6d Revised

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA               Item No.      6d 
ACTION ITEM 
Date of Meeting    December 8, 2015 
DATE:    December 4, 2015 
Revised December 23, 2015 
TO:      Ted Fick, Chief Executive Officer 
FROM:   David Soike, Director, Aviation Facilities and Capital Program 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT:  C60 Interim Baggage Handling System Project (CIP #C800823) (CIP #C800825) 
Amount of This Request:        $4,377,000   Source of Funds:   Airport Development
Fund 
Est. Total Project Cost:         $14,200,000 
Est. State and Local Taxes:        $259,000 
ACTION REQUESTED 
Request Commission authorization for the Chief Executive Officer to: 
(1) Proceed and complete the design for the work elements in the C60 Interim Baggage
Handling System (BHS) Project; 
(2) Authorize the use of Port crews to self-perform work; 
(3) Purchase equipment for various work elements; 
(4) Amend the BNP Baggage Handling System Design Indefinite Design Indefinite
Quantity (IDIQ) by $3,500,000 and; 
(5) Execute a contract to provide proprietary software services for the integration of
upper and lower level controls and software programming on the baggage handling
systems, campus-wide. 
The amount of this request is $4,377,000. 
SYNOPSIS 
The C60 system is at or beyond design capacity during peak operations and had the highest
negative impact to airline customers in 2015. This current body of work is necessary to meet the
airlines' growth and baggage handling demandsby accomplishing as much of it as possible
before the 2016 summer peak travel season beginning in late May. This project has been vetted
by Delta Air Lines, the Transportation Security Administration (TSA), Port of Seattle, and the
Port's baggage system design consultant to be the most likely to provideimmediate operational
relief and efficiency gains for the C60 system. Without these improvements, it is likely that some

Template revised May 30, 2013.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
December 4, 2015 
Page 2 of 9 
baggage volume would need to be moved to the north systems, C1 and C88, creating additional
capacity issues for those systems; and require increased manual handling of baggage. 
During challenging operations on the C60 system, the C61 system is negatively impacted due to
its use as a contingency. Airlines that used the C60 and C61 systems reported over 2,100 missed
bags and over 200 delayed flights during June, July, and August 2015. These were directly
related to baggage system capacity and performance issues. This translates to an estimated
$500,000 - $1,000,000 of cost to airlines for baggage delivery and delayed flight time (based on
industry-accepted standards for baggage delivery costs, the cost per minute of aircraft and crew
time, and the value of a passenger's delayed time). 
Other impacts included slowed passenger check-in processing in the terminal check-in lobbies.
Staff is continuing to evaluate the other areas among all baggage systems at the Airport. Staff 
expects that work yet to be defined will also be needed to manage interim baggage capacity
needs prior to optimization on some of the other baggage handling systems.
This project will accelerate improvements to the C60 baggage handling system to provide
essential capacity and improve performance in order to handle current passenger demands and
expected growth at minimum through 2016. Multiple projects have been performed on the C60
system to improve performance over the last two years. Because of the challenges the Airport
faced this past summer, it was determined that the Port should indeed move forward as quickly
as possible with additional enhancements to the system. Some of these enhancements have been
identified in the past, but have not been pursued due to the cost and the expectation that the
Baggage Optimization Project would address these needs. However, the unprecedented growth
of our airline customers in the south end specifically has highlighted the need to move forward
with as many of the enhancements as possible. 
A major renewal and replacement of the baggage handling systems, the Baggage Optimization
Project, is now underway. Due to constraints in the airport baggage area, however, the C60
upgrade will be the last phase of the project, scheduled for completion in 2023. 
This project is to include design and construction of four work elements that bolster capacity,
reliability,  and performance in the C60 Baggage Handling System. These work elements 
specifically related  to C60 are intended to have design and the majority of construction
completed prior to the summer peak in 2016. T he balance will be completed before summer 
2017. As needed to improve the C60 Baggage Handling System, other individual work elements 
may be identified or the scope of these four elements may require changes as the design
progresses. This work will also help the C61 system. 
The four work elements currently included in this project are: 
1.  The Baggage Input Load Balancing element will allow for better utilization between two
screening loops in the system, gaining better efficiency.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
December 4, 2015 
Page 3 of 9 
2.  TSA Search Room Expansion/Enhancements element will increase the TSA search room
capacity; eliminate a single point of failure; incorporate reinsertion/rescreening
equipment; and will improve the overall system functionality. 
3.  Security Zone Tracking Enhancements element will reduce error bags to the TSA search
room and improve the overall system capability. 
4.  Clear Bag Reconciliation Scanners element will reduce error bags to TSA search room,
reduce manual bag transfers, and improve worker safety. 
BACKGROUND 
The C60 system was in the process of being assembled as part of the South Terminal Expansion
Program (STEP) including construction of Concourse A when the events of September 11, 2001,
occurred. As a result, the bag screening capability of C60 was dramatically and rapidly built to
meet federal requirements while those requirements were still being developed. C60 was one of
the first operational in-line baggage scanning systems in the country. As new systems were built
and brought on line here in Seattle, lessons learned and best practices were added to avoid some
of the challenges that came with the C60 system design. 
The most recent project executed on the C60 baggage system replaced existing aging computer
hardware and software and added baggage make-up capacity. This upgrade improved system
performance outside of the security tracking-zone. The results of this project have proven to be
very effective. Although there were some performance improvements to the system from this
work, it was primarily renewal and replacement and did not address the capacity constraints. The
need to improve and upgrade the security tracking-zone may even be of more value to the overall
operation than the work that has been completed recently.
Because of capacity and performance issues during the summer of 2015, impacts to airline
customers have occurred, including delayed flights, delayed baggage, and customer
dissatisfaction. Delta Air Lines has indicated that the baggage system in Seattle is of great
importance to them as they grow their operation. Other airline users of the C60 system have
expressed similar concerns because of the impacts to their operations. This project is critical to
addressing those concerns as we move towards the next summer season. Staff has only recently
completed the evaluation of the work needed on the C60 system to address these concerns and 
are therefore bringing this project forward now. 
The urgency of this work is very high. The Port's airline customers have demanded that the
Airport find solutions to the frequent disruptions to their operations they experienced this past
summer, and be prepared to handle an even larger volume of passengers on the system in the
summer of 2016. The elements of the project are designed to address these concerns. 
PROJECT JUSTIFICATION AND DETAILS 
This project, consisting of four distinct work elements, is focused on addressing the most urgent
C60 baggage system challenges. These elements are being proposed to meet interimbaggage

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
December 4, 2015 
Page 4 of 9 
capacity needs prior to optimization. The current request will upgrade the security tracking-zone,
install robust software, and implement best practices that enhance the baggage screening process. 
Interim improvement projects are necessary to keep up with airline customers' rapid growth of
flights and passengers prior to when the Baggage Optimization project will affect this portion of
the airport. This request is to approve a project to implement interim improvements that are
expected to be put in place over the next two years on the C60 system as baggage volumes grow.
Meetings with both airline and TSA leadership and their respective technical staff teams from
across the country confirm that these interim elements are necessary. 
Project Objectives 
The project is necessary for the following reasons: 
The C60 baggage system has exceeded capacity during peak operations; 
Twelve airlines regularly use C60 for normal operations and all airlines may use it for
irregular operations; 
Delta Air Lines, the largest user of C60, intends to grow their operation for the next
several years including adding approximately 30 flights in 2016 at summer peak; and 
Baggage Optimization will not be ready to replace the C60 system for several years  
estimated date of completion is 2023. 
Scope of Work 
Currently the project includes the following work elements: 
Baggage Input Load Balancing: Install crossover TX-4/TC9-OB1 at an estimated cost of
$970,000. 
TSA Search Room Expansion/Enhancements: Expand C-60 search room and install
additional feeds, CTX machine, increased number of search tables and input belt at an
estimated cost of $7,730,000. 
Security Zone Tracking Enhancements: Eliminate slope from XR tracking lines and
provide multiple enhancements to improve tracking within the system at an estimated
cost of $5,200,000. 
Clear Bag Reconciliation Scanners: Install decision diverter scan guns at an estimated
cost of $300,000. 
The elements currently being proposed under the C60 Interim Baggage Handling System Project
are needed prior to the 2016 summer peak; therefore, the project must move forward
immediately. While specific elements have been identified to be included in the project,
necessary adjustments to element scopes and budgets is a risk due to the rapid pace required to
meet summer deadlines.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
December 4, 2015 
Page 5 of 9 
Staff anticipates Port Crews will be utilized in each of these elements at varying levels of
engagement. The Port will be advertising and executing one major works contract for theTSA 
Search Room Expansion/Enhancements element. 
A Sole Source Competition Waiver was authorized for Brock Solutions to provide proprietary
software services for integration of upper and lower level controls and software programming for
the baggage handling systems, campus-wide. This waiver also authorized the Port to require
construction contractors to use Brock Solutions for such proprietary software services.
Additionally, with the Commission's approval, staff will amend an existing Baggage Handling
Systems Design Indefinite Delivery Indefinite Quantity (IDIQ) with BNP Associates to provide
design and design support during construction. 
Schedule 
The goal of this project is to complete design and construction of all elements prior to summer
peak 2016, or as soon thereafter as possible.
FINANCIAL IMPLICATIONS 
Budget/Authorization Summary              Capital     Expense   Total Project 
Original Budget                            $0          $0          $0 
Previous Authorizations                       $0          $0          $0 
Current request for authorization            $4,377,000          $0    $4,377,000 
Total Authorizations, including this request     $4,377,000          $0    $4,377,000 
Remaining budget to be authorized         $9,823,000          $0    $9,823,000 
Total Estimated Project Cost             $14,200,000          $0   $14,200,000 
Project Cost Breakdown                     This Request       Total Project 
Design Phase                             $2,455,000         $4,599,000 
Construction Phase                          $1,663,000         $9,022,000 
Sales Tax                                  $259,000          $579,000 
Budget Status and Source of Funds 
This project was not included in the 2016-2020 capital budget and plan of finance. After the
summer peak season, during which the C60 baggage system was regularly pushed to the
breaking point, staff worked to identify solutions to the most critical problems. The budget for
this project (C800823) (C800825) will be transferred from the aeronautical allowance CIP
(C800404) resulting in no net change to the Aviation Division capital budget. Since the expected
average life of the assets will be approximately seven years (until replaced by the Baggage
Optimization project), the funding source will be the Airport Development Fund.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
December 4, 2015 
Page 6 of 9 
Financial Analysis and Summary 
CIP Category             Renewal/Enhancement 
Project Type              Infrastructure Upgrades 
Risk adjusted discount rate     N/A 
Key risk factors             N/A 
Project cost for analysis        $14,200,000 
Business Unit (BU)          Baggage Equipment cost center 
Effect on business performance  NOI after depreciation will increase (capital costs added
to airline rate base, amortized over 7 years) 
IRR/NPV             N/A 
CPE Impact             $.11 in 2017 
Lifecycle Cost and Savings 
These elements are not anticipated to add significant cost or savings to the Aviation Maintenance
budget. It is anticipated these elements will improve system performance as their primary
objective. Staff recognizes the shorter useful life of these elements and is  adjusting the 
amortization period accordingly. 
STRATEGIES AND OBJECTIVES 
This project promotes the Port's Century Agenda objectives to make Sea-TacAirport the West
Coast "Gateway of Choice" for international travel, meet the region's air transportation needs at
Seattle-Tacoma International Airport for the next 25 years, and encourage the cost-effective
expansion of domestic and international passenger and cargo services. 
TRIPLE BOTTOM LINE 
Economic Development 
This project will improve the system functionality to address Airlines' growth. This project
improves the effectiveness of the existing system. 
Environmental Responsibility 
This project demonstrates environmental sustainability by improving existing Port assets to
better utilize existing resources. 
Community Benefits 
This project will help enable airline activity to grow at the airport, and that helps increase vitality
across neighboring communities. The project manager will collaborate with the Office of Social
Responsibility (OSR) to maximize small business participation.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
December 4, 2015 
Page 7 of 9 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1)  Authorize the funding for design only, leaving construction, purchasing of
equipment and additional funding authorization as a separate Commission action in January. 
Cost Estimate: $2,500,000 
Pros: This allows for design to get started. This alternative also allows Commission additional
time prior to committing construction funding. 
Cons: This project is extremely time sensitive and this alternative creates inefficiencies and
delays. This project requires equipment with long lead times; this alternative will not allow
summer completion and will affect airline operations and costs.
This is not the recommended solution. 
Alternative 2) - Status Quo - Do not proceed with these projects 
Cost Estimate: No cost to airport.
Pros:  No capital expenditure. 
Cons:  Many bags would fail to make it to aircraft on time due to baggage system capacity
overload events. Airline baggage delivery performance will suffer, and airlines will be dis-
satisfied with the Port's ability to provide anecessary service. Airlines have been complaining
about system performance and will continue to do so in an escalated manner. Airlines expect
their growth can be met and supported consistently and reliably. This alternative does not
address their needs.
This is not the recommended solution. 
Alternative 3) - Airlines and TSA add labor and equipment to process bags manually  ask
airlines to change their operations to remove bags from the automated system by manually
shuttling transfer bags between aircraft via tugs. Ask TSA to consider "pop-up" screening
locations to facilitate re-screening of trans-border transfer bags and other re-screening needs that
arise. 
Cost Estimate: No cost to airport. Cost yet undetermined - Increased labor and equipment cost to
airlines. 
Pros: There would be little to no capital expenditure by the airport. Benefits to airport automated
system would be varied depending on the quantity of bags removed. If enough bags are
processed manually, the system would operate effectively.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
December 4, 2015 
Page 8 of 9 
Cons:  It is not expected that this alternative will create enough relief to keep the system
operating properly during the peaks. This would require significant manual effort on the part of
the airline staff and potentially the TSA who both expect automated bag systems. It would
increase the amount of tug traffic on the AOA and in the bagwell, creating congestion related
inefficiencies and heightened safety concerns between aircraft and concourses in order to shuttle
bags manually. There may be unforeseen operational staffing and cost impacts to the airport to
enable this non-automated process to occur. 
This is not the recommended solution. 
Alternative 4) - Remove the summer cruise bag peak from the system flow 
Cost Estimate: Cost as yet undetermined  future separate long-term project 
Pros: Removing volume is as beneficial, or more, than the manual shuttle process alternative
above. 
Cons: There is no current project defined to provide an alternative for cruise baggage. Planning,
designing, & implementing a project to do so will take longer than the immediate need for 2016.
Both manual shuttling of transfer bags and removing cruise bag volumes may be necessary in
longer term future. 
Alternative 5) - Move forward with a single design and construction authorization, funding, and
enablement of the listed projects so they can be constructed and activated in time for the 2016
and 2017 summer peak volumes. 
Cost Estimate: $14,200,000 
Pros: A single Commission authorization for design and construction would allow the work to
start immediately and this will give the airlines, TSA, and the airport the best opportunity to be
successful with the continued growth of the airlines.     TSA  will  have  improved  and
expanded operating space to provide the necessary baggage screening operations for the
increased volumes.  Airlines will benefit with improved system efficiency and will see reduced
congestion in their check-in lobbies as well as less downtime of the baggage system. This
alternative will also improve customer service. It is expected that these options will provide the
best opportunity for success in the coming years.  These  projects  will  help  increase  the
capacity and efficiency of the checked baggage inspection processing section of the system to
match the automated sections of the system. Throughput should increase as a result. 
Cons:  Capital cost  However, it is necessary to meet rapid airline growth. Port processes may
hinder the speed of delivery of these elements  it will be necessary to find ways to move these
efforts ahead rapidly. This may not be enough to eliminate the need to manually process bags or
to use north bag systems for cruise/trans-border screening. However, a single Commission

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
December 4, 2015 
Page 9 of 9 
authorization does not allow the typical two opportunities for public comment and Commission
consideration of capital project authorization action. 
This is not the recommended solution. 
Alternative 6) - Move forward with design, use of Port crews, and purchase of equipment of the 
listed projects, leaving advertising, execution of contract, and construction activities as a separate
Commission action in January. 
Cost Estimate: $4,377,000 
Pros:  This allows for design, Port crews and procurement of long lead items to being. This
alternative also provides additional public transparency, and provides the Commission with
additional review time prior to committing construction funding. 
Cons:  This project is extremely time sensitive and this alternative creates inefficiencies. This
method is not a fast-track process and will create additional burden on the limited resources at
the Port.  This alternative requires additional and redundant Port processes and it will be
necessary to find ways to move these efforts ahead rapidly. 
This is the recommended alternative. 
ATTACHMENTS TO THIS REQUEST 
PowerPoint Presentation. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
June 23, 2015 - Baggage Optimization Briefing.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.