5g

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA                   Item No.        5g 
ACTION ITEM                   Date of Meeting   December 11, 2012 

DATE:      December 3, 2012 
TO:       Tay Yoshitani, Chief Executive Officer 
FROM:     Wayne Grotheer, Director, Aviation Project Management Group 
Tina Soike, Senior Manager, Airport Operations 
SUBJECT:   Airline Realignment Miscellaneous Building Improvements-Airline Realignment
(CIP #C800475) 
Amount of This Request: $0            Source of Funds: Airport Development Fund 
Est. State and Local Taxes: $94,000      Est. Jobs Created: 15 
Est. Total Project Cost:     2,722,000 
ACTION REQUESTED: 
Request Commission authorization for the Chief Executive Officer to (1) reduce the scope of the
Miscellaneous Building Improvements project that is part of the Airline Realignment program at
Seattle-Tacoma International Airport; (2) execute a contract estimated at $220,000 for purchase
of equipment; and (3) use Port crews for project construction. No additional funding is requested
with this authorization. 
SYNOPSIS: 
The work planned under this authorization represents the next phase in a time-critical sequence
supporting the broader airline realignment effort while also providing improved operational
flexibility and efficiency at the Airport. 
This project is part of the one-time realignment of air carrier operations that will occur in 2013. 
This authorization is necessary due to a change in scope since the December 6, 2011, 
authorization.  Concourse A is not currently equipped to provide accessible passenger loading
onto the small regional aircraft of United Express and Air Canada/Jazz, so a new exterior
covered passenger ramp will be needed at that location. During the design process, the planned
gate assignment for the United Airlines regional aircraft was changed from Gates A13/14 to Gate
A6. Additionally, the scope was reduced from a fully enclosed architectural ramp, stairs, or
elevator to a pre-fabricated covered ramp to be assembled on-site by Port crews and small works
contractors. The contract to purchase pre-fabricated covered ramp equipment is estimated to be
approximately $220,000. These scope changes were made in order to reduce construction costs
for the project, and the changes are supported by United Airlines. The project also includes other
miscellaneous capital improvements that are part of the airline realignment program. This project
was included in the 2013  2017 capital budget and plan of finance. Authorization in the amount
of $1,721,000 was previously granted for the project and no additional funding is being

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
December 3, 2012 
Page 2 of 6 
requested at this time.  As a result of the change in scope, the total project budget has been
reduced by $5.2 million. 
BACKGROUND: 
With ongoing airline consolidation interests and a goal to maximize utilization of existing
facilities, the Airport is exercising the One-Time Reallocation provision in the current Signatory
Lease & Operating Agreement.  The reallocation will require a number of modifications
associated with the airlines that  will relocate their gate and ticket counter operations, to
effectively operate in their new locations. 
This  project  includes  other  miscellaneous  capital  improvements  in  the  Airport  terminal 
associated with Airline Realignment. At present that includes upgrades to the air ventilation
ductwork for the new ticket offices for three relocated airlines. 
PROJECT JUSTIFICATION: 
Project Objectives: 
Accommodate the airline relocations by providing miscellaneous building improvements
throughout the Airport terminal. 
Provide accessible boarding between the concourse level and the regional aircraft ground
boarding at Gate A6. 
Provide safer access to the ground level by providing a weatherprotected, sloped
walkway. 
Improve customer service and safety by providing new vertical circulation between the
concourse and ground level for access to/from regional aircraft. 
PROJECT SCOPE OF WORK AND SCHEDULE: 
Scope of Work: 
This project will provide an exterior passenger boarding ramp that is compliant with the
Americans with Disabilities Act (ADA) at Gate A6 on Concourse A as part of the Airline
Realignment program. 
Schedule: 
Design Start                                                       January 2012 
Design Complete                                             January 2013 
Commission Authorization to Execute Purchase Contract          December 2012 
Pre-fabricated Ramp Delivered to Airport                         April 2013 
Construction/Ramp Assembly Start                              April 2013 
Construction/Ramp Assembly Compete                        May 2013

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
December 3, 2012 
Page 3 of 6 
FINANCIAL IMPLICATIONS: 
Budget/Authorization Summary:                      Capital   Expense       Total Project 
Original Budget                                    $7,922,000         $0         $7,922,000 
Budget (Decrease)                                 -$5,165,000         $0        -$5,165,000 
Budget Transfers                                     -$35,000         $0            -$35,000 
Revised Budget                                   $2,722,000        $0         $2,722,000 
Previous Authorizations                             $1,721,000         $0          $1,721,000 
Authorization Transfers                               -$160,000         $0           -$160,000 
Current Authorizations                              $1,561,000         $0         $1,561,000 
Current request for authorization                               $0         $0                   $0 
Total Authorizations, including this request           $1,561,000         $0          $1,561,000 
Remaining budget to be authorized                  $1,161,000         $0         $1,161,000 
Total Estimated Project Cost                        $2,722,000         $0          $2,722,000 
Project Cost Breakdown:                            Total Project 
Construction                                              $988,000 
Construction Management                                    $0 
Design                                                  $290,000 
Project Management                                   $171,000
Permitting                                                  $18,000 
State & Local Taxes (estimated)                            $94,000 
Sub-total                                                  $1,561,000 
Future Projects*                                          $1,161,000 
Total                                                      $2,722,000 
*The "Future Projects" cost item includes cost breakdown items such as additional state and
local taxes that have not been fully defined at this time. 
Budget Status and Source of Funds: 
This project is included in the 2013-2017 Capital Budget and Plan of Finance within CIP
#C800475, Miscellaneous Building Improvements-Airline Realignment.   The budget was
decreased due to a combination of transfer of budget and authorization for the relocation of
Virgin America's ticket counter and office,to the Convert Ticket Zone 3 Flow Thru (CIP
#C800492) project,  and to recognize anticipated cost savings. The funding source will be the
Airport Development Fund.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
December 3, 2012 
Page 4 of 6 
Financial Analysis and Summary: 
CIP Category                   New/Enhancement 
Project Type                     Renewal & Replacement 
Risk adjusted discount rate       N/A 
Key risk factors                   N/A 
Project cost for analysis           $1,561,000 (Based on current authorization) 
Business Unit (BU)               Terminal 
Effect on business performance   NOI after depreciation will increase 
IRR/NPV                   N/A 
CPE Impact                   CPE will increase by $.01 in 2014, but no change to
business plan forecast as this project was included.
Lifecycle Cost and Savings: 
There will be a minor increase in staff costs to maintain the ramp equipment and new access
control card reader at the ramp, but the annual operating and maintenance costs are not
forecasted to change appreciably. 
STRATEGIC OBJECTIVES: 
The project supports  the Port's Century Agenda objective of meeting the region's air
transportation needs at Sea-Tac Airport for the next 25 years, by providing flexibility of the
existing airport facilities. It  supports  the airline realignment program, which benefits our
passengers and airline partners. 
ENVIRONMENTAL SUSTAINABILITY: 
This project demonstrates environmental sustainability by improving existing Port assets and
better utilizing  existing  resources.  Realignment  will  allow more  effective  use of  terminal
facilities, and this enables efficient operation for airlines at new locations. More sustainable
operations  of  the  Airport  are  expected  to  generate  lower  lifecycle  costs  of  the  needed
investments. 
BUSINESS PLAN OBJECTIVES: 
The Airport business plan notes that a strategic goal is to operate a world-class international
airport by meeting the needs of our tenants, passengers, and the region's economy. This project
facilitates airline relocations to different gates and ticket counters and meets the needs of our
tenants, passengers, and the region's economy. 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
Alternative 1 (Do nothing): This alternative would preclude the realignment program as jointly
recommended by the Airline Airport Affairs Committee and the Aviation Division. This
alternative is not recommended.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
December 3, 2012 
Page 5 of 6 
Alternative 2: Provide a custom-designed, fully-enclosed architectural ramp or elevator. This
alternative would cost significantly more and would limit flexibility for future aircraft gate
assignments. This alternative is not recommended. 
Alternative 3: Provide miscellaneous building improvements at the Airport terminal to support
the airline realignment program. Work consists of a pre-fabricated passenger accessible loading
ramp to board planes at Gate A6 and other miscellaneous capital improvements. This is the
recommended alternative. 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
None. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
On September 11, 2012, the Commission authorized Airline Realignment Tenant Improvement
Program - Reimbursement for Alaska Airlines for Seattle-Tacoma International Airport (Expense
WP 104756) in the amount of $1,179,000. 
On September 11, 2012, the Commission authorized Airline Realignment Tenant Improvements
(Expense) Regulated Materials Management for Zone 2 Ticket Counter and Offices and Tenant
Relocation in the amount of $730,000. 
On July 10, 2012, the Commission authorized Airline Realignment Tenant Improvements in the
amount of $4,243,400 to advertise and execute a construction contract and use of Port Crews for
Airline Tenant Improvements  Airline Realignment. 
On July 10, 2012, the Commission authorized CUSE construction at ticket counters and gates,
and seating in the amount of $1,887,000. 
On June 26, 2012, the Commission was provided an update briefing with the NorthSTAR budget
restructuring. 
On June 26, 2012, the Commission authorized additional budget of $400,000 to add two fuel pits
(C800472). 
On April 24, 2012, the Commission authorized Airline Realignment Tenant Improvements in the
amount of $225,000 for regulated materials management. 
On April 10, 2012, the Commission authorized additional budget to enter into a construction
contract for airfield improvements including Exterior Gate Improvements  Airline Realignment
(C800472). 
On January 24, 2012, the Commission received a briefing on the Airport Realignment Program. 
On January 24, 2012, the Commission authorized construction of Exterior Gate Improvements  
Airline Realignment (C800472) in the amount of $2,613,000. 
On January 24, 2012, the Commission authorized design for CUSE at Ticket Counter/Gates &
Seating (C800473) in the amount of $484,000.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
December 3, 2012 
Page 6 of 6 
On December 6, 2011, the Commission authorized construction of Baggage Handling System
(BHS) Improvements  C22 BHS Connection to C1/C1-MK1 Replacement (C800382) at the
Airport in the amount of $3,604,000. 
On December 6, 2011, the Commission authorized design of the Miscellaneous Building
Improvements  Airline Realignment (C800475) at the Airport in the amount of $1,721,000. 
On December 6, 2011, the Commission authorized design of the Airline Tenant Improvements  
Airline Realignment (expense) at the Airport in the amount of $3,776,000. 
On September 27, 2011, the Port Commission authorized execution of an IDIQ contract for
Airline Realignment Tenant Improvements and Ticket Counter Design services totaling
$10,000,000.
On September 12, 2011, the Port Commission received a summary briefing on the Airport
Realignment Program at Seattle-Tacoma International Airport. 
On June 14, 2011, the Port Commission authorized design of the Exterior Gate Improvements-
Airline Realignment project (C800472) at Seattle-Tacoma International Airport in the amount of
$499,000. 
On June 14, 2011, the Port Commission authorized design of the Airport Signage-Airline
Realignment project (C800474) at Seattle-Tacoma International Airport in the amount of
$238,000. 
On March 1, 2011, the Port Commission authorized design and some construction of the
Baggage Handling System (BHS) Improvements - C22 BHS connection to C1/C1-MK1
Replacement /TC3 Replacement (C800382) in the amount of $1,731,000. 
On February 22, 2011, the Port Commission was shown a summary listing of realignment
projects and authorized Planning for Terminal Realignment in the amount of $713,000. 
On February 22, 2011, the Port Commission authorized design and some construction for the
Passenger Loading Bridge Replacement Project - Airline Realignment (C800467) in the amount
of $6,700,000. 
On January 25, 2011, the Port Commission was given an overview of the airline realignment and
authorized design and construction of the Concourse D Common Use Expansion Project
(C800455) in the amount of $4,250,000. Commission was also briefed on the Airline
Realignment Program as part of this item. 
On September 28, 2010, the Port Commission was given a summary briefing of the upcoming
201 capital improvement plan that included the airline realignment program elements. 
On June 8, 2010, the Port Commission authorized execution of an IDIQ contract for the
Terminal Development Strategy Campus Planning Services IDIQ in the amount of $1,300,000.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.