8c. Presentation

Bell Harbor Marina Pier66 Corrosion Protection Project

Item No.: 8c_Supp
Meeting Date: May 28, 2024

C800539: Bell Harbor Marina Pile Wrap & Cathodic Protection
C800517: Pier 66 Breakwater Cathodic Protection

Linda Springmann, Director, Cruise and Maritime Marketing
Karlina Smith, Sr. Manager, Recreational Boating
Julie Yun, WPM Capital Project Manager

                Action Requested
Request Commission Authorization from the Executive Director to:
Request Commission authorization for the Executive Director to advertise 
and  execute  a  major  public  works  construction  contract  for  the 
completion of the Corrosion Protection projects at Bell Harbor Marina 
and Pier 66 (CIP# C800539 and C800517). This request is in the amount of 
$5,900,000 ($2,500,000 for C800539 BHM / $3,400,000 for C800517 P66) 
for a total estimated project cost of $7,095,000 ($3,145,000 for C800539 
BHM / $3,950,000 for C800517 P66).
2

                 Project Overview

P66/ BHM
Proj ect Area



3

                  Existing Condition


Corrosion and marine growth on battered piles         Typical anode with approximately 70% depletion
with no pile wrap

4

           Project Scope & Coordination
Project Scope:
– Pile Wrap at (92) steel piles at the south
apron
– Cathodic Protection Anode Replacement
at (498) steel piles at BHM and Pier 66.
Coordination:
– Permit approved in-water work window
with requested extension
– Avoid tribal fishery
– Facility operations (cruise season, rec
boating events schedule)
– Simultaneous projects

5

                      Project Info
Cost Breakdown                   This Request                     Total Project
C800539 (BHM)   C800517 (P66)   C800539 (BHM)   C800517 (P66)
Design                               $0              $0        $645,000        $550,000
Construction                   $2,500,000       $3,400,000       $2,500,000       $3,400,000
Total - per project                 $2,500,000        $3,400,000        $3,145,000        $3,950,000
Total - both projects                                  $5,900,000                           $7,095,000

6

                  Project Timeline
Activity                                                                        Date
Construction Authorization                                            5/28/2024
Advertise Contract                                                      Q4 2024
NTP                                                    Q1 2025
Construction Start                                                       Q4 2025
In-use date                                                              Q2 2026


7

                   Questions?


8



Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.