3a Supp

Item No.:                    3a_supp 
Meeting Date:          February 10, 2015 
Port of Seattle Commission Briefing 
Alaskan Way Viaduct Replacement Program and 
Alaskan Way Street Reconstruction

Funding Agreement Provisions 
Program benefits to the Port: 
Maintains SR-99 corridor throughput capacity. 
Facilitates efficient traffic movement in the corridor
and along the city's waterfront street. 
Supports access to fishing, cruise and other Port
facilities. 
Minimizes construction disruption to regional traffic,
freight mobility for industrial and maritime
businesses, and Port facilities. 

2

Funding Agreement Provisions 
State responsibilities are to: 
Ensure program design and construction provide
the direct Port and public benefit outlined in the
agreement. 
Coordinate with the Port regarding design and
plan changes. 
Continue Port participation in construction traffic
management. 
Ensure use of POS bond proceeds meets IRS
requirements for tax-exempt bonds. 

3

Funding Agreement Provisions 
Port financial contributions 
2010 commitment of not to exceed $300m        $300.0m 
Prior Port program-related investments            19.0m 
Future Port program-related investment            6.0m 
Port costs for early financing and staff time            7.3m 
Port cash contribution                        267.7m 

Port payment schedule 
May 1, 2015                           $120.0m 
May 1, 2016                           $147.7m 


4

Key Components with Port Benefits 



Critical Project Components     Complementary System   Construction Impact
South End Holgate to King         Upgrades                   Mitigation 
Surface Alaskan Way to             Spokane Street Corridor 
Elliott/Western connections        East Marginal Way        Risk Mitigation 
SR 99 Tunnel, South Access, North   SR 519                      Elliott Bay Seawall 
Access and North Surface Streets   Duwamish ITS           Viaduct risk mitigation 
Mercer Corridor 
Transit 
5

Alaskan Way Surface Street 
Ongoing design discussions 
Terminal 46-North and Pier 46: Truck and labor access 
Pier 66 Cruise Terminal: Landside access 
Pine/Alaskan Way intersection: Freight/cruise needs 
Lenora Street: Overpass access for inspection,
maintenance, repair and renewal 
Alaskan Way Surface Street: Through capacity 

6

Organization Port of Seattle Commission briefing 
Date Feb. 10, 2015

Building a new
SR 99
Corridor 

8

This is a
SAFETY
project 




The viaduct and neighboring seawall are vulnerable to earthquakes 

The viaduct in 1953 

9

Overview of
COMPLETED WORK 
Map of state-led/funded improvements 






*Partially funded by the state. 
** Per 2014 legislation, mitigation funding through June 2015 is being
provided by WSDOT from funds outside the AWV Program. 
10

FUNDING
overview 

Port of Seattle 
Toll         $281 
Local $200 
$22.8 

Federal 
$787.2                           Gas Tax     = $3.1 billion 
$1,817.3 


Other state 
$36.9 
Funding sources (shown in millions) 

11

Improving
FREIGHT MOBILITY 



SR 519 improvements near Safeco Field. 

12

Improving
FREIGHT MOBILITY 


Holgate to King: the South Atlantic Street
overpass 



13

Building the 
SR 99 tunnel 
Southbound SR 99 

Northbound SR 99 


14

Seattle Tunnel
Partners 
has completed excavation of a
circular pit to access and repair
the machine and resume
tunneling 



15

THE TUNNEL 
will carry drivers through downtown 
South portal 



SR 99 tunnel
Drivers will enter and exit
downtown at the
TUNNEL      North portal 
PORTALS 
16

SR 99 tunnel contract
OVERVIEW 
Project management 
6% 
Advance
mitigation 
7% 
Bored tunnel                           Bond and
29%                         insurance
allowance 
8% 

Escalation fund 
8%           = $1.35 billion 

South portal roadways             North portal roadways 
(south c-and-c, south u)                     11% 
19%            Operations
buildings and
tunnel systems
(north bldg, south
bldg, systems) 
12% 
17

SOUTH PORTAL ROADWAYS 
82 percent complete 
Estimated cost: $250 million 
Paid to date: $205 million                Components include: 
South cut-and-cover tunnel 
Ramps and other highway connections 


South
portal
roadways 

Inside the south cut-and-cover tunnel 

18

NORTH PORTAL ROADWAYS 
71 percent complete 
Estimated cost: $140 million 
Paid to date: $99.5 million                Components include: 
North cut-and-cover tunnel 
Ramps and other highway connections 

11 percent
of budget 
11 percent
North portal
of budget 
roadways 

The SR 99 tunnel's future north portal. 

19

BORED TUNNEL  
Design 
94 percent complete 
Estimated cost: $26 million 
Paid to date: $24 million 


42 percent
of budget 
Bored
tunnel 


SR 99 tunnel rendering. 

20

BORED TUNNEL  Tunneling
machine and conveyor system 
92 percent complete 
Estimated cost: $162 million             Components include: 
Paid to date: $150 million                      Conveyor system 
Manufacture, transport, assembly and
support for the tunneling machine 
Muck storage facility 
42 percent
of budget 
Bored
tunnel 



Bertha and the conveyor system. 
21

BORED TUNNEL  
Interior structures 
16 percent complete 
Estimated cost: $44 million              Components include: 
Paid to date: $7 million 
Materials 
Significant up-front costs due to
fabrication of form work 
42 percent
of budget 
Bored
tunnel 



Construction of the tunnel's interior structures. 
22

BORED TUNNEL  
Tunnel liner fabrication 
96 percent complete 
Estimated cost: $71 million              Components include: 
Paid to date: $68 million 
Fabrication of tunnel liners 

42 percent
of budget 
Bored
tunnel 


Tunnel liners at the manufacturing
facility in Frederickson, Wash. 

23

BORED TUNNEL  Tunnel
mining and liner installation 
26 percent complete 
Estimated cost: $78 million              Components include: 
Paid to date: $20.5 million                      Tunnel excavation and associated costs 
Liner installation 
Significant up-front costs 
42 percent
of budget 
Bored
tunnel 



Bertha at the start of the tunnel drive. 

24

THANK YOU 
Website: 
www.AlaskanWayViaduct.org 
Twitter: 
@BerthaDigsSR99 
Email: 
Our information center,
viaduct@wsdot.wa.gov 
Milepost 31, is located
at 211 First Ave. S. in
Hotline: 
Seattle's Pioneer
1-888-AWV-LINE 
Square neighborhood. 
25

WATERFRONT SEATTLE 
February 2015

ELLIOTT BAY -   Elliott Bay Seawall Project
Phase 2


Elliott Bay Seawall Project
Phase 1 [2013-2016)

'          ~


'
~

_ .3                        Seattle MultimodalTerminal
._
'
1'
'                                                       at Colman Dock Project

, I!
.7
.
A   -: '- L l 2017-2022

~
)
- FQEN'   .5


' :.A;ir

I                 . 'r':$':". '.
't". ..' a -V   ,3"
V".
"553', 9'1"": Waterfront Seattle '"'
7
j       "'3'" "013*,
. K
.-.
.                              - wnnnrnomsunts PHASE 1AREA
'
kgli' ~ W" ~ n, et
V?  fit. (1 ill'I'; ELLIOTT BAY SEMALL PROJECT PHASE 1               9. ti
L'V"        ' '-
o"'41'
_
_

'  _ I IELLIOTT BAY SEAVIALL PROJECT PHASE 2
U I SR"TUNNEL PROJECT
'
'
- SR99TunnelProlect        - sumsHumuomt.TERMINALAT
comm DOCK PROJECT
(2011-1301
- PARTNER PROJECTS
Project construction dates are tentative and
subject to change
v              Sources: City of Seattle GIS, Googlo maps,
9" , _ ..
' 'V SDOT 2010 Bike Map. ROMA 2002 Urban DooignAssossment

. a.
, :
.4 .'   v.4
, . .  t -.   ~.
' 3' .Afetdwt "-.;"'}l.' 11-1329'


.                                                                              rte-m

2010-
WATERFRONT SEATTLE    2014 2015 2016  2017 2018  2019 2020+
2013


COMPLETE JULY 2012
CONCEPT DESIGN

MAIN CORRIDOR DESIGN [PHASE 11
60%         90%   COMPLETE
Alaskan Way. Elliott Way. Cycle Track.
O      O
Promenade & utility projects
BEGIN
CONSTRUCTION
Columbia Street 8: Seneca Street
{dependent on Alaskan
Way Viaduct demolition)
30% 60% 90% COMPLETE
Marion Street Bridge  Alaskan Way to
Western Avenue & Lenora Street Bridge                  O  O   O

EAST-WEST CONNECTIONS &
PUBLIC PIERS DESIGN [PHASE 1)
30%             60%  90%    COMPLETE
Overlook Walk         O               O     O
l
30%  60/           90%       COMPLETE
,
Union Street - Alaskan Way to Western Avenue       0    O              O
BEGIN
30% 60% 90%   COMPLETE
CONSTRUCTION
Main Street & Washington Street                        O  O  O
i                               (dependent on
30% 60% 90%  COMPLETE       Alaskan Way
Bell Street Park extension                                                       Viaduct demolition}

30%               60%  90%    COMPLETE
Waterfront Park                          O   O

30% 60% 90%   COMPLETE
Pier 62/63 basic repairs                          O  O  O

COMPLETE
BEGIN CONSTRUCTION
Railroad Way
(dependent an Alaskan
Way Viaduct demolition]
l
30% 60%  90%  COMPLETE 
Pike/Pine corridor                          m                             BEGIN
CONSTRUCTION
[dependent on Alaskan
Way Viaduct demolition]

WATERFRONT 
SEAWALL PROJECT 
TYPICAL SECTION: SEAWALL, HABITAT SHELF + L.P.S.

:  I',\\;,_
SUSTAINABILITY
THE NEW ELLIOTT BAY SEAWALL
SEAWALL PANEL INSTALLATION

WATERFRONT SEATTLE 
Core Project - South

WATERFRONT SEATTLE 
Core Project - North

WATERFRONT SEATTLE 
Questions?

Pocket Slides

STREET DESIGN 
FUNCTIONS OF THE STREET 











VEHICLES, PARKING AND LOADING 
FERRIES: LOADING AND UNLOADING 
TRANSIT: SW TRANSIT PATHWAY 
NORTH/SOUTH BICYCLE AND PEDESTRIAN
MOVEMENT

STREET DESIGN
ALASKAN WAY
FUNCTIONS OF THE STREET

\
\
__\
PORT in:
'
SEATTLE   ,
i Q



y
D
.5"; -
.5.        I
Hf.

II          "        1


KING TO YESLER     YESLER TO MADISON            MADISON TO PINE

SWTP DEDICATED LANES I2]   SWTP DEDICATED LANES I0-2I           GENERAL PURPOSE LANES [4]
GENERAL PURPOSE LANES I4]  GENERAL PURPOSE LANES [4]          WATERFRONT TRANSIT [SHARED]
G
FERRY OUEUING LANES [1-2]  WATERFRONT TRANSIT [SHARED]             PARKING/LOADING [2]
PARKING/LOADING IO-II    FERRY PARKING/LOADING [0-2I

WATERFRONT PROMENADE TYPICAL SECTION

_)_ RESTORED _} RESTORED ).RESToREo.,_                             ,
3  PROMENADE                        ROADWAY                    mum-use                                                                                          #
I
a                                                 PATH
LINE"  LI                                                                                                                                                 III
E
J
PROPERTY  "Eiff''viili        SEAWALL                                                                                                                                        >.
.-
2
III
E.
O
I
' I.
'
'
'
'

---------
,                                                                                                                                            r
d? 

_
'r      TF            i                VI?
"A     Am



mu  4         WATEIIIOIT          "I f  f                ALASKAN        EAST SIDE 
' HOMEMADE
PATH                    WAY

WATERFRONT PROGRAM UPDATE
CONTINUOUS PROGRAM ELEMENTS

12' AOUATIC IIIADITAT

20' fk'
SITTING [WATCHING

WEST        PAUSE I
SIDE               ,
EXPLORE I
35'
ESCAPE
' 'Iiltilllllllllilltljl'    "ll!.[l|

-
SOCIAL                            HI]
'llll[IllIIII'IIIIIII'IIIJJIIII         ._.'l'l:.[:[lgl{|l . alL..
INTERSECTION

12' CYCLING

s.  ACCESS

10' PARKING I LOADING


ALASKAN   '.4.O' DRIVING I
WAY        USING TRANSIT


10' PARKING / LOADING

ACCESSIILE
f   u-zo' STROLLINO I
EAST         SHOPPING
suns
RETAIL


BUDGET

Parks - Central Waterfront          Local Improvement District
Piers Rehabilitation               [LID] administration
$94M                  $6M
Parks - Aquarium
Expansion
$34M
I. 
Alaskan Way
Pike Place Market                    roadway and
PC-1 North Market  pedestrian
.
Front Entrance Project,-                              promenade
$34-40M                              $400M

Overlook Walk
and East/West
Connecons
$165M

Elliott Bay Seawall
Replacement
$331 M

TOTAL: $1.073

FUNDING SOURCES

PC-1
North bonds
$34-40M
|:Grants King County
Other sources [TBDl           and WA State
$52M                         $34M

Commercial 
parking tax                              Voted
$65M                            Seawall bond
$290M
City general fund
$65M

Philanthropy
$100M

Local Improvement                       WSDOT funding
District [LID]                                      $220M
$200M

TOTAL: $1.073

STREET DESIGN
PINE ST. INTERSECTION
JUNE 2013 ALIGNMENT

STREET DESIGN
PINE ST. INTERSECTION
II I I I I I lurks-

SEAWALL 





44 44

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.