10b. Presentation
Post IAF Airline Realignment Construction Authorization
Item No. 10b_ supp Meeting Date: June 25, 2024 Post IAF Airline Realignment Construction Authorization (CIP# 801158) June 25, 2024 Project Purpose: Relocate United Airlines’ domestic only operations to Concourse B and thus increase international gate capacity on Concourse A. Scope of Work: CONCOURSE B CONCOURSE A 2 Requested Action Request Commission authorization for the Executive Director to approve (1) a total project budget of $154,500,000 and to allocate $85,800,000 of that budget for the Post IAF Airline Realignment Project at Seattle-Tacoma International Airport and (2) to execute the Maximum Allowable Construction Cost Contract Amendment, any related project change orders, amendments, work authorizations, purchases, contracts, and to take any actions necessary to support and deliver the project within the approved budget. 3 Cone of Certainty - 202406 4 Cost Breakdown Cost Estimate/Authorization Summary Current Budget $102,000,000 Budget Range per January 2024 Action $102M - $140M Revised Budget $154,500,000 Budget Increase $52,500,000 Previous authorizations $55,100,000 Current request for authorization $85,800,000 Total authorizations, including this request $140,900,000 Remaining amount to be authorized $13,600,000 (United Airlines Lounge remaining budget) 5 Reasons for Budget Increase Greater than anticipated Design budget • Additional design packages to accelerate enabling work, incorporate building and accessibility code deficiencies, and decouple Concourse B mechanical upgrades from delivery of airline realignment scope. • A/E Negotiated Level of Effort includes weekly on-site coordination during the RFI and Submittal process to mitigate schedule delays. Greater than anticipated Construction budget • Temporary provisions to maintain existing operations, uncovered since Project Notebook, have been identified through site investigation and design development. • Market conditions with bids received reflected higher costs than estimated at 60% design development and can be attributed to increases in material and shipping costs, shortages in the labor market and the complexity of the phased work. Reasons for Budget Increase Greater than anticipated Construction costs ($36M) • Additional construction to address building and accessibility code deficiencies, aging infrastructure and current Port Standards. • More temporary provisions to maintain existing operations • Bids received indicate changed market conditions with higher costs due to increases in material and shipping, shortages in the labor market and the complexity of the phased work. Undesirable size of bid packages created less bidder interest. Greater than anticipated Design and other Soft costs ($16M) • Additional design packages to start enabling work sooner, address code deficiencies, and occupy Concourse B offices sooner using temporary air handlers. • Additional on-site design staff to address early construction submittals and questions to mitigate schedule delay risk. • Complexity of construction requiring additional resources Phased Schedule Delivery Activity Enabling Work Construction Start 2024 – April 18 Airline Realignment Construction Authorization 2024 – June 25 Airline Realignment Construction Start 2024 – September In-use Date Concourse B offices and Concourses A&B gates 2025 – Quarter 3 In-use Date Concourse A offices 2026 – Quarter 1 8 Concourse B Cross Section Concourse B Ramp 10 Sustainability Framework • Environmental Regulatory EQUITY STRATEGIES Compliance Tier 2 Project • Gender Neutral Restrooms (non-public facing) • New safe & accessible interior corridor • Improved employee access to daylight at ramp • Met with Sustainability, CARBON/ENERGY STRATEGIES Environment, and Climate (SEAC) • Improved efficiency with updated controls Committee on 05.08.24 • Gas water heating replaced with electric • Exterior envelope thermal improvements • Equity, Carbon/Energy and MATERIALS STRATEGIES • Polyvinyl chloride (PVC) material removed from Materials Strategies incorporated specifications into design and included in • Emphasis on recycled materials that meet high construction costs. standard of durability 11 Project Risks RISK DESCRIPTION PROBABILITY IMPACT MITIGATION PLAN Unforeseen Existing Potential impacts to underground utilities and other Demolition activities for enabling scope have Conditions existing systems. commenced in advance of the airline realignment scope to allow more time for resolution of impacts M H identified. Additionally, 3D modeling coordination is ongoing to resolve conflicts in Mechanical and Electrical scope. Impact to Construction activities take place in and adjacent to Detailed phasing and operations discussions with Airport Operations existing operations. Port Facilities and Infrastructure, airlines and other L M stakeholders have informed the design and construction schedule to avoid impacts from project work. Electrical Electrical and mechanical component lead times may be The project team has identified these components Component Lead long and need to be ordered at an appropriate time to L L and accelerated design and procurement to facilitate Times efficiently maintain schedule. delivery to meet current construction schedule. Complex Phasing Project in coordination with multiple projects including Cross project coordination will be on-going Airfield Improvement Program, Baggage Optimization L M throughout construction. The GCCM has included Program, and CHIRRP float in the schedule to mitigate this risk. QUESTIONS/DISCUSSION 13
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.