5d

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      5d 
ACTION ITEM             Date of Meeting   December 4, 2012 

DATE:    November 21, 2012 
TO:      Tay Yoshitani, Chief Executive Officer 
FROM:    Mike Ehl, Director, Airport Operations 
Wayne Grotheer, Director, Aviation Project Management Group 
SUBJECT: Cargo 2-West Hardstand Expansion at Seattle-Tacoma International Airport  
FAA Agreement for Antenna Relocation (CIP #C800247) 
Amount of This Request:  $300,000    Source of Funds: Airport Development Fund and
future revenue bonds 
Est. State and Local Taxes: N/A       Est. Jobs Created: TBD 
Est. Total Project Cost:   $12,130,000 
ACTION REQUESTED: 
Request Commission authorization for the Chief Executive Officer to execute one or more
contracts with the Federal Aviation Administration (FAA) for relocation of the Airport Surface
Detection Equipment Model X Remote Unit Number 7 (ASDE-X RU No. 7) antenna at the 
Airport, at a cost not to exceed $300,000. The total estimated project cost is $12,130,000. 
SYNOPSIS: 
The relocation of FAA's ASDE-X RU No. 7 antenna is required for construction of the Cargo 2
Hardstand Expansion project. The Commission earlier authorized the design for the Cargo 2
Hardstand Expansion project and the termination of the lease with ProLogis on September 25,
2012. The contracts with the FAA will allow antenna relocation design and later antenna
construction to proceed.
The FAA has an ASDE-X RU No. 7 antenna located on a building that is owned by ProLogis in
a leased area that will be demolished as part of the Cargo 2 West Hardstand Expansion project.
The building is scheduled to be demolished in January 2014 following the one-year notification
period for termination of the lease with ProLogis.
A high-level estimate of total cost for the relocation of the ASDE-X RU No. 7 antenna is
$300,000, although the actual cost will be established as part of the preliminary engineering

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
November 21, 2012 
Page 2 of 5 
effort. The FAA has provided an agreement that addresses preliminary engineering to relocate
their ASDE-X RU No. 7 antenna and estimates the cost of that specific work at $30,000. The
preliminary engineering includes technical consultation, site visit, feasibility assessments, project
planning, scope definition, development of cost estimates, and review of the Port's design for the
hardstand expansion. The estimate of cost for design, construction, and installation will be
established as part of the preliminary engineering effort.
Federal regulations require that federal agencies receive funds prior to performing work. If
approved by the Commission, the Port will transfer $30,000 to the FAA to perform the
preliminary engineering. Once the estimate of cost to design, construct, and install the antenna
in a new location is established, the Port will modify the agreement with the FAA and transfer
additional funds to the FAA so the remaining work can be performed. Port staff will return to
the Commission and seek additional fund authorization should the estimate of total cost for the
relocation of the ASDE-X RU No. 7 exceed $300,000. 
The capital costs associated with this project were included in the 2013-2017 capital budget and
plan of finance; however, the current authorization request of $300,000 was not specifically
identified in the 2013 operating budget. The Airport will utilize the contingency budget and/or
identify other savings in the 2013 budget to absorb this cost. 
BACKGROUND: 
The existing Cargo 2 hardstand is too short to accommodate straight-in parking for certain types
of cargo loading operations. The current nose-load parking position line has to be angled, and
the 747-8F line must be configured east to west across two hardstands. This results in an
inefficient use of the ramp by taking up two parking positions for a single operation and reducing
overall capacity. 
All existing hardstands have limited space in front of parked aircraft to allow for cargo/ground
service equipment (GSE) staging. Consequently, cargo and GSE end up staged on either side of
the aircraft, impinging on adjacent hardstands. 
This project will provide additional concrete apron space to enlarge the western cargo hardstand
toward the north, which will provide enough room for two simultaneous straight-in wide body
freighter nose-load operations by aircraft including the 747-8F. The larger ramp area will allow
the taxi lane to be moved to the north and provide better maneuverability and increased
operational room for users of both Cargo 2 and Cargo 3 ramps.
ProLogis has a ground lease in the Cargo 2 area and owns two buildings there, one of which will
require demolition. The lease requires a one-year notice prior to termination and compensation
for the unamortized value of the buildings. The notice of lease termination was given to
ProLogis on October 3, 2012. The building that is to be demolished is occupied by a tenant,
Cargo Airport Services; this building will be relocated prior to construction. The FAA ASDE-X
RU No. 7 antenna is located on top of the building and will require relocation prior to building
demolition.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
November 21, 2012 
Page 3 of 5 
PROJECT JUSTIFICATION: 
The existing Cargo 2-West hardstand is the only existing hardstand position at the Airport that
can efficiently and safely accommodate the cargo operation of the new 747-8F aircraft, and other
aircraft design group (ADG) VI very large freighter aircraft. Because Cargo 2 -West lacks
adequate depth, the current -8F nose-load parking position is required to be perpendicular to
existing parking lines, which results in the aircraft having to be positioned across a number of 
hardstand lines. This results in an inefficient use of the ramp by taking up two parking positions
for a single operation. Effective alternatives do not exist. 
Project Objectives: 
Improve the Cargo 2-West hardstand in order to accommodate the increased size and
frequency of wide body cargo aircraft at the Airport 
Improve overall air cargo efficiency 
Support cargo volume growth 
PROJECT SCOPE OF WORK AND SCHEDULE: 
Scope of Work: 
Lease buyout from ProLogis 
Relocation of FAA ASDE-X RU No. 7 antenna 
Demolition of one cargo building currently owned by ProLogis 
Construction of the Cargo 2 hardstand expansion 
Schedule: 
Commission Authorization to Terminate Lease and 100% Design     September   2012 
Lease Termination Notice                              October     2012 
Commission Authorization to Execute an Agreement with FAA      December   2012 
Commission Authorization to Advertise Construction Contract       August      2013 
Advertise Construction Contract                           September   2013 
Building Acquisition                                  October     2013 
Tenant Relocation Complete                            December    2013 
FAA Antenna Relocation Complete                      December   2013 
Notice to Proceed                                    January     2014 
Construction Complete                              October    2014

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
November 21, 2012 
Page 4 of 5 
FINANCIAL IMPLICATIONS: 
Budget/Authorization Summary:             Capital      Expense   Total Project 
Original Budget                      $13,300,000      $300,000   $13,600,000 
Budget Decrease                     (1,470,000)          $0    (1,470,000) 
Revised Budget                     $11,830,000      $300,000   $12,130,000 
Previous Authorizations                  $2,410,000          $0          $0 
Current request for authorization                   $0      $300,000      $300,000 
Total Authorizations, including this request      $2,410,000      $300,000    $2,710,000 
Remaining budget to be authorized           $9,420,000          $0    $9,690,000 
Total Estimated Project Cost              $11,830,000      $300,000   $12,130,000 
Budget Status and Source of Funds: 
Cargo 2West Hardstand Expansion CIP #C800247 is included in the 2013-2017 capital budget
and plan of finance.  The operating expense of $300,000 was not specifically included in the
2013 operating budget. Consequently, the Airport will utilize the contingency budget and/or
identify other savings in the 2013 budget to absorb this cost. The source of funds for this
authorization request will be the Airport Development Fund. The total project funding plan will
also include future revenue bonds. As presented in the Port's plan of finance, the Airport has a
number of projects that will require a revenue bond issue in 2013 or 2014. 
Financial Analysis and Summary: 
CIP Category                   Revenue/Capacity Growth 
Project Type                    Business Expansion 
Risk adjusted Discount rate           N/A 
Key risk factors                    N/A 
Project cost for analysis               $12,130,000 
Business Unit (BU)                 Airfield 
Effect on business performance         NOI after depreciation will increase since capital and
operating costs will be recovered through landing fees 
IRR/NPV                  N/A 
CPE Impact                  $0.06 in 2015; however, no change from business plan
forecast as this project was included. 
STRATEGIC OBJECTIVES: 
This project is consistent and necessary for the implementation of the Commission's Century
Agenda goals that call for tripling air cargo volume over 25 years.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
November 21, 2012 
Page 5 of 5 
BUSINESS PLAN OBJECTIVES: 
This project is included in the 2013-2017 Aviation Business Plan to support the goal of operating
a world-class airport by anticipating and meeting the needs of our tenants, passengers, and the
region's economy by expanding and modernizing existing on-airport cargo facilities. 
TRIPLE BOTTOM LINE SUMMARY: 
This project will improve two hardstands in Cargo 2 area to accommodate the increased size and
frequency of wide-body cargo aircraft to increase the Airport's ability to retain and attract key
cargo customers, who want to operate the larger and more efficient newly available freighters.
The project will also reduce airfield carbon and other gas emissions by providing electrical
power as an alternative to fuel-powered generator operations. 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
Alternative 1 - Do Nothing: This alternative would not allow for relocation of the FAA
ASDE-X RU No. 7 antenna nor would it allow for the demolition of the building at the
Cargo 2 area that must occur prior to the expansion of the hardstand. This would not
promote air cargo growth and the associated economic development, and does not align
with Commission Century Agenda goals. This alternative is not recommended. 
Alternative 2  Enter into one or more agreements with FAA for relocation of the
ASDE-X RU No. 7 antenna and allow the Cargo 2-West Hardstand Expansion to occur. 
This alternative is consistent with the goals of the Century Agenda for promoting growth
in air cargo by alleviating capacity constraints, and is consistent with the Airport's
Comprehensive Development Plan (CDP). This is the recommended alternative. 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
Draft FAA/Port Agreement for Relocation of ASDE-X RU No. 7 Antenna. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
On September 25, 2012, the Port Commission authorized the Chief Executive Officer to 1)
design and prepare construction documents for the demolition of a cargo building (Building 2)
and for the enlargement of the hardstand in the Cargo 2 West area in the amount of $830,000 and
2) to terminate the lease containing two cargo buildings in the Cargo 1 and Cargo 2 areas owned
by ProLogis at Seattle-Tacoma International Airport at a cost not to exceed $1,580,000.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.