7a

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA               Item No.      7a 
STAFF BRIEFING 
Date of Meeting    April 28, 2015 
DATE:    April 21, 2015 
TO:     Ted Fick, Chief Executive Officer 
FROM:    Elizabeth Leavitt, Director, Aviation Planning and Environmental 
SUBJECT:  Sustainable Airport Master Plan (SAMP) Planning Update 
SYNOPSIS 
This briefing provides an update on SAMP planning. The Sustainable Airport Master Plan
(SAMP) will provide a facilities plan to guide cohesive development both in the near- and
long-term. 
With the draft airport activity forecast complete, the SAMP team developed and assessed
several terminal expansion concepts to meet long-term gate requirements. A few of the better
preliminary terminal concepts were presented to the Commission in January of 2015. This
briefing includes a recommended gate expansion concept and a preliminary evaluation of 
airfield capacity.  The SAMP team is currently in the initial stages of airfield simulation
modeling and is beginning to develop a plan for phased gate expansion. Over the next six to
seven months, the SAMP team will: 
1)  Conduct detailed simulation modeling to assess the capacity of the existing airfield
system and potential future capacity with identified capital improvements, 
2)  Refine the recommended terminal expansion concept, 
3)  Determine landside and airport/airline support facility requirements to support the
refined terminal expansion concept and 
4)  Develop a phased plan for implementation of the entire SAMP capital program.
With the recent surge in flight activity, all existing gates are currently utilized at peak times of
the day. The SAMP forecasts solid growth and Port staff anticipates the need to push some
flights to remote hardstands next year. The demand for hardstand operations will increase
significantly in the near-term as gates are taken out of service due to construction associated
with the International Arrivals Facility.  While the NorthSTAR program will expand gate
capacity at the North Satellite in 2020, accommodating increasing aircraft operations prior to
the opening of additional gates, beyond the NorthSTAR program, will be a considerable
challenge. 
Preliminary airfield capacity analysis indicates that throughput of the three runway system is
currently reaching capacity in peak periods and average annual delay per aircraft operation may
reach a maximum acceptable delay range of 15 to 20 minutes within 10 to 15 years without
improvements. Twenty minutes of average annual delay is the highest ever experienced at any
airport in the United States.  The SAMP planning team is beginning detailed simulation
analysis to confirm the early findings and assess the benefit of potential airfield taxiway
improvements to increase capacity. 
Template revised May 30, 2013.

COMMISSION AGENDA 
Ted Fick, Chief Executive Officer 
April 21, 2015 
Page 2 of 2 

BACKGROUND 
In September 2012, the Port Commission approved scope and budget of $6,000,000 for the
creation of a Sustainable Airport Master Plan (SAMP). Since October of 2014, staff has
briefed the Commission three times on SAMP planning progress, including: forecast results
and challenges associated with planning to accommodate forecast activity; and preliminary
options for terminal, landside and cargo development.
The master plan process provides an opportunity to take a comprehensive assessment of
facilities capacity and forecasted demand over 5-, 10-, and 20-year timeframes. Airport master
plans are typically prepared approximately every 10 years. The last formal master plan for Sea-
Tac was developed in the mid-1990s and was focused primarily on the third runway. 
The primary objective of an airport master plan is to provide a roadmap for the phased
redevelopment/expansion of facilities; maintaining a balance of capacity in all key functional
areas. Overall airport system capacity is limited by functional areas with the least capacity. 
Terminal and landside facilities are generally balanced to the fixed capacity of the airfield.
Through alternatives development and evaluation, the SAMP will culminate in a capital
improvement program and plan of finance that will deliver cost effective projects to remove
capacity pinch points, increase efficiency and provide a high level of service to airport
customers. 
ATTACHMENTS TO THIS BRIEFING 
PowerPoint presentation 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS 
March 24, 2015 - Commission Briefing: "Briefing on Sea-Tac Cargo as part of the
Sustainable Airport Master Plan" 
January 27, 2015 - Commission Briefing: "Sustainable Airport Master Plan (SAMP)
Planning Update" 
October 7, 2014 - Commission Briefing: "Sustainable Airport Master Plan (SAMP)
Forecast and Facilities Challenges" 
February 28, 2014 - Commission authorization to amend the existing Sustainable
Airport Master Plan (SAMP) service agreement with Leigh Fisher Associates for IAF-
related planning tasks for an increase of $3,650,000 and a new total contract amount
of $9,650,000 
September 5, 2012 -  Commission authorization for SAMP development and to
advertise and execute a contract for consulting services for the SAMP, with a total
estimated value of $6 million 
August 14, 2012 - Commission deferred consideration of a request to approve funding
for the Sustainable Airport Master Plan (SAMP) 
June 27, 2012 - Commission Briefing: "Terminal Development Challenges"

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.