4f Memo Stairs

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA               Item No.       4f 
ACTION ITEM 
Date of Meeting    October 27, 2015 
DATE:    October 19, 2015 
TO:      Ted Fick, Chief Executive Officer 
FROM:   Wayne Grotheer, Director, Aviation Project Management Group 
James Schone, Director, Aviation Business Development 
SUBJECT:  Central Terminal Mezzanine to Ticketing Stair Project (CIP #C800716) 
Amount of This Request:      $491,000      Source of Funds:   Airport Development
Fund 
Est. Total Project Cost:      $2,560,000 
ACTION REQUESTED 
Request Commission authorization for the Chief Executive Officer to execute professional
services contracts and prepare design and construction bid documents for the Central Terminal
Mezzanine to Ticketing Stair project at Seattle-Tacoma International Airport for $491,000 of a
total estimated project cost of $2,560,000. 
SYNOPSIS 
Available office space on the mezzanine is becoming increasingly scarce due to recent United
Services Organization (USO) and airline growth; therefore, it is necessary to build stairways to
the remaining available space to meet egress (exiting) building code requirements and provide
developable space for future growth.
This project will build two stairways near the central checkpoint (see Exhibit A) to provide
egress capacity from the mezzanine level to the ticketing level on the non-secure side of the
Airport. This is needed in order to allow future occupancy of currently un-leasable space on the
mezzanine for airlines, dining and retail businesses, staff, or other tenants. This project will also
install fire sprinklers to support egress from this portion of the terminal. 
Upon project completion, lease revenue is anticipated at $770,750 in 2017, escalating to an
estimated $1,593,850 in 2018. 
This project is within the existing terminal building and therefore would not be affected by future
decisions related to the sustainable airport master plan.
BACKGROUND 
In 2004, as part of the construction of the Central Terminal Expansion (CTE) project, a staircase,
which provided egress from the mezzanine level, was removed. The growth in operations and

Template revised May 30, 2013.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
October 19, 2015 
Page 2 of 8 
passengers at the Airport, and the related increase in support space needed by the Port's airline
partners, has led to greater levels of occupancy on the mezzanine above the ticketing and
checkpoint area. The occupancy levels have now reached a point where if the Port wishes to
make use of any vacant space on the mezzanine level, egress stairways and fire sprinklers must
be installed in the central area of the terminal building. There are approximately 10,000 square
feet of office space on the mezzanine level that are now vacant. 
In 2012, the Airport worked with the USO Northwest to build a new and expanded Airport USO
lounge on the mezzanine level. The initial code review for th e USO project highlighted the
reduced egress capacity on the mezzanine level. While sufficient egress capacity existed for the
lounge to be constructed, there was no remaining capacity for the central zone of the mezzanine
level, thereby making the current  vacant space on the mezzanine level unusable until
improvements to egress capacity are made. The two stairways proposed by this project will
supply the additional egress capacity required to occupy the space located in the central zone of
the mezzanine level when installed in concert with fire sprinklers in the central terminal area. 
The Airport main terminal building opened in the 1970s without a comprehensive fire sprinkler
system. This met the provisions of the Uniform Building Code that was in force when it was
designed and built. Today, the International Building Code (IBC) recognizes the benefits of a
building fire sprinkler system by allowing longer and narrower egress pathways for buildings
that have them installed. In order for the mezzanine stairs to qualify as egress pathways for the
full use of the mezzanine, fire sprinklers must be installed. 
The Sustainable Airport Master Plan (SAMP) is currently reviewing alternatives to
accommodate future airport growth including an alternative that may change the configuration of
the ticket lobby and departures drive. As part of this review, a study of the building's fire
protection, smoke control, and egress capacity would be required in order to ensure compliance
with applicable IBC codes. Should SAMP determine that the airport's future growth be
accommodated elsewhere such as a new terminal building, staff would complete an egress study
separately in order to determine how best to meet the building code requirements. 
PROJECT JUSTIFICATION AND DETAILS 
Airport staff is managing an increasingly scarce resource of available office space in the main
terminal largely due to recent growth in demand from airlines operating at the Airport. The need
for additional leasable office area is imminent. Recent requests from both Delta Air Lines and
Alaska Airlines have largely committed all pre-security leasable space of significance in the
main terminal. This makes the remaining 10,000 square feet of un-leasable space critically
important. It is also anticipated that up to half of this space will be required to support the office
needs of the companies awarded contracts under the Airport Dining and Retail (ADR) group's
master plan that is currently underway. Although the ADR tenants have not yet been selected, 
staff has estimated office space requirements based on current tenant use along with the number
of anticipated future lease packages.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
October 19, 2015 
Page 3 of 8 
It should be noted that in addition to providing sprinklers that will benefit the two stairs and their
associated egress pathways, the fire sprinklers will benefit a future Baggage Optimization project
which will be able to use an egress pathway nearby once the fire sprinklers are installed. 
Project Objectives 
This project will provide additional egress capacity in the form of stairs from the mezzanine
level of the Airport, making the currently un-leasable office space usable. 
Scope of Work 
Install two stairways from the mezzanine level of the Airport to the ticketing level at the central
breezeway between the ticket lobby and the security checkpoint. The s cope includes: way
finding signage, structural modifications for support, modifications to the credential center, 
asbestos abatement, and modifications to the lighting and fire alarm and sprinkler systems to
accommodate the new stairways. 
Schedule 
Commission authorization to Design:                          4th Quarter 2015 
Commission authorization for Construction:                     2nd Quarter 2016 
Issue Notice to Proceed                                   3rd Quarter 2016 
Construction Complete                                 1st Quarter 2017 
FINANCIAL IMPLICATIONS 
Budget/Authorization Summary              Capital     Expense   Total Project 
Original Budget                      $1,250,000          $0    $1,250,000 
Current Budget Increase                  $967,000     $343,000    $1,310,000 
Revised Budget                     $2,217,000     $343,000    $2,560,000 
Previous Authorizations                   $20,000          $0      $20,000 
Current request for authorization              $491,000          $0      $491,000 
Total Authorizations, including this request      $511,000          $0      $511,000 
Remaining budget to be authorized         $1,706,000     $343,000    $2,049,000 
Total Estimated Project Cost              $2,217,000     $343,000    $2,560,000 
Project Cost Breakdown                     This Request       Total Project 
Design Phase                              $491,000          $511,000 
Construction Phase                                          $1,949,000 
State & Local Taxes (estimated)                                   $100,000 
Total                                       $491,000         $2,560,000

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
October 19, 2015 
Page 4 of 8 
Budget Status and Source of Funds 
This project was included in the 2015  2019 capital budget and plan of finance as a business
plan prospective project with a budget of $1.25 million. The cost increase is due to the need for
additional structural support, fire sprinklers (which were previously not in scope and are a
requirement of the building code) and abatement. The capital budget increase will be transferred
from the aeronautical allowance CIP (C800404) so that there will be no change to the overall
capital budget. The funding source will be the Airport Development Fund. 
The expense portion of the project cost includes $343,000 estimate for asbestos removal. This
will be included in the 2016 operating budget. 
Financial Analysis and Summary 
CIP Category             Renewal and Enhancement 
Project Type              Infrastructure upgrades 
Risk adjusted discount rate     8% 
Key risk factors             Demand for additional terminal space 
Project cost for analysis        $2,560,000 
Business Unit (BU)          Terminal 
Effect on business performance  Although there are no current commitments to lease this
space, the financial analysis estimates lease payments to
begin in 2017 at $770,750 for 5,000 square feet, and
increase to $1,593,850 for 10,000 square feet in 2018, and
then subject to adjustment along with other terminal rental
rates thereafter. 
IRR/NPV             5-year analysis (assumes leases with 4 tenants): 
NPV: $2.9 million 
IRR: 34.0% 
Payback: 2 years 
30-year analysis (based on probable asset life, continued
split of 5,000 square feet aeronautical, 5,000 square feet
non-aeronautical tenant mix): 
NPV: $17.8 million 
IRR: 46.2%

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
October 19, 2015 
Page 5 of 8 
Assumptions: 
-Aviation Finance and Budget projects a lease rate of
$171.45 per square foot per year in 2017, which increases
to $235.64 in 2024 and then is held flat thereafter for
aeronautical space 
- Aviation Finance and Budgets project a lease rate of
$136.85 per square foot per year in 2017, which increases
to $190.11 in 2024 and then is held flat thereafter for nonaeronautical
space 
-2,500 square feet leased to an aeronautical tenant and
2,500 square feet leased to a non-aeronautical tenant for
each of 2017 and 2018. 
-Each build-out incurs approximately $189,216 of costs
that are eligible for reimbursement under the Port's AV-2
Tenant Reimbursement Policy (though funds for these
potential reimbursements are not part of this authorization
request). 
Looking at the airport impacts after accounting for the
lease payments through the airline agreement, 77% of the
capital costs are recovered through airline rates and
charges. The non-aeronautical business is allocated 23%
of the capital costs. Looking at the net impact on the nonaeronautical
side, the capital investment is approximately
$510,000 (23%), and the potential annual lease revenue
exceeds $685,000 per year, for a short payback and a very 
favorable NPV. 
CPE Impact             $.03 in 2016 due to O&M costs, then $.01 annually
beginning in 2017. 
Lifecycle Cost and Savings 
Aviation Maintenance may experience some additional operating and maintenance costs for
materials, depending on the stair type/quality/installation, though they are not anticipated to be
significant. A more detailed estimate of operating and maintenance costs will be provided once
design is complete. 
STRATEGIES AND OBJECTIVES 
This project supports the Port's Century Agenda objective of meeting the region's air
transportation needs at the Airport for the next 25 years and encouraging the cost-effective
expansion of domestic and international passenger and cargo service. The Airport must meet the
business needs of tenants by providing office space to support their operations.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
October 19, 2015 
Page 6 of 8 
This project supports the Aviation Division's Strategy of operating a world class international
airport by ensuring safe egress routes for those using the mezzanine facilities and meeting the
needs of our tenants and the region's economy. 
ALTERNATIVES AND IMPLICATIONS CONSIDERED 
Alternative 1)  Expand the terminal footprint through the addition of approximately 10,000 
square feet of terminal space in an alternate location (i.e., additional floor on top of the C1
Building). 
Capital Cost - $11.5 M (rough order of magnitude) 
Pros: 
Provides needed square footage for additional tenant office needs. 
Preserves the full open architecture of the Airport's Central Checkpoint. 
Has no effect on queuing during construction. 
Cons: 
Additional office space would be post security, which is not where the greatest gap
between supply and demand for tenant office space resides. 
Would not solve egress capacity limits in the central main terminal space or
incrementally improve fire sprinkler coverage. 
Would still leave unusable/un-leasable space in the valuable central area of the Terminal. 
Would not provide added easy access benefit for passenger use for pre-security access to
Lost and Found, Credential Center, USO, and Central Auditorium on the mezzanine
level. 
This is not the recommended alternative. 
Alternative 2)  Install two exterior egress paths from the mezzanine over the roof ending on the
airfield side of the mezzanine to provide the code-required egress path. 
Capital Cost: $3.3M (rough order of magnitude) 
Pros: 
Less expensive than Alternative 1.
Would provide the necessary egress capacity to make the currently un-leasable space on
the mezzanine leasable.
Preserves the full open architecture of the Airport's Central Checkpoint. 
Cons: 
There are many security concerns with allowing unscreened people to egress from the
building on the secure side of the Airport.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
October 19, 2015 
Page 7 of 8 
One of the pathways runs along the south CTE wall. The wall is currently glass and
allows natural light into the central area of the main terminal, not within the CTE. This
alternative would remove all glass panels and install solid panels, diminishing natural
light in the terminal area. 
This alternative requires that the structure under the roof be reinforced to meet
requirements for additional load and seismic stability, which would significantly restrict 
passenger flow in Concourse B. 
The contractor working on this project could damage the roof by puncturing or
carrying/dragging heavy materials across the surface leaving the roof membrane in an
irreparable state, requiring roof replacement. 
This alternative would limit Maintenance access to portions of the roof making it more
costly to repair and replace. 
Additional security equipment would be required including but not limited to cameras
and security access control. 
Would not provide added customer service benefit for passenger use for pre-security
access to Lost and Found, Credential Center, USO, and Central Auditorium on the
mezzanine level. 
Would not provide the required egress for the Baggage Optimization project, which
would need to install fire sprinklers along the egress pathway at a cost of approximately
$1.7 M, or identify a new location for the break room. 
This is not the recommended alternative. 
Alternative 3)  Install two interior stairways and required sprinkler coverage in the open high
ceiling breezeway area between the ticket counters near the central checkpoint, providing egress
from the north and south sides of the mezzanine on the non-secure side of the Central Terminal. 
Capital Cost: $2.56M 
Pros: 
Lowest cost alternative. 
Would solve egresscapacity limits and incrementally improve fire sprinkler coverage in 
the central main terminal.
Keeps non-screened passengers on non-secure side of Airport rather than providing
egress into the secure side of the Airport. 
Would not require additional security equipment, improvements to airfield side roof or
risk potential roof damage by contractors. 
Would provide added passenger and employee customer service benefit through
improved vertical access to Lost and Found, Credential Center, USO, and Central
Auditorium. 
Provides egress capacity for other projects, such as the Baggage Optimization project.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
October 19, 2015 
Page 8 of 8 
Cons: 
Slightly lessens the full open architecture of the central breezeway. 
Requires the relocation of the movable (portable) art display cases. 
This is the recommended alternative. 
ATTACHMENTS TO THIS REQUEST 
Exhibit A: Floor plan illustrating new stairs and adjacent space utilization 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
None.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.