Memo

S Concourse Evolution Facilitating Projects Design

COMMISSION 
AGENDA MEMORANDUM                        Item No.          10c 
ACTION ITEM                            Date of Meeting       May 14, 2024 

DATE:     May 7, 2024 
TO:        Stephen P. Metruck, Executive Director 
FROM:    Keri Stephens, Director, Aviation Facilities and Capital Programs 
Eileen Francisco, Director, Aviation Project Management 
SUBJECT:  S Concourse Evolution Facilitating Projects Design Authorization (CIP #801203) 
Amount of this request:                    $25M 
Total estimated project cost:           $1.9B-2.2B 
ACTION REQUESTED 
Request Commission authorization for the Executive Director  to  (1)  Prepare design and
construction bid packages for S Concourse facilitating projects, (2) Procure long-lead items, (3)
Utilize Port crews for design support, (4) execute an alternative delivery contract, and (5) Increase
the project authorization by $25,000,000 for a total project authorization to date of
$127,500,000. 
The total estimated S Concourse Program cost range is $1.9B to $2.2B. 
EXECUTIVE SUMMARY 
The S Concourse Evolution (SCE) project extends the useful life of the S Concourse, located at
Seattle-Tacoma International Airport (SEA), by upgrading structural, seismic, and all building
systems, meeting required building codes. This project also enhances the customer experience
by renovating and modernizing the existing S Concourse. A multi-phased construction approach,
combined with facilitating projects will address and mitigate the impact that S Concourse
construction will have on passengers, airlines, and airport operations. These facilitating projects 
directly offset gate and holdroom capacity lost at the S Concourse during construction through 
short-term improvements at multiple locations around SEA. 
This project does not increase the number of gates or increase the overall capacity at SEA. 



Template revised January 10, 2019.

             COMMISSION AGENDA – Action Item No. 10c                                  Page 2 of 7 
Meeting Date: May 14, 2024 
JUSTIFICATION 
The S Concourse facility is over 50-years old and is need of seismic, code, and passenger
experience upgrades. The SCE project will renew this important regional facility through its twotiered
project objectives: 
• To extend the useful life and meet current code including Structural/Seismic Upgrades 
• To re-purpose space left vacant from services moved to the International Arrivals Facility
(IAF) and enhance passenger experience, including Increased passenger amenities/level
of service and increased airport dining and retail (ADR) opportunities. 
During the initial Commission authorization for SCE design and project management support, the
project team communicated that they would come back to Commission on how to address the
project’s operational and passenger impacts during construction. The initial approach to project
phasing indicated that the necessary gate and holdroom outages during construction would
greatly impact aircraft operations, resulting in between 50 and 70 flights without a gate
assignment or parking position at SEA during the airport’s busiest days. 
Working with airlines at SEA as well as Operations, Customer Experience, Security and other
stakeholders, the project team developed a comprehensive plan to address the construction
impacts during the SCE project. The result is a unique multi-phase approach that accomplishes
the exterior seismic upgrades while limiting gate closures during any given project phase. This
phasing approach is paired with facilitating projects at other SEA locations that temporarily
accommodate the displaced flights. These facilitating projects are described fully in the details
section below and include a short-term holdroom facility to replace holdrooms eliminated at S
Concourse during construction, improvements at hardstand locations for passenger operations,
and converting an existing bussing gate back to a gate served by a loading bridge. 
Developing the planned approach to construction outages and passenger impacts took into
consideration a variety of competing factors including performance in offsetting project impacts,
cost, schedule, customer experience, airline support, and compatibility with SEA’s facility
planning objectives. 
Diversity in Contracting 
The SCE project designer has a DBE requirement of 12%, the project management and controls
contract has a WMBE requirement of 26%, and the two existing IDIQ contracts anticipated to be
used in support of the facilitating projects have existing WMBE requirements of 24% and 27%
which the project team will ensure is met. 
DETAILS 
The SCE project will extend the useful life of the building to support airport operations for
another 50 years by modernizing the facility. The phasing will occur such that no more than three
(3) positions for large international aircraft at S Concourse will be closed at a time. The facilitating

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10c                                  Page 3 of 7 
Meeting Date: May 14, 2024 
projects will be short-term projects to support operations during SCE construction, utilize existing
airport infrastructure when available, and are not permanent. 
Scope of Work 
S Concourse 
• Perform structural and seismic upgrades to meet code requirements. 
• Upgrade mechanical, electrical, plumbing, and communications systems. 
• Upgrade utilities inside and outside the building. 
• Install smoke control system to meet code. 
• Perform environmental and sustainability upgrades. 
• Ensure building meets ADA compliance. 
• Provide increased ADR opportunities. 
• Increase passenger amenities and level of service with additional restrooms, nursing
suite, children’s play area, and sensory room. 
Cargo 7 Hardstand and Short-Term Holdroom 
• Construct short-term holdroom serving aircraft hardstanding at Cargo 7 (holdroom
includes bathrooms, seating, modest dining and retail, and employee breakroom, to
replace facilities lost to construction in S Concourse). 
• Utility Modifications. 
• Additional Security and Lighting per Code. 
• Holdroom will be removed at the completion of the SCE project. 
Cargo 6 Hardstand 
• Re-purpose existing hardstand for passenger operations: 
o  Utility Modifications. 
o  Additional Security and Lighting per Code. 
o  Apron pavement replacement as required. 
Cargo 3 Ground Support Equipment (GSE) Storage Area 
• Re-purpose an existing parking area for storage of GSE during SCE project: 
o  Modify Perimeter Fencing. 
o  Additional Cameras and Lights to support employee shuttles, bus parking and GSE
storage. 
Gate D6 Passenger Loading Bridge (PLB) Conversion 
• Restore a gate currently configured for over-ramp bussing back to an aircraft contact gate: 
o  Remove existing D6 passenger ramp and bus parking and install a passenger
loading bridge. 
o  Modify adjacent passenger  loading bridges as needed  to support the D6
conversion. 

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10c                                  Page 4 of 7 
Meeting Date: May 14, 2024 

Supporting Equipment 
• Procurement of long-lead infrastructure and equipment (e.g., 400 Hz gate box, electrical
panels, pre-conditioned air unit). 
• Procurement of GSE to support passenger and employee operations at hardstands during
SCE construction (e.g., staff shuttles, busses, aircraft boarding ramps, aircraft GSE). 
Schedule 
The near-term focus will be on starting design for the facilitating projects and continuing with the
S Concourse design. 
Activity 
Commission Design Authorization – S           Q4 2022 
Concourse 
Commission Design Authorization –             Q2 2024 
Facilitating Projects 
Design Start – S Concourse                       Q1 2024 
Design Start – Facilitating Projects                 Q2 2024 
Commission Construction Authorization –        Q1 2025 
Facilitating Projects 
Construction Start – Facilitating Projects          Q2 2025 
Commission Construction Authorization – S     Q3 2025 
Concourse 
Construction Start – S Concourse                Q4 2025 
In-use date – Facilitating Projects                  Q1 2028 
Full In-use date – S Concourse                    Q3 2033 
Cost Breakdown                                     This Request           Total Project 
Design                                                       $25M                 $200M 
Construction                                                     $0            $1.7B-$2.0B 
Total                                                               $25M             $1.9B-$2.2B 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative  1  –  Utilize  a  standard  two-phase  concourse  renovation  approach  without
implementing facilitating projects at other SEA locations. 
Cost Implications: $1.4-1.7B. 
Pros: 
(1)   Shortest construction timeline. 
(2)   Smaller capital investment. 

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10c                                  Page 5 of 7 
Meeting Date: May 14, 2024 
Cons: 
(1)   Reduced airport and airline operational flexibility. 
(2)   Large impact to customer experience. 
(3)   Several significant operational constraints to passengers, airlines, and employees. 
This is the NOT the preferred alternative. 
Alternative 2 –Perform S Concourse renovation in up to five phases, and construct facilitating
projects at other SEA locations including short-term improvements to Cargo Hardstands 3, 6, and
7, and restore Gate D6 to a contact gate position. 
Cost Implications: $1.9B-$2.2B. 
Pros: 
(1)   Maintain airport operation flexibility with available gates per scheduled operations. 
(2)   Improved customer experience, especially for hardstand operations. 
(3)   Improved efficiency and operational continuity for passengers, employees, and airlines. 
Cons: 
(1)   Highest Capital Investment. 
(2)   Extends S Concourse construction duration 2 years. 
This is the Preferred alternative. 
FINANCIAL IMPLICATIONS 
The current estimate range is expected to be $1.9-2.2B. 
Cost Estimate/Authorization Summary               Capital        Expense            Total 
COST ESTIMATE 
Original estimate                                          $1B               $0               $1B 
Previous changes – net                               $370M              $0           $370M 
Current change                                     $500M              $0           $500M 
Revised estimate                               $1.9B - $2.2B              $0     $1.9B - $2.2B 
AUTHORIZATION 
Previous authorizations                         $102,750,000               $0     $102,750,000 
Current request for authorization                $25,000,000               $0      $25,000,000 
Total authorizations, including this              $127,750,000               $0     $127,750,000 
request 
Remaining amount to be authorized              TBD                   $0        TBD 
Annual Budget Status and Source of Funds 
This project, CIP C801203, was included in the 2024-2028 capital budget and plan of finance with
a budget of $1,370,000,000. A budget increase of $500,000,000 was transferred from the
Aeronautical Reserve CIP (C800753) resulting in zero net change to the Aviation capital budget.

Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10c                                  Page 6 of 7 
Meeting Date: May 14, 2024 
The funding sources would be revenue bonds, Airport Development Fund (ADF), the Bipartisan
Infrastructure Law (BIL) grant funding through the FAA-AIP program, and future Passenger
Facility Charge. 
Financial Analysis and Summary 
Business Unit (BU)                  Terminal Building        Terminal Building 
Project cost for analysis                                $1.9B                      $2.2B 
Infrastructure grants                                $225M                    $225M 
NPV incremental to Base                        $(223M)               $(339.5M) 
Non-aero net cashflow in 2034                  $(16.7M)                $(23.4M) 
Incremental Terminal Rental Rate                  $74.84                   $88.20 
CPE Impact in 2034                                 $3.73                    $4.40 
Future Revenues and Expenses (Total cost of ownership) 
The cost savings of keeping the current terminal operational would likely present no long-term
savings even with discounting the risk of a potential catastrophic failure; the terminal is still in
need of upgrades driven by code and safety. Balancing the deferral of these costs against the
structural, seismic, and operational needs of the terminal is not recommended. 
ADDITIONAL BACKGROUND 
The S Concourse (originally referred to as South Satellite) at SEA opened in 1973. The building 
has not been updated to meet current building codes for seismic restraint, includes infrastructure
past useful service life, and has been limited by code authorities from any further development 
due to code deficiencies. The building systems and materials are aging and are difficult/costly to 
replace and maintain.  The building also contains areas of encapsulated regulated materials, such
as asbestos, which further complicates maintenance, renovation, and replacement. Since the S
Concourse was constructed, passenger volumes and aircraft operations have increased
dramatically, security regulations have expanded, passenger level of service expectations have
evolved, and airlines and retailers have changed their marketing strategies.  Recently, the S
Concourse was connected directly to the new International Arrivals Facility (IAF) across the taxi
lane separating it via an above ground pedestrian walkway. TheS concourse evolution project
will  better  accommodate  current  passenger  volumes  and  improved  level  of  service  for
passengers and create a continuity of design from the IAF and walkway to the S concourse with
a seamless terminal aesthetic. 
ATTACHMENTS TO THIS REQUEST 
(1)   Presentation 


Template revised June 27, 2019 (Diversity in Contracting).

             COMMISSION AGENDA – Action Item No. 10c                                  Page 7 of 7 
Meeting Date: May 14, 2024 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
October 22, 2022 – The Commission authorized to procure a Designer, GC/CM, Project
Management/Controls Support, and Commissioning Agent for SCE. 
September 27, 2022 - The Commission was briefed on S Concourse Evolution and project
status. 
April 13, 2021 – The Commission was briefed on SSAT Renovation Renewal PDD. 
















Template revised June 27, 2019 (Diversity in Contracting).



Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.