7a report

Item Number:   7a_Report
Meeting Date: September 22, 2015


Commission Staff Brieng
Capital Improvement Projects
Second Quarter Report 2015

This page intentionally left blank









ii  Port of Seattle 2Q 2015 Report

Port of Seattle
Capital Improvement Project Report
Second Quarter 2015
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the status of the Port's capital projects.
Background
During 2015, the Port plans to invest $373,800,000 to expand and upgrade the infrastructure that supports marine and
aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping companies,
airlines, rental car companies, concessionaires and public parking. About 2 percent of the Port's capital budget comes
from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in transportation
facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, budget transfers, and cost growth of construction if it exceeds 10% of contract. The
report may include graphics that report project costs compared to authorization, construction costs (including change
orders (CO)) compared to the construction contract, location maps, and photographs. The Port implements a number
of different types of projects and not all information may be relevant to a specific project; as such, the reports may vary
in detail and content. Project types may range from construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (substantial completion). This section also includes "Project Status" illustrating at a
glance if the project is on schedule, and within budget, and the date Construction authorization received.
x  Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x  Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x  Budget addresses the total project budget and includes information on the overall budget status, recent
Commission authorizations, forecasted overruns or savings, and scope changes.
x  Change Orders provides information on current quarter's COs and total project COs including justification for CO's for
the reporting period and information on any CO over $200,000 or 10% of the contract value.
x  Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x  Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x  Budget Transfers reports any transfers between authorized projects during the reporting period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports intend to meet the reporting requirements of Port of Seattle Commission Resolution 3605, as amended by
Resolution No. 3628, and the Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page on the Port of Seattle web site to ask a question, make a comment or
request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 2Q 2015 Report  1

Aviation
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C101107 ................160th GT Lot ..........................................................6 ...........
C102032 ...............Sanitary Sewer Pump Station Upgrade ................7 ........... ..............................
C102112 ................Hennelly Service Tunnel Renewal Rep .................8 ...........
C102573 ...............Aireld Pavement Replacement ............................9 ...........
C800019 ...............Gate Utilities Improvement ...................................10 ..........
C800034 ...............North Expressway Relocation ..............................11 ..........
C800061 ...............Main Terminal South Low Voltage ........................12 ..........
C800107 ...............C4 UPS System Improvements ............................13 .......... .............................. 
C800168 ...............C60-C61 BHS Modications ................................14 ..........
C800218 ...............Security Exit Lane Breach Control Phase I ..........15 .......... ..............................
C800230 ...............Emergency Lighting Parking.................................16 .......... 
C800238 ...............Central Plant Pre-Conditioned Air ........................17 ..........
C800247 ...............Cargo 2 West Hardstand ......................................18 .......... ..............................
C800251 ...............Vertical Conveyance Modernization.....................19 ..........
C800253 ...............Parking System Replacement ..............................20 .......... ..............................
C800254 ...............Aircraft RON Parking Post Ofce Site..................21 .......... ..............................
C800274 ...............8th Floor Weather Proong ..................................22 .......... 
C800324 ...............Long-Term Cell Phone Lot ....................................23 .......... ..............................
C800334 ...............Two new CTE Freight Elevators ...........................24 .......... ..............................
C800335 ...............EGSE Electrical Charging Stations ................... 25-26 ....... ..............
C800390 ...............Cargo 6 Enhancements ........................................27 .......... ..............
C800406 ...............RW 16C/34C Reconstruction ...............................28 .......... ...............
C800451 ...............Doug Fox Site Improvement .................................29 .......... .............. ..................
C800464 ...............Fiber Infrastructure to Gate Backstands ..............30 .......... ..............................
C800479 ...............Fire Station Electrical Upgrades ...........................31 ..........
C800483 ...............Aireld Pavement Program ..................................32 ..........
C800495 ...............Facility Monitoring System Renewal ....................33 .......... ..............................
C800497 ...............Airport Wide Mechanical Controls System ..........34 ..........
C800543 ...............Replace PLBs at S7, S9, B4 .................................35 .......... .............................. 
C800544 ...............NorthSTAR Program.............................................36 ..........
C800545 ...............NorthSTAR Main Terminal Improvements............37 ..........
C800547 ...............NorthSTAR Concourse C Vertical Circ. ...............38 .......... .............................. 
C800549 ...............SSAT Interior Renovations ...................................39 .......... .............................. 
C800551 ...............Grease Interceptor Augmentation ........................40 .......... ..............................
C800555 ...............NorthSTAR Refurbish Baggage Systems ............41 ..........
C800556 ...............NorthSTAR North Satellite Lobbies ......................42 ..........


2  Port of Seattle 2Q 2015 Report

Aviation, cont.
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800560 ...............MT Mezzanine Tenant Relocation ........................43 ..........
C800576 ...............Known Crew Member Employee Bypass .............44 .......... ..............................
C800581 ...............Parking Garage Lights ..........................................45 ..........
C800583 ...............International Arrivals Facility ................................46 ..........
C800585 ...............Wi-Fi Enhancement for Ramp and Terminal ........47 .......... ..............................
C800612 ...............Checked Baggage Recapitalization/Optimzation.48 ..........
C800615 ...............Second Floor Mezzanine Infra Upgrade ..............49 .......... ..............................
C800629 ...............S1 Ramp ...............................................................50 ..........
C800637 ...............2014-15 Roof Replacement ..................................51 ..........
C800638 ...............Dining and Retail Infrastructure Modernization ....52 ..........
C800642 ...............CCTV Camera Data Improvements ....................53 ..........
C800653 ...............Passenger Loading Bridge Renew .......................54 ..........
C800657 ...............Domestic Water Piping .........................................55 ..........
C800658 ...............Mech Energy Conservation ..................................56 ..........
C800659 ...............North Utility Tunnel Steam Pipe ...........................57 ..........
C800662 ...............S4 and S6 IC Connection .....................................58 .......... ..............................
C800667 ...............Automated Passport Control ................................59 ..........
C800688 ...............Construction Logistics Expansion .....................60-61 ....... ................................................................................
C800692 ...............2016 Fuel System Modications...........................62 .......... ..............................
C800702 ...............2015-2016 C Concourse Roof Repl .....................63 ..........
C800717................N. Terminal Utilities Upgrade ................................64 ..........
C800722 ...............CTE HVAC ............................................................65 ..........
U00239 .................R NERA ................................................................66 ..........
Other Aviation
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C200007...............Highline School Noise Insulation ..........................67 .......... ..............................
C200042 ...............Highline Community College Noise Insulation .....68 ..........
C200048 ...............Home Insulation Retrot .......................................69 ..........
C200093 ...............Single Family Home Sound Insulation .................70 ..........
C800154 ...............Tenant Reimbursement ........................................71 ..........



Port of Seattle 2Q 2015 Report  3

Maritime
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C102554-U00050 Terminal 46 Development....................................72 ..........
C102554-U00175. Container Dock Upgrade .....................................73 ..........
C102858 et al ....... Street Vacations T-5/18/105.................................74 .......... ..............................
C800132 ...............T-5 Berth Modernization .......................................75 ..........
C800137 ...............FT C15 HVAC Improvements ...............................76 .......... ..............................
C800160 ...............T-91 Lighting Upgrade ..........................................77 .......... ..............................
C800196 ...............T-102 Roof and HVAC ..........................................78 ..........
C800356 ...............Shilshole Tenant Service Buildings .....................79 ..........
C800430 ...............T-91 Building C175 Roof Replacement ................80 ..........
C800439 ...............T-91 Substation Upgrades ....................................81 ..........
C800546 ...............Argo Yard Truck Roadway ....................................82 .......... ..............................
C800603 ...............T-46 Dock Rehabilitation ......................................83 .......... ..............................
C800678 ...............HIM E Dock Rehab ..............................................84 ..........
C800691 ...............P69 Carpet Replacement .....................................85 .......... ..............................
C800698 ...............P69 Beam Rehab .................................................86 ..........

WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ..................87 ..........
E104324 ................Viaduct Construction Coordination ......................88 ..........
E104838................FT Net Shed Code Compliance ...........................89 ..........
E104840................T-5, T-18 and T-91 E. Maintenance Dredging ......90 .......... ..............................
U00033 .................T-18 Maintenance Dredging .................................91 ..........
U00099 .................IHI Cranes Removal .............................................92 .......... ..............................









4  Port of Seattle 2Q 2015 Report

Corporate
Overall Project   Variance
Status
CIP Number  Project Title             Page     Schedule  Budget
C800162 ...............ID Badge Replacement ........................................93 .......... ..............................
C800436 ...............Terrminal 91 Visitor Management .........................94 ..........
C800519 ...............Contractor Data System Upgrade.........................95 ..........
C800520 ...............Computer Dispatch System Upgrade ...................96 ..........
C800521 ...............Construction Document Management .................97 .......... ..............................
C800693 ...............Noise Monitoring System Replacement ...............98 ..........
C800694 ...............Umbrella Authorizations .......................................99 .......... .............................. 
C800728 ...............Parking System Replacement .............................100 .........
C800745 ...............HCM Upgrade ......................................................101 .........
C800746 ...............Maximo Upgrade .................................................102 .........
C800763 ...............Performance Management ..................................103 .........


Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Negative Variance Status
New Variance
Previously Reported
Schedule Completion on the Project Reports refers to:
Benecial Occupancy or Last Asset In-Use date







Port of Seattle 2Q 2015 Report  5

SECOND QUARTER REPORT, 2015
So. 160th GT Lot Expansion 
Project: C101107              Improve lot drainage, underground    Project Status:
Budget: $3,559,000             existing overhead utility lines, fencing   Schedule: Within or Ahead
Phase: Design                 and landscaping. Renovation of       Budget: On or Under
Start: 2/1/2013                 layover facility is being re-evaluated.   Status Reset: 11/22/2013
Schedule Completion: 9/30/2015                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Project scope has been substantially reduced, and design documents have been     4         3.6
altered accordingly. Undergrounding of existing overhead utility lines along S.
160th is in progress. Preparing a commission memo to obtain authorization to      3
contruct the reduce scope proejct in Q3 2015.                          Dollars in Millions 2
1.0
Schedule                                       1            0.5
Scope revision at 100% design has led to a delay in the project schedule.         0
Authorized Forecasted   Costs
Incurred
Budget
The project forecast is within the approved budget and authorization.         Construction Costs
None at this time 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The project may be subject to weather delays. Complications in executing
agreements with utilities for underground lines are a schedule risk.
Budget Transfers
Amount       From         To
$0



AIRPORT 
6  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Sanitary Sewer Pump Station Upgrade 
Project: C102032             Upgrade the aging control systems of 22  Project Status:
Budget: $1,133,000           sanitary sewer lift stations.            Schedule: Delayed
Phase: Construction                                       Budget: On or Under
Start: 3/1/2013                                            Status Reset: N/A
Schedule Completion: 7/31/2015                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Nineteen (19) of the 22 panels have now been installed.                        1.1
1.2             1.1
1
Schedule
0.8                      0.7
The project is behind schedule due to changes to the control panels and         0.6
installation challenges. We are carefully proceeding forward in a manner that     Dollars in Millions 0.4                                                          minimizes risk during and after system switchover.                      0.2
0
Budget                                       Authorized Forecasted  Costs
Incurred
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                               Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 2Q 2015 Report  7

SECOND QUARTER REPORT, 2015
Service Tunnel Renewal/Replace 
Project: C102112              Project will seismically retrofit and    Project Status:
Budget: $27,586,000            structurally strengthen the airport      Schedule: Within or Ahead
Phase: Design                 Service Tunnel that resides between    Budget: On or Under
Start: 11/4/2012                the Main Terminal and Airport       Status Reset: 8/5/2014
Schedule Completion: 6/1/2018    Garage.                      (Commission Design Auth.)
Significant Developments                             Budget/Costs Incurred
The design team is in the discovery phase of their design work performing       30         27.6
extensive site investigations, surveying and geotechnical field analysis.         25
20
Schedule
15
Project is underway and on schedule.                              Dollars in Millions 10
4.6
5
0.1
Budget                                      0
Authorized Forecasted   Costs
The project is within budget.                                                     Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       None at this time 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0




AIRPORT 
8  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Airfield Pavement Replacement 
Project: C102573              This is a multi-year program to      Project Status:
Budget: $24,117,213            replace distressed pavement and joint   Schedule: Within or Ahead
Phase: Design                 seal on the airfield.                Budget: On or Under
Start: 5/2/2010                                             Status Reset: 4/1/2014
Schedule Completion: 10/31/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Authorization for 2015 Apron Panel Replacement to go for Bid/Award or       40
Change Order in conjunction with the16C Reconstruction project received           30.2
April 28, 2015. A successful Change Order negotiated and signed on June 26,    30
23.6      21.7
2015.                                               Dollars in Millions 20
Schedule                                      10
2015 Panel Replacement work scheduled to begin August 24, 2015 progressing    0
Authorized Forecasted   Costs
through October 2015.
Incurred
Budget
Construction Costs
The project forecast is within the approved budget.
20   17.1        16.8
Change Order
15
Current Quarter     Project Total
10
Number of COs           0             13
Amount of Cos           $0           $100,024          Dollars in Millions  5
Justification for COs: None at this time                                        0.1
0
Initial  Change  Spent
Risks                                                Orders
Possible weather delays as the rainy season approaches.
Photo
Budget Transfers
Amount       From         To
$0



AIRPORT
Port of Seattle 2Q 2015 Report  9

SECOND QUARTER REPORT, 2015
Gate Utility improvements 
Project: C800019              Upgrade the Concourse B loading    Project Status:
Budget: $15,648,312           bridges to the standard 400Hz power.    Schedule: Within or Ahead
Phase: Design                 This will reduce aircraft emissions and   Budget: On or Under
Start: 6/28/2007                noise; improve energy efficiency and    Status Reset: N/A
Schedule Completion: 10/16/2017  save money for the airlines.          (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
South Satellite 400Hz construction and project closeout completed. Final phase    20
of CIP; Concourse B 400Hz project 30% design submitted 20 days ahead of               15.6
13.2
schedule. MUST, PEST, and START meetings completed with positive        15
feedback/comments from reviewers. 60% design submittal due 2nd quarter      Dollars in Millions                9.4
10
2015.
5
Schedule                                       0
Design for Concourse B 400Hz is on schedule.                          Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
Validating design firm estimate to determine any potential project increases.
6
5.1          5.1
Change Order                                  5
Current Quarter     Project Total          4
Number of COs           0             46           Dollars in Millions  3
Amount of COs          $0          $299,867           2
1
Justification for COs:                                                    0.3
0
Initial  Change  Spent
Risks                                                Orders
Construction cost increases
Budget Transfers
Amount       From         To
$0



AIRPORT 
10  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
North Expressway Relocation 
Project: C800034             Reconstruct the Northern Airport      Project Status:
Budget: $102,564,300         Expressway, support the extension of    Schedule: Within or Ahead
Phase: Construction          light rail to the Airport, and construct    Budget: On or Under
Start: 7/1/2004                improvements to Wall 14.            Status Reset: 2/20/2014
Schedule Completion: 11/26/2014                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Reconstruction of the Northern Airport Expressway and the light rail transit     $115.00
components are complete. The construction of the Wall 14 Improvements is          110.2
complete and beneficial occupancy issued November 26, 2014. The         $110.00
replacement of a damaged power conduit on S 170th St is also complete. The   $105.00   Dollars in Millions           102.2   102.1
Resident Engineer Completion Memo issued May 7, 2015 and this will be the
$100.00
last quarterly report for this project since it is in closeout.
$95.00
Schedule                                         Authorized Forecasted  Costs
Incurred
The Wall 14 improvements and the replacement of the damaged power conduit
on S 170th St are both complete.                                 Construction Costs
Budget                                    $120.00        107.7
99.4
Project forecast is within the approved budget and authorization. The total     $100.00
budget for the Wall 14 Improvements is $1,529,000 and $120,000 for the       $80.00
replacement power conduit.                                   $60.00
$40.00   Dollars in Millions
Change Order                                $20.00     8.3
Current Quarter     Project Total        $0.00
Initial  Change  Spent
Number of COs           2            241                  Order
Amount of Cos         ($26,904)        $8,302,697
Justification for COs: Scope change and disputes (liquidated damages).       Photo
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0


AIRPORT
Port of Seattle 2Q 2015 Report  11

SECOND QUARTER REPORT, 2015
Main Terminal Low Voltage 
Project: C800061             Renewal and replacement of low      Project Status:
Budget: 20,730,000           voltage (600 volts and below) electrical   Schedule: Within or Ahead
Phase: Design               distribution equipment in the Main       Budget: On or Under
Start: 6/28/2007              Terminal.                      Status Reset: N/A
Schedule Completion: 7/31/2019                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Due to project deferral and the possibility of changes in site conditions and
25
building codes, the design phase changed from 100% to 0% complete.                   20.7
Commission re-approved the project in Q3 2014. Preliminary site investigation    20
has identified a significant volume increase in the work to be completed.        Dollars in Millions 15
10    8.1
Schedule
5
0.7
The scope of work, schedule and final design budget finalized. The 100%
0
design documents scheduled for completion by the end of Q4 2016.             Authorized Forecasted  Costs
Incurred
Budget
The forecast is within the approved budget.                          Construction Costs
Not Applicable 
Change Order
Photo
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
In order to reduce regulated materials management (RMM) abatement impacts
to the project schedule, the RMM contractor will be required to add additional
crews to complete work in a timely manner. This area is a 24/7/365 operation.
Sequencing of this work is critical and electrical power has to be maintained
without interruptions. Significant work growth is possible due to lack of project
definition.
Budget Transfers
Amount       From         To
$0

AIRPORT 
12  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
C4 UPS System Improvement 
Project: C800107             Replace existing Uninterruptible Power  Project Status:
Budget: $4,555,238           Supply (UPS) System, including       Schedule: Delayed
Phase: Planning             batteries, with a new system located in   Budget: On or Under
Start: 4/14/2015               the Airport Combined Communications  Status Reset: 4/14/2015
Schedule Completion: 2/15/2017  and Command Center (C4).          (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Due to project deferral, changes to site conditions, and building codes, the       $5          4.6
design phase changed from 100% to 30% complete. Approval of the project
$4
Notebook received.                                        Dollars in Millions $3   2.3
Schedule                                      $2
Project reactivated. Preliminary Schedule shows Substantial Completion as      $1               0.6
February 2017.                                          $0
Authorized Forecasted   Costs
Incurred
Budget
New estimate has been developed based on new design concept.           Construction Costs
Not Applicable 
Change Order
Current Quarter     Project Total       Photo
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The C4 center is a 24/7/365 operation. Sequencing of this work is critical and
electrical power has to be maintained without interruptions.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 2Q 2015 Report  13

SECOND QUARTER REPORT, 2015
C60 - C61 BHS Modifications 
Project: C800168             This work represents a critical        Project Status:
Budget: $11,084,991          component to providing improved       Schedule: Within or Ahead
Phase: Construction          operational baggage in-line screening at   Budget: On or Under
Start: 6/1/2012               the South end of the Airport and more    Status Reset: 4/14/2014
Schedule Completion: 6/30/2015  baggage make-up capacity for airlines.    (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The Automatic Tag readers (ATR's) and upper level controls installation is
15
ongoing. The project team completed satisfactory acceptance testing on the          11.9
11.1
ATR's and upper level controls. High volume baggage testing completed                       8.9
during the period. We are working with the contractor on enhanced reporting
10
for the airlines. Work started on installation of additional EDS machine.         Dollars in Millions 5
Schedule
0
Original scope of work completed April 27, 2015. The additional EDS expected     Authorized Forecasted  Costs
Incurred
to complete prior to Q3.
Budget                                    Construction Costs
The project forecast is within the approved budget and authorization.            6  5.2       5.0
5
Change Order                                  4
Current Quarter     Project Total          3
Number of COs           2             20             2
Amount of Cos          $15,080         $197,544          Dollars in Millions  1      0.2
0
Justification for COs: The change order issued was due to varying site
Initial  Change  Spent
conditions and added reporting                                          Orders
Risks
None
Budget Transfers
Amount       From         To
$0


AIRPORT 
14  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Security Exit Lane Breach Control Exit B  Phase II 
Project: C800218              Procure and extend new automated,     Project Status:
Budget: $1,558,300            exit-land breach control, equipment at     Schedule: Delayed
Phase: Construction            the Concourse B exit.                Budget: On or Under
Start: 3/1/2012                                               Status Reset: N/A
Schedule Completion: 11/30/2015                               (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Opened Public Works Bids for Small Works Contractors in August and bids      2
were within budget. The contract has been executed.                          1.6     1.5
1.5
Schedule                                                   1.0
1
Construction delayed until after the busy passenger summer season. Project is
on schedule to start construction in mid-September 2015.                  Dollars in Millions 0.5
0
Budget                                       Authorized Forecasted  Costs
Incurred
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No major risks at this time
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 2Q 2015 Report  15

SECOND QUARTER REPORT, 2015
Emergency Lighting - Parking 
Project: C800230             Provide electrical infrastructure for a    Project Status:
Budget: $2,683,179           new source of emergency power to feed   Schedule: Within or Ahead
Phase: Closeout              the parking garage emergency lighting    Budget: On or Under
Start: 7/24/2012              circuits and ensure that code required     Status Reset: N/A
Schedule Completion: 7/16/2014  level of egress illumination is provided   (Commission Construction Auth.)
for safety.
Significant Developments                             Budget/Costs Incurred
F&I is working with Maintenance to perform a shutdown for the installation of    5   4.7
the split core CT. The shutdown will require intensive investigations of what
4
will be affected. The work will be completed before the end of the year.        Dollars in Millions 3         2.3     2.1
Schedule                                       2
Major works contract is complete. Final installation of split core CT is the final    1
piece of the project.                                              0
Authorized Forecasted   Costs
Incurred
Budget
The project forecast is within the approved budget and authorization.         Construction Costs
Change Order                                  2
1.7
1.6
Current Quarter     Project Total         1.5
Number of COs           0             0           Dollars in Millions  1
Amount of Cos           $0             $0
Justification for COs: N/A                                        0.5
0.0
0
Risks                                             Initial Change Spent
Orders
None
Budget Transfers
Amount       From         To
$0



AIRPORT 
16  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Central Plan Pre-Conditioned Air 
Project: C800238             Provide a centralized pre-conditioned   Project Status:
Budget: $55,140,463          air (PC-Air) plant (PCAP), associated    Schedule: Within or Ahead
Phase: Construction          heating and cooling piping systems,     Budget: On or Under
Start: 6/15/2009               and jet bridge terminal air handling     Status Reset: 2/25/2014
Schedule Completion: 8/31/2013  units to serve airplanes with heating     (Commission Construction Auth.)
and cooling while at the gates.
Significant Developments                             Budget/Costs Incurred
The major-works Contractor's construction is complete. PC-Air is operating at
56    55.3     55.1
72 gates. Work on the four remaining gates is complete. Design to replace the     55
chilled water insulation, anchor and guides on Concourse A, and the anchors      54
Dollars in Millions 53
and guides on Concourse B, C and South Satellite is on schedule.
52                   50.9
51
Schedule                                       50
49
Completion of the final gate system in 2Q 2015.
48
Authorized Forecasted   Costs
Budget                                                 Incurred
The major works contract is complete. Work for completing the remaining four
gates and anchors and guides is within budget.                        Construction Costs
40             36.6
Change Order
35
Current Quarter     Project Total          30  27.0
Number of COs           0            230            25
Amount of Cos           $0          $9,886,034
20
15
Justification for COs: None this quarter                              Dollars in Millions          9.9
10
5
Risks                                           0
Initial  Change  Spent
None at this time                                                     Orders
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 2Q 2015 Report  17

SECOND QUARTER REPORT, 2015
Cargo 2 West Cargo Hardstand 
Project: C800247             Enlarge the western cargo hardstand in the  Project Status:
Budget: $7,890,000           Cargo 2 area. Includes buyout of two      Schedule: Delayed
Phase: Construction          cargo buildings and tenant relocations;      Budget: On or Under
Start: 9/5/2012               relocation of FAA antenna, security gate,    Status Reset: 10/8/2013
Schedule Completion: 4/30/2015  and guard shack; and installation of 400Hz   (Commission Construction Auth.)
in-ground power.
Significant Developments                             Budget/Costs Incurred
Work at Cargo 2 Hardstand and E190 Security Guard Shelter is complete. Due    15
12.5
to the great size and weight of Gate E190 and the lengthy opening/closing times
evaluate alternative opening devices to decrease opening and closing times,     10
separate from the contract.                                       Dollars in Millions           7.0     6.6
5
Schedule
Complete additional modification to the 400Hz electrical vaults to address fall     0
Authorized Forecasted   Costs
protection outside of the contract schedule.
Incurred
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
5   4.5
Change Order                                          3.8
4
Current Quarter     Project Total          3
Number of COs           2             7             2
Amount of Cos          $7,388          $41,909          Dollars in Millions  1
Justification for COs: 1) Gate E-190 gate control and communication                   0.0
0
modifications; Replace door hardware at Cargo 2; Gate E-190 gate operators         Initial Change Spent
additional requirements; 2) Gate E-190 Door Type change.                        Orders
Risks                                        Photo
None 
Budget Transfers
Amount       From         To
$0


AIRPORT 
18  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Vertical Conveyance Modernization Program -
Aeronautical 
Project: C800251             Perform modernization on 9 existing    Project Status:
Budget: $24,556,408          elevators and 4 escalators: SSAF, MT-2,   Schedule: Within or Ahead
Phase: Construction          MT-3, MT-4, MT-5, MT-6, MT-7, SSB,   Budget: On or Under
Start: 10/25/2011             SSC. Install new elevators SSM and     Status Reset: 11/11/2013
Schedule Completion: 10/30/2016 SSN. Install cooling packages on 12     (Commission Construction Auth.)
existing hydraulic elevators throughout
Main Terminal.
Significant Developments                             Budget/Costs Incurred
Construction continued with the contractor working on first four elevators.
20
16.4
Schedule                                      15       13.2
Construction is underway with partial substantial completion of portions of the    10
first phase of construction in Q4 2015.                               Dollars in Millions                 5.6
5
Budget                                      0
Authorized Forecasted   Costs
The project forecast is within the approved budget and construction is                         Incurred
underway. Project has returned budget upon deferral of second phase of work.
Construction Costs
Change Order
5   4.6
Current Quarter     Project Total
Number of COs           4             22             4
Amount of Cos          $22,000         $106,902           3
2.0
Justification for COs: differing site conditions, sequencing of work, and          2
administrative changes.                                        Dollars in Millions  1
0.1
Risks                                           0
Initial  Change  Spent
Contractor is projecting missing delivery milestones and will fail to complete             Orders
work on time in 2016.
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 2Q 2015 Report  19

SECOND QUARTER REPORT, 2015
Parking System Replacement 
Project: C800253              Replace the previous Parking Revenue  Project Status:
Budget: $5,427,364             Control System, which manages       Schedule: Delayed
Phase: Closeout                parking access and revenue collection   Budget: On or Under
Start: 4/6/2010                 in the Airport's Main Parking Garage.   Status Reset: 3/8/2011
Schedule Completion: 8/31/2012                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Scheidt & Bachmann (S&B) system is operational and exhibits accuracy and     12
availability rates above 99.99%. However, the Port continues working with          9.8
10
S&B to correct an outstanding system certification issue. Ports' Legal and ICT     8
departments are also involved.                                   Dollars in Millions           5.4
6                   5.1
4
Schedule                                       2
The system is complete and in use. However, a critical Payment Card Industry    0
Authorized Forecasted   Costs
(PCI) certification issue remains to be resolved prior to closing the project.
Incurred
Budget
Construction Costs
The project forecast is within the approved budget and authorization.         None this quarter 
Change Order                               Photo
Current Quarter     Project Total
Number of COs           0             9
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The Port is working with the contractor to address an outstanding PCI
certification issue.
Budget Transfers
Amount       From         To
$150,000         C800253         C800404



AIRPORT 
20  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Aircraft RON Parking USPS Site 
Project: C800254              Prepare the site for the construction of  Project Status:
Budget: $41,456,350            hardstands for use as Remain         Schedule: Delayed
Phase: Construction            Overnight (RON) parking of aircraft at  Budget: On or Under
Start: 8/26/2008                the Cargo 5 area.                Status Reset: 10/8/2013
Schedule Completion: 5/31/2015                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Beneficial Occupancy from the Building Department received on the Security    50   45.6
Guard Shelter E125. 400Hz Ground Power Units (GPU's) have been tested and            38.4
40                  36.0
passed for acceptance and use.
30
Schedule                                      Dollars in Millions 20
Security testing and TSA approval for Security Guard Shelter E125, final         10
O&Ms received and complete electrical training session in the third quarter.       0
Authorized Forecasted   Costs
Incurred
Budget
The project forecast is within the approved budget and authorization.         Construction Costs
Change Order                                 30
25.4
25             22.3
Current Quarter     Project Total
20
Number of COs           1             7
Amount of Cos          $56,650         $209,511
15
Justification for COs: 1) Modifications to the E-125 gate control and          Dollars in Millions 10
5
communication; and 2) the Cargo 5 North Edge Utility and Pavement                  0.2
0
modifications.                                                  Initial Change Spent
Orders
Risks
A significant amount of contaminated soil at Cargo 5  contract bid quantity    Photo
was 13,500 total TNs, 21,500 TNs to date. Overrun managed through
construction contingency.
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 2Q 2015 Report  21

SECOND QUARTER REPORT, 2015
8th Floor Weatherproofing 
Project: C800274              Removal and replacement of the floor  Project Status:
Budget: $9,324,000             covering system on the eighth floor of   Schedule: Within or Ahead
Phase: Closeout                the STIA parking garage and of the     Budget: On or Under
Start: 3/23/2010                expansion joints and flashing.        Status Reset: 5/27/2014
Schedule Completion: 7/31/2014                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The Port and its' contractor, PCL, have reached a tentative settlement on PCL's    15   13.1
claim. Port Construction Management is working with Legal and CPO contract
administration to execute the settlement.                              Dollars in Millions           9.3
10                  8.2
Schedule
5
Project complete
0
Budget                                       Authorized Forecasted  Costs
Incurred
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
7
Current Quarter     Project Total            6.1      6.1
6
Number of COs           0             30
5
Amount of Cos           $0           $84,555            4
Justification for COs: None this quarter                              Dollars in Millions  3
2
1
Risks                                                 0.1
0
Contractor claim                                               Initial Change Spent
Orders
Budget Transfers
Amount       From         To
$0




AIRPORT 
22  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Long-Term Cell Phone Lot 
Project: C800324              Construct a new cell phone waiting lot  Project Status:
Budget: $3,300,000            to replace the existing lot that is being   Schedule: Delayed
Phase: Construction            displaced, including permanent access   Budget: On or Under
Start: 12/31/2012               control on South 170th Street.         Status Reset: 5/6/2014
Schedule Completion: 4/1/2014                               (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Construction of the Cell Phone Lot and interim traffic signal under the first       6          5.2
phase of the project is complete. Staff has coordinated with the City of SeaTac     5
and determined that a traffic signal, and associated roadway improvements, is     4   3.3
the likely permanent access solution. Given the uncertainty of future          Dollars in Millions 3                2.6
development associated with the Sustainable Airport Master Plan, staff is        2
continuing to evaluate options in order to minimize the overall investment.       1
0
Schedule                                        Authorized Forecasted  Costs
Incurred
Expect a recommendation on the permanent traffic control solution considering
the scope and timing of future development in Q1 2016.                 Construction Costs
Budget                                      1
0.8
The current authorized budget for the Cell Phone Lot is $3,300,000. The total      0.8   0.7
budget forecast is $5,200,000, which includes the permanent access solution.     Dollars in Millions 0.6
0.4
Change Order
0.2
0.2
Current Quarter     Project Total
0
Number of COs           1             6               Initial  Change  Spent
Amount of Cos          $53,359         $204,664                  Orders
Justification for COs: A change in the scope for the completion of the S 170th
St utility crossings                                              Photo
Risks
Displacement of completed improvements by future development in 5-10 years.
Until completion of the permanent access solution, congestion and complaints
during summer/holiday months continue. Completion of the permanent access
solution improvements to satisfy State Environmental Protection Agency and
roadway standard requirements.
Budget Transfers
Amount       From         To
$6,900          C800404         C800324
AIRPORT
Port of Seattle 2Q 2015 Report  23

SECOND QUARTER REPORT, 2015
Two New CTE Freight Elevators 
Project: C800334             Provide two new freight elevators to    Project Status:
Budget: $8,315,100         support concession operations in the     Schedule: Delayed
Phase: Construction          Central Terminal/Pacific Marketplace.     Budget: On or Under
Start: 8/5/2011                                            Status Reset: N/A
Schedule Completion: 11/19/2014                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Construction is complete. Delivered As-Built and project is in the closeout
8.4     8.3
process. This will be the final report.                                   8.2
Dollars in Millions 8             7.8
Schedule                                      7.8
7.6
7.6
Construction complete
7.4
7.2
Budget                                      7
Authorized Forecasted   Costs
The project forecast is within approved budget and authorization.                            Incurred
Change Order                               Construction Costs
Current Quarter     Project Total
5
Number of COs           0             41               4.3      4.3
Amount of Cos           $0           $314,638           4
Justification for COs: None this quarter                                3
2
Risks                                         Dollars in Millions  1     0.3
No new risks identified this quarter.
0
Initial  Change  Spent
Budget Transfers                                        Orders
Amount       From         To
$0                                     Photo




AIRPORT 
24  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Electrical Ground Support Equipment (EGSE)
Electrical Charge Stations 
Project: C800335             Airport-wide electrical charging system Project Status:
Budget: $30,700,000          for electrical ground support equipment   Schedule: Delayed
Phase: Construction          at the Concourses and the North and     Budget: On or Under
Start: 10/26/2010              South Satellites.                  Status Reset: 10/23/2012
Schedule Completion: 6/30/2017                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
EGSE Phase 1 Project: Completed the re-configuration of the communication    40
network for Charging Corrals C8 and D11. This new configuration receives                30.7
data from each charger in a charging corral instead of the designated master      30   25.6
charger.                                                  Dollars in Millions 20               15.5
EGSE Phase 2 Project: CPO approved for the Port to purchase the GSE
10
Chargers and for the contractor to receive, install and commission them.
0
Schedule                                        Authorized Forecasted  Costs
Incurred
Phase 1- Record Drawings received and archived March 2015.
Phase 2- Construction scheduled for late 2017.                       Construction Costs
Budget                                      5
4.0
The project forecast is within the approved budget. Request the remaining         4  3.6
authorization for the construction funding and authority to advertise for           3
construction when the design and bid documents are complete for EGSE
Charger Phase 2 Project.                                       Dollars in Millions  2
0.8
1
Change Order                                  0
Initial  Change  Spent
Current Quarter     Project Total               Orders
Number of COs           0             56
Amount of COs          $0          $804,166        Photo
Justification for COs: None this quarter
Risks
Coordinate with other airfield projects and Airline Gate Realignment program.
Budget and schedule may affect project implementation and completion of the
EGSE Phase 2 Project.



Port of Seattle 2Q 2015 Report  25

Budget Transfers
Amount       From         To
$0
Cost Growth During Construction:
Airline Realignment contributed to cost increase; varying site conditions related
to equipment installation; scope change for providing back-up power to
concourse D.












AIRPORT
26  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Cargo 6 Enhancements 
Project: C800390             Enlarge the Cargo 6 off-gate hardstand  Project Status:
Budget: $6,428,000           to allow simultaneous nose-loading of    Schedule: Delayed
Phase: Construction          wide-body freight aircraft as well as     Budget: On or Under
Start: 9/25/2012               provide fuel hydrant and ground power   Status Reset: 10/8/2013
Schedule Completion: 6/30/2015   capabilities.                    (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Due to safety concerns, relocated electrical panels originally installed on the       8
north side of the light pole, adjoining the service road, to the east side away           6.3
5.9
from traffic.                                                    6
4.5
Schedule
4
Complete additional modification to the 400Hz electrical vaults to address fall    Dollars in Millions 2
protection outside of the contract.                                    0
Authorized Forecasted   Costs
Incurred
Budget
The project forecast is within the approved budget and authorization.         Construction Costs
Change Order                                  4
3.4
3.2
Current Quarter     Project Total          3
Number of COs           0             5
2
Amount of Cos           $0           $455,000
Justification for COs: 1). None this quarter                            Dollars in Millions  1       0.5
0
Risks                                             Initial Change Spent
Orders
None
Budget Transfers                                 Photo
Amount       From         To
$0



AIRPORT
Port of Seattle 2Q 2015 Report  27

SECOND QUARTER REPORT, 2015
RW16C/34C Design and Reconstruction 
Project: C800406             Produce final design and reconstruct the   Project Status:
Budget: $101,395,000          existing RW 16C/34C in its existing       Schedule: Delayed
Phase: Construction           location, replace TW C and N, econfigure   Budget: On or Under
Start: 5/4/2010                TWs H and J, install FOD detection       Status Reset: 12/2/2014
Schedule Completion: 8/31/2016   equipment, and LED lighting system.      (Commission Construction Auth.)
Significant Developments                         Budget/Costs Incurred
Runway closure for construction occurred in May 2015.Taxiway E and    120   110.2
100.5
Q work completed and reopened for aircraft traffic in July 2015.        100
Taxiways P, H and J are closed. FAA contracts to address impacts to      80
their navigational aids and fiber optic transmission system are           60
underway. Design started for the SR 518 Interchange, currently used as   40
a haul route for the runway reconstruction.                       Dollars in Millions                 13.0
20
0
Schedule                                    Authorized Forecasted  Costs
Incurred
The runway scheduled to reopen in Q4 2015 has a 17-day delay due to
the impacts of low concrete strength results for the pavement. The
contractor is developing a recovery schedule.                    Construction Costs
57.0
60
Budget
50
The project forecast is within the approved budget and authorization.       40
30
Change Order                              20
Current Quarter     Project Total     Dollars in Millions 10         4.3
1.1
Number of COs          3             3          0
Initial  Change  Spent
Amount of Cos       $1,060,835.75      $1,060,835.75            Orders
Justification for COs: 2015 Airfield Improvement contract work,
project scheduler, and additional traffic control.                   Photo
Risks
The Contractor is conducting investigations and taking steps in order to
achieve the specified strength for concrete pavements. Contingency
plans made to address potential outcomes and impacts to schedule.
Replacement of the FAA threshold light foundations on both ends of the
runway to address a vertical elevation difference being evaluated. This
approach should not affect the schedule but will result in additional
cost. 
Budget Transfers
Amount       From        To
$0
AIRPORT 
28  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Doug Fox Lot Service Upgrades 
Project: C800451              Construct a new drainage system,     Project Status:
Budget: $6,909,000            asphalt resurfacing, improved lot       Schedule: Delayed
Phase: Construction            lighting, new building, and road       Budget: Forecast Overrun
Start: 2/29/2012                signage to improve lot appearance,     Status Reset: 10/8/2013
Schedule Completion: 2/27/2015   function, and revenue generation .     (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Commission authorized completion of the project in January. Overall project   $7.00   6.9     6.9
construction is now complete and beneficial occupancy achieved on February
27, 2015. The Port has received protests (claims) from the contractor totaling   $6.50
$273,566 and dispute resolution is on-going.                          Dollars in Millions                 6.1
$6.00
Schedule
The overall project delayed with project beneficial occupancy occurring on     $5.50
Authorized Forecasted   Costs
February 27, 2015. 
Incurred
Budget
Construction Costs
Project forecast, including the resolution of the claims, is within the revised
budget.                                                  5
4.0              4.0
4
Change Order
3
Current Quarter     Project Total
2
Number of COs          10            42
1
Amount of Cos         ($8,464)         $51,467          Dollars in Millions          0.1
0
Justification for COs: Changes related to errors and omissions (scope gap),           Initial  Change   Spent
varying site conditions (unknown utilities, pavement conditions), tenant                   Orders
requested changes, regulatory requirements (egress lighting, fire code), and
disputes.                                                  Photo
Risks
Project is complete  no additional risks identified.
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 2Q 2015 Report  29

SECOND QUARTER REPORT, 2015
Fiber Infrastructure to Gate Backstands 
Project: C800464             Extend airport provided           Project Status:
Budget: $3,195,000           communications infrastructure to       Schedule: Within or Ahead
Phase: Design               additional gates, gate information       Budget: On or Under
Start: 7/9/2013                displays to all gates and Wi-Fi antennas  Status Reset: 5/26/2015
Schedule Completion: 9/30/2016  throughout Concourses A and B.       (Commission Construction Auth.)
Significant Developments
Construction bids opened and a contract awarded. Contractor has begun pre-    Budget/Costs Incurred
construction submittal process. Anticipate construction to start in September.      4
3.20      3.01
3
Schedule
Schedule affected by design issues uncovered at 90% review.               Dollars in Millions 2
1                  0.60
Budget
0
Additional budget authorized in May 2015.
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable 
Amount of COs          $0            $0
Justification for COs: N/A
Risks
Continue to evaluate how construction impacts to airport operations can be
minimized. The airport is busier then when this project design was completed.
Budget Transfers
Amount       From         To
$0




AIRPORT 
30  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Feeder 101 Taps Replacement/Fire Station
Electric Upgrades 
Project: C800479             Replace: 1) existing 208V transformer,   Project Status:
Budget: $4,775,400           12.47 KV feeder, and add a 500 KVA      Schedule: Within or Ahead
Phase: Construction          generator and a 1000KVA transformer; 2)   Budget: On or Under
Start: 4/1/2013               electrical feeds to 13 locations along Air    Status Reset: 7/1/2014
Schedule Completion: 10/31/2016 Cargo Road; and 3) electrical transformer   (Commission Construction Auth.)
and associated switchgear for Air Cargo
#4.
Significant Developments                             Budget/Costs Incurred
The project continues to run smoothly. The feeders to the tenant buildings        6
along Air Cargo Road were completed.                                4.8    4.8
5
Dollars in Millions 4
Schedule
3
The Contractor is on schedule to complete the project in Q4 2015.             2               1.3
1
Budget                                      0
Authorized Forecasted   Costs
The project is on budget.                                                       Incurred
Change Order                               Construction Costs
Current Quarter     Project Total
2.5   2.3
Number of COs          11            11
Amount of Cos          $96,179          $96,179            2
Justification for COs: Replaced feeders (wire) that were to remain in place;      Dollars in Millions 1.5
however, water damage was found inside the insulation of the feeders. Damage     1
was not seen until the wire was de-energized and the insulation was removed to    0.5           0.2
0.1
be spliced.
0
Initial  Change  Spent
Risks                                                Orders
Delivery of the Fire Station stand-by generator is in question. A late delivery
will result in a schedule shift; however, the contractor may be responsible for
any damages.
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 2Q 2015 Report  31

SECOND QUARTER REPORT, 2015
Airfield Pavement Program 
Project: C800483               This is a multi-year program to    Project Status:
Budget: $32,500,000            replace distressed pavement and     Schedule: Within or Ahead
Phase: Design                  joint seal on the airfield starting in    Budget: On or Under
Start: 5/5/2011                  2016 through 2020.             Status Reset: 2/24/2015
Schedule Completion: 6/30/2021                             (Commission Design Auth.)
Significant Developments                             Budget/Costs Incurred
2016 Airfield Replacement Project 30% Design will be out for review in
40
August 2015.                                                    32.5
30
Schedule
20
Projects will occur annually through 2020. Anticipate completion of 2016
Airfield Replacement work by October 31, 2016.                      Dollars in Millions 10
0.2               0.1
0
Budget                                       Authorized Forecasted  Costs
Incurred
Within budget 
Change Order                               Construction Costs
None at this time 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: None at this time
Risks
None at this time
Budget Transfers
Amount       From         To
$0




AIRPORT 
32  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Facility Monitoring System Renewal 
Project: C800495             Provide a system upgrade that will allow Project Status:
Budget: $3,423,500           the system to maintain and expand       Schedule: Delayed
Phase: Construction          monitoring of critical systems such as    Budget: On or Under
Start: 10/23/2011             elevators, escalators, moving walks,     Status Reset: 12/10/2013
Schedule Completion: 4/11/2015  passenger boarding bridges and baggage  (Commission Construction Auth.)
systems.
Significant Developments                             Budget/Costs Incurred
Kolkay received beneficial occupancy and substantial completion in April. F&I    4   3.4     3.4
and PCS will need to work on connecting one of the elevators for this project to
be complete.                                              3
1.9
Schedule
2
Project completed in Q2 2015                                  Dollars in Millions 1
0
Budget                                       Authorized Forecasted  Costs
Incurred
The forecast is within the approved budget and authorization.
Construction Costs
Change Order
Current Quarter     Project Total
Number of COs           0             6           0.4
0.3               0.3
Amount of Cos          $2,330          $1,310
0.3
Justification for COs: Change orders were due to errors and omission, varying
0.2
site conditions, and scope change. CO No. 1 was a credit to the Port.          Dollars in Millions 0.1         0.0
Risks
0
None identified at this time.                                           Initial   Change   Spent
-0.1             Orders
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 2Q 2015 Report  33

SECOND QUARTER REPORT, 2015
Airportwide Mechanical Controls System 
Project: C800497             Upgrade the Mechanical Control System Project Status:
Budget: $3,500,000           for Concourse A at the Airport. This     Schedule: Within or Ahead
Phase: Construction          includes adding a wireless connection to   Budget: On or Under
Start: 5/1/2013               the Logistics area to the south of the     Status Reset: 12/9/2014
Schedule Completion: 3/11/2016  Airport.                       (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Project successfully bid and the contract awarded.                        4   3.5     3.5
Schedule                                          3
Project is within schedule.                                         2
Budget                                     Dollars in Millions 1
0.3
Project is within budget.                                          0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0
2.5
Amount of Cos           $0             $0                2.1
2
Justification for COs: N/A
1.5
Risks                                           1
Unplanned electrical shut downs could affect the project schedule increased      Dollars in Millions 0.5
control component costs. An allowance added to the estimate.                        0.0   0.0
0
Initial  Change  Spent
The contractor has never acted as a prime at the Airport. They may have                Orders
difficulties with the paper work. Construction Management is assisting the
contractor to help expedite the process.
Budget Transfers
Amount       From         To
$0



AIRPORT 
34  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Replace PLBs at S7, S9 and B4 
Project: C800543             Replace the Passenger Loading Bridges  Project Status:
Budget: $2,950,000           at S7 and S9 and install a new bridge at   Schedule: Delayed
Phase: Construction          B4                           Budget: On or Under
Start: 12/21/2014                                          Status Reset: 1/21/2014
Schedule Completion: 12/31/2014                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
All three gates are operational. PC Air installation on the new B4 gate is         3   2.95
scheduled to be completed during 3Q 2015.
2.9             2.86
Dollars in Millions 2.8                                                                                     Schedule
2.69
2.7
All PLBs completed on schedule. Expect completion of PC Air at B4 in 3rd
Quarter 2015. Delay is the result of extended time needed for construction       2.6
contract execution.                                            2.5
Authorized Forecasted   Costs
Incurred
Budget
Project is under budget.                                        Construction Costs
Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None at this time
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 2Q 2015 Report  35

SECOND QUARTER REPORT, 2015
NorthSTAR Program 
Project: C800544             Includes programmatic project        Project Status:
Budget: $18,764,150          management and project controls costs    Schedule: Within or Ahead
Phase: Design               for the NorthSTAR program; consisting   Budget: On or Under
Start: 4/5/2012               of 5 capital projects that represent a      Status Reset: N/A
Schedule Completion: 7/27/2020  unique partnership between the Port and   (Commission Construction Auth.)
Alaska Airlines.
Significant Developments                             Budget/Costs Incurred
Updated the NorthSTAR webpage in conjunction with Port Public Affairs.      20         18.8
AAG realigned NorthSTAR team for the remaining work on the program.
Three signed decisions received from AAG regarding scope direction          15
associated with North Satellite Renovations, Main Terminal Improvements and    10
Concourse C/D Exterior Stairs. AAG requested deletion of the exterior stairs     Dollars in Millions 5   3.6           3.2
component of the program. 
0
Schedule                                        Authorized Forecasted  Costs
Incurred
Continue programmatic linkage coordination to assure airport-wide gate
availability is not compromised during construction.
Construction Costs
None at this time 
Budget
The project forecast is inclusive of Programmatic Management Reserve and is
within the approved budget.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Communication and coordination across multiple teams and stakeholders along
with identification/monitoring of all "linked" Capital projects outside of
NorthSTAR.
Budget Transfers
Amount       From         To
$0            N/A           N/A

AIRPORT 
36  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
NorthSTAR Main Terminal Improvements 
Project: C800545             Renovate the North Main Terminal    Project Status:
Budget: $29,200,000          security checkpoint, curbside and       Schedule: Within or Ahead
Phase: Design               ticketing lobby areas incorporate self-    Budget: On or Under
Start: 12/3/2013              operated technologies and improve      Status Reset: N/A
Schedule Completion: 11/29/2018 aesthetics.                      (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Presented draft final alternatives of security checkpoint size/configuration and     40
ticket lobby passenger check-in and circulation options to stakeholders. Facility              29.2
Determination Analysis concluded insufficient space in North Main Terminal     30
for projected checkpoint and check-in facilities. AAG decided to delete their     Dollars in Millions 20
tenant improvement scope of the project.
10
1.5               0.3
Schedule                                       0
Authorized Forecasted   Costs
Project is holding pending SAMP recommendation for project area.
Incurred
Issue final report in Q3 2015.
Construction Costs
Budget                                    Not Applicable 
Project forecast is within the approved budget.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Project scope definition could increase scope and budget.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 2Q 2015 Report  37

SECOND QUARTER REPORT, 2015
NorthSTAR Concourse C Vertical Circulation 
Project: C800547              Construct exterior, weather protected  Project Status:
Budget: $17,938,950            sloped walkways with elevators at      Schedule: Delayed
Phase: Construction            Gates C2/4, C10/12, and C14 to       Budget: On or Under
Start: 11/6/2012                provide enhanced access from        Status Reset: 10/22/2013
Schedule Completion: 6/17/2015   concourse to aircraft ramp for        (Commission Construction Auth.)
Alaska/Horizon regional operations.
Significant Developments                             Budget/Costs Incurred
Gates C2, C10 & C16 sloped walkways, AAG ground level walkways, AAG     25
Employee Space, and two of four elevators opened as planned.                  19.3
20           17.9
13.9
15
Schedule
10
Delay in completion of elevators was due to the workforce availability in the
elevator industry.                                              Dollars in Millions 5
0
Budget                                       Authorized Forecasted  Costs
Incurred
The project is within approved budget.
Construction Costs
Change Order
10             8.9
Current Quarter     Project Total            8.7
Number of COs          12            40             8
Amount of Cos         $108,882         $819,850          Dollars in Millions  6
Justification for COs: E&O issues: revised cabling and conduit routing, steel       4
clearance, and waterline valve replacement .                             2       0.8
0
Risks                                             Initial Change Spent
Orders
Delays in Elevator completion
Budget Transfers
Amount       From         To
$0            N/A           N/A



AIRPORT 
38  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
South Satellite Interior Renovations 
Project: C800549             Modify the mezzanine and concourse   Project Status:
Budget: $5,167,000           levels of the South Satellite to improve   Schedule: Delayed
Phase: Construction          the passenger experience.           Budget: On or Under
Start: 11/4/2012                                           Status Reset: 12/9/2014
Schedule Completion: 6/1/2016                              (Commission Construction Auth.)
Significant Developments
Phase 1 completed on schedule.                                Budget/Costs Incurred
6
4.97
Schedule                                       5
Project is behind schedule due to lengthy design reviews. Increased flight        4
activity has reduced the construction window of opportunity built into the        3
project schedule and will thus lengthen construction as well.                Dollars in Millions     1.92
2
0.88
1
Budget                                      0
Authorized Forecasted   Costs
Within budget                                                        Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Review scope against forthcoming South Satellite renovation project to
determine continued feasibility of all elements of the project.
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 2Q 2015 Report  39

SECOND QUARTER REPORT, 2015
Grease Interceptor Augmentation 
Project: C800551             Install one underground 9,000 gallon   Project Status:
Budget: $1,484,200           grease interceptor and one 6,000 gallon   Schedule: Delayed
Phase: Construction          above ground interceptor to service the   Budget: On or Under
Start: 5/1/2013                South Satellite, as well as hooking up    Status Reset: N/A
Schedule Completion: 3/1/2016   an existing interceptor to concessions at  (Commission Construction Auth.)
Concourse C.
Significant Developments                             Budget/Costs Incurred
Decision made to go forward with internal resources to perform the work            1.5     1.5
1.6
1.4
Schedule                                       1.2
1
Work to begin late Q3 2015                                   Dollars in Millions 0.8
0.6                           0.4
0.4
Budget
0.2
The project forecast is within the approved budget with PCS performing work.     0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable 
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Construction impacts Delta Operations at S. Satellite. Risk of encountering
contaminated soil in excavation- but not expected.
Budget Transfers
Amount       From         To
$0




AIRPORT 
40  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
NorthSTAR Refurbish Baggage Systems 
Project: C800555             Refurbish existing baggage systems in   Project Status:
Budget: $20,002,500          support of AAG operation at North      Schedule: Within or Ahead
Phase: Construction          Satellite and Concourse D. The work    Budget: On or Under
Start: 11/6/2012              will extend the service life of part of the   Status Reset: 9/24/2013
Schedule Completion: 6/15/2015  C92 systems, C88 North Satellite       (Commission Construction Auth.)
systems, and C88 tunnel systems.
Significant Developments                             Budget/Costs Incurred
C88 and C92 conveyor system modifications are complete and system is        25   22.0
20.0
operational. Began C92 Automated Bag Tag Reader (ATR) replacements.      20              16.4
15
Schedule
10
Project completion slipped to address added scope from BSO/MCP relocation    Dollars in Millions 5
and construction phasing. Remaining punchlist items and access/platform
0
modification issues are being addressed. C92 Power Turns will be completed
Authorized Forecasted   Costs
after the summer passenger load decreases.                                          Incurred
Budget                                    Construction Costs
The project forecast is within the approved budget.
14
11.8         11.3
12
Change Order
10
Current Quarter     Project Total          8
Number of COs          26            48             6
Amount of Cos         $152,611        $1,590,272         Dollars in Millions  4
1.6
2
Justification for COs: Regulatory requirements (i.e., Regulated Material          0
Management; Fireproof patch) E&O issues (Ladders; Control Stations, conduit       Initial Change Spent
Orders
routing)
Risks
Project schedule has no float remaining.
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 2Q 2015 Report  41

SECOND QUARTER REPORT, 2015
NorthSTAR North Satellite Renovation and NSTS Lobbies 
Project: C800556             Renovation and expansion of the North  Project Status:
Budget: $421,612,944         Satellite (NSAT), including NSAT      Schedule: Within or Ahead
Phase: Design               Satellite Transit System (STS) stations    Budget: On or Under
Start: 7/24/2012              "refresh", ramp level, Concourse level,    Status Reset: N/A
Schedule Completion: 7/27/2020  and new rooftop airline lounge.        (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Commission approval to expand NSAT baggage handling system received.     500
421.7
Sixty percent design submitted for Port review. Completed additional Aircraft
400
parking/ground service equipment (GSE) layout analysis. Selected and awarded
300
Mechanical & Electrical Contractor/Construction Manager (MC/CM &
EC/CM) under the Hensel Phelps GC/CM contract. AAG decided to delete      200
Dual Door scope from the project. Began decision analysis process to         100  Dollars in Millions    62.7
15.2
determine optimal construction phasing option.                         0
Authorized Forecasted   Costs
Incurred
Schedule
Continue to evaluate construction phasing options in collaboration with the
Construction Costs
GC/CM contractor and AAG.                              Not Applicable 
Budget
The forecast is currently within the approved budget.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Inclusion of additional scope items combined with delays in design decisions
may impact Q3 2020 construction completion and current project budget.
Budget Transfers
Amount       From         To
$0

AIRPORT 
42  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Main Terminal Mezzanine Tenant Relocations 
Project: C800560             Construct new tenant leased spaces in   Project Status:
Budget: $2,025,000           order to move existing tenants and       Schedule: Within or Ahead
Phase: Construction          provide new leasable office space for     Budget: On or Under
Start: 3/26/2013              airlines on the mezzanine of the main    Status Reset: 11/19/2013
Schedule Completion: 3/30/2015  terminal.                      (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Construction of all leased spaces completed.                           2.1   2.03    2.02
2
Schedule
1.9
Construction of all spaces completed on schedule.                      Dollars in Millions 1.8               1.76
Budget                                     1.7
The project forecast is within the approved budget and authorization.          1.6
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           9             19
1   0.9         0.9
Amount of COs        $29,380.34       $118,159.98
0.8
Justification for COs: Design changes and varying site conditions.            Dollars in Millions 0.6
Risks                                          0.4
None identified at this time.                                        0.2       0.1
0
Budget Transfers                                     Initial Change Spent
Orders
Amount       From         To
$0




AIRPORT 
Port of Seattle 2Q 2015 Report  43

SECOND QUARTER REPORT, 2015
Known Crewmember Employee Bypass 
Project: C800576             Construct two Known Crew Member    Project Status:
Budget: $780,000            points of entry and employee bypass     Schedule: Delayed
Phase: Closeout              portals with Airport access control       Budget: On or Under
Start: 12/11/2012             equipment at each end of the main      Status Reset: 9/30/2014
Schedule Completion: 1/15/2015  terminal.                       (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Portal is in operation and project is in close out.                          0.8   0.8     0.8
Schedule                                         0.75
Project completed.                                          0.7               0.7
0.65
Budget                                     Dollars in Millions
The project forecast is within approved budget and authorization.             0.6
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable 
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0




AIRPORT 
44  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Parking Garage Lights (CA) 
Project: C800581             Use current technology to replace all    Project Status:
Budget: $6,235,000           normal lighting in the Airport Parking    Schedule: Within or Ahead
Phase: Design               Garage on all 8 floors and in the helices.   Budget: On or Under
Start: 1/31/2014              This will reduce energy consumption     Status Reset: N/A
Schedule Completion: 12/31/2019 over 60%.                     (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Phase I Major Works awarded to Foy Group. The bid was 58% below the EE.     8
Phase 2 Maintenance work original plan driven to change due to procurement         6.2    6.2
requirements for purchase of the lights. CPO put out a RFP for the lights.        6
Schedule
4
The Project is on schedule.                                      Dollars in Millions 2
0.6
0
Budget                                       Authorized Forecasted  Costs
Incurred
The forecast is within the approved budget and authorization.
Construction Costs
Change Order
Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No risks at this time.
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 2Q 2015 Report  45

SECOND QUARTER REPORT, 2015
International Arrivals Facility (IAF) 
Project: C800583              Planning, design, and construction of  Project Status:
Budget: $608,365,000           new Federal Inspection Services (FIS)   Schedule: Within or Ahead
Phase: Planning               facility, including connector between    Budget: On or Under
Start: 6/25/2013                South Satellite and FIS and sterile     Status Reset: 12/22/2015
Schedule Completion: 11/9/2019    corridors between Concourse A and   (Commission Authorization  to  start 
FIS.                       Design & Construction)
Significant Developments                             Budget/Costs Incurred
Finalized the Program Definition Document (PDD) and obtained Commission    800
Authorization to award the DB Contract for Validation. Completed design                608.4
builder selection process with apparent low bidder identified as Clark/SOM.     600
Commission initiated a 90-day Program Review Plan.                   400
200
Schedule                                      Dollars in Millions    24.5        8.6
Project schedule revised to reduce the time required for contract negotiation and    0
Authorized Forecasted   Costs
allow validation services to commence in July 2015 instead of September 2015.                  Incurred
The 120-day validation services period is retained with anticipated completion
and associated Commission request to proceed with design and construction    Construction Costs
now targeted for early December 2015 instead of February 2016.           Not Applicable 
Budget
The IAF Project Notebook Status II Budget approval granted subject to
amendment after Validation Period and receipt of Design-Builder's Target
Budget commitment (anticipated in 4Q 2015).
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Program budget may increase due to additional scope development.
Budget Transfers
Amount       From         To
$0

AIRPORT 
46  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Wi-Fi Enhancement 
Project: C800585              Upgrade Wi-Fi system in the public   Project Status:
Budget: $9,880,000             and ramp operational areas of the      Schedule: Delayed
Phase: Design                 Airport.                       Budget: On or Under
Start: 11/4/2012                                            Status Reset: N/A
Schedule Completion: 6/5/2017                               (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Design consultant is now under contract. Design has begun. Wi-Fi signal audits    12
9.87
underway and nearly complete. As-build documentation has been reviewed and   10
field-verified.                                                    8
Schedule
6
4
Design is taking longer than expected to start.                          Dollars in Millions     1.95
2                  0.19
0
Budget                                       Authorized Forecasted  Costs
Incurred
On budget
Construction Costs
Change Order                               Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of COs          $0            $0
Justification for COs: N/A
Risks
Design has taken longer than expected to start. Tenants are proposing their own
systems that will need not to interfere.
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 2Q 2015 Report  47

SECOND QUARTER REPORT, 2015
Checked Baggage Recapitalization/Optimization 
Project: C800612             TSA approached the Airport in 2012    Project Status:
Budget: $320,550,000         with plan to replace all federally owned   Schedule: Within or Ahead
Phase: Design               and operated baggage scanning         Budget: On or Under
Start: 2/26/2013              equipment, known as Explosive        Status Reset: N/A
Schedule Completion: 12/31/2024 Detection System (EDS) equipment.     (Commission Construction Auth.)
The EDS equipment is approaching the
end of its life.
Significant Developments                             Budget/Costs Incurred
Seventy percent design reviewed in Q2. The design team is progressing toward
400
100% design due in Q4. Project phasing plans progressing.                         320.6
300
Schedule
200
The project is currently on schedule, but is being reviewed for 10-year plan
100  Dollars in Millions     20.4             9.7
Budget                                      0
Authorized Forecasted   Costs
The project forecast is within the approved budget. When the bid documents are                  Incurred
completed, request Commission Authorization for construction funding and
authority to advertise for construction.                               Construction Costs
Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0



AIRPORT 
48  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Second Floor Mezzanine Infrastructure Upgrade 
Project: C800615             Upgrade and extend the infrastructure   Project Status:
Budget: $2,666,000           (HVAC, Communications, Electrical,     Schedule: Delayed
Phase: Construction          Plumbing, WiFi) to 14,000sq ft of future  Budget: On or Under
Start: 8/1/2013               lease space on the 2nd floor, including    Status Reset: 6/25/2013
Schedule Completion: 2/13/2015  7,000 sq ft for a new USO.           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Project complete. This will be the final report for this project.
2.7    2.67
2.6             2.55
Schedule
Currently working on project closeout.                                              2.41
2.4
Budget                                     Dollars in Millions 2.5 2.3
The forecast is within the approved budget and authorization.               2.2
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs          17            25
1.2
Amount of COs         $115,000         $123,429                    1.0
1.0
1
Justification for COs: Designer and owner error and omissions.
0.8
Risks
0.6
None                                       Dollars in Millions 0.4
0.2          0.1
0
Budget Transfers                                     Initial Change Spent
Orders
Amount       From         To
$0




AIRPORT 
Port of Seattle 2Q 2015 Report  49

SECOND QUARTER REPORT, 2015
Gate S1 Ramp 
Project: C800629             Install a ramp to facilitate travel       Project Status:
Budget: $1,405,000           between the ramp surface and the       Schedule: Within or Ahead
Phase: Construction          International arrivals facility for        Budget: On or Under
Start: 11/24/2013             passenger use.                    Status Reset: 12/9/2014
Schedule Completion: 6/1/2015                               (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Ramp is in use.                                             1.5   1.4
1.2
1.1
Schedule
Dollars in Millions 1
Project completed, construction on schedule
0.5
Budget
The project forecast is within approved budget and authorization.              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable 
Amount of Cos            0             0
Justification for COs: N/A
Risks
Project came in on time and under budget. The project team is evaluating the
degree of weather shelter the structure provides, and it maybe adjusted if
necessary.
Budget Transfers
Amount       From         To
$0




AIRPORT 
50  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
2015-2016 Concourse C Roof Replacement 
Project: C800702               Remove and replace the existing    Project Status:
Budget: $5,596,000             roof system (approximately 83,000   Schedule: Within or Ahead
Phase: Design                  square feet) on Concourse C; install   Budget: On or Under
Start: 5/26/2010                 a new elastomeric roofing system;    Status Reset: Click here to enter a 
Schedule Completion: 11/30/2016  ladders and fall protection; and     date.
replace and refurbish the existing    (Commission Construction Auth.)
skylight window/walls.
Significant Developments                             Budget/Costs Incurred
Selection of a designer is complete pending negotiations.
6           5.60
5
Schedule
4
Project is on schedule
3
2
Budget                                     Dollars in Millions   0.87
1
0.00
Project is within budget                                           0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total
Construction Costs
Number of COs           0             0
None at this time
Amount of Cos           $0             $0
Risks
If the designer selection takes longer than planned, it could mean design
completion will take longer as well.
Budget Transfers
Amount       From         To
$0




AIRPORT

Port of Seattle 2Q 2015 Report  51

SECOND QUARTER REPORT, 2015
Dining and Retail Infrastructure Modernization 
Project: C800638             Project is to provide infrastructure     Project Status:
Budget: $13,953,000.00        modifications, re-demise of spaces, two   Schedule: Within or Ahead
Phase: Design               new elevators, and two new Children's   Budget: On or Under
Start: 10/28/2014              Play Areas in support of the Airport     Status Reset: N/A
Schedule Completion: 6/30/2020  Dining and Retail concessions plan.     (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Design Package 1 at 90%. Design Package 2 at 30%. Award for Job Order      15        13.95
Contract is imminent.
Dollars in Millions 10    8.83
Schedule
Overall project is on schedule.                                      5
0.54
Budget                                      0
Authorized Forecasted   Costs
Currently on budget                                                       Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
1. Construction is linked with leasing;
2. Projects in the Central Terminal are linked with other projects; delays in
these projects could impact this project.
Budget Transfers
Amount       From         To
$0



AIRPORT 
52  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
CCTV Camera and System Enhancement 
Project: C800642             Add cameras and improve the video    Project Status:
Budget: $11,000,000          management system at the Airport.      Schedule: Delayed
Phase: Design               Project funded by a TSA Other        Budget: On or Under
Start: 11/4/2012               Transaction Agreement (OTA)        Status Reset: N/A
Schedule Completion: 11/30/2016                            (Commission Construction Auth.)
Significant Developments
Design consultant is now under contract. Design has begun. Designer has      Budget/Costs Incurred
received as-built documentation and begun field verification of existing         12         11.00
conditions. Monthly meetings held with TSA.                        10
Dollars in Millions 8
Schedule                                       6
4.07
While the project design has taken longer than anticipated, the team is           4
reviewing options to bring the project back on schedule.                    2               0.15
0
Authorized Forecasted   Costs
Budget
Incurred
Project continues to be within approved budget.
Construction Costs
Change Order                               Not Applicable 
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The project team is reviewing as-built information and site conditions in order
to understand variances.
Budget Transfers
Amount       From         To
$0



AIRPORT 
Port of Seattle 2Q 2015 Report  53

SECOND QUARTER REPORT, 2015
Passenger Loading Bridge Renew 
Project: C800653               Renewal/Replacement of Passenger  Project Status:
Budget: $7,250,000             Loading Bridges B6, B8, B14, C3    Schedule: Within or Ahead
Phase: Design                  and S15                      Budget: On or Under
Start: 7/18/2014                                           Status Reset: 10/7/2014
Schedule Completion: 12/31/2015                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The new Passenger Loading Bridge (PLB) at B14 began operation on May 20th
8.00    7.25     7.25
and PLB at C3 was operational on June 15th.
6.00
Schedule
4.00
Completion schedule for the loading bridges:
2.00  Dollars in Millions                       1.74
B14 and C3       Complete
0.00
S15           September 21, 2015                      Authorized Forecasted  Costs
Incurred
B6          October 12, 2015
B8          November 2, 2015
Construction Costs
Not Applicable at this time 
Budget
NSTR 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Risks
Delivery of PLB for S15 is close to the projected completion date.
Budget Transfers
Amount       From         To
$0



AIRPORT 
54  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Domestic Water Piping 
Project: C800657             Replace domestic water piping       Project Status:
Budget: $1,950,000           branches and manifolds including       Schedule: Within or Ahead
Phase: Design               valves.                         Budget: On or Under
Start: 11/4/2012                                           Status Reset: 5/13/2014
Schedule Completion: 1/29/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
One hundred percent (100%) design is complete.
$3
2.0       2.0
$2
Schedule
Dollars in Millions $2
Approval for construction received second quarter of 2015. The project will
$1
advertise and bid during the Quarter 3. Substantial completion scheduled for
0.5
April 29, 2016. This is a 3 month delay from the schedule prepared for the       $1
notebook. Preparing ready-to-bid documents took longer than expected.         $0
Authorized Forecasted   Costs
Incurred
Budget
The authorized amount is $1,950,000 to complete project.                Construction Costs
Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0



AIRPORT
Port of Seattle 2Q 2015 Report  55

SECOND QUARTER REPORT, 2015
Mech Energy Conservation (CA) 
Project: C800658             Stage 3 Mechanical Energy          Project Status:
Budget: $3,500,000           Conservation to improve the efficiency    Schedule: Within or Ahead
Phase: Audit/Notebook        of portions of the mechanical          Budget: On or Under
Start: 8/25/2014              infrastructure system at the Airport.      Status Reset: N/A
Schedule Completion: 12/31/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Investment Grade Audit Final report received on February 27, 2015. PBS
4           3.5
Engineering and PCS conducting lead paint and asbestos RMM survey.
3
Schedule
2
Schedule for completing RMM survey and incorporating POS costs in funding
1
request is aggressive when considering scope of work due to diversity in scope    Dollars in Millions     0.3           0.2
and location of nine separate energy conservation measures.                 0
Authorized Forecasted   Costs
Incurred
Budget
Schedule future Commission authorization for additional funds after         Construction Costs
completion of Audit and with an updated construction schedule.            Not Applicable 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time.
Budget Transfers
Amount       From         To
$0



AIRPORT 
56  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
North Utility Tunnel Steam Pipe 
Project: C800659             Replace 45 year old steam piping      Project Status:
Budget: $1,250,000          expansion joints in the North Utility      Schedule: Within or Ahead
Phase: Closeout              Tunnel.                          Budget: On or Under
Start: 3/18/2014                                            Status Reset: N/A
Schedule Completion: 10/8/2014                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Project closed out. This will be the last report.                           1.5
1.3
Schedule
1
0.7       0.7
Project closed out.
0.5
Budget                                     Dollars in Millions
The project completed below the authorized amount.                     0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             5
0.5
Amount of Cos           $0           $19,915
0.4          0.4
0.4
Justification for COs: None this quarter
0.3
Risks                                          0.2
None                                       Dollars in Millions 0.1
0.0
0
Budget Transfers                                     Initial Change Spent
Orders
Amount       From         To
$0




AIRPORT 
Port of Seattle 2Q 2015 Report  57

SECOND QUARTER REPORT, 2015
S4 & S6 International Corridor Connection 
Project: C800662             Installation of a fixed bridge and      Project Status:
Budget: 4,850,000            corridor extension to connect gates S6    Schedule: Delayed
Phase: Construction          and S4 to the International Corridor      Budget: On or Under
Start: 11/4/2012                                           Status Reset: 2/25/2014
Schedule Completion: 10/22/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Installation of new S4 passenger loading bridge and fixed walkways started. A
6           5.1
scope change is in process to retain the S5 gate and operation.                    4.9
5
Dollars in Millions 4
Schedule
3
Project completion scheduled for October 2015.
2                   1.3
1
Budget
0
Additional budget requested in July to handle the higher cost of regulated          Authorized Forecasted  Costs
Incurred
materials management and the scope to retain the S5 gate.
Change Order                               Construction Costs
Current Quarter     Project Total          2
1.7
Number of COs          12            12
1.5
Amount of Cos          $36,360          $36,360
0.9
Justification for COs: Designer and Owner error/omissions and varying site           1
conditions                                                    Dollars in Millions 0.5
0.0
Risks                                           0
Initial  Change  Spent
Schedule delays possible due to late delivery of PC Air PAC 30 unit and                Orders
additional scope to retain S5 gate.
Budget Transfers
Amount       From         To
$0



AIRPORT 
58  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Automated Passport Control 
Project: C800667              Install additional Automated Passport  Project Status:
Budget: $2,197,900            Control (APC) kiosks in the existing    Schedule: Within or Ahead
Phase: Construction            FIS at the South Satellite.            Budget: On or Under
Start: 10/31/2013                                           Status Reset: N/A
Schedule Completion: 6/1/2015                               (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Project is complete and in use. Some final items are being addressed.            2
2.2
2
Schedule                                              2.1
2
Project is complete.
2                   2.0
Budget                                     Dollars in Millions 2
Project remains within current budget.                               2
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable 
Amount of Cos           $0             $0
Justification for COs: N/A                                      Photo
Risks
None
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 2Q 2015 Report  59

SECOND QUARTER REPORT, 2015
Construction Logistics Expansion 
Project: C800688              The expansion and reconfiguration of   Project Status:
Budget: $7,400,000            the existing construction logistics        Schedule: Within or Ahead
Phase: Design                 facilities (including contractor parking)    Budget: Forecast Overrun
Start: 8/1/2014                 and the renovation of Port field offices.    Status Reset: N/A
Schedule Completion: Q4 2016                                (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Work began on the Contractor Parking Lot. Completed 50% design for the     10.000
reconfiguration of the Construction Logistics facilities. Decision made to                   8.0
8.000
accelerate a portion of the Construction Logistics work (Lots 1 and 2) in order
6.000
to support the Aviation Capital Program. Plan to have Port Construction
Services complete the accelerated work. The assessment of the existing        4.000   2.5
facilities was completed and design continues for the renovation of the Field     2.000  Dollars in Millions                  0.3
Offices.                                                   0.000
Authorized Forecasted   Costs
Incurred
Schedule
The project is currently on schedule with the following completion dates:
Construction Costs
x Contractor Parking Relocation  Q3 2015                      Not Applicable 
x Construction Logistics (Lots 1 and 2)  Q4 2015
x Construction Logistics  Q3 2016                          Location
x Field Office Renovation - Q4 2016
Budget
The project is forecast to exceed budget given the risks below. Additional funds
for construction planned for authorization in Q3 2015 for Construction
Logistics, and in Q1 2016 for Field Offices.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of COs          $0            $0
Justification for COs: N/A
Risks
x Completion of this project to support the Aviation Capital Program;.
x Construction Logistics: additional costs due to unsuitable materials and
additional electrical scope (this was added in Q3 and increased the budget
to $7.8M;
x Field Offices: additional scope due to unknown building conditions; project
team is planning to design around the risks to avoid cost increases.

60  Port of Seattle 2Q 2015 Report

Budget Transfers
Amount       From         To
$0














AIRPORT
Port of Seattle 2Q 2015 Report  61

SECOND QUARTER REPORT, 2015
2016 Fuel System Modifications 
Project: C800692               Airline activity growth at the      Project Status:
Budget: $2,069,000             Airport is requiring the installation   Schedule: Delayed
Phase: Design                  of a new fuel pits in 2016.         Budget: On or Under
Start: 11/6/2013                                           Status Reset: 11/11/2014
Schedule Completion: 10/31/2016                            (Commission Design Auth.)
Significant Developments                             Budget/Costs Incurred
Scope has increased by five additional new fuel pits to accommodate the new
2.5
narrow body gate configurations at the South Satellite, bringing the total to nine              2.1
new fuel pits.                                                  2
1.5
Schedule                                       1
Project originally scheduled for completion in Q4 2015 postponed to 2016 to    Dollars in Millions 0.5   0.2
allow time for new design of "hot tap" fuel connection, which reduces fuel                       0.1
0
system down time during construction.                               Authorized Forecasted  Costs
Incurred
Budget
Commission Authorization will be requested in third quarter to increase budget  Construction Costs
to reflect the increase in scope.                                      None at this time 
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: None at this time
Risks
Not Applicable
Budget Transfers
Amount       From         To
$0



AIRPORT 
62  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
2015-2016 Concourse C Roof Replacement 
Project: C800702               Remove and replace the existing    Project Status:
Budget: $5,596,000             roof system (approximately 83,000   Schedule: Within or Ahead
Phase: Design                  square feet) on Concourse C; install   Budget: On or Under
Start: 5/26/2010                 a new elastomeric roofing system;    Status Reset:
Schedule Completion: 11/30/2016  ladders and fall protection; and      (Commission Construction Auth.)
replace and refurbish the existing
skylight window/walls.
Significant Developments                             Budget/Costs Incurred
Selection of a designer is complete pending negotiations.
6           5.60
5
Schedule
Project is on schedule                                          Dollars in Millions 4
3
2
Budget                                        0.87
1
0.00
Project is within budget                                           0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total
Construction Costs
Number of COs           0             0
None at this time
Amount of Cos           $0             $0
Risks
If the designer selection takes longer than planned, it could mean design
completion will take longer as well.
Budget Transfers
Amount       From         To
$0




AIRPORT

Port of Seattle 2Q 2015 Report  63

SECOND QUARTER REPORT, 2015
Terminal Utilities Upgrade Project 
Project: C800717               Click here to enter text.          Project Status:
Budget: $9,950,000                                         Schedule: Within or Ahead
Phase: PM                                              Budget: On or Under
Start: 9/21/2010                                           Status Reset: Click here to enter a 
Schedule Completion: 3/1/2018                             date.
(Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Design firm selected
12
10.0
10
Schedule
Dollars in Millions 8
Start design: 3rd quarter 2015
6
Design Complete: 3rd quarter 2016
4
Commission Authorization for Construction: 4th quarter 2016                  2.0
2
Advertise for Construction: 1st quarter 2017                                           0.0
0
Construction Complete: 1st quarter 2018                             Authorized Forecasted  Costs
Incurred
Budget
Design: $2,000,000                                       Construction Costs
Construction: $7,285,000                                    Not Applicable
Sales Tax: $665,000
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Risks
Design cost
Design delay
Construction cost
Construction delay
Unforeseen conditions during construction
Coordination with adjacent projects
Budget Transfers
Amount       From         To
$0

AIRPORT
64  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
CTE HVAC Upgrade 
Project: C800722               Install two new air-handling units   Project Status:
Budget: $$6,612,000            (AHUs) on the roof above the N.     Schedule: Within or Ahead
Phase: Design                  and S. mezzanine levels of the       Budget: On or Under
Start: 8/10/2010                 central terminal to provide heating,   Status Reset: Click here to enter a 
Schedule Completion: 12/31/2017  ventilation, and air conditioning    date.
infrastructure systems.            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Design kickoff meeting with HNTB Corp design team held on August 10,
8
2015.                                                        6.6
6
Schedule
4
Start Design: 2nd quarter 2015
Complete Design: 2nd quarter 2016                             Dollars in Millions 2   1.1
Commission Authorization for Construction: 3rd quarter 2016                              0.0
0
Advertise for Construction: 4th quarter 2016                             Authorized Forecasted  Costs
Substantial Construction Complete: 4th quarter 2017                                    Incurred
Budget                                    Construction Costs
Design: $1,114,000                                       Not Applicable
Construction: $5,078,000
Sales Tax: $420,000
Expense: $23,000
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: None at this time
Risks
Design delay
Construction costs
Construction delay
Unforeseen conditions during construction
Coordination with adjacent projects Schedule delay in design
Budget Transfers
Amount       From         To
$0
AIRPORT
Port of Seattle 2Q 2015 Report  65

SECOND QUARTER REPORT, 2015
North East Redevelopment Area Program 
Project: U000239               This is an FAA funded project with  Project Status:
Budget: $5,000,000             participation from the City of       Schedule: Within or Ahead
Phase: Design                  Burien but led the Port (500K       Budget: On or Under
Start: 8/16/2015                 each). The project is to redevelop    Status Reset: 10/14/2014
Schedule Completion: 5/12/2019   the Area north of the airport in the    (Commission Construction Auth.)
City of Burien.
Significant Developments                             Budget/Costs Incurred
Professional Service Agreement executed August 2015.
6
5.0       5.0
5
Schedule
Dollars in Millions 4
Project Schedule not yet developed
3
2
Budget
1
0.0
Budget commission authorization received on October 14, 2014.              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total
Construction Costs
Number of COs           0             0
None at this time
Amount of Cos           $0             $0
Photo
Risks
None
Budget Transfers
Amount       From         To
$0




AIRPORT

66  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Highline Schools Noise Insulation 
Project: C200007              Highline School Insulation Agreement  Project Status:
Budget: $101,797,000           will provide funding for sound        Schedule: Delayed
Phase: Construction            insulation for 15 schools that are      Budget: On or Under
Start: 3/23/1999                impacted by aircraft noise from Sea-    Status Reset: N/A
Schedule Completion: 11/30/2021  Tac Airport                    (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Port funds authorized for availability when the FAA, the State of Washington,    120   102.1    101.8
and the Highline School District (HSD) provide matching funds. HSD was      100
unable to pass a school bond vote in February. Project has an unknown         80               63.4
timeframe until a bond passes.                                   Dollars in Millions 60
40
Schedule                                      20
The schedule for state funds is unknown. The district's schedule is dependent on    0
Authorized Forecasted   Costs
obtaining general election bonds at various intervals. The district's construction                   Incurred
schedule at this point is unknown.
Construction Costs
Budget                                    Not Applicable 
The project forecast is within the approved budget and authorization.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Project delayed due to funding issues with HSD. There is a risk if there are no
bonds passed in the general election, and if FAA Airport Improvement Program
(AIP) Grant funding is not available.
Budget Transfers
Amount       From         To
$0


AIRPORT 
Port of Seattle 2Q 2015 Report  67

SECOND QUARTER REPORT, 2015
Highline Community College Noise Insulation 
Project: C200042              Highline Community College       Project Status:
Budget: $7,970,266             Insulation Agreement will provide     Schedule: Within or Ahead
Phase: Construction            funding for up to 22 eligible buildings   Budget: On or Under
Start: 1/11/2005                that are impacted by aircraft noise     Status Reset: N/A
Schedule Completion: 12/31/2013  from Sea-Tac Airport.             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Fourteen of the original 22 eligible buildings have been sound insulated by the    8.3
college. The College sound insulation program has been dependent on receiving       8.2
8.2
funds from FAA grants. The FAA notified the Port that the Highline
8.1
Community College Campus is no longer located within the 65 DNL Noise
Contour and therefore is not eligible for any further grant funding. Without the    Dollars in Millions 8         8.0     8.0
FAA's approval and funding, the remainder of the college buildings cannot be    7.9
sound insulated.                                             7.8
Authorized Forecasted   Costs
Incurred
Schedule
The construction is complete on the last building (Building #4) and the Noise   Construction Costs
Office is working with FAA to Close Grant AIP 127. We have received the    Not Applicable 
Final Grant Closure letter from the FAA. The project is closed.
Budget
The project forecast is within the approved budget. No further authorization
anticipated.
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The FAA will not allocate future grant funds to this project.
Budget Transfers
Amount       From         To
$0


AIRPORT 
68  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Home Insulation Retrofit 
Project: C200048              Storm window retrofit of previously   Project Status:
Budget: $4,060,147             insulated homes.                  Schedule: Within or Ahead
Phase: Construction                                        Budget: On or Under
Start: 1/11/2005                                            Status Reset: N/A
Schedule Completion: 12/31/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The Port has identified eligible homes and notified homeowners of their         6   5.3
eligibility. The Port is continuing with storm window retrofit.                 5
4.1
3.4
Schedule
4
3
The project is on hold until new eligible homes are identified.               Dollars in Millions 2
1
Budget                                      0
Authorized Forecasted   Costs
The project forecast is within the approved budget and authorization.                          Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
The ability to accomplish the retrofit is dependent on homeowner's schedules,
and structural integrity of the home. Ability to Identify future potentially
eligible homes.
Budget Transfers
Amount       From         To
$0




AIRPORT 
Port of Seattle 2Q 2015 Report  69

SECOND QUARTER REPORT, 2015
Single Family Home Sound Insulation 
Project: C200093             Sound insulate remaining homes that are Project Status:
Budget: $13,747,395          within the 1998 65 decibel day night     Schedule: Within or Ahead
Phase: Construction          level (DNL) noise contour.            Budget: On or Under
Start: 3/27/2007                                           Status Reset: N/A
Schedule Completion: 12/31/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Seventy-one homes are complete; and ten homes are in the process of receiving
15    13.7     13.7
sound insulation.
Schedule
10
Project is on schedule. Anticipate completion by 4th quarter 2015.            Dollars in Millions                 5.4
5
Budget                                      0
Authorized Forecasted   Costs
The project forecast is within approved budget and authorization to complete all                  Incurred
homes currently in progress.
Construction Costs
Change Order
3.8
Current Quarter     Project Total          4
Number of COs           0             0             3
Amount of Cos           $0             $0
1.8
Justification for COs: N/A                                       Dollars in Millions  2
1
Risks                                                 0.0
0
The ability to accomplish the insulation is dependent on the homeowner's           Initial Change Spent
schedules, willingness to sign an aviation easement, obtain a subordination               Orders
agreement from their lender, and structural integrity of the home.
Budget Transfers
Amount       From         To
$0



AIRPORT 
70  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Tenant Reimbursement 
Project: C800154              Build-out of spaces for new and      Project Status:
Budget: $4,709,577             existing tenants. If more than a "basic   Schedule: Within or Ahead
Phase: Construction            finish", condition space is built for the   Budget: On or Under
Start: 8/14/2007                tenant. Tenant is required to reimburse  Status Reset: N/A
Schedule Completion: TBD      the Port for the cost of the work       (Commission Construction Auth.)
beyond the "basic finish. Reimb
allowed under the guidelines in the
"Tenant Reimb. Policy:
Significant Developments                             Budget/Costs Incurred
In 2015, anticipate a reimbursement to TSA for build-out of the last unfinished               4.7
5    4.7
space on the concourse level of the C1 building, likely Q3 or Q4.
4
Schedule
3
Schedules vary to meet the tenant's needs.                            Dollars in Millions 2               1.3
1
Budget                                      0
Authorized Forecasted   Costs
The project forecast is within the approved budget and authorization.                          Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable 
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
None identified at this time
Budget Transfers
Amount       From         To
$0



AIRPORT 

Port of Seattle 2Q 2015 Report  71

SECOND QUARTER REPORT, 2015
T-46 Lease Improvements  Stormwater Improvements 
Project: U00050 (C102554)         Construct stormwater treatment    Project Status:
Budget: $8,000,000             system to comply with Ecology      Schedule: Within or Ahead
Phase: Construction             order.                      Budget: On or Under
Start: 4/12/2013                                          Status Reset: 5/7/2015
Schedule Completion: 2020                                 (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
All contracted work complete. Design team continues commissioning of the
10
three treatment vaults. Vault media replaced due to contamination. Perform          8.00    8.00
8
testing in Quarter 3 to determine treatment effectiveness of system. Outfall
inspection revealed replacement of vault to outfall pipes in three remaining
6                  4.80
basins require replacement or repair due to cracking, breaks, voids and sag        4
conditions found.                                           Dollars in Millions 2
0
Schedule                                        Authorized Forecasted  Costs
Incurred
Construction of the three treatment vaults was on schedule. The fourth
treatment vault will be complete once Washington State Department of
Construction Costs
Transportation (WSDOT) vacates the lease area.
2.5
Budget                                         1.9
2              1.8
Authorized budget of $8,000,000 for Stormwater Treatment System is currently   Dollars in Millions 1.5
within budget. 
1
Change Order                                 0.5     0.3
Current Quarter     Project Total          0
Initial  Change  Spent
Number of COs           0             8                  Orders
Amount of Cos           $0           $259,264
Justification for COs: None this quarter
Risks
Delay of completing the treatment vaults commission due to terminal operation.
Vaults may not provide level of treatment required by Ecology.
Budget Transfers
Amount       From         To
$0

SEAPORT ALLIANCE 

72  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
T-46 Lease Improvements  Container Dock Apron Upgrade
Project: U00175 (C102554)         Upgrade 200 LF at existing T-46   Project Status:
Budget: $10,195,000            dock apron to increase load        Schedule: Within or Ahead
Phase: Design                  capacity to accommodate 100-foot    Budget: On or Under
Start: 4/12/2013                 gauge cranes. Upgrade electrical     Status Reset: 5/7/2015
Schedule Completion: 3/31/2017   power to support new cranes if      (Commission Construction Auth.)
requested by tenant.
Significant Developments                             Budget/Costs Incurred
Sixty percent phase work in progress. Completion scheduled for late August
3
2.50      2.50
2015. Design team is preparing Master Use Permit (MUP) submittal for City
2.5
Shoreline requirements. Draft JARPA and Biological Evaluation documents
Dollars in Millions 2
submitted for Port review.
1.5
1
Schedule
0.5                      0.23
Schedule adjusted to tenant request timeline. Construction scheduled to begin     0
July 2016.                                                  Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
Currently project is within budget.                                 None at this time
Change Order                               Photo
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Permit review timeline uncertain. Meet federal funding procurement
requirements. Contractor's ability to procure long lead items on schedule.
Coordination and work performed by SCL on schedule. Meet tenant requests
due to change in operation.
Budget Transfers
Amount       From         To
$0


SEAPORT ALLIANCE 
Port of Seattle 2Q 2015 Report  73

SECOND QUARTER REPORT, 2015
Street Vacations T-5, T-18 and T-105 
Project: C102858, C102875, E104366  Street vacation related real estate   Project Status:
Budget: $1,500,000             negotiations and agreements  T-5,   Schedule: Delayed
Phase: Permitting               T-18 and T-105 (complete).        Budget: On or Under
Start: 6/1/2010                                            Status Reset: N/A
Schedule Completion: 2016; T-18                           (Commission Construction Auth.)
end of 2015 
Budget/Costs Incurred
Significant Developments
Draft Easement and Utility transfer documents prepared by the City and are     1.55
1.50      1.50
under Port Legal Department review for T-18. Discussion and Title work has     1.5
begun for Terminal 5.                                       1.45
1.4                      1.37
Schedule
1.35
Current schedule has T-18 completed by end of 2015 (City Council action by    Dollars in Millions
1.3
end of September 2015) and T-5 by the end of 2016.                       Authorized Forecasted  Costs
Incurred
Budget
The budget revised for 2015 and beyond.                           Construction Costs
None at this time
Change Order
Photo
Current Quarter     Project Total
Number of COs           0             2
Amount of Cos           $0          $20,390.33
Justification for COs: None this quarter
Risks
Not applicable
Budget Transfers
Amount       From         To
$0



MARITIME 
74  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
T-5 Berth Modernization 
Project: C800132               Improvements to support larger    Project Status:
Budget: $180,000,000 - $250,000,000  vessels at T5, including crane rail    Schedule: Within or Ahead
Phase: Design                  strengthening, berth deepening, and   Budget: On or Under
Start: 6/3/2014                  electrical upgrades.             Status Reset: 6/3/2014
Schedule Completion: 6/30/2018                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Design documents reached 60% completion in May, Hydraulic Project         6
5.00      5.00
Approval received in June, and tenant selection process is underway.           5
Additional design funding was approved in July.                        4               3.53
Schedule                                      Dollars in Millions 3
2
Ninety percent design completion expected in October. Test pile program will     1
begin in December.                                         0
Authorized Forecasted   Costs
Incurred
Budget
Authorized budget is now $10,000,000, which will cover 100% level design,    Construction Costs
test pile program, and continued permit process.                        None at this time
Change Order                               Photo
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Scope of work is subject to change depending on securing tenant and any
impacts of leasing requirements. Design and agency permit reviews are on
critical path. Schedule is partially dependent on Seattle City Light upgrades.
Early dock demolition and pre-purchase of some piles are necessary in order to
deliver project in 2018.
Budget Transfers
Amount       From         To
$0


SEAPORT ALLIANCE 
Port of Seattle 2Q 2015 Report  75

SECOND QUARTER REPORT, 2015
FT C15 HVAC Improvement 
Project: C800137               Replace existing HVAC systems   Project Status:
Budget: $4,887,000             within Building C-15 that are at the   Schedule: Delayed
Phase: Construction             end of their service life.           Budget: On or Under
Start: 5/1/2010                                            Status Reset: 10/8/2013
Scheduled Completion: 6/30/2014                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
HVAC equipment manufacturer has completed most of the retrofit work to
5    4.9      4.9
resolve equipment manufacturing problem. Remaining insulation replacement
work is being scheduled and commissioning of the system continues.          4.8
Schedule
4.5
Contractor continues to be behind schedule on the corrective work and         Dollars in Millions 4.6 4.4
substantial completion date has been pushed back further. Contractor likely      4.2
would be able to reach substantial completion milestone sometime in             Authorized Forecasted  Costs
Incurred
September.
Budget                                    Construction Costs
Project is still within the October 8, 2013 Commission funding authorization.       3.5  3.0
3             2.6
Change Order                                 2.5
2
Current Quarter     Project Total         1.5
Number of COs           0             15             1
Amount of COs          $0          $111,790         Dollars in Millions 0.5     0.1
0
Justification for COs: None this quarter
Initial  Change  Spent
Orders
Risks
Some significant cost items have been raised by the contractor but Port        Photo
disagrees with their merits. These likely would result in claims/dispute
resolution. Liquidated damage is continuing to be assessed which will offset
change order costs in a significant way.
Budget Transfers
Amount       From         To
$0


MARITIME 
76  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
T-91 Lighting Upgrade 
Project: C800160               Lighting upgrade at Terminal 91    Project Status:
Budget: $1,160,000                                         Schedule: Delayed
Phase: Construction                                       Budget: On or Under
Start: 6/23/2014                                          Status Reset: 9/3/2015
Schedule Completion: 11/30/2015                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
On April 14, 2015, Commission approved an additional $125,000. Additional
1.2
fixtures purchased to satisfy the goals of this project. Following the end of            1.16    1.16
Cruise Season the installation will be completed and commissioning following   1.15
immediately afterward.                                      Dollars in Millions 1.1              1.06
Schedule                                      1.05
Expect to finish the project in November of 2015.                        1
Authorized Forecasted   Costs
Incurred
Budget
The budget was increased by $125,000; now totaling $1,160,000 total project   Construction Costs
cost. Costs incurred to date are $1,060,000.                           Not Applicable
Change Order                               Photos
Current Quarter     Project Total
Number of COs           1             2
Amount of Cos          $18,154         ($4,856)
Justification for COs: Add additional fixtures to meet the goals of this project.
Risks
None
Budget Transfers
Amount       From         To
$0



MARITIME 
Port of Seattle 2Q 2015 Report  77

SECOND QUARTER REPORT, 2015
T-102 HMCC Roofs and HVAC Units
Replacement 
Project: C800196               Replace Corporate Center building  Project Status:
Budget: $6,350,000             roofs, final group (3rd phase) of      Schedule: Within or Ahead
Phase: Design                  rooftop HVAC units, and all        Budget: On or Under
Start: 9/1/2014                  rooftop gas piping. Assets are at the   Status Reset: Click here to enter a 
Scheduled Completion: 10/31/2016 end of their service lives.         date.
(Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Preliminary roof analysis and recommendation complete; final roof and HVAC
8
replacement design is in progress per July 14, 2015 Commission design funding             6.4
approval.                                                 6
4
Schedule                                      Dollars in Millions 2
Project currently on schedule for design completion in 2015 and construction in        0.5
0.0
2016.                                                0
Authorized Forecasted   Costs
Incurred
Budget
Project currently within design budget.                              Construction Costs
Change Order                                  1
Current Quarter     Project Total         0.8
Number of COs           0             0            0.6
Amount of COs          $0            $0
0.4
Justification for COs: None at this time                              Dollars in Millions 0.2
0.0    0.0    0.0
Risks                                           0
Initial  Change  Spent
Nothing significant at this time.                                             Orders
Budget Transfers                                 Photo
Amount       From         To
$0



ECON. DEVELOPMENT 
78  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Shilshole Tenant Service Buildings 
Project: C800356               Replacement/rehabilitation of five   Project Status:
Budget: $5,500,000 to $6,500,000    restrooms and laundry facilities at    Schedule: Within or Ahead
Phase: Design                  Shilshole Bay Marina by June 2017   Budget: On or Under
Start: 1/6/2015                  for $5.5M.                   Status Reset: N/A
Schedule Completion: 6/30/2017                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Selection of design consultant completed, contract negotiation underway.
2
Public outreach for tenant feedback and priorities with moorage and business               1.61
tenants continues.                                             1.5
1    0.71
Schedule
0.5
Design completion by February 2016.                            Dollars in Millions               0.06
0
Budget                                       Authorized Forecasted  Costs
Incurred
Project is within the approved budget. 
Construction Costs
Change Order
None at this time
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant known risks at this time
Budget Transfers
Amount       From         To
$0




MARITIME 
Port of Seattle 2Q 2015 Report  79

SECOND QUARTER REPORT, 2015
T91, Bldg. C175 Roof Replacement 
Project: C800430               Replace roof on the C175 Building  Project Status:
Budget: $2,450,000             at Terminal 91                 Schedule: Delayed
Phase: Construction                                       Budget: On or Under
Start: 7/26/2011                                          Status Reset: 1/14/2014
Schedule Completion: 11/14/2014                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Substantial completion issued during the quarter. The project is now in the
3
closeout phase. Final change orders are under negotiation.                      2.45
2.5             2.05
Dollars in Millions                        1.84
2
Schedule
1.5
Substantial completion achieved on April 22, 2015, 159 days past the original     1
contract milestone date. The majority of days are excusable due to weather or    0.5
scope changes, but 50 are not and liquidated damages are being accessed.        0
Authorized Forecasted   Costs
Incurred
Budget
Project is within approved budget and the final costs are anticipated to come in  Construction Costs
approximately $400,000 below budget. 
2   1.7
Change Order                                          1.5
1.5
Current Quarter     Project Total          1
Number of COs           3             11
0.5
Amount of Cos         $-74,778         $-26,750
0
Justification for COs: Varying site conditions, weather delays, reconciliation of   Dollars in Millions    Initial Change0.0  Spent
-0.5
bid quantities, and liquidated damages                                       Orders
Risks
None at this time                                           Photos
Budget Transfers
Amount       From         To
$0



MARITIME 
80  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
T-91 Substation Upgrades 
Project: C800439               Upgrade/replace existing        Project Status:
Budget: $2,058,000             substations/equipment at Substation   Schedule: Within or Ahead
Phase: Design                  Nos. 1, 14 and 15.               Budget: On or Under
Start: 11/4/2013                                          Status Reset: 3/10/2015
Schedule Completion: 4/30/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Opened major works construction contract bids on May 14th. Six bidder
2.5
submitted bids with lowest responsive and responsible bidder VECA Electric         1.995   1.995
2
Co., Inc.'s bid of $1,027,031 within 7% of the Engineer's Estimate. Executed
1.5
construction contract.
1
Schedule                                      Dollars in Millions             0.417
0.5
On Schedule                                          0
Authorized Forecasted   Costs
Incurred
Budget
On budget                                            Construction Costs
Not Applicable
Change Order
Current Quarter     Project Total       Photo
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Equipment procurement duration could be very volatile due to demands.
Unable to verify As-built condition due to locations/accessibility issues -
differing site conditions may result.
Budget Transfers
Amount       From         To
$0



MARITIME 
Port of Seattle 2Q 2015 Report  81

SECOND QUARTER REPORT, 2015
Argo Yard Truck Roadway 
Project: C800546, E104751,       New Port of Seattle owned truck    Project Status:
E104754                   roadway between East Marginal    Schedule: Within or Ahead
Budget: $7,750,000             Way and Colorado Avenue South    Budget: On or Under
Phase: Construction             right-of-way.                 Status Reset: 4/22/2014
Start: 3/11/2012                                          (Commission Construction Auth.)
Schedule Completion: 4/15/2015 
Significant Developments                             Budget/Costs Incurred
Construction for POS improvements completed in May 2015. Union Pacific     10
(UP) railroad crossing improvements (POS sharing costs) to still be completed;        7.75    7.75
8
awaiting finalization of construction agreements and scheduling of UP crew.     Dollars in Millions                6.10
6
UP Element III Argo Yard improvements (POS administering FMSIB funds)
construction start awaiting finalization of FMSIB funding agreements with POS    4
and WSDOT.                                   2
0
Schedule                                        Authorized Forecasted  Costs
Incurred
UP railroad crossing improvements anticipated to be completed Q4 2015/Q1
2016. UP Element III Argo Yard improvements anticipated to be completed in  Construction Costs
early 2017.
6
5.05
Budget                                      5        4.50
Project is currently within the budget authorized by Commission on April 22,       4
2014.                                                   3
2
Change Order                                Dollars in Millions 1     0.41
0
Current Quarter     Project Total
Initial  Change  Spent
Number of COs          14            34                  Orders
Amount of COs         $156,932         $408,681
Justification for COs: Construction requirements not addressed by design
documents.
Risks
No significant known risks at this time.
Budget Transfers
Amount       From         To
$0

MARITIME 
82  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
T-46 Dock Rehabilitation 
Project: C800603               Terminal 46 Dock Rehabilitation   Project Status:
Budget: $32,659,000            Project.                      Schedule: Delayed
Phase: Design                                             Budget: On or Under
Start: 11/6/2012                                          Status Reset: N/A
Schedule Completion: Q4 2018                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The project is at 90% design and is on hold. This project has been postponed
2    1.85
and scheduled to resume design in Q1 2016. Tiger grant agreement executed as
of July 21, 2015.                                              1.5
1.02
1
Schedule
0.45
0.5
Design work is scheduled to resume in February 2016, construction is         Dollars in Millions
anticipated to start in 2016/2017.                                    0
Authorized Forecasted   Costs
Incurred
Budget
The project is on budget.                                        Construction Costs
None at this time
Change Order
Current Quarter     Project Total       Photo
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Container operation variation which can cause additional construction phasing.
Budget Transfers
Amount       From         To
$0



SEAPORT ALLIANCE 
Port of Seattle 2Q 2015 Report  83

SECOND QUARTER REPORT, 2015
HIM E Dock Improvements 
Project: C800678               Dock currently under consideration  Project Status:
Budget: $500,000 minimum        for improvements ranging from     Schedule: Within or Ahead
Phase: Planning                partial elements (walers, rub strips,   Budget: On or Under
Start: 9/1/2014                  cleats, etc.) replacement to         Status Reset: Click here to enter a 
Scheduled Completion: TBD     complete floats and pile         date.
replacements and electrical system   (Commission Construction Auth.)
upgrade.
Significant Developments                             Budget/Costs Incurred
Dock condition assessment and improvement options study completed.
0.5             0.47
Finance currently performing TCO analysis. Maritime to decide on final
0.4
project scope and schedule.
Schedule                                      Dollars in Millions 0.30.2  0.07
Final schedule to be determined.                                  0.1
0.01
0
Budget                                       Authorized Forecasted  Costs
Incurred
Budget dependent on final scope decision. 
Construction Costs
Change Order
Current Quarter     Project Total          1
Number of COs           0             0            0.8
Amount of COs          $0            $0            0.6
Justification for COs: N/A                                       Dollars in Millions 0.4
0.2
Risks                                             0.0  0.0  0.0
0
Nothing significant at this time.                                         Initial Change Spent
Orders
Budget Transfers
Amount       From         To
$0



ECON. DEVELOPMENT 
84  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
P69 Carpet Replacement 
Project: C800691               Replace approximately 10,200     Project Status:
Budget: $1,200,000             sq.ydds. of carpeting on the second   Schedule: Delayed
Phase: Construction             and third floors of the Port's       Budget: On or Under
Start: 7/7/2014                  Corporate Headquarters.          Status Reset: 9/3/2015
Schedule Completion: 9/30/2014                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The Contractor has successfully completed 100% of the contract scope. The      1.5
hold-up on closing this project is ongoing labor determinations. There are            1.20    1.20
concerns regarding appropriate labor rates and application of small business       1               0.77
involvement. (No change as of September 3, 2015)
Schedule                                      Dollars in Millions 0.5
Port legal counsel and CPO are working to resolve the mentioned issues.         0
Authorized Forecasted   Costs
Expectations are that resolution will linger into the first quarter of 2016 before
Incurred
documentation can be completed with Labor & Industries.
Construction Costs
Budget
Not Applicable
We do not anticipate any additional costs to be incurred other than internal
processing soft costs. 
Change Order
Current Quarter     Project Total
Number of COs           0             3
Amount of Cos           $0           $4,700
Justification for COs: None this quarter
Risks
None at this time
Budget Transfers
Amount       From         To
$0


MARITIME 
Port of Seattle 2Q 2015 Report  85

SECOND QUARTER REPORT, 2015
P69 Beam Rehabilitation Project 
Project: C800698               Rehabilitate five rows of concrete   Project Status:
Budget: $2,300,000 to $3,300,000   beams supporting top of clerestory   Schedule: Within or Ahead
Phase: Design                  windows at P69..               Budget: On or Under
Start: 7/1/2014                                            Status Reset: 10/27/2015
Schedule Completion: 9/1/2016                              (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
One hundred percent design phase in progress.
4
3.30
Schedule                                       3
RTB documents scheduled for completion by October 1st. Commission        Dollars in Millions 2
authorization scheduled for October 27, 2015. Ad date scheduled for November
1
3, 2015.                                                       0.33
0.13
0
Budget                                       Authorized Forecasted  Costs
Incurred
Design phase budget authorization is $330,000. Current total project cost
estimate is $2,771,000.                                         Construction Costs
Change Order                               None at this time
Current Quarter     Project Total       Photos
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
x Contractor access during construction will restrict space and create visual
impacts on third floor and second floor atrium for estimated 6-7 months.
x Need to mitigate environmental impacts due to presence of lead paint /
concrete silica dust / asbestos insulation behind interior flashing.
x Need to hire security guard for variable shifts based on Contractor after
office hours work schedule.
Budget Transfers
Amount       From         To
$0


MARITIME 
86  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
East Marginal Way Grade Separation 
Project: E102007               FAST Corridor funded project;    Project Status:
Budget: $56,256,171            FHWA, State, City with Port       Schedule: Within or Ahead
Phase: Closeout                commitment of $22,480,807. Scope   Budget: On or Under
Start: 5/1/2006                  is to construct grade separation in    Status Reset: 4/22/2014
Schedule Completion: Q4 2015    vicinity of T5 and T18 to minimize   (Commission Construction Auth.)
truck traffic/rail conflicts.
Significant Developments                             Budget/Costs Incurred
Coordination underway with City of Seattle for properties and easements       56.5   56.25   56.25
conveyance to City. Proposed Lot Boundary Adjustment for POS properties
under review by Seattle DPD. POS preparing proposed easement documents     56
for review by SDOT as well as Seattle City Light and Seattle Public Utilities.    55.5  Dollars in Millions                 55.30
Schedule                                      55
Anticipate final acceptance by Seattle Department of Transportation (SDOT) in   54.5
Authorized Forecasted   Costs
early 2016.
Incurred
Budget
Construction Costs
Project is on track within the April 22, 2014 Commission authorization. 
25   22.0        22.0
Change Order                                 20
Current Quarter     Project Total         15
Number of COs           0             97            10
Amount of COs          $0          $1,922,967         Dollars in Millions  5     2.0
Justification for COs: None this quarter.
0
Initial  Change  Spent
Risks                                                Orders
No risks at this time.
Budget Transfers
Amount       From         To
$0



MARITIME 
Port of Seattle 2Q 2015 Report  87

SECOND QUARTER REPORT, 2015
Viaduct Construction Coordination 
Project: E104324, E104535-38       Participate in the design &       Project Status:
Budget: $2,900,000             construction of the bored tunnel, N.   Schedule: Within or Ahead
Phase: Implementation          & S. portals, Holgate to King St,    Budget: On or Under
Start: 1/1/2009                  Central Waterfront surface streets,   Status Reset: N/A
Schedule Completion: 12/31/2018  & related projects to ensure        (Commission Construction Auth.)
adequate connection to port
facilities.
Significant Developments                             Budget/Costs Incurred
First transfer of port contribution occurred in May. Contractor continued repairs
4
to the SR 99 tunnel boring machine. Seawall and Mercer corridor construction
2.90
continued.                                                3
2           1.75
Schedule                                      Dollars in Millions             1.08
1
Tunnel boring machine expected to resume operation in late November.
Mercer West construction will continue through 2015. Seawall Phase I         0
construction to be completed in mid-2016. Central Waterfront start/completion      Authorized Forecasted  Costs
Incurred
depends on completion of SR99 tunnel and Viaduct demolition.
Budget                                    Construction Costs
Not Applicable
Port staff costs were within anticipated 2015 spending. 
Photos
Change Order
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Project delays due to repairs to the tunneling machine.
Budget Transfers
Amount       From         To
$0



MARITIME 
88  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
FT Net Shed Code Compliance 
Project: E104838               FT Net Sheds 3-11: Improvements  Project Status:
Budget: $2,950,000             required per City of Seattle building  Schedule: Delayed
Phase: Construction             & fire codes.                  Budget: On or Under
Start: 5/1/2012                                            Status Reset: 6/25/2013
Schedule Completion: 6/30/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Port Construction Services completed code compliance improvements to
4
Netsheds 3 and 4 (Netsheds 5, 6, 9, 10 and 11 completed previous quarter).           2.95    2.95
Netsheds7 retrofit work started.                                     3
1.93
2
Schedule
1
Netshed retrofit work has taken longer in some netlockers and is impacting      Dollars in Millions
overall construction completion schedule. Currently projecting completing all     0
improvement by end of November 2015.                            Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
Project budget is on track.                                        Port Self Perform Construction
Change Order                               Photo
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
It is difficult to forecast the amount of stored materials that needs to be moved
out and moved back into the netlockers since tenant storage habits vary
significantly. In addition, the amount of work required in each unit is difficult
to assess until some stored materials are cleared and locker conditions are more
visible. These would impact the overall project schedule and budget.
However, with construction more than three quarters complete, budget risks
have lessened significantly since the project budget is trending well.
Budget Transfers
Amount       From         To
$0

MARITIME 
Port of Seattle 2Q 2015 Report  89

SECOND QUARTER REPORT, 2015
T-5 and T-91 Maintenance Dredging 
Project: E104840, E105038, U00067,  Maintenance Dredge at T-5 all     Project Status:
E105050,                    three berths and at T-91 East cruise  Schedule: Delayed
Budget: $4,800,000             berth.                       Budget: On or Under
Phase: Design                                             Status Reset: N/A
Start: 8/14/2012                                          (Commission Construction Auth.)
Schedule Completion: 2/28/2016 
Significant Developments                             Budget/Costs Incurred
T-5 Maintenance Dredging was completed earlier in 2014.                 6
T-91 East Cruise Berth: The Port continues negotiations with the permitting          4.80    4.80
5
agencies for the preferred under-water regrading alternative to minimize health,    4               3.36
safety, and environmental impact, and to reduce costs. Construction planned     Dollars in Millions 3
for the 2015-16 in-water construction window.                         2
1
Schedule                                       0
Authorized Forecasted   Costs
As previously reported, T-91 East Cruise Berth is delayed due to permitting
Incurred
complications.
Construction Costs
Budget
None at this time
Project is on budget 
Photo
Change Order
Current Quarter     Project Total
Number of COs           0             2
Amount of Cos           $0          $20,390.33
Justification for COs: None this quarter
Risks
Environmental permitting may cause further delays, scope change, and cost
impact to the T-91 East Cruise Berth Dredging project.
Budget Transfers
Amount       From         To
$0



MARITIME 
90  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
T-18 Maintenance Dredging 
Project: U00033 and U00231       Design, permitting, and         Project Status:
Budget: $3,216,000             construction of T-18 Maintenance    Schedule: Within or Ahead
Phase: Design                  Dreddging; Advertise and execute    Budget: On or Under
Start: 2/10/2015                 an on-call major construction       Status Reset: N/A
Schedule Completion: 2/28/2016   dredging contract               (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Commission approved construction phase of the project on July 14, 2015.
2.5
Design and permitting work is underway. On-call major construction dredging              2.09
2
contract has received bids and award is in progress.
Schedule
1.00
1
Project is on schedule.                                          Dollars in Millions 1.5 0.5               0.26
0
Budget                                       Authorized Forecasted  Costs
Incurred
Project is on budget. 
Change Order                               Construction Costs
None at this time
Current Quarter     Project Total
Number of COs           0             0          Photo
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Project is within an EPA Superfund site requiring additional reviews and
coordination with permitting agencies.
Budget Transfers
Amount       From         To
$0




MARITIME 
Port of Seattle 2Q 2015 Report  91

SECOND QUARTER REPORT, 2015
IHI Crane Removal 
Project: U00099                Remove three IHI Cranes from     Project Status:
Budget: $1,835,000             Terminal 18                   Schedule: Within or Ahead
Phase: Construction                                       Budget: On or Under
Start: 9/11/2012                                          Status Reset: 6/23/2015
Schedule Completion: 1/31/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The agreement between PMA and ILWU was ratified in 2015 and the project
2    1.84     1.84
restarted. On June 23 Commission authorized additional funds and contract
time. A change order has been executed to the contractor for the delay costs      1.5
and the project is being rescheduled
1
Schedule                                      Dollars in Millions 0.5            0.21
The project has been re-activated and fieldwork scheduled to commence in       0
October. The project is scheduled to be complete by the end of January 2016       Authorized Forecasted  Costs
Incurred
Budget
Construction Costs
The project is within budget.                                     None at this time
Change Order                               Photo
Current Quarter     Project Total
Number of COs           1             1
Amount of Cos         $173,400         $173,400
Justification for COs: A work suspension delay is the justification for the
change order justification
Risks
Risks for the project continue to be varying conditions and potential work
stoppages

Budget Transfers
Amount       From         To
$0


MARITIME 
92  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
ID Badge System Replacement 
Project: C800162               Procurement and replacement of    Project Status:
Budget: $2,500,000             the Portwide ID Badge system      Schedule: Delayed
Phase: Implementation          including software, hardware, and    Budget: On or Under
Start: 5/1/2012                  equipment.                   Status Reset: N/A
Schedule Completion: 12/30/2015                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
The first phase of the new Badge System deployed on November 5, 2014. A     2.6   2.50    2.50
2nd deployment to add mobile functionality and authorized signer efficiencies is   2.5
in the implementation stage.
Schedule
2.14
Resources focused on new TSA Security requirements, delaying 2nd phase      Dollars in Millions 2.42.32.2 2.1
2
implementation three months.                                   1.9
Authorized Forecasted   Costs
Incurred
Budget
On budget                                            Construction Costs
Not Applicable
Change Order
Current Quarter     Project Total
Number of COs           0             1
Amount of Cos           $0           $108,497
Justification for COs: None this quarter
Risks
Resource availability may continue to delay the second phase mobile
deliverables.
Budget Transfers
Amount       From         To
$0



CORPORATE 
Port of Seattle 2Q 2015 Report  93

SECOND QUARTER REPORT, 2015
Terminal 91 Visitor Management 
Project: C800436               Upgrade of the Radio System Core  Project Status:
Budget: $520,000               Hardware and Software and        Schedule: Within or Ahead
Phase: Implementation          Dispatch Consoles.             Budget: On or Under
Start: 7/1/2013                                            Status Reset: 11/4/2014
Scheduled Completion: 5/1/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Development and implementation is in progress for an August 2015          0.6   0.52    0.52
implementation.                                          0.5
Schedule                                                   0.24
On schedule                                             Dollars in Millions 0.40.3 0.2
0.1
Budget                                      0
Authorized Forecasted   Costs
On Budget                                                         Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
Expected grant extensions not approved. Substantially deliver the project by
August 2015. Mitigation plans in progress.
Budget Transfers
Amount       From         To
$0




CORPORATE 
94  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Contractor Data System Upgrade 
Project: C800519               Upgrade of the Contractor Data    Project Status:
Budget: $675,000               System used by Engineering and     Schedule: Within or Ahead
Phase: Implementation          other groups to track contracts for    Budget: On or Under
Start: 7/1/2013                  construction projects.            Status Reset: N/A
Schedule Completion: 2/28/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Development is in progress.                                     2
1.50      1.50
Schedule                                      1.5
On schedule                                          Dollars in Millions 1
0.5
Budget                                                 0.23
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount       From         To
$0





CORPORATE 
Port of Seattle 2Q 2015 Report  95

SECOND QUARTER REPORT, 2015
Computer Dispatch System Upgrade 
Project: C800520               Upgrade Computer Dispatch      Project Status:
Budget: $790,000               System used by 911 and           Schedule: Within or Ahead
Phase: Implementation          Emergency Responders.          Budget: On or Under
Start: 4/1/2014                                            Status Reset: N/A
Schedule Completion: 8/31/2015                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Upgrade is in progress.                                         1
0.79      0.79
0.8
Schedule
0.6
On schedule
0.4                      0.26
Budget                                     Dollars in Millions 0.2
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount       From         To
$0




CORPORATE 
96  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Construction Document Management 
Project: C800521               Replacement of the Construction   Project Status:
Budget: $900,000               Document Management System;     Schedule: Delayed
Phase: Implementation          used by Construction Management,   Budget: On or Under
Start: 9/10/2013                 to accept, review, and distribute     Status Reset: N/A
Schedule Completion: 9/30/2015    critical documentation.           (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Implementation is in progress.                                    1   0.90    0.90
0.8
Schedule
Dollars in Millions 0.6                                                                                     Prior Report: Procurement took seven months longer than planned to complete,
0.4                      0.33
resulting in a 6-month delay to the project.
0.2
Budget                                      0
Authorized Forecasted   Costs
On budget                                                           Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable
Number of COs           2             2
Amount of Cos         $121,000         $121,000
Justification for COs: 1) Original software recommendation in RFP for license
type did not meet all requirements. CO initiated to purchase full licenses. Credit
given for original purchase. 2) Additional requirements were identified during
requirements workshops
Risks
No significant risks at this time.
Budget Transfers
Amount       From         To
$0



CORPORATE 
Port of Seattle 2Q 2015 Report  97

SECOND QUARTER REPORT, 2015
Noise Monitoring System Replacement 
Project: C800693               Replacement of the Airport Noise   Project Status:
Budget: $1,900,000             Monitoring System              Schedule: Within or Ahead
Phase: Closeout                                           Budget: On or Under
Start: 4/1/2015                                            Status Reset: N/A
Scheduled Completion: 8/31/2015                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Implementation completed July 2015.                                 1.90
2
1.40
Schedule                                      1.5
On schedule 
0.96
1
Budget                                     Dollars in Millions 0.5
Expect a $500,000 underrun                                     0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: None this quarter
Risks
No significant risks at this time
Budget Transfers
Amount       From         To
$0





CORPORATE 
98  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Umbrella Authorizations 
Project: C800694               Expand planning, tracking, and    Project Status:
Budget: $650,000               commitment control capabilities in   Schedule: Delayed
Phase: Implementation          PeopleSoft Financials System that    Budget: On or Under
Start: 6/3/2014                  will cover an entire authorization    Status Reset: N/A
Scheduled Completion: 7/31/2016  with both capital and expense       (Commission Construction Auth.)
project components.
Significant Developments                             Budget/Costs Incurred
Project on-hold due to resource conflicts focused on changes in the Financial     0.8
System to support the Seaport Alliance. The expected restart date is late Spring        0.65    0.65
2016.                                               0.6
0.45
0.4
Schedule                                      Dollars in Millions 0.2                                             Schedule Delay due to resource constraints and competing priorities.
0
Budget                                       Authorized Forecasted  Costs
Incurred
On budget 
Construction Costs
Change Order                               Not Applicable
Current Quarter     Project Total
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
New resources will need to be procured and current designs communicated. There is a
risk that this ramp up will require additional funding. Risk mitigated by detailed
planning and a vendor request to use the same resources.
Budget Transfers
Amount       From         To
$0



CORPORATE 
Port of Seattle 2Q 2015 Report  99

SECOND QUARTER REPORT, 2015
Parking System Replacement 
Project: C800728               Replacement of the Airport Main     Project Status:
Budget: $5,500,000             Garage Parking System            Schedule: Within or Ahead
Phase: Planning                                          Budget: On or Under
Start: 1/6/2015                                            Status Reset: N/A
Scheduled Completion: 6/30/2017                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Procurement is in process. Awaiting vendor responses expected at the end of      6   5.50    5.50
August.                                              5
Dollars in Millions 4
Schedule
3
On schedule                                              2
1
0.03
Budget                                      0
Authorized Forecasted   Costs
On budget                                                           Incurred
Change Order                               Construction Costs
Current Quarter     Project Total       Not Applicable
Number of COs           0             0
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
We expect the procurement process changes to engage other vendors but the
risk remains that we may not receive the number of responses desired. In
addition, the re-advertising could delay the project up to three months. At this
time, we expect this delay to be accommodated in the contingency.
Budget Transfers
Amount       From         To
$0



CORPORATE 
100  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Human Capital Management System Upgrade 
Project: C800745               Upgrade of the Human Capital     Project Status:
Budget: $1,500,000             Management system.             Schedule: Within or Ahead
Phase: Implementation                                   Budget: On or Under
Start: 2/24/2015                                          Status Reset: N/A
Schedule Completion: 12/31/2015                            (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Implementation is in progress.                                    2
1.50      1.50
Schedule                                      1.5
On schedule                                              1
Budget                                     Dollars in Millions            0.40
0.5
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount       From         To
$0





CORPORATE 
Port of Seattle 2Q 2015 Report  101

SECOND QUARTER REPORT, 2015
Maximo Upgrade 
Project: C800746               Upgrade Maximo System used by   Project Status:
Budget: $1,000,000             Aviation and Maritime           Schedule: Within or Ahead
Phase: Implementation          Maintenance and Information &     Budget: On or Under
Start: 5/10/2015                 Communication Technology       Status Reset: N/A
Schedule Completion: 8/31/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Procurement of implementation vendor is in progress.                    1.2
1.00      1.00
1
Schedule
Dollars in Millions 0.8                                                                                     On schedule                                                                       0.6
0.4
Budget                                     0.2
0.00
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount       From         To
$0




CORPORATE 
102  Port of Seattle 2Q 2015 Report

SECOND QUARTER REPORT, 2015
Employee Performance Management System 
Project: C800763               Implement the PeopleSoft        Project Status:
Budget: $400,000               e-Performance Management system   Schedule: Within or Ahead
Phase: Implementation          to support the Port Performance     Budget: On or Under
Start: 5/17/2015                 Management Program.           Status Reset: N/A
Schedule Completion: 5/31/2016                             (Commission Construction Auth.)
Significant Developments                             Budget/Costs Incurred
Procurement is complete. Implementation planning is in process.             0.5
0.40      0.40
0.4
Schedule
0.3
On schedule                                          Dollars in Millions 0.2             0.10
Budget                                     0.1
On budget                                              0
Authorized Forecasted   Costs
Incurred
Change Order
Current Quarter     Project Total       Construction Costs
Number of COs           0             0          Not Applicable
Amount of Cos           $0             $0
Justification for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount       From         To
$0




CORPORATE 
Port of Seattle 2Q 2015 Report  103

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.