6a EXHIBIT

GCB 1140
SR 99
ALASKAN WAY VIADUCT REPLACEMENT PROGRAM
Funding Agreement

THIS AGREEMENT ("Agreement") for the Alaskan Way Viaduct Replacement
Program ("PROGRAM") is made and entered into between the State of Washington,
hereinafter the "STATE," and the Port of Seattle hereinafter the "PORT," collectively the
"Parties" and individually the "Party."

WHEREAS, in the 19503, the City of Seattle ("City") and the Washington State
Department of Transportation jointly designed and built the Alaskan Way Viaduct to
accommodate passenger and freight mobility into the foreseeable iture; and

WHEREAS, the central waterfront section of the Alaskan Way Viaduct passes through
and is adjacent to downtown Seattle's urban core and the Seattle waterfront; and

WHEREAS, the Duwamish and Ballard-Interbay industrial areas in Seattle are served
by the SR 99 corridor and constitute a signicant portion of Seattle's maritime and
industrial sector jobs and annual citywide revenue; and

WHEREAS, in 2001 the Nisqually earthquake damaged the Alaskan Way Viaduct; and

WHEREAS, the Alaskan Way Viaduct is at risk of sudden and catastrophic failure in an
earthquake and is nearing the end of its useJl life; and

WHEREAS, a failure to maintain the Alaskan Way Viaduct capacity would result in
unacceptable congestion for freight and other trafc within and between Seattle's harbor
and industrial areas; and

WHEREAS, in March 2007, the Washington State Governor, the King County
Executive, and the Mayor of Seattle pledged to advance a series of key SR 99 projects
(Moving Forward Projects) that will facilitate the removal and/or repair of key portions
of SR 99, including the Yesler Way Vicinity Stabilization Project, the Electrical Line
Relocation project, Battery Street Tunnel Fire and Life Safety Upgrades, SR 99 Lenora to
Battery Street Tunnel Improvements, the SR 99 South Holgate Street to South King
Street Viaduct Replacement Project, Transit Enhancements and Other Improvements; and

WHEREAS, in January 2009, the Governor of Washington State, the Mayor of Seattle
and the King County Executive jointly recommended replacing the Alaskan Way Viaduct
with a bored tunnel beneath downtown Seattle in conjunction with improvements in
surface streets and transit service, and Port of Seattle Chief Executive Ofcer, Tay
Yoshitani, endorsed the deep-bore tunnel concept; and

GCB 1140
Page 1 of 10

WHEREAS, the PROGRAM includes system-wide projects led by the Washington State
Department of Transportation (such as H01gate to King viaduct replacement, Atlantic
Street overcrossing, SR519 Phase 2, New Alaskan Way, Connection to Elliott
Avenue/Western Avenue, SR 99 Bored Tunnel, new connections at the north and south
portals), King County (such as South End Transit, North End Transit and other transit
investments), the City (such as Spokane Street Viaduct, Mercer Corridor, Central seawall
replacement and First Avenue Street car study) and the PORT (East Marginal Way Grade
Separation), anticipated to total $4.2 billion; and

WHEREAS, the Washington State Legislature passed ESSB 5768 and the Governor
signed the bill into law designating and mding the SR 99 Bored Tunnel Project as the
replacement for the Viaduct; and

WHEREAS, the STATE executed a design-build contract with Seattle Tunnel Partners in
January 201] for the design and construction of the SR 99 Bored Tunnel Project as a
replacement for the Alaskan Way Viaduct as part of the PROGRAM; and

WHEREAS, the STATE issued a Supplemental Draft Environmental Impact Statement
meeting the requirements of the National Environmental Policy Act and State
Environmental Policy Act in 2010, issued a Final Supplemental Environmental Impact
Statement and Section 4(f) Evaluation in July 2011 and issued a Record of Decision in
August 201] for the SR 99 Bored Tunnel Project; and

WHEREAS, as outlined in the Parties' prior Memorandum of Agreement No. GCA 6444;
the STATE and the PORT are committed to a replacement for the Viaduct that will
improve transportation access to and along the Seattle waterfront, including access for
over eight million annual ferry riders; ensure connectivity and capacity between the
Ballard-Interbay and Duwamish industrial areas and Seattle-Tacoma International
Airport, including a corridor for oversized vehicles; provide access to port cargo, shing
and cruise facilities; minimize construction disruption; and increase opportunities for the
public and freight to access the shoreline and waterfront; and

WHEREAS, the PORT's international trade, aviation, economic development, tourism
and passenger terminal activities are vital to the economic growth of the region and the
state, supporting nearly 194,000 jobs in the region, and the STATE and the PORT
support infrastructure improvements necessary to achieve growth in trade and jobs and
increase the region's competitiveness in global markets; and

WHEREAS, the Viaduct corridor is crucial to the region's freight mobility because it
provides for 1.5 million freight trips annually by grade-separation of through traffic, rail
lines and industrial corridors near the Port's marine terminals, which support the
movement of $30 billion in international and domestic cargo through the Port each year;
and


GCB 1140
Page 2 of 10

WHEREAS, the STATE has designed and is constructing improvements, also known as
AWV S Holgate to S King St Stage 3  Atlantic St Bypass Project, to the surface street
system in the vicinity of the corridor segment from S. Holgate Street to S. King Street
that are designed to increase access to Terminal 46 and other port waterfront facilities.
This project provides a new overcrossing at South Atlantic Street which will signicantly
improve freight hauling efciency between the Port and Interstate 5 and Interstate 90,
allowing trucks to bypass the frequent and lengthy railroad track blockages across South
Atlantic Street; and

WHEREAS, the STATE's contractor is designing and will construct the SR 99 Tunnel
Alternative, Tunnel Design Build (also known as, the SR 99 Bored Tunnel Project), and
the PORT has reviewed its design scope and determined that, when completed, it will
offer a direct benet to the PORT by maintaining throughput capacity in the SR 99
corridor; keeping additional trafc off 1-5; and minimizing construction disruption to
regional trafc, industrial and maritime businesses, and PORT facilities; and
WHEREAS, the STATE and the City are designing and will construct other projects
included in the PROGRAM that will maintain and improve trafc ow along the Seattle
waterfront and between the Seattle waterfront and STATE highways; and,

WHEREAS the STATE has developed a plan for delivering the PROGRAM that
includes: (i) the SR 99/Tunnel Alternative, South Access Connection Project that will
facilitate freight movement to and from PORT container terminals along East Frontage
Road, South Atlantic Street, South Royal Brougham Way, Alaskan Way South, East
Marginal Way South, and South Dearbom Street; and (ii) the SR 99/1'unnel Alternative,
North Access Connection Project that will ensure access to PORT cargo, shing and
cruise facilities via the tunnel or north end arterials, including Sixth Avenue North, North
Republican Street, Dexter Avenue North, Aurora Avenue, and two-way North Mercer
Street; and,

WHEREAS, the STATE has proposed that the PORT assist with the funding of the SR 99
Tunnel Alternative, Tunnel Design Build; the SR 99/Tunnel Alternative, South Access
Connection Project; and the SR 99/Tunnel Alternative, North Access Connection Project
hereinafter identied individually as the "PROJECT" and collectively as the
"PROJECTS" and the PORT deems the PROJECTS to provide a direct benet to the
PORT; and

WHEREAS, the STATE will construct the PROJECTS using the design-build and
design-bid-build methods of project delivery; and

WHEREAS, the Parties executed Memorandum of Agreement No. GCA 6444, Alaskan
Way Viaduct and Seawall Replacement Program Bored Tunnel Alternative on April 12,
2010 in which the PORT agreed, to the extent feasible and authorized by the Port
Commission, to fund or procure funding within the life of the PROGRAM not to exceed
Three Hundred Million Dollars ($300,000,000) toward the STATE'S PROGRAM elements
with the majority of the PORT's contribution occurring between 2016 and 2018; and

GCB 1140
Page 3 of 10

WHEREAS, the PORT allocated Twenty-Five Million Dollars ($25,000,000) of up to
Three Hundred Million Dollars ($300,000,000) for funding of transportation projects
serving the SR 99 system; and

WHEREAS, the Parties agree that the PORT has contributed Nineteen Million Dollars
($19,000,000) of the Twenty-Five Million Dollars ($25,000,000) towards funding of the
East Marginal Way Overpass, Spokane Street widening, Duwamish Intelligent
Transportation System and the SR 519 South Seattle Intermodal Access Project Phase 2
projects that complement the PROGRAM and provide capacity for future growth and
improved safety; and

WHEREAS, the STATE has requested that the PORT's contribution toward funding of
the PROJECTS begin on May I, 2015; and

WHEREAS, the PORT would incur additional costs associated with issuing bonds prior
to 2016; and

WHEREAS, the PORT has incurred additional costs associated with stafng
requirements for assisting the STATE in developing the design, coordinating construction
and other activities required to successfully complete the PROGRAM, including the
PROJECTS; and

WHEREAS, the Parties wish to provide the terms and conditions of the PORT's future
contribution towards funding the PROJECTS;

NOW, THEREFORE, by virtue ofRCW 53.08.330, RCW 53.08.340 and RCW
47.28.140 and in consideration of the terms, conditions, covenants and performances
contained herein, or attached and incorporated and made a part hereof, the Parties agree
as follows:

1.0   STATE RESPONSIBILITIES

1.1    The STATE will ensure that the PROGRAM will be designed and constructed to
facilitate efcient movement of freight and other trafc on the west corridors of the
Seattle transportation system between the Duwamish and Ballard-Interbay neighborhoods,
including maintaining access to shing, cruise and other PORT facilities. The STATE
further agrees that, at a minimum, the reconstruction of the surface streets on the central
waterfront segment of the PROGRAM will include two lanes in each direction with left
turn lanes at intersections between Pine Street and the Colman Dock. The section south of
Colman Dock will have at a minimum, two continuous general purpose lanes in each
direction, at all times, and a continuous northbound ferry queuing lane that expands to two
lanes between Main Street and Yesler Way.

1.2   The STATE will ensure that: (i) all environmental review and documentation has
been successfully completed and approved prior to construction of the tunnel, north portal,

GCB 1140
Page 4 of 10

south portal and central waterfront surface street projects; (ii) designs of PROJECTS are
consistent with the STATE'S and PORT's needs and provide the PORT with the direct
benet that has been committed to by the Parties; (iii) the PORT has the opportunity to
review and comment on channelization plans prior to construction of each project in the
PROGRAM; (iv)it coordinates with the PORT prior to making any changes to
channelization plans that have been reviewed and commented on by the PORT; (v) all
costs of the PROJECTS funded with proceeds from PORT issued bonds meet the
requirements of the Internal Revenue Service ("IRS") for the use of tax exempt bond
proceeds; and (vi) that the PORT continues as a member of Maintenance of Trafc Task
Forces associated with construction of the PROJECTS.

2.0   PORT RESPONSIBILITIES

2.1    The PORT agrees to contribute Two Hundred Seventy-ve Million Dollars
($275,000,000) solely towards the costs of constructing the PROJECTS, less Seven
Million Three Hundred Thousand Dollars ($7,300,000) representing PORT costs for work
performed by PORT staff that is related to the PROGRAM, including the PROJECTS,
plus additional PORT costs associated with issuing bonds earlier than 2016 to meet its
obligations under Section 3.0, for a total PORT contribution not to exceed Two Hundred
and Sixty-seven Million, Seven Hundred Thousand Dollars ($267,700,000).

2.2   Subject to this Section 2, the PORT agrees to fund construction for the
PROJECTS, including mobilization, temporary erosion and sedimentation control,
earthwork, pavement, drainage, structures, and utilities in the amounts and according to
the schedule as described in Section 3.0 - Payment.

2.3    In addition to the total PORT contribution set forth in Section 2.1, the STATE
may, by no later than 2018, request an additional PORT contribution of up to Six Million
Dollars ($6,000,000) to assist in funding transportation projects identied by the STATE
as serving the SR 99 system. The Parties acknowledge and agree that PORT shall
determine in its sole and absolute discretion whether and how much to contribute under
this Section and, if so, how it will allocate any such contribution among the projects
identied by the STATE. Any additional PORT contribution under this Section 2.3 shall
be documented by attaching the minutes of the Port Commission authorizing such
contribution as Supplement 1 to this Agreement, thereby incorporating it herein without
further amendment.

2.4   The Port shall follow all requirements, included but not limited to I.R.S.
regulations, associated with bond proceeds arbitrage.

3.0   PAYMENT

3.1    Subject to Section 2, the PORT agrees to make payments to the STATE in the
amounts and according to the schedule set forth below:

GCB 1140
Page 5 of 10

a.     Upon receiving the STATE's request for payment no later than April 1, 2015,
the PORT shall make a lump sum payment of One Hundred Twenty Million Dollars
($120,000,000) no later than May 1, 2015.

b.     Upon receiving the STATE's request for payment no later than
April 1, 2016, the PORT shall make a lump sum payment of One Hundred
and Forty-seven Million Dollars ($147,700,000) no later than May 1,
2016.

3.2    All requests for payment by the STATE under Section 3.1 shall include copies
of contractor progress payments that support reimbursement to the STATE for actual
construction costs incurred for the PROJECTS.

3.3    In the event the PORT commits to an additional contribution under Section 2.3,
all requests for payment by the STATE therefor shall include copies of contractor
progress payments that support reimbursement to the STATE for actual construction
costs incurred for the project(s) identied in Supplement 1 to this Agreement.

4.0   MODIFICATIONS TO FUNDING OR SCOPE OF THE PROJECTS AND
AMENDMENT

4.1    The Parties may adjust the PORT's contributions to the Projects under Section 2.0
by written amendment reecting changes to the Port's timing and contribution, except as
otherwise set forth in Section 2.3. In fullling its obligations under this Agreement, the
Port will at all times retain its duty to act in the best interests of the Port.

4.2   Either Party may request changes to the provisions contained in this Agreement.
Such changes shall be mutually agreed upon and incorporated by written amendment to
this Agreement, except as otherwise set forth in Section 2.3. No variation or alteration of
the terms of this Agreement shall be valid unless made in writing and signed by
authorized representatives of the Parties hereto, except as otherwise set forth in Section
2.3.

5.0   NOTIFICATION

5.1    Any notice required or permitted to be given pursuant to this Agreement shall be
in writing, and shall be sent postage prepaid by US. Mail, return receipt requested, to the
following addresses unless otherwise indicated by the Parties to this Agreement:

To the STATE:    Linea Laird, P.E.
Program Administrator
Washington State Dept. of Transportation
999 Third Avenue, Suite 2424
Seattle, WA 98104

GCB 1140
Page 6 of 10

To the PORT:     Tay Yoshitani
Chief Executive Ofcer
Port of Seattle
P. O. Box 1209
Seattle, WA 98111

6.0   RECORDS RETENTION AND AUDIT

6.1    The PORT or its designee shall have the right to inspect, audit and/or copy
records supporting or pertaining to the PORT's funding assistance to the PROGRAM and
accounting thereof for the purpose of determining anything that is of consequence to this
Agreement.

6.2   The STATE shall retain the records pertaining to or supporting the PORT's
funding assistance to the PROGRAM for the periods required below. The STATE shall
also ensure that relevant wage, payroll and cost records of all contractors, subcontractors
and suppliers at all tiers shall be retained and open to similar inspection or audit for the
periods required below:

a.  During the progress of work related to the PROJECTS funded by the PORT;

b.  For a period of not less than six (6) years after the PORT's nal payment to
the STATE under this Agreement; provided that if tax exempt bonds are used to
provide funding assistance to the PROGRAM, the STATE shall retain records
necessary to address an IRS audit for the period required under applicable IRS
regulations; and

c.  If any claim, audit, or litigation arising out of, in connection with, or related to
this Agreement is initiated, all documents and records shall be retained until such
claim, audit or litigation involving the records is resolved or completed,
whichever occurs later.

6.4   The STATE, its contractors, subcontractors and suppliers shall make a good faith
effort to cooperate with the PORT and its designees when the PORT gives notice of its
need to inspect or audit records referenced in this Section 6. Cooperation shall include
assistance as may be reasonably required in the course of inspection or audit, including
reasonable access to personnel with knowledge of the contents of the records being
inspected or audited so that the information in the records is properly understood by the
persons performing the inspection or audit. Cooperation shall also include establishing a
specific mutually agreeable timetable for making the records available for inspection by
the PORT and its designee. Unless otherwise agreed, if the STATE, its contractor,
subcontractors and suppliers cannot make at least some of the relevant records available
for inspection within twenty-eight (28) calendar days of the PORT's written request,
cooperation will necessarily entail providing the PORT with a reasonable explanation for
the delay in production of records.

GCB 1140
Page 7 of 10

7.0   DISPUTE AVOIDANCE AND RESOLUTION

7.I    Designated Representatives:

PORT:    Anne Porter
Capital Project Manager V
Port of Seattle
Capital Development Division
P. O. Box 1209
Seattle, WA 98104
206-787-3133

STATE:   Todd V. Trepanier
Deputy Administrator  Operation
Alaskan Way Viaduct Replacement Program
999 Third Avenue, Suite 2200
Seattle, WA 98104
206805-2813

7.2   The designated representatives herein under section 7. 1, shall use their best efforts
to resolve disputes between the Parties. If the designated representatives are unable to
resolve a dispute, then the responsible project managers or directors for each Party shall
review the matter and meet as soon as possible, but in no case later than ten (10) business
days after request by either Party, to attempt to resolve it. If the project managers or
directors are unable to resolve the dispute, the matter shall be reviewed by the department
director or Chief Executive Ofcer of each Party or his or her designee. The department
director or Chief Executive Ofcer of each Party shall meet within ten (10) business days
of request by either Party after exhaustion of the previous procedural steps. If after that
meeting, the Parties are still not able to resolve the dispute, the Parties shall submit the
dispute to mediation. Representatives of each party with authority to settle the claim, or
in the case of the PORT, if Commission approval is required, management authority to
recommend settlement of the claim directly to Commission, shall participate in the
mediation. The mediator's fee will be divided equally among the parties participating in
the mediation. The Parties agree to exhaust each of these procedural steps before seeking
to resolve disputes in a court of law or any other forum.

8.0   EFFECTIVENESS AND DURATION

8.1    This Agreement is effective upon execution by both Parties and will remain in
effect until nal completion of all Parties' obligations contained or referenced in this
Agreement, unless otherwise amended or terminated.


GCB 1140
Page 8 of 10

9.0   INDEMNIFICATION AND HOLD HARMLESS

9.1    Each of the Parties shall protect, defend, indemnify, and save harmless the other
Party, its ofcers, ofcials, employees, and agents, while acting within the scope of their
employment as such, from any and all costs, claims, judgment, and/0r awards of
damages, arising out of, or in any way resulting from, each of the Party's own negligent
acts or omissions. The STATE shall also protect, defend, indemnify and save harmless
the PORT, its ofcers, ofcials, employees and agents ("PORT indemnied parties"),
from any and all costs, claims, judgment and/or awards of damages, arising out of, or in
any way resulting from the design, permitting, or construction of the PROJECTS or the
PROGRAM. In no event shall the PORT have any maintenance or repair obligation with
respect to Alaskan Way, or facilities lying in public right-of-way along Alaskan Way, or
arising out of or related to the PROGRAM or the PROJECTS. No Party will be required
to indemnify, defend, or save harmless the other Party, its ofcers, ofcials, employees
and agents if the claim, suit, or action for injuries, death, or damages is caused by the sole
negligence of the other Party. Where such claims, suits, or actions result from the
concurrent negligence of the Parties, the indemnity provisions provided herein shall be
valid and enforceable only to the extent of a Party's own negligence.

Each of the Parties agrees that its obligations under this Section extend to any
claim, demand and/or cause of action brought by, or on behalf of, any of its employees or
agents. For this purpose, each of the Parties, by mutual negotiation, hereby waives, with
respect to each of the other Party only, any immunity that would otherwise be available
against such claims under the Industrial Insurance provision of Title 51 RCW.

9.2.   In the event of legal action challenging the PORT's legal authority to provide
funding assistance to the PROGRAM or the PROJECTS, the PORT, in its sole discretion,
may defend such legal action or may tender the defense to the STATE within ten (10)
business days after the service of such legal action. Failure to tender the legal action to
the STATE as provided herein shall constitute a waiver of PORT's right, if any, to seek
indemnity for the claims asserted therein. In the event that the PORT chooses to tender
to the STATE the defense of such legal action, and, to the extent permitted by law, the
STATE shall defend, pay the cost of such defense, save harmless, and indemnify the
PORT indemnied parties from any and all costs, claims, judgment and/or awards of
damages, arising out of, or in any way resulting from, such legal action.

9.3   The indemnication, hold harmless, and/or waiver obligations described in this
section shall survive the termination of this Agreement. In any action to enforce the
provisions of the Section, the prevailing Party shall be entitled to recover its reasonable
attorney's fees and costs incurred from the other Party.

10.0  VENUE

10.1   This Agreement shall be deemed to be made in the County of King, State of
Washington, and the legal rights and obligations of the STATE and PORT shall be

GCB 1140
Page 9 of 10

determined in accordance with the laws of the State of Washington. All legal actions in
connection with this Agreement shall be brought in the County of King, State of
Washington.

11.0  RELATIONSHIP OF PORT AND STATE

11.1   Nothing contained herein shall  be deemed or construed as creating the
relationship of principal and agent, partnership, or joint venture partners between the
STATE and the PORT.

12.0 AUTHORIZED SIGNATURES

12.1  The undersigned acknowledge that they are authorized to execute this Agreement
and bind their respective agencies to the obligations set forth herein.

IN WITNESS WHEREOF, the Parties hereto have executed this Agreement as of the
latest date written below.

PORT OF SEATTLE           STATE OF WASHINGTON
DEPARTMENT OF TRANSPORTATION


Program Administrator
Alaskan Way Viaduct and Seawall
Replacement Program

Date:  3/ 12%; 22'               Date:   Kill; 2523

APPROVED AS TO FORM:       APPROVED AS TO FORM:

1
__MW W
By: Isabel R. Safo a               By: S san
cruise
Deputy General Counsel            Assi ant Attorney General

Date:  (Z/Z//3                Date:     PM     71  J'( old"


GCB 1140
Page 10 of 10

Alaskan Way Viaduct
RE P LAC E M E N T
PROGRAM

05 Wow-W
P'
- m1HMmm  wsnor 

999 Third Avenue, Suite 2400
Seattle, WA 93104                                                    Transmittal
Fax: 206-382-5291
"WM
To Tay Yoshitani, Port of Seattle      From  Doug Murdock, AWV Agreements

Date  August 28, 2013

Project AWV Replacement Program

Agreement   Status     Description                               Original(s)   Sign. Date

GCB1140   Final     SR 99 AWV Replacement Program               1       08/27/2013

WSDOT/Port of Seattle Funding Agreement

If enclosures are not as noted, kindly notify us

Please nd enclosed one (1) original of the above noted Agreement for your files and
use.

Please give me a call at (206) 805-2857 if you have any questions.

Thanks.

CC: Geraldine Poor, Port of Seattle

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.