7a Report

Item Number: 7a_Report
Meeting Date: September 25, 2012


Commission Staff Brieng
Capital Improvement Projects
Second Quarter Report 2012

This page intentionally left blank









ii  Port of Seattle 2Q 2012 Report

Port of Seattle
Capital Improvement Project Report
Second Quarter 2012
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the status of the Port's capital projects.
Background
During 2012 the Port plans to invest over $319,000,000 to expand and upgrade the infrastructure that supports marine
and aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping
companies, airlines, rental car companies, concessionaires and public parking. About 4 percent of the Port's capital
budget comes from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in
transportation facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes a "Status Snapshot" illustrating at a
glance if the project is on schedule, within budget, the total number of change orders to date, and the total value of
executed change orders.
x Significant Developments covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x Schedule includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x Budget addresses the total project budget and includes things like overall budget status, recent Commission
authorizations, forecasted overruns or savings, and scope changes.
x Change Orders provides a description of CO for the reporting period and information on any CO over $200,000 or
10% of the contract value.
x Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
x Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
x Budget Transfers reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page and select the Audit/Accountability button. Use the form to ask a
question, make a comment or request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 2Q 2012 Report  1

Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000683 et al .......3rd Runway Program .............................................6 ........... 
C100266 et al .......Rental Car Facility ...............................................7-8 .......... ...............
C102163................Main Terminal Baggage Screening ....................9-10......... ...................................
C102334 ...............Water System Isolation Valve Upgrade ................11 .......... ...............
C102573 ...............Airf eld Pavement Replacement ...........................12 ..........
C800019 ...............Loading Bridge Utilities .........................................13 ........................................ 
C800034 ...............North Expressway Relocation ..............................14 .......... ...............
C800061 ...............Main Terminal South Low Voltage ........................15 .......... ...............
C800105 ...............Airport Owned Gate Infrastructure .......................16 ..........
C800107 ...............C4 UPS System Improvements ............................17 .......... ...............
C800112................Runway 16C/34C Panel/Joint Sealant .................18 ..........
C800147 ...............Concessions Unit Readiness Program ................19 .......... ...............
C800148 ...............GML Arrivals Hall Concessions ...........................20 .......... ...............
C800168 ...............C60-C61 BHS Modif cations ................................21 ..........
C800174................FIS - New Primary Inspection Booths ..................22 .......... ...............
C800203 ...............Common Use Lounge Remodel ...........................23 ..........
C800237 ...............Terminal Escalators Modernization ...................24-25 .......
C800238 ...............Central Plant Pre-Conditioned Air ........................26 .......... ...............
C800242 ...............Security Checkpoint Cameras..............................27 .......... ...............
C800251 ...............Vertical Conveyance Modernization.....................28 .......... .................................. 
C800253 ...............Parking System Replacement ..............................29 ........................................
C800254 ...............Aircraft RON Parking Post Off ce Site..................30 ........................................ 
C800267 ...............Port Owned Loading Bridges ...............................31 ..........
C800268 ...............Stage 2 Mechanical Energy Implementation .......32 .......... ...............
C800274 ...............8th Floor Weather Proof ng ..................................33 ..........  ...............
C800276 ...............Common Use Equipment Expansion (CUSE) ......34 ..........
C800334 ...............Two new CTE Freight Elevators ...........................35 .......... ............... .................. 
C800335 ...............EGSE Electrical Charging Stations ...................36-37 ....... ...............
C800374 ...............Claim Device 14 and Lower Inland .......................38 ..........
C800382 ...............BHS (C22-C1, MK1 and TC3) ...............................39 ..........
C800406 ...............RW 16C/34C Reconstruction Design ...................40 ..........
C800412 ...............South Satellite Concessions Project ....................41 ........................................ 
C800414 ...............Access Control Door Additions ............................42 .......... ...............
C800415 ...............ALCMS Upgrade...................................................43 .......... 
C800417 ...............Lagoon 3 Bird Wires .............................................44 ..........



2  Port of Seattle 2Q 2012 Report

Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule Budget
C800420 ...............Additional Air f eld Mitigations at Tyee ..................45 ..........
C800426 ...............FIS Improvement - Short Term .............................46 ..........
C800451 ...............Doug Fox Site Improvement .................................47 ..........
C800455 ...............Concourse D Common Use Environment ............48 ........................................ 
C800459 ...............2011-2013 Roof Replacement Program ...............49 ..........
C800461 ...............IWTP Fiber Installation .........................................50 ..........
C800466 ...............South Satellite - Additional Gate Lobby ................51 ........................................ 
C800467 ...............PLB Replacement .................................................52 .......... 
C800472 ...............Exterior Gate Improvements ................................53 ..........
C800473 ...............CUSE at Ticket Counters/Gates - AR ..................54 ..........
C800474 ...............Airport Signage .....................................................55 .......... 
C800475 ...............Miscellaneous Building Improvements - AR.........56 ........................................
C800484 ...............Laptop Power In Concourses ...............................57 ..........
C800490 ...............New Window Wall Ticket Zone 1 ..........................58 ..........
C800492 ...............Convert Ticket Zone 3 Flow Thru .........................59 ..........
C800544 ...............NorthSTAR Program.............................................60 .......... 
C800556 ...............NorthSTAR North Satellite Renovations ..............61 ..........
Other Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C200007...............Highline School Noise Insulation ..........................62 .......... ...............
C200042 ...............Highline Community College Noise Insulation .....63 .......... ...............
C200048 ...............Home Insulation Retrof t .......................................64 ..........  ...............
C200093 ...............Single Family Home Sound Insulation .................65 .......... ...............
C800046 ...............Street Vacations  Des Moines Creek 1 ..............66 ........................................ ........................................
C800146 ...............RMU/Kiosk Concession Program ........................67 ........................................ 
C800150 ...............Burien Commercial Property Acquisition .............68 .......... ...............
C800154 ...............Tenant Reimbursement ........................................69 .......... 
C800482 ...............Rubber and Paint Removal Equipment ................70 ..........
C800498 ...............Snow Removal Equipment ...................................71 ..........
Seaport
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800165 ..............Seaport Security Grant Round 7 .........................72 ..........
C800183 ...............P91 Fender System Upgrade ...............................73 ..........

Port of Seattle 2Q 2012 Report  3

Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800264 ...............T-10 Interim Redevelopment.................................74 ..........
C800298 ...............T-91 Watermain Replacement ..............................75 ..........
C800349 ...............T-5 Crane Cable Reels .........................................76 ........................................ 
C800416 ...............T-18 Fender Replacement ....................................77 ..........
C800516 ...............SEA P-66 Apron Pile Wrap ..................................78 ..........
C800546 ...............Argo Yard Truck Roadway ....................................79 ..........

WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ..................80 ..........
E104324 ................Viaduct Construction Coordination ......................81 ..........
E104362 et al ........Street Vacations T-5/18/105 .................................82 ..........
E104559................T-18 Pile Cap Repair Pilot Project ........................83 ........................................ 
E104610 ................Underdock Inspections .........................................84 .......... 
Real Estate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800137 ...............FT C15 HVAC Improvements ...............................85 ..........
C800187 ...............RE Maintenance Shop Solutions..........................86 ..........
C800313 ...............P69 N Apron Corrosion Control ...........................87 ..........
Corporate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C101117 ................Flight Information Systems (FIMS) II ....................88 ..........
C800003...............Maximo Enterprise Implementation......................89 .......... ...................................
C800162 ...............ID Badge Replacement ........................................90 ..........
C800222 ...............Airline Activity Management .................................91 ..........
C800321 ...............Enterprise Project Cost Management ..................92 .......... ...................................
C800322 ...............Records and Document Management .................93 ........................................  ....................



4  Port of Seattle 2Q 2012 Report

Overall Project    Variance since
Statuslast report
CIP Number  Project Title             Page     Schedule  Budget
C800328 ...............Propworks Upgrade ..............................................94 .......... 
C800387 ...............Time Clock System ...............................................95 ........................................  ....................
C800392 ...............PeopleSoft Financial Upgrade ..............................96 ........................................  ....................
C800393 ...............Police Records Management System ..................97 ........................................  ....................
C800477 ...............CUSS Kiosk Expansion ........................................98 .......... ............... ....................
C800481 ...............CUSE Migration ....................................................99 .......... .............................. 
C800501 ...............Maintenance Planning System ............................100 ......... ............... ....................

Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Variance Status
Over Budget or Delayed Schedule
Under Budget or Ahead of Schedule
Potential Over Budget or Delayed Schedule
Variance Since Last Report
No Diamond  On Budget or On Schedule










Port of Seattle 2Q 2012 Report  5

SECOND QUARTER REPORT, 2012
3rd Runway Program
Status Snapshot
On Schedule
Project: C000683,       The 3rd Runway Program
On Budget
C001138, C001175,      constructed a new 8,500 foot long
13 Change Orders
C001331, C001751,      runway, connecting taxiways, and
Total Change Orders Amount:
C001760, C100172      related infrastructure.
$90,369
Budget: $920,415,659
Phase: Construction                       Budget/Costs Incurred
Start: 05/27/1997
1150
Completion: 12/31/2011
1100
1050
Significant Developments                    1000 Millions
950
The Port of Seattle Maintenance Building was demolished in April
2012. The remaining work includes RST property acquisition.        Dollars in 900850
800
Authorized  Forecasted Costs Incurred
Schedule
Maintenance Building Demolition project is in contract closeout.
Purchase of the RST property will occur in the summer of 2012.
2012 Contract Const. Costs
Budget
2
The project forecast is within the approved budget and authorization.
1.5
Change Order                          Millions 1
None this quarter                                      0.5
Dollars in 
0
Risks
Initial   Change   Spent
None                                        Orders
Budget Transfer                         Photo
To C102166 (Aeronautical Renewal/Replace)    $9,000,000



AIRPORT
6  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Rental Car Facility
Status Snapshot Prior Report
Delayed Schedule 1Q 12
Project:   C100266,     The program will construct a       Under Budget
C102167, C800032     consolidated rental car facility (RCF)  1,550 Change Orders
Budget: $419,306,000   for all rental car companies at the    Total Change Orders Amount:
Phase: Construction    airport, a bus maintenance facility    $13,884,840
Start: 02/24/1998        (BMF), and mitigation with the off-site
roadway improvements (ORI), plus
Completion: Spring 2012
purchase a fleet of buses.          Budget/Costs Incurred
Significant Developments                     430
420
The Consolidated Rental Car Facility officially opened May 17, 2012
Millions 410                                                                                    with almost 13,000 riders utilizing the new bus system the first day.
400
The rental car industry reported it was the smoothest transition they
390
have every experienced for a facility of this size. Reports came in the
industry and customers were pleased with the appearance of the       Dollars in 380
370
facility. The facility received Silver LEED certification and two
360
plaques are mounted on the 5th floor.
Authorized  Forecasted Costs Incurred
BMF construction is 100% complete.
ORI construction complete.
Construction Costs
Schedule
300
RCF opened May 17, 2012. Each project within the program has
250
now begun closing. Asset plans are being prepared for an initial
Millions  200
booking in mid-August.
150
100
Budget                             Dollars in  50
Customer Facility Charge revenues continue to increase slightly         0
each month, trending over $2,200,000 above projections. Forecasted        Initial Change Spent
Orders
cost to complete the program is $396,000,000, $23,300,000 under
the approved budget. Savings is anticipated on both ORI and BMF.
Photo
Change Order
149 change orders were issued this quarter in the amount of
$183,450



Port of Seattle 2Q 2012 Report  7

Risks
x For RCF: claims resolution; quality issues, and post opening work completion.
x For ORI: claims
x For BMF: claims and post opening work completion
Budget Transfers
$2,158,400 was drawn down from the budget in recognition of savings realized along with $856,000
removed to cover Expense.
Cost Growth of Construction
RCF Airport Wayfinding Signage and Curbside Modifications - MC-0316968 - Cumulative change
order percentage through this quarter increased by 1.8% to 21.3%. Primary reasons for these
changes are Main Terminal signage support and miscellaneous electrical.
Consolidated Rental Car Facility - Small Operator Build Out - MC-0317022 - Cumulative change
order percentage through this quarter is 0.3% ($2,300) associated with the installation of beam wraps
& conduit.
Consolidated Rental Car Facility Offsite Roadway Improvements and SR99 Bridge Seismic Upgrade
MC-0316568 - cumulative change order percentage through this quarter is increased by 2% to
35.3%. Primary reasons for these changes were associated with claim settlement for delays.
Bus Maintenance Facility - MC-0316730 - cumulative change order percentage through this quarter is
3.5%. Primary reasons for the changes this quarter are associated with boiler flue backpressure
corrections and splashguards on bus washing equipment.
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - On June 30, Commission authorized the
$32,000,000 suspension impact including a $6,973,300 budget increase and an increase in change
order limit from 10% to 18% requiring Commission notification. The current cumulative change order
percentage through this quarter is 3.99%.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - cumulative change order percentage through this 
quarter is 19.4%. Primary reason for changes is the removal of contaminated soils and associated
impacts. This work and the final contract reconciliation is complete.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  the cumulative change order percentage
through the quarter is at 170.5%. Primary reasons for changes are for additional contractor
management, estimating, scheduling and bidding effort for cost estimate reconciliation,
constructability reviews and value engineering beyond the extent of the original scope to validate
project costs and support the rental car companies and the Port on final approval of the project. This
work and the final contract reconciliation is complete.

AIRPORT
8  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Main Terminal Baggage Screening
Project:   C102163     This project creates automated      Status Snapshot Prior Report
Budget: $218,712,358   systems for explosive detection     Delayed Schedule 4Q 08
Phase: Close Out     screening of baggage for the north   Under Budget   4Q 09
Start: 09/24/2002        Main Terminal and South Satellite.    665 Change Orders
Completion: 02/13/2009  The systems will meet all security    Total Change Orders Amount:
requirements while reducing staffing   $51,165,622
and providing capacity for future
growth.                    Budget/Costs Incurred
Significant Developments                     235
The C-1 baggage handling/screening system has been placed into     230
revenue service for the Alaska Air Group. The C-1 Lid Replacement    Millions 225
and Repair work is complete. The only work remaining on this project    220
is the installation of new Direct Digital Controls (DDC) to indicate to     Dollars in 215
boiler room when pumps are off-line.                         210
Authorized   Forecasted  Costs Incurred
Schedule
The project was delayed approximately two years from the original
Construction Costs
completion date due to replacement of the original baggage
subcontractor, changing TSA requirements and other scope
200
changes. Turner Construction demobilized on May 31, 2009. The
150
GCCM construction contract with Turner Construction has been
closed. The remaining fire sprinkler and fire proofing work was          100   Millions
completed.
50
Dollars in 
Budget                              0
Initial    Change    Spent
Orders
The project forecast is within the approved budget and authorization.
Change Order                         Photo
665 Change Orders have been issued on this project.
Risks
None
Budget Transfers
None this quarter


Port of Seattle 2Q 2012 Report  9

Cost Growth of Construction
In 2006, the baggage handling system subcontractor was terminated as they were unable to meet the
project schedule requirements. The remaining work was rebid in the fall of 2006. Alaska Airlines
asked that we include the BHS work within the 2-step ticket counter project; which increased the
amount of BHS work in the bidding (attracting more competition), and eliminated the issues with
having two different BHS subcontractors in the same work area.












AIRPORT
10  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Water System Isolation Valve Upgrade-non AF
Status Snapshot
Delayed Schedule
Project:   C102334      This project replaces isolation     On Budget
Budget: $954,000       valves on the aging water       0 Change Orders
Phase: Construction     distribution system, necessary for   Total Change Orders Amount:
Start: 10/01/2010         isolating portions of the system in    $0
Completion: 10/31/2012   the event of breaks, leaks, or tieins
, in non-airfield (AF) locations.    Budget/Costs Incurred
1.2
Significant Developments                      1
0.8
The project is currently in construction.
MillionsDollars in     0.6
Schedule                             0.4
0.2
The schedule was extended to avoid operational impacts during the
busy holiday season, as previously reported. To minimize potential      0
Authorized       Forecasted      Costs Incurred
for operational impacts, the final sets of valves will be installed after
the busy summer travel season, which required an additional
schedule extension.
Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time
Budget Transfers
From C800469 (Water System Isolation Valve - Airfield)  $100,000



AIRPORT
Port of Seattle 2Q 2012 Report  11

SECOND QUARTER REPORT, 2012
Airfield Pavement Replacement
Status Snapshot
Project:   C102573      The project is intended to be a     On Schedule
Budget: $30,421,085     multi-year pavement replacement   On Budget
Phase: Construction     program to replace some of the    0 Change Orders
Start: 05/02/2010         worst pavement and joint seal on    Total Change Orders Amount:
Completion: 12/31/2016   the airfield.              $0
Budget/Costs Incurred
Significant Developments
40
Bids were opened on March 8, 2012. Gary Merlino Construction was
the low bidder.                                         30
Millions
20
Dollars in 
Schedule
Gary Merlino Construction began work in May 2012. The            10
construction work scheduled in 2012 will be the second phase of a
0
multi-year pavement replacement program performed from 2011 to
Authorized  Forecasted Costs Incurred
2015. Scoping for the 2013 construction work has begun.
Budget
2012 Construction Costs
The project forecast is within the approved budget.
7
Change Order                           6
None                                  Millions  5
4
Dollars in 
3
Risks
2
None this quarter.                                        1
0
Budget Transfers                             Initial Change Spent
Orders
None this quarter.



AIRPORT

12  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Loading Bridge Utilities
Status Snapshot Prior Report
Delayed Schedule     4Q 11
Project:   C800019   This project will upgrade all Port-       On Budget
owned loading bridges to the same
Budget: $12,883,000                         0 Change Orders
standards, including 400Hz power and
Phase: Design                            Total Change Orders Amount:
potable water. It will reduce air
Start: 06/28/2007                                 $0
emissions, improve energy efficiency
Completion: 2/28/2014 and save money for the airlines.      Budget/Costs Incurred
15
Significant Developments
A sole source justification document for the 400 Hz motor generators    Millions 10
has been prepared and sumbited for approval.
5
Schedule                            Dollars in 
As previously reported, the 400Hz equipment will now be provided      0
Authorized  Forecasted Costs Incurred
by the contractor. Sole source justification was requested; the design
completion and construction advertisment is dependent on this
approval.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
Airport Operations at certain gates could be impacted during the
construction phase of the project. The Port's power centers might
need to be upgraded to support the Pre-Conditioned Air, Electrical
Ground Support Equipment, and Loading Bridge Utilities projects.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 2Q 2012 Report  13

SECOND QUARTER REPORT, 2012
North Expressway Relocation
Project:   C800034
The project is a collaboration       Status Snapshot  Prior Report
Budget: $110,347,700    between the Port and Sound     Delayed Schedule 2Q 11
Phase: Construction     Transit. It reconstructs the North   On Budget
Start: 07/27/2004         Airport Expressway and brought    225 Change Orders
Completion: 07/31/2012   light rail to the Airport.         Total Change Orders Amount:
$8,314,360
Significant Developments
Budget/Costs Incurred
The work in the main contract for reconstruction of the North Airport
Expressway and light rail transit components is complete. The        115
intelligent transportation management system is complete. A final
110
contract to complete paving, landscaping, the north entry art          Millions
features, and other miscellaneous work is complete except for punch    105
list work and the first year plant establishment.
Dollars in 100
Schedule
95
The main contract reached substantial completion in August 2008         Authorized Forecasted Costs Incurred
and plant establishment was completed in December 2010. A
contract for final paving, landscaping, and reclamation is underway 
and is complete except for punch list work and the first year plant     Construction Costs
establishment period to be complete in mid-2012.
120
Budget                             100
Millions 80
The project forecast is within the approved budget and authorization.
60
Change Order                          40
Dollars in  20
Thirteen change orders were issued this quarter.
0
Initial    Change Order    Spent
Risks
None identified at this time.
Photo
Budget Transfers
None this quarter


AIRPORT
14  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Main Terminal South Low Voltage
Project:   C800061   This project covers the renewal and     Status Snapshot Prior Report
Budget: $1,925,000   replacement of low voltage (600 volts   Delayed Schedule 1Q 08
Phase: Design      and below) electrical distribution      On Budget
Start: 06/28/2007      equipment in the southern part of the    0 Change Orders
Total Change Orders Amount:
Completion: TBD    Main Terminal.
$0
Significant Developments
Budget/Costs Incurred
Due to project deferral and the possibility of changes in site
conditions and building codes, the design phase changed from 100%    2.5
to 90% complete. A new Project Notebook is under development to
2
address scope of work, schedule, and budget and will be presented    Millions 1.5
to the Investment Committee. A Service Directive is in development
so the Consultant can assist with specialized sections of Project        1
Notebook.                                     Dollars in 0.5
0
Schedule                               Authorized Forecasted Costs Incurred
The project was reactivated and is in the process of determining the
scope of work, schedule and final design budget.
Construction Costs
Budget                            Not Applicable
The project budget is being evaluated based on delays and scope
changes.                                    Photo
Change Order
None
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner. This area is a 24/7/365 operation. Sequencing of this work
is critical and electrical power has to be maintained without
interruptions.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 2Q 2012 Report  15

SECOND QUARTER REPORT, 2012
Airport Owned Gate Infrastructure
This project purchases and        Status Snapshot
Project:   C800105
replaces passenger loading bridges  On Schedule
Budget: $6,000,000
(PLB) at gates throughout the      On Budget
Phase: Construction                        0 Change Orders
Start: 07/24/2007         airport. The project is being
performed in phases.           Total Change Orders Amount:
Completion: 12/31/2011                       $0
Significant Developments                    Budget/Costs Incurred
On April 24, 2012, the Port of Seattle Commission authorized Port      6.5
Construction Services (PCS) to refurbish the PLB removed from
6
Gate S10 and install it in place of the existing Delta Air Lines owned    Millions
PLB at Gate S8. However, the PLB at S8 suffered a catastrophic      5.5
failure in late June 2012 and was out of service for 9 days. The Port
5
approved the diversion of one of the new PLBs manufactured for the    Dollars in 
Concourse D (under project C800467) to replace the existing bridge     4.5
Authorized  Forecasted Costs Incurred
at S8. The old S10 bridge will still be refurbished but will now be
provided to the Concourse D project in place of the new bridge
diverted to S8.
Construction Costs
Schedule                           Not Applicable
The project is currently on schedule.
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

16  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
C4 UPS System Improvements
Project:   C800107    Project will replace existing          Status Snapshot Prior Report
Budget: $2,336,000   Uninterruptible Power Supply (UPS)    Delayed Schedule 1Q 09
Phase: Construction  System, including batteries, with a new  On Budget
Start: 06/28/2007      new system located in the Airport      0 Change Orders
Completion: TBD     Combined Communications and      Total Change Orders Amount:
Command Center (C4).           $0
Significant Developments                    Budget/Costs Incurred
Due to project deferral and the possibility of changes in site
2.5
conditions and building codes, the design phase changed from 100%
to 90% complete. A new Project Notebook is under development to      2
address scope of work, schedule, and budget and will be presented    Millions 1.5
to the Investment Committee. A Service Directive is in development      1
so the Consultant can assist with specialized sections of Project       Dollars in 0.5
Notebook.
0
Authorized  Forecasted Costs Incurred
Schedule
The project was reactivated and is in the process of determining the
scope of work, schedule and final design budget.               Construction Costs
Not Applicable
Budget
The project budget is being evaluated based on delays and scope    Photo
changes.
Change Order
None
Risks
The C4 center is a 24/7/365 operation and sequencing of this work is
critical and electrical power has to be maintained without
interruptions. It is not known when the construction will proceed as 
this is specialized equipment and due to the complexity the new
system will require rigorous testing during the commissioning phase.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 2Q 2012 Report  17

SECOND QUARTER REPORT, 2012
Runway 16C/34C Panel/Joint Sealant
Replacement
Status Snapshot
The scope of work will remove and   On Schedule
Project:   C800112      replace the pavement and joint seal  On Budget
in areas on Runway 16C-34C.
Budget: $4,161,623                         0 Change Orders
Phase: Design                            Total Change Orders Amount:
Start: 02/26/2008                                 $0
Completion: 09/01/2012
Significant Developments                    Budget/Costs Incurred
Bid opening was on March 8, 2012. Gary Merlino Construction is the     6
low bidder. The intent of this contract is to coordinate this work with      5
an apron panel replacement project, an airline realignment project,      4
and a fuel hydrant installation project all with similar work and timing.    Millions
3
2
Schedule                            Dollars in  1
The overall construction contract started in May 2012 and the          0
replacement of runway panels is scheduled to begin in late July           Authorized  Forecasted Costs Incurred
2012.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order                         Photo
None this quarter
Risks
No risks have been identified at this time.
Budget Transfers
None this quarter



AIRPORT
18  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Concessions Unit Readiness Project
Project:   C800147      This project will upgrade         Status Snapshot Prior Report
Budget: $2,087,000      concession locations which were   Delayed Schedule    2Q 09
Phase: Construction     previously vacated or slated to be   On Budget
Start: 08/26/2008         vacated to Port standards for use    0 Change Orders
Completion: 06/30/2013   as specialty concession space.    Total Change Orders Amount:
$0
Significant Developments
This project received Commission authorization in September 2010   Budget/Costs Incurred
to design and build concession spaces in two locations. Design of
these two locations is complete. Commission authorized            2.5
design/construction of two additional locations on August 9, 2011.       2
Construction is anticipated to be complete by the end of the third       Millions 1.5
quarter 2012.                                        1
Dollars in 0.5
Schedule
0
The construction phase has been restructured and re-sequenced,        Authorized Forecasted Costs Incurred
with the intent to maximize the timing for new Concessions
opportunities. The project was put on hold until the prioritization
decisions were made by Aviation Business Development.         Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 2Q 2012 Report  19

SECOND QUARTER REPORT, 2012
Gina Marie Lindsey (GML) Arrivals Hall
Concessions
This project will provide a new retail  Status Snapshot  Prior Report
Project:   C800148      merchandising corridor in the Gina   Delayed Schedule 1Q 11
Marie Lindsey Arrivals Hall. The     On Budget
Budget: $1,033,000
project includes installing three      0 Change Orders
Phase: Design        Retail Merchandizing Units (RMUs)  Total Change Orders Amount:
Start: 11/20/2007         and providing utilities to a new      $0
Completion: 07/01/2012   approximate 25-seat restaurant
and bar.
Budget/Costs Incurred
Significant Developments
1.2
The design for utilities was previously completed in 2009 but put on      1
hold due to market conditions. Plans for the new food-beverage       Millions 0.8
concession will be reviewed by the Concessions group for viability      0.6
via a cost analysis to be performed later in 2012.                  0.4
Dollars in 0.2
Schedule                             0
Authorized  Forecasted Costs Incurred
As previously reported, the project schedule was delayed due to the
pending decision by the Business Development Group to proceed
with the concessionaire.
Construction Costs
Budget                            Not applicable
The project forecast is within the approved budget and authorization.  Photo
Change Order
None
Risks
Due to delay in schedule, bidding climate may change when the
project is bid and additional budget may be required.
Budget Transfers
None this quarter


AIRPORT
20  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
C60 - C61 BHS Modifications
Project:   C800168      The work planned under this      Status Snapshot
Budget: $10,969,000     project represents a critical      On Schedule
Phase: Design        component in providing improved   On Budget
Start: 06/01/2012         operational baggage in-line       0 Change Orders
Completion: 04/30/2014   screening at the south end of the   Total Change Orders Amount:
Airport and provide more baggage   $0
make-up capacity for airlines.
Budget/Costs Incurred
12
Significant Developments
10
The Port of Seattle Commission authorized design funding for the       8
project. The project team is currently working with the design
Millions
6
consultant to start design.
4
Dollars in   2
Schedule
0
The project is currently on schedule.                             Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to advertise for construction will    Not Applicable
be requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 2Q 2012 Report  21

SECOND QUARTER REPORT, 2012
Federal Inspection Services - New Primary
Inspection Booths
This project will replace existing     Status Snapshot  Prior Report
Project:   C800174      primary inspection booths for      Delayed Schedule 2Q 11
Customs and Border Protection in   On Budget
Budget: $2,000,000
the International Arrivals Federal    0 Change Orders
Phase: Construction     Inspection Services (FIS) facility in  Total Change Orders Amount:
Start: 07/27/2010         the South Satellite.             $0
Completion: 09/08/2011
Budget/Costs Incurred
Significant Developments
Defective signs are being replaced by the signage vendor.           2.5
2
Schedule                            Millions 1.5
The project is substantially complete. The current schedule for
1
completion of the replacement signs is by the end of the third quarter    Dollars in 0.5
2012.
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
Not Applicable
None
Risks                               Photo
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

22  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Common Use Lounge Remodel
Status Snapshot
On Schedule
Project:   C800203      This project will relocate the Port's   On Budget
Budget: $1,061,000      common-use lounge from the     9 Change Orders
Phase: Close Out      mezzanine level to the departure   Total Change Orders Amount:
Start: 03/01/2011         level of the South Satellite.        $32,782
Completion: 02/28/2012   Improvements consist of new
finishes, new furnishings and other  Budget/Costs Incurred
minor cosmetic improvements.
1.07
1.06
Significant Developments                     1.05 Millions
Project is in closeout awaiting asbuilts.                         1.04
1.03
1.02
Schedule
1.01   Dollars in 
Construction completed by the end of February 2012 and the lounge     1
opened on March 1, 2012.                                Authorized Forecasted Costs Incurred
Budget
The current project forecast is within the approved budget.         Construction Costs
Change Order                          0.6
Nine change orders have been issued.
Risks                                Millions 0.4
0.2
Project is forecasted to complete in current budget, but without much
remaining. If more soft costs hit the project than anticipated, we
could run over budget.                                  Dollars in  0
Initial    Change Order    Spent
Budget Transfers
None this quarter




AIRPORT
Port of Seattle 2Q 2012 Report  23

SECOND QUARTER REPORT, 2012
Terminal Escalators Modernization
Status Snapshot
On Schedule
On Budget
Project:   C800237      This project will replace 42        80 Change Orders
Budget: $37,789,259     escalators in the Main Terminal,    Total Change Orders Amount:
$4,354,729
Phase: Construction    Concourse B, and South Satellite.
In addition, two new escalators will
Start: 11/02/2007
be installed at the South Satellite.    Budget/Costs Incurred
Completion: 07/01/2013
60
50
Significant Developments
Millions 40
Eight new escalators at Concourse C and the South Satellite were      30
placed in service this quarter, for a total of 24. Replacement of four     20
escalators in the Main Terminal and two in the South Satellite are      Dollars in  10
expected to be in service in third quarter of 2012. Replacement of
0
the remaining Main Terminal and South Satellite escalators will           Authorized Forecasted   Costs
continue in multiple phases through second quarter of 2013.                         Incurred
Schedule                           Construction Costs
The project is currently on schedule.
20
Budget                             15
The project forecast is within the approved budget and authorization.   Millions
10
Change Order                          Dollars in  5
The most significant change orders this quarter involved the
0
recladding of the stairs next to the North and South Main Terminal          Initial  Change Order  Spent
train station escalators to be consistent in appearance with the
adjacent units. Other change orders were required to address
varying site conditions.
Risks
None identified at this time.
Budget Transfers
To C102066 (Art Pool)                    $233,000
To C102166 (Aeronautical Renewal/Replace)      $26,224


24  Port of Seattle 2Q 2012 Report

Cost of Construction Growth
Circumstances contributing to cost growth: Change orders/cost growth can be grouped into 4 primary
areas: 1) Electrical upgrades to address the condition of 40 year old wiring and electrical panels. 2)
Aesthetic upgrades to the escalators, associated cladding, and passageway under escalators. The
appearance of the escalators and cladding were upgraded to be consistent with the brighter, more
modern appearance in other newer areas of the terminal. Furthermore, the passageway under the
escalators were dark and poorly lit. 3) Rephasing of work due to operational concerns: The
sequencing of the escalator installations was re-phased to lessen the impacts on passenger
circulation and airport operations, and address unanticipated security concerns. 4) Varying site
conditions impacting hoisting plans for the escalators, escalator pit conditions/alignment to
accommodate new and wider units, and miscellaneous MEP items.
Measures taken to respond to these factors: 1) Electrical upgrades: As a design-build contract, the
RFP tasked the successful proposer to evaluate the condition of the electrical panels and wiring for
the 44 escalators included in the project. The Port concurred with the designers recommendation to
replace the electrical panels and wiring. 2) Aesthetic upgrades: Materials consistent with the newer
parts of the main terminal were used, such as high-impact glass balustrades, stainless steel cladding
on the sides of the escalators to replace the existing dark cladding, and construction of stainless steel
enclosures including lighting upgrades in the passageway under the escalators. These changes are
specific to the main terminal and are not anticipated in the other areas of the project. 3)RePhasing:
Subsequent discussions have occurred concerning other project areas with no planned rephasing.
Future potential acceleration or rephasing may occur depending on unforeseen operation conditions.
4) Greater investigation of the project site areas has been taken to anticipate varying conditions and
means to mitigate in advance of starting construction.






AIRPORT
Port of Seattle 2Q 2012 Report  25

SECOND QUARTER REPORT, 2012
Central Plant Pre-Conditioned Air
Project:   C800238     This project will provide a centralized  Status Snapshot Prior Report
Budget: $43,535,000    pre-conditioned air (PC-Air) plant,    Delayed Schedule 3Q 09
Phase: Construction    associated heating and cooling piping  On Budget
Start: 06/15/2009       systems, and jet bridge terminal air    95 Change Orders
Completion: 12/10/2012  handling units to serve airplanes with  Total Change Orders Amount:
heating and cooling while at the      $2,539,611
gates.
Significant Developments                    Budget/Costs Incurred
The contractor has finished installation of major equipment in the
PCAP. PC-Air equipment is installed at 29 of 73 total gates. Pipe and    50
electrical conduit installation continue at the Concourse C and North     40
Satellite.
30
in Millions 20
Schedule
Dollars  10
The original contract completion date was December 11, 2012. One
time extension of 37 days was approved. The contract completion      0
Authorized  Forecasted Costs Incurred
date is January 17, 2013.
Budget
Construction Costs
Negotiations with the contractor on potential change orders and
claims risk are in process. As negotiations proceed, any potential
30
budget issues will be identified. Current project forecast including
25
open claims exceeds approved budget and authorization by
Millions   20
approximately 10%. Staff will return to Commission in 3Q requesting
15
additional funding.
10
Dollars in    5
Change Order
0
Sixteen change orders were issued this quarter. There are 95 total          Initial  Change  Spent
change orders on this contract. The large change orders were issued            Orders
for piping and electrical site conflicts on the concourse and at the
gates.
Risks
There is budget risk based on the dollar amount of open potential
change orders and claims. There is schedule risk based on delays of
equipment delivery, incomplete submittals, and sequencing of
construction.
Budget Transfers
None this quarter
26  Port of Seattle 2Q 2012 ReportAIRPORT

SECOND QUARTER REPORT, 2012
Security Checkpoint Cameras
Project:   C800242      This project will install new       Status Snapshot Prior Report
Budget: $500,000       cameras to view passenger      Delayed Schedule 1Q 12
Phase: Construction     screening processes at passenger  On Budget
Start: 07/17/2011         security checkpoints.           0 Change Orders
Completion: 06/31/2012                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Installation is complete at Checkpoints #4, #2 and #3.
0.6
Schedule                             0.5
The project schedule was delayed by one month, as previously       Millions 0.4
0.3
Dollars in 
reported. Checkpoint #5 had to be redesigned due to TSA
reorganizing their equipment.                              0.2
0.1
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
None                                 Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None at this time





AIRPORT
Port of Seattle 2Q 2012 Report  27

SECOND QUARTER REPORT, 2012
Vertical Conveyance Modernization Program -
Aeronautical                        Status Snapshot Prior Report
Perform modernization on 8       Delayed Schedule 4Q 11
Project:   C800251      elevators: SSAF, MT-2, MT-6, MT-   Forecast Overrun
7, C-4, NSCF & 2 new elevators at   0 Change Orders
Budget: $9,773,150
S. Satelite, plus install cooling       Total Change Orders Amount:
Phase: Design        packages on 11 existing hydraulic   $0
Start: 10/25/2011         elevators throughout Main
Completion: 12/31/2014   Terminal.               Budget/Costs Incurred
14
12
Significant Developments
Millions 10
Phasing of the program has shown a critical link between             8
construction of two new elevators at South Satellite, which must be      6
completed prior to modernization efforts on SSB and SSC elevators.    Dollars in  4
2
Service Directives were executed for design of Phase I and for pre-
0
design of two new elevators at South Satellite, report due early May
Authorized  Forecasted Costs Incurred
2012. Installation of two new elevators moved to Phase I, and
elevators SSB, SSC & C4 moved to Phase II.
Schedule                           Construction Costs
Not Applicable
The project is scheduled to begin design in the second quarter of
2012; construction is scheduled to begin in the second quarter of
2013, with construction completion in the fourth quarter of 2014.
Budget
The project has been revised following Investment Committee (IC)
approval of revision of specific elevators in Phase I & Phase II. Still
awaiting IC approval of new budgets, then will proceed to
Commission for additional funding authorization. Authorization for
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order
None
Risks
Delays in siting two new elevators for South Satellite, currently
scheduled to be included in the second phase of the project.
Budget Transfers
None
28  Port of Seattle 2Q 2012 ReportAIRPORT

SECOND QUARTER REPORT, 2012
Parking System Replacement
Project:   C800253      This project replaces the current    Status Snapshot
Budget: $6,777,000      Parking Revenue Control System,   Delayed Schedule
Phase: Construction     which manages parking access    On Budget
Start: 04/06/2010         and revenue collection in the      0 Change Orders
Completion: 08/31/2012   Airport's Main Parking Garage.    Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Scheidt & Bachmann's (S&B) began installing the central processing
equipment and several field devices, with Lane Acceptance Tests      12
(LAT) being performed by a consultant, Kimley Horn.               10
Millions  8
Schedule                             6
4
Project advertisement and negotiations of the final contract took       Dollars in  2
longer than anticipated. S&B delayed the start of the Factory
0
Acceptance Test by a month due to a scheduled plant shutdown.
Authorized  Forecasted Costs Incurred
Failure of the system components to pass all aspects of the LAT,
and several quality control issues delayed the installation schedule. 
Completion of the system is now scheduled for August 2012.
Construction Costs
Budget                            None this quarter
The project forecast is within the approved budget and authorization.  Photo
Change Order
No change orders were issued this quarter.
Risks
This project schedule continues to be aggressive.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 2Q 2012 Report  29

SECOND QUARTER REPORT, 2012
Aircraft RON Parking USPS Site
Status Snapshot Prior Report
Delayed Schedule     1Q 11
Project: C800254        This project will prepare the site for
On Budget
Budget: $45,906,000     the construction of Hardstands for
1 Change Orders
Phase: Closeout       use as Remain Overnight (RON)
Total Change Orders Amount:
Start: 08/26/2008        parking of aircraft at the Air Mail
-$150,211
Center site.
Completion: 12/31/2014
Budget/Costs Incurred
Significant Developments
50
Demolition of the USPS building is complete and the project is in
40
contract closeout.
Millions 30
Schedule                             20
The Port of Seattle Commission approved the design authorization     Dollars in  10
of Cargo 5 Hardstand on March 27, 2012. Proposed construction of     0
a permanent hardstand is scheduled to begin the second quarter of       Authorized  Forecasted Costs Incurred
2013.
Budget                           2012 Contract Const. Costs
The project forecast is within the approved budget.
1
Change Order                           0.8
One change order was executed this quarter.                  Millions 0.6
0.4
Risks                                 0.2
Dollars in    0
None identified at this time.
Initial   Change   Spent
0.2
Orders
Budget Transfers
To C102165 (Aeronautical New Projects)       $5,800,000
Photo



AIRPORT

30  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Port-Owned Loading Bridge Renewal &
Replacement
Project:   C800267      This project will allow the Airport to  Status Snapshot
replace or refurbish Port-owned     On Schedule
Budget: $2,405,000
Passenger Loading Bridges (PLBs)  On Budget
Phase: Design        that have reached the end of their   0 Change Orders
Start: 02/28/2012         service life.                 Total Change Orders Amount:
Completion: 12/31/2014                       $0
Significant Developments                    Budget/Costs Incurred
This project was approved by the Commission in February 2012 and
originally included replacment of the PLB at N3 and refurbishment of     3
the PLBs at S3, S4 & S12. Removal of N3 from this scope and        2.5
replacement of S3 (instead of refurbishment) was approved by the     Millions 2
Commission in June 2012. In addition, the fixed walkway at S3 will     1.5
be replaced and the fixed walkway at S12 will be refurbished. No       1
increase in funding was required as a result of these changes.        Dollars in 0.5
0
Schedule                               Authorized Forecasted Costs Incurred
The project is currently on schedule.
Budget                            Construction Costs
Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 2Q 2012 Report  31

SECOND QUARTER REPORT, 2012
Stage 2 Mechanical Energy Implementation
Status Snapshot Prior Report
Delayed Schedule 1Q 12
Project:   C800268      This project will improve the energy  On Budget
Budget: $3,182,000.00    performance of the mechanical    0 Change Orders
Phase: Planning       infrastructure systems at the     Total Change Orders Amount:
Start: 10/01/2011         Airport.                    $0
Completion: 02/25/2013
Budget/Costs Incurred
3
Significant Developments                     2.5
2
The contract documents have been finalized and forwarded to the     Millions
1.5
State GA. University Mechanical Contractors (UMC) is prepared to
1
start the design effort and take part in the coordination with other       Dollars in 
projects that are happening in the Terminal building.                0.5
0
Authorized  Forecasted Costs Incurred
Schedule
The schedule was delayed by three months during the contract
document review, as previously reported.
Construction Costs
Not Applicable
Budget
The forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

32  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
8th Floor Weatherproofing
Status Snapshot Prior Report
Delayed Schedule 1Q 12
Project:   C800274      This project includes removal and   On Budget
Budget: $10,050,000     replacement of the floor covering   0 Change Orders
Phase: Construction     system on the 8th floor of the STIA  Total Change Orders Amount:
Start: 03/23/2010         parking garage and repair or       $0
Completion: 12/31/2013   replacement of expansion joints
and flashings.
Budget/Costs Incurred
Significant Developments                     15
The Port's contractor, PCL Construction completed the submittal
process, received a notice to proceed, mobilized and began          10
construction. The Port has requested a two year construction
Millions
schedule, which would extend the completion to the end of 2013.       5
Dollars in 
Schedule                             0
Authorized  Forecasted Costs Incurred
The current schedule is for project completion at the end of 2013.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
7
Change Order                           6
No change orders were issued this quarter.                    Millions 5
4
3
Risks
Dollars in   2
This is a weather-dependent project.                          1
0
Budget Transfers                             Initial Change Order Spent
None this quarter
Photo



AIRPORT
Port of Seattle 2Q 2012 Report  33

SECOND QUARTER REPORT, 2012
Common Use Equipment Expansion (CUSE)
Project:   C800276      This project installs flexible       Status Snapshot
Budget: $2,581,000      passenger processing         On Schedule
Phase: Construction     infrastructure and equipment at the  On Budget
Start: 09/01/2009         airline gates at some South       0 Change Orders
Completion: 09/30/2012   Satellite gates.            Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
3
The contractor has begun work on site and is schedule to relocate
2.5
two gate podiums per week thru August 2012.                 Millions  2
Schedule                            Dollars in  1.5
1
The project schedule anticipates construction completion by the end
0.5
of third quarter 2012.
0
Authorized       Forecasted      Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
None                                   0.7
0.6
Risks                               Millions 0.5
0.4
None identified at this time                                Dollars in 
0.3
0.2
Budget Transfers                          0.1
None this quarter.                                       0
Initial        Change Orders        Spent




AIRPORT
34  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Two New CTE Freight Elevators
Status Snapshot
Delayed Schedule
Project:   C800334      Provide two new freight elevators   Forecast Overrun
Budget: $6,664,000      to support concession operations in  0 Change Orders
Phase: Design        the Central Terminal/Pacific      Total Change Orders Amount:
Start: 08/05/2011         Marketplace.                $0
Completion: 07/31/2014
Budget/Costs Incurred
10
Significant Developments
8
The project design commenced third quarter 2011. Currently in       Millions 6
100% design. Interferences with ongoing Pre-Conditioned Air Project
4
and Alaska Air Group (AAG) relocation program caused scoping
changes and redesign efforts.                             Dollars in  2
0
Schedule                               Authorized Forecasted Costs Incurred
The project is scheduled to complete design in third quarter of 2012.
Construction is anticipated to commence in fourth quarter of 2012.
The project is now anticipating a one year delay due to scope       Construction Costs
changes included in the redesign efforts, and delays in reviews.      Not Applicable
Budget
The project forecast is increased due to the redesign. Authorization
of construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order
None
Risks
There is a potential risk due to unknown conditions where the freight
elevator foundations will be constructed, i.e., outside of the Central
Terminal building envelope. Installation and relocation of grease
interceptors will require significant coordination during construction
with Horizon Air and their current use of the site for their ground
service equipment.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 2Q 2012 Report  35

SECOND QUARTER REPORT, 2012
Electrical Ground Support Equipment (EGSE)
Electrical Charge Stations                Status Snapshot Prior Report
Delayed Schedule 1Q 12
On Budget
Airport-wide electrical charging     0 Change Orders
Project:   C800335      system for electrical ground       Total Change Orders Amount:
Budget: $30,198,000     support equipment (EGSE) at the   $0
Phase: Design        Concourses and the North and
Start: 10/26/2010         South Satellites.
Completion: 09/30/2014                       Budget/Costs Incurred
Significant Developments
Design is split into three parts as follows: 1) Install 40 demonstration      35
charge stations on Concourse C2 for Horizon Airlines - 100% Issue      30
for Construction Documents completed and chargers have been     Millions  25
Dollars in 
20
received. PCS is in process of mobilizing to install these chargers by
15
October 2012; 2) Phase I includes balance of Concourse C charge
10
stations, Concourse D and North Satellite - Service Directive now
5
executed and design is proceeding and chargers are on order; and      0
Authorized       Forecasted      Costs Incurred
3) Phase II includes Concourse A, Concourse B and South Satellite -
Service Directive is with CPO for review and expect that it will be
executed in August 2012.
Construction Costs
Schedule                           Not Applicable
Current plan is to complete implementation of demonstration charge
station phase by October 2012, Phase I by March 2013, and Phase
II by the end of 2014.
Budget
The project forecast is within the approved budget. Authorization for
the construction funding and authority to advertise for construction
will be requested when the design and bid documents are
completed.
Change Order
None



36  Port of Seattle 2Q 2012 Report

Risks
Coordinate with other airfield projects and Airline Gate Realignment program. Budget and schedule
may impact project implementation and completion.
Budget Transfers
To C102165 (Aeronautical New Projects)        $502,000












AIRPORT
Port of Seattle 2Q 2012 Report  37

SECOND QUARTER REPORT, 2012
Claim Device 14 & Lower Inbound
Project:   C800374      This project will replace the slope-   Status Snapshot
Budget: $3,900,000      plate bag claim device 14 and     On Schedule
Phase: Design        associated controls, in addition to   On Budget
Start: 04/01/2011         removing the lower feed conveyor   0 Change Orders
Completion: 05/31/2012   and replacing it with a new      Total Change Orders Amount:
overhead feed.               $0
Budget/Costs Incurred
5
Significant Developments
4
The major construction contract was bid and awarded to MD Moore
Company. Contractor is currently working towards a notice to        Millions 3
proceed. Construction is expected to start in September 2012.         2
Dollars in   1
Schedule
0
The project is currently on schedule.                             Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to award for construction was
1.2
requested.
1
Change Order                          Millions 0.8
0.6
None
0.4
Dollars in   0.2
Risks
0
None identified at this time.                                      Initial  Change  Spent
Orders
Budget Transfers
None this quarter



AIRPORT
38  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Baggage Handling System (C22-C1, MK1, and
Status Snapshot
TC3)                          On Schedule
This project will replace the ticket    On Budget
Project:   C800382      counter (TC3) conveyors and      0 Change Orders
declines, reroute the conveyors of   Total Change Orders Amount:
Budget: $4,750,000
the C-22 system and connect it to   $0
Phase: Construction     the C-1 screening system, replace
Start: 03/01/2011         the existing makeup (MK1) device,  Budget/Costs Incurred
Completion: 05/31/2013   and install a new odd size baggage
6
system.
5
Millions  4
Significant Developments                     3
2
The major construction contract was executed with MD Moore       Dollars in  1
Company. Construction is currently ongoing. All conveyor demolition
0
has been complete. The new conveyor equipment will be arriving for      Authorized Forecasted  Costs
installation in July.                                                            Incurred
Schedule                           Construction Costs
The project is currently on schedule.
2
Budget                              1.5
The project forecast is within the approved budget. Authorization of     Millions
1
construction funding and authority to award for construction have
been requested.                                    Dollars in  0.5
0
Change Order
Initial   Change   Spent
None                                         Orders
Risks
None identified at this time
Budget Transfers
To C800411 (Terminal Realignment)        $585,000


AIRPORT
Port of Seattle 2Q 2012 Report  39

SECOND QUARTER REPORT, 2012
RW16C/34C Reconstruction Design
Status Snapshot
On Schedule
Project:   C800406      This project will produce the 60%   On Budget
Budget: $669,000       design for the runway 16C/34C    0 Change Orders
Phase: Design        reconstruction. The design will    Total Change Orders Amount:
Start: 05/04/2010         include utilities, runway status      $0
Completion: TBD       lights, and other scope items
related to the project.            Budget/Costs Incurred
Significant Developments                     0.8
The 60% design was issued in December 2010. Incorporation of       0.6
comments on the 60% design work has been completed.          Millions
0.4
Schedule                            Dollars in 0.2
Staff will return to Commission for authorization of the remaining
0
design funds in late 2014 or early 2015. The forecast will be             Authorized  Forecasted Costs Incurred
reassessed when staff returns to the Commission for authorization of
the final design funds.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

40  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
South Satellite Concessions Project
Status Snapshot Prior Report
Delayed Schedule 3Q 11
Project:   C800412      This project will demolish and      On Budget
Budget: $2,020,200      relocate the existing duty free shop,  0 Change Orders
Phase: Design        electric/communications to support  Total Change Orders Amount:
Start: 01/01/2011         a temporary duty free location, and   $0
Completion: 03/31/2013   construct a new food and beverage
shell space in the South Satellite at
Sea-Tac Airport.
Budget/Costs Incurred
Significant Developments                     2.5
2
The project is currently being advertised for bids, which are
scheduled to be opened on July 17, 2012.                     Millions 1.5
1
Schedule                            Dollars in 0.5
As previously reported, the design concept alternatives required
0
more extensive review than anticipated. The new concept allows the       Authorized Forecasted Costs Incurred
existing duty free to remain operational during construction, but
requires a longer construction period.
Construction Costs
Budget
Not Applicable
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
This project schedule is tied closely to the Duty Free Request for
Proposal.
Budget Transfers
From C800153 (Non-Aero Renewal/Replacement)   $147,461


AIRPORT
Port of Seattle 2Q 2012 Report  41

SECOND QUARTER REPORT, 2012
Access Control Door Additions
Project:   C800414      This project will provide biometric   Status Snapshot
Budget: $1,800,000      access controls and security     Delayed Schedule
Phase: Design        cameras at airport terminal doors.   On Budget
Start: 09/27/2011                                 0 Change Orders
Completion: 06/30/2013                       Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
There was only one constuction bidder in May and it was 48% above
the engineer's cost estimate, so the project is being redesigned and      2
will be rebid in October. The work at the North Satellite will be
1.5
removed from this project and added to the NorthSTAR project.       Millions 1
Schedule                             0.5
Dollars in 
The 60% redesign documents were completed in June and the 90%     0
documents are scheduled for completion in August.                  Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
A portion of the scope and budget for the North Satellite scope of     Not Applicable
work will be transferred to the NorthSTAR project next quarter.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT
42  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Airfield Lighting Control and Monitoring System
Status Snapshot
(ALCMS) Upgrades                  On Schedule
Provide modifications to the Airfield   On Budget
Project:   C800415      Lighting Control and Monitoring    0 Change Orders
System to update, enhance and    Total Change Orders Amount:
Budget: $2,129,144
stabilize the system to meet the     $0
Phase: Construction     latest FAA specifications.
Start: 01/01/2011                                Budget/Costs Incurred
Completion: 12/31/2014
2.5
Significant Developments                      2
New single mode fiber optic cable in airfield has been installed and     Millions 1.5
tested. Back-up airfield lighting vault 55-foot tower was installed to       1
raise antenna. The antenna is operational.                     Dollars in 0.5
0
Schedule                               Authorized Forecasted Costs Incurred
The project is currently on schedule.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
None this quarter
Risks
Coordination with on-going airfield operations is a consideration.
The Port is also working to eliminate unplanned outages when
transitioning from the older computer platform to the one.
Budget Transfers
None this quarter.



AIRPORT

Port of Seattle 2Q 2012 Report  43

SECOND QUARTER REPORT, 2012
Lagoon 3 Bird Wires
Status Snapshot
On Schedule
Project:   C800417      This project will reduce access by   On Budget
Budget: $1,833,000      waterfowl to the industrial       0 Change Orders
Phase: Construction     wastewater system Lagoon 3,     Total Change Orders Amount:
Start: 10/11/2011         which is located near the south end  $0
Completion: 10/31/2012   of the airfield.
Budget/Costs Incurred
2
Significant Developments
1.5
The project advertised for construction in March 2012.              Millions
1
Schedule                            Dollars in 0.5
Contract bid opening occurred in April 2012 with construction starting
0
in the summer of 2012.                                    Authorized Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.              Construction Costs
Change Order                           1
None this quarter                                       0.8
Millions  0.6
Dollars in 
Risks                                 0.4
No risks have been identified at this time.                        0.2
0
Budget Transfers                             Initial Change Spent
Orders
None this quarter
Photo



AIRPORT
44  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Additional Airfield Mitigation at Tyee
Status Snapshot
Project:   C800420      The project will design and       On Schedule
Budget: $800,000       complete the Tyee Golf Course    On Budget
Phase: Close Out      Area Mitigation which includes    5 Change Orders
Start: 02/08/2011         removing a culvert, new wetland    Total Change Orders Amount:
Completion: 03/30/2012   planting, updating existing wetlands  $15,604.00
to environmental permit standards,
and installing a temporary irrigation  Budget/Costs Incurred
system.
1
Significant Developments                     0.8
Substantial completion was issued on April 19, 2012.              Millions 0.6
0.4
Schedule                            Dollars in 0.2
The project is complete and is in contract closeout.                 0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
0.4
Five change orders were executed this quarter. The contract is in
closeout.                                            0.3
Millions 0.2
Risks
0.1
None identified at this time.                                 Dollars in  0
Initial    Change Order    Spent
Budget Transfers                          0.1
None this quarter
Photo


AIRPORT

Port of Seattle 2Q 2012 Report  45

SECOND QUARTER REPORT, 2012
Federal Inspection Service Improvements -
Status Snapshot
Short Term                        On Schedule
Short Term Improvements to the    On Budget
Project:   C800426      Federal Inspection Service area at   0 Change Orders
the South Satellite to improve      Total Change Orders Amount:
Budget: $1,041,000
through put and improve conditions  $0
Phase: Design        for passengers waiting in the
Start: 04/01/2012         International Corridor prior to      Budget/Costs Incurred
Completion: 05/31/2013   Primary Inspection.
1.2
1
Significant Developments
Millions 0.8
0.6
Dollars in 
Project notebook has been approved and authorization for design is
scheduled for July 24, 2012. Service Directive to design consultant     0.4
is in progress.                                           0.2
0
Schedule                               Authorized Forecasted Costs Incurred
The project schedule for the revised scope is in its early phases, but
currently on track.
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
To C102166 (Aeronautical Renewal/Replacement)   $341,000


AIRPORT

46  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Doug Fox Lot Service Upgrades
Project:   C800451      Construct a new drainage system,   Status Snapshot
Budget: $6,073,000      asphalt resurfacing, improved lot   On Schedule
Phase: Design        lighting, new or renovated building,  On Budget
Start: 02/01/2012         and road signage to improve lot     0 Change Orders
Completion: 12/31/2013   appearance, function, and revenue  Total Change Orders Amount:
generation.                  $0
Budget/Costs Incurred
Significant Developments
8
In the process of evaluating building renovation versus constructing
6
a new building; the type and location of road signage is being         Millions
evaluated; design of the other improvements is in progress.           4
Schedule                            Dollars in  2
The project is currently on schedule.                           0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
From C800548 (Doug Fox Lot Service Upgrades)   $5,045,000




AIRPORT
Port of Seattle 2Q 2012 Report  47

SECOND QUARTER REPORT, 2012
Concourse D Common Use Environment
Status Snapshot Prior Report
Project:   C800455      This project installs a common-use  Delayed Schedule 3Q 11
Budget: $4,250,000      environment at all gates on      On Budget
Phase: Construction     Concourse D. Scope includes new  0 Change Orders
Start: 03/01/2011         communications infrastructure,     Total Change Orders Amount:
Completion: 12/31/2012   casework built to a new Airport    $0
standard, new carpet, wall
coverings and task lighting.       Budget/Costs Incurred
5
Significant Developments
4
The construction contract has been awarded and the Contractor is     Millions 3
working on shop drawings for new casework as a long lead item.
2
Schedule                            Dollars in  1
Schedule milestone dates are included in the general contractor's       0
construction documents that will ensure work is accomplished in time       Authorized  Forecasted Costs Incurred
to facilitate the airline realignment project milestones.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.
1.5
Change Order
1
None                                  Millions
0.5
Risks                                Dollars in 
Despite inclusion of the schedule milestones referenced above, the
0
contractor is going to be challenged to keep the project on schedule         Initial  Change  Spent
due to the long lead times for casework fabrication.                         Orders
Budget Transfers
None this quarter



AIRPORT
48  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
2011-2013 Roof Replacement Program
Project:   C800459      This project will remove and      Status Snapshot
Budget: $4,777,000      replace the roofing systems on the  On Schedule
Phase: Design        fire station and north end of the    On Budget
Start: 07/01/2011         main terminal.                0 Change Orders
Completion: 10/31/2013                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Design of the main terminal roof is underway.
6
The Fire Station contractor is working on pre-NTP submittals.          5
Millions  4
Schedule                             3
2
The project is currently one week behind schedule while            Dollars in  1
the contractor works on their pre-NTP submittals, however, the final
completion date of October 2013 is still on schedule.                0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization for
construction funding and authority to award for construction will be    Construction Costs
requested when the design and bid documents are completed.
0.5
Change Order                           0.4
None                                  Millions 0.3
0.2
Risks                                Dollars in  0.1
None at this time                                         0
Initial   Change   Spent
Budget Transfers                                Orders
None this quarter



AIRPORT
Port of Seattle 2Q 2012 Report  49

SECOND QUARTER REPORT, 2012
Industrial Waste Treatment Plant (IWTP) Fiber
Installation
Install new Single Mode Fiber cable
Project:   C800461      from Main Terminal to IWTP and    Status Snapshot
Gate E-45.                 On Schedule
Budget: $514,000
On Budget
Phase: Design                            0 Change Orders
Start: 03/01/2012                                 Total Change Orders Amount:
Completion: 09/30/2012                       $0
Significant Developments                    Budget/Costs Incurred
The Fiber Optic Cable was ordered. Formed and poured equipment
pad for new termination cabinet near the Alaska Hangar.            0.6
0.5
Schedule                            Millions 0.4
0.3
The design is approximately one month behind schedule, however,
this delay will be recovered in construction.                      0.2
Dollars in 0.1
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
None                                 Not Applicable
Risks
None identified at this time. However, this will require a permit from
the City of SeaTac and they may impose some screening
requirements, as a portion of the work area is visible from S. 188th
Street.
Budget Transfers
None this quarter.



AIRPORT
50  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
South Satellite - Additional Gate Lobby
Status Snapshot Prior Report
Project:   C800466      Demolition of glass partitions,      Delayed Schedule 3Q 11
Budget: $1,344,000      restrooms, relocation of gate     On Budget
Phase: Design        podiums new flooring, ceilings and  0 Change Orders
Start: 11/01/2010         infrastucture to provide additional    Total Change Orders Amount:
Completion: 03/31/2013   gate lobby in the South Satellite.   $0
Significant Developments
This project is currently out for bids as one major contract in        Budget/Costs Incurred
conjunction with the South Satellite Concessions Projects
(C800412). Bids are scheduled to be opened on July 17, 2012.
1.5
Schedule
1
As previously reported, the project delay was caused by delayed
design negotiations and contracting. Additionally, a longer design      in Millions
0.5
period is required due to dependency on the South Satellite          Dollars 
Concessions Project (C800412).
0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
Not Applicable
None
Risks
This project is tied closely to the Duty Free RFP in that this project is
closely aligned with the South Satellite Concessions Project.
Budget Transfers
To C102165 (Aeronautical New Projects)         $87,000


AIRPORT

Port of Seattle 2Q 2012 Report  51

SECOND QUARTER REPORT, 2012
Passenger Loading Bridge Replacement
Project:   C800467      This project entails Passenger     Status Snapshot
Budget: $14,874,000     Loading Bridge (PLB)         On Schedule
Phase: Design        replacements associated with the   On Budget
Start: 04/12/2011         one-time airline realignment (AR).   0 Change Orders
Completion: 09/30/2013   The work will take place at      Total Change Orders Amount:
Concourse D, Concourse B and    $0
North Satellite.
Significant Developments
Budget/Costs Incurred
Concourse D was awarded to PCL with work scheduled to
commence in August 2012. The Concourse B scope of work went
20
out to bid on June 28, 2012 with bids due on July 24, 2012.
15
One of the PLBs for Concourse D has been diverted to Gate S8.      Millions
10
The PLB removed from S10 last December will be refurbished and
installed in place of the diverted PLB.                          Dollars in  5
0
The PLB work at the North Satellite is currently under review and if it
Authorized  Forecasted Costs Incurred
continues it is tentatively scheduled to begin in second quarter of
2013 and continue through the end of second quarter of 2014.
Schedule                           Construction Costs
The project is currently on schedule. Commission approval for each      2
phase is being requested separately.
1.5
Budget                             Millions
1
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will      Dollars in  0.5
be requested when the design and bid documents are completed.        0
Initial   Change   Spent
Orders
Change Order
None
Risks
None identified at this time.
Budget Transfers
From C800475 (Miscellaneous Building Improvements)  $24,000

AIRPORT
52  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Exterior Gate Improvements (Airline
Realignment)
This project will install new fuel      Status Snapshot
Project:   C800472      hydrant pits and aircraft docking    On Schedule
systems at exterior gates for the     On Budget
Budget: $4,064,000
airline reallocation program.        0 Change Orders
Phase: Design                            Total Change Orders Amount:
Start: 06/01/2011                                 $0
Completion: 10/31/2012
Budget/Costs Incurred
Significant Developments                      5
The project is in construction.                                 4
Millions  3
Schedule
2
The project is currently on schedule.                          Dollars in  1
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None                                 Not Applicable
Risks
If the fuel system lease amendment is not finalized, it could limit the
use of the new fuel hydrants.
Budget Transfers
To C800411 (Terminal Realignment)         $400,000




AIRPORT

Port of Seattle 2Q 2012 Report  53

SECOND QUARTER REPORT, 2012
CUSE at Gates & Ticket Counters- Airline
Realignment
Provide common use equipment,    Status Snapshot
Project:   C800473      casework and infrastructure at     On Schedule
gates and ticket counters for the     On Budget
Budget: $2,371,000
Airline Realignment program.      0 Change Orders
Phase: Design                            Total Change Orders Amount:
Start: 04/02/2012                                 $0
Completion: 12/20/2012
Budget/Costs Incurred
Significant Developments
100% design documents for Concourse B CUSE were completed.     2.5
2
Schedule                            Millions 1.5
The project is currently on schedule.
1
Dollars in 0.5
Budget
0
The project forecast is within the approved budget. Authorization of
Authorized  Forecasted Costs Incurred
construction funding and authority to advertise for construction was
approved in July.
Construction Costs
Change Order
Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None




AIRPORT

54  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Airport Signage (Airline Realignment)
Project:   C800474      The project will provide airport     Status Snapshot
Budget: $646,000       directional signage for the airline   On Schedule
Phase: Design        realignment program.         On Budget
Start: 06/01/2011                                 0 Change Orders
Completion: 04/30/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
No significant developments this quarter.                       0.8
0.6
Schedule                            Millions
0.4
The project is currently on schedule.
0.2
Budget                             Dollars in 
0
The project forecast is within the approved budget. Authorization of
Authorized  Forecasted Costs Incurred
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order                         Construction Costs
Not Applicable
None this quarter
Risks
None this quarter
Budget Transfers
None this quarter




AIRPORT

Port of Seattle 2Q 2012 Report  55

SECOND QUARTER REPORT, 2012
Miscellaneous Building Improvements (Airline
Realignment)
Status Snapshot
Project:   C800475      This project will install a new ramp   Delayed Schedule
for passenger access to regional    On Budget
Budget: $7,898,000
aircraft on Concourse A for the     0 Change Orders
Phase: Design        Airline Realignment program.     Total Change Orders Amount:
Start: 11/01/2011                                 $0
Completion: 07/31/2013
Budget/Costs Incurred
10
Significant Developments
8
The 30% design of the passenger ramp was reviewed by the project
6
stakeholders.                                       Millions
4
Schedule                            Dollars in  2
Due to a delay in final agreement on gate assignments for the         0
regional aircraft, the project design start was delayed and the             Authorized  Forecasted Costs Incurred
construction completion will now be July 2013.
Budget                            Construction Costs
The project forecast is within the approved budget. Authorization of   Not Applicable
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order
None
Risks
If the aircraft assignments at the gates changes, the ramp would
need to be in a different location.
Budget Transfers
To C800467 (Passanger Loading Bridge Replacement)  $24,000


AIRPORT

56  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Laptop Power in Concourses
Project:   C800484      This project adds additional       Status Snapshot
Budget: $2,020,000      charging opportunities for personal  On Schedule
Phase: Planning       electronic devices at several     On Budget
Start: 6/26/12           strategic locations throughout the    0 Change Orders
Completion: 12/2013     airport terminal.            Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
2.5
The revised project notebook has been approved and authorization
for design was authorized in June 2012.                       2
Millions 1.5
Schedule
1
The project is currently on schedule.                         Dollars in 0.5
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.    Construction Costs
Not Applicable
Change Order
None
Risks
No risks identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 2Q 2012 Report  57

SECOND QUARTER REPORT, 2012
New Window Wall Ticket Zone 1
Project:   C800490      This project will install new       Status Snapshot
Budget: $4,025,000      common use ticket counters and   On Schedule
Phase: Design        new baggage system along the    On Budget
Start: 07/01/2012         window wall                 0 Change Orders
Completion: 09/30/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
5
A design contract will be executed in third quarter.
4
Schedule                            Millions 3
The project is scheduled to bid a major contract in January 2013       2
Dollars in   1
Budget                             0
The project forecast is within the approved budget. Authorization of        Authorized  Forecasted Costs Incurred
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Construction Costs
Change Order                         Not Applicable
None.
Risks
The project is on an accelerated design and construction schedule.
Budget Transfers
None this quarter.




AIRPORT
58  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Convert Ticket Zone 3 Flow Thru
Project:   C800492      This project will convert the Zone 3  Status Snapshot
Budget: $13,000,000     Ticketing Area to a flow through    On Schedule
Phase: Design        concept.               On Budget
Start: 08/07/2012                                 0 Change Orders
Completion: 10/31/2013                       Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
14
The project went to MII for approval with results due on July 20,
12
2012. The project is going to Commission for authorization in third
Millions 10
quarter 2012. Delta is moving ahead with the deisgn of their new       8
ATO space and the Zone 3 flow through at their own risk.            6
Dollars in   4
Schedule                             2
0
The project is currently on schedule.
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget. Authorization of   Construction Costs
construction funding and authority to advertise for construction will    Not Applicable
be requested when the design and bid documents are completed.
Change Order
None
Risks
Three other projects must take place before the work at Zone 3 can
commence.
Budget Transfers
None this quarter


AIRPORT

Port of Seattle 2Q 2012 Report  59

SECOND QUARTER REPORT, 2012
NorthSTAR Program
Status Snapshot
On Schedule
Project:   C800544      For all programmatic project      On Budget
Budget: $13,000,000     management and project controls   0 Change Orders
Phase: Design        costs for the NorthSTAR program   Total Change Orders Amount:
Start: 04/05/2012         consisting of five capital projects    $0
Completion: 12/31/2018   that represents a unique
partnership between the Port and   Budget/Costs Incurred
Alaska Airlines.
15
Significant Developments
10
The Port and Alaska Airline reached agreement on April 5, 2012 with   Millions
the Port issuing a Letter of Agreement. The program consists of six
5
CIP's. Preliminary budgets have been developed and Status 1 and 2   Dollars in 
forms have been approved by the Investment Committee for most
0
projects. The preliminary program notebook is in its final review for
Authorized  Forecasted Costs Incurred
Alaska's and the Investment Committee's approval.
Schedule                           Construction Costs
Program Management and Program Controls Consultant under     Not Applicable
contract by August. Preliminary program schedule (various projects);
design begins late 2013 into 2014, construction begins from late
2013 through fall 2014, completion winter 2016 and closeout 2018.
Each project schedule will be reported on separately.
Budget
$13,000,000 to manage a program of $285 to approximately
$300,000,000 including the five capital projects.
Change Order
None
Risks
The Airline Relocation project schedule changes potentially impacts
the program schedule. Alaska concurence at specific milestones is 
critical to the program moving forward. Consultant negotiation is
critical to getting resources on board to begin moving the program
forward.
Budget Transfers
None this quarter

AIRPORT
60  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
NorthSTAR NSAT Renovation
Project:   C800556      Renovation of the North Satellite    Status Snapshot
Budget: $194,300,000    building, including STS station    On Schedule
Phase: Design        "refresh", ramp level, Concourse   On Budget
Start: 7/24/2012          level, and new rooftop airline      0 Change Orders
Completion: 12/31/2016   lounge.                Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
250
The project will go to Commission for authorization of design in July
2012.                                        200
Millions 150
Schedule
100
The project is currently on schedule.                         Dollars in  50
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.    Construction Costs
Not Applicable
Change Order
None.
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 2Q 2012 Report  61

SECOND QUARTER REPORT, 2012
Highline School Noise Insulation
Status Snapshot Prior Report
Delayed Schedule 4Q 10
Project:   C200007      Highline School Insulation        On Budget
Budget: $101,797,000    Agreement will provide funding for  0 Change Orders
Phase: Construction     sound mitigation for 15 schools that  Total Change Orders Amount:
Start: 03/23/1999         are impacted by aircraft noise from   $0
Completion: 11/30/2021   Sea-Tac Airport.
Budget/Costs Incurred
Significant Developments
120
The insulation of seven schools has been completed and no more
100
are scheduled until Olympic is closed in 2013 and continuing through
80
2030. Olympic will be closed, however it is eligible for funds if the      Millions
60
square footage of other built schools increases to accommodate
40
displaced students from Olympic.                          Dollars in  20
0
Schedule
Authorized  Forecasted Costs Incurred
Port funding is authorized and will be available when the matching
funds are provided by the FAA, the State of Washington, and the
Highline School District. The schedule for state funding is not
Construction Costs
known. The district's schedule is dependent on obtaining general
Not Applicable
election bonds at various intervals.
Budget
The project forecast is within the approved budget and authorization.
Change Order
Not applicable
Risks
Project delayed due to funding issues with the Highline School
District. Risk is if no bonds are passed in general election. Obtain
FAA AIP Grant funding.
Budget Transfers
None this quarter


AIRPORT
62  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Highline Community College Noise Insulation
Project:   C200042      Highline Community College      Status Snapshot Prior Report
Budget: $32,050,000     Insulation Agreement will provide   Delayed Schedule 4Q10
Phase: Construction     funding for up to 22 eligible      On Budget
Start: 01/11/2005         buildings that are impacted by      0 Change Orders
Completion: 12/31/2013   aircraft noise from Sea-Tac Airport.  Total Change Orders Amount:
$0
Significant Developments
Thirteen of the 22 eligible buildings have been sound insulated by    Budget/Costs Incurred
the college.
40
Schedule                             30
Building #4 received FAA AIP Grant and scheduled to begin         Millions
20
construction in summer 2012. The schedules for the remaining
buildings are dependent on state funding.                      Dollars in  10
0
Budget
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget. Authorization of
the remaining project budget will be requested for one building at a
time from the Commission in the future when schedule is          Construction Costs
determined.                                     Not Applicable
Change Order
Not Applicable
Risks
The Highline Community College competes for state funding with
other colleges. If they do not receive adequate funding, projects will
be delayed.
Budget Transfers
Noise Program Increase                $21,228,000


AIRPORT
Port of Seattle 2Q 2012 Report  63

SECOND QUARTER REPORT, 2012
Home Insulation Retrofit
Project:   C200048      This project includes storm window  Status Snapshot Prior Report
Budget: $5,344,000      retrofit of previously insulated     Delayed Schedule 4Q 11
Phase: Construction     homes.                On Budget
Start: 01/11/2005                                 2 Change Orders
Completion: 12/31/2013                       Total Change Orders Amount:
$384
Significant Developments
Budget/Costs Incurred
The Port has identified eligible homes and notified homeowners.
Continue with storm window retrofit.                           6
5
Schedule                             4
Two homes are in process and reviewing potential homes for          3
in Millions
eligibility.                                                          2
Dollars   1
Budget                              0
Authorized  Forecasted Costs Incurred
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
Small miscellaneous items.                            Not Applicable
Risks
The ability to accomplish the retrofit is dependent on homeowner's
schedules, and structural integrity of the home.
Budget Transfers
None this quarter




AIRPORT
64  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Single Family Home Sound Insulation
Project:   C200093      Sound insulate remaining homes    Status Snapshot Prior Report
Budget: $4,947,395      that are within the 1998 65 decibel  Delayed Schedule    4Q 11
Phase: Construction     day night level (DNL) noise      On Budget
Start: 03/27/2007         contour.                   10 Change Orders
Completion: 12/31/2013                       Total Change Orders Amount:
$11,317.00
Significant Developments                    Budget/Costs Incurred
Thirty two homes are complete; six homes are in the process of
6
receiving sound insulation; fourteen homes are on the waiting list for
5
the next group.
Millions  4
3
Schedule
2
This project is underway and should near completion by summer      Dollars in  1
2013.                                         0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within approved budget and authorization to
complete all homes currently in progress. Any additional homes     Construction Costs
identified as eligible will require additional funding authorization.
4
Change Order                           3
Change orders are miscellaneous small items and permits for the      Millions
2
cities.
Dollars in   1
Risks
0
The ability to accomplish the insulation is dependent on the               Initial  Change Order  Spent
homeowner's schedules, willingness to sign an aviation easement
and obtain a subordination agreement from their lender, and
structural integrity of the home. If more eligible homes than
anticipated are identified in the future, then additional funding may be
needed.
Budget Transfers
None this quarter

AIRPORT
Port of Seattle 2Q 2012 Report  65

SECOND QUARTER REPORT, 2012
Street Vacations - Des Moines Creek 1
Project:   C800046    Purchase the City of Des Moines-      Status Snapshot Prior Report
Budget: $3,850,000   owned streets in the Des Moines Creek  Delayed Schedule 4Q 11
Phase: Implementation Business Park site that are surrounded  Under Budget       4Q 11
Start: 10/01/2008      by Port-owned property. This        0 Change Orders
Completion: 01/31/2012 acquisition will enable the Port to     Total Change Orders Amount:
develop the business park site.        $0
Significant Developments                    Budget/Costs Incurred
Closing on the large majority of the streets with the City of Des
5
Moines occurred in March 2011. Closing on the last small parcel
4
from the Washington State Department of Transportation occurred in
the first quarter of 2012. This will be the last quarterly report for this     Millions 3
project.                                                 2
Dollars in   1
Schedule
0
Final acquisition was delayed by one month as previously reported.        Authorized Forecasted Costs Incurred
Budget
The project was under the approved budget and authorization. It is
anticipated that approximately $1,400,000 in unspent funds will be    Construction Costs
returned back to the Airport CIP.                           Not Applicable
Change Order
Not applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
66  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
RMU/Kiosk Concession Program
Project:   C800146    The project will provide design and     Status Snapshot Prior Report
Budget: $879,146     fabrication of eight Retail         Delayed Schedule 3Q 10
Phase: Construction   Merchandising Units (RMUs); provide   On Budget
Start: 11/20/2007      power, communications, and data to    0 Change Orders
Completion: 06/30/2011 sixteen RMU locations; and install floor-  Total Change Orders Amount:
mounted receptacles for the utilities to    $0
allow easy connection points as well as
flexibility for future utilization.
Budget/Costs Incurred
1.5
Significant Developments
All RMU utility installations are finished and considered substantially
complete. The remaining tasks include purchasing and installing the    Millions 1
RMU kiosk units.
0.5
Dollars in 
Schedule
0
Substantial completion is done.                                Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
None
Risks
None identified at this time.
Budget Transfers
From C800152 (Non Aeronautical New Projects)      $226,900



AIRPORT
Port of Seattle 2Q 2012 Report  67

SECOND QUARTER REPORT, 2012
Burien Commercial Property Acquisition
Project:   C800150      Acquire commercial properties     Status Snapshot Prior Report
Budget: $3,000,000      along Des Moines Memorial Drive,  Delayed Schedule    2Q 10
Phase: Implementation   and vacate one street, in the City of  On Budget
Start: 05/31/2007         Burien that is surrounded by Port-   0 Change Orders
Completion: 12/31/2013   owned properties.           Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The Sunnydale sub-station was purchased from Seattle City Light on
4
July 25, 2011. The last anticipated acquisition will be the street
vacation of 12th Place S. in Burien, Washington.                   3
Millions
2
Schedule
Dollars in   1
It is anticipated that the street vacation will occur in the 2012-2013
time frame.                                          0
Authorized  Forecasted Costs Incurred
Budget
The project forecast is within the approved budget.
Construction
Change Order                         Not Applicable
None
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
68  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Tenant Reimbursement
Status Snapshot
Project:   C800154    Build out of spaces for new and      On Schedule
Budget: $4,709,577    existing tenants. If more than a "basic  On Budget
finish" condition space is built for the    0 Change Orders
Phase: Construction
tenant, the tenant is required to       Total Change Orders Amount:
Start: 08/14/2007
reimburse the Port for the cost of the   $0
Completion: TBD
work beyond this "basic finish". These
reimbursements are allowed under    Budget/Costs Incurred
the guidelines described in the
"Tenant Reimbursement Policy".        5
4
Significant Developments                     Millions 3
There were no tenant reimbursements during the second quarter of      2
2012. Future tenant projects will likely be part of the Airline           Dollars in  1
Realignment over the next few years, so this project may have
limited activity.                                               0
Authorized  Forecasted Costs Incurred
Schedule
Schedules vary to meet the tenant's needs.                  Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
Port of Seattle 2Q 2012 Report  69

SECOND QUARTER REPORT, 2012
Rubber and Paint Removal Equipment
Project:   C800482    Purchase and delivery of a          Status Snapshot
Budget: $600,000    Rubber/Paint Removal Truck       On Schedule
Phase: Implementation                       On Budget
Start: 02/14/2012                                 0 Change Orders
Completion: 08/31/2012                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The contract was awarded to Stripe Hog.
0.8
Schedule                             0.6
Delivery of the equipment is scheduled for August 2012.            Millions
0.4
Budget                             Dollars in 0.2
The project forecast is within the approved budget and authorization.     0
Authorized  Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
None identified at this time.
Budget Transfers
None this quarter





AIRPORT
70  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Snow Removal Equipment - 2013
Project:   C800498      This project will purchase four     Status Snapshot
Budget: $2,000,000      pieces of runway snow removal    On Schedule
Phase: Implementation   equipment.              On Budget
Start: 02/14/2012                                 0 Change Orders
Completion: 03/31/2013                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The project went out to bid in April 2012.
Schedule                             2.5
2
Delivery is anticipated for March 2013.
Millions 1.5
Dollars in 
Budget                              1
The project forecast is within the approved budget and authorization.    0.5
0
Change Order                            Authorized Forecasted Costs Incurred
None
Risks                               Construction Costs
None identified at this time.                                Not Applicable
Budget Transfers
None this quarter.





AIRPORT
Port of Seattle 2Q 2012 Report  71

SECOND QUARTER REPORT, 2012
Seaport Security Grant Round 7
Project:   C800165      Seaport Security Grant Round 7    Status Snapshot
Budget: $2,283,090                         On Schedule 4Q 11
Revised Budget $2,582,490                      On Budget
Phase: Construction                        1 change Orders
Start: March 2007                                Total Change Orders Amount:
$24,515.00
Completion: Dec 2010
Budget/Costs Incurred
Significant Developments
3
The construction is complete and invoices have been submitted for
2.5
grant reimbursement but we're waiting for ICT to complete the final
programming to get the system up and running.                 Millions 2
1.5
1
Schedule                            Dollars in 0.5
Project is on schedule.
0
Authorized  Forecasted Costs Incurred
Budget
On budget as revised
Construction Costs
Change Order                         Not Applicable
No change orders over 10% in the aggregate.
Risks
If ICT doesn't get the programming completed quickly, the guards will
continue to be required at the TWIC gates.
Budget Transfers
No budget transfers over $200,000.



SEAPORT

72  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
P91 Fender System Upgrade
Project:   C800183      Upgrades to the vessel berths of    Status Snapshot
Budget: $5,700,000      P91 to better accommodate cruise  On Schedule
Phase: Design        ships and also serve the other    On Budget
Start: 01/31/10          industrial customers who utilize the   0 Change Orders
Completion: 04/30/2012   berths and adjacent dock/apron    Total Change Orders Amount:
areas on P91 for less than $6M by   $0
spring 2011.
Budget/Costs Incurred
Significant Developments
6
Fender pile replacement construction complete in Q2 2012. Design
for Camel standoff barges underway.
Millions  4
Schedule
2
Full Fender replacement has been completed by April 2012. Camel    Dollars in 
Barge replacement will be completed by April 2013.                0
Authorized  Forecasted Costs Incurred
Budget
Project is within approved budget.
Construction Costs
Change Order
2.5
None this quarter
2
Risks                                Millions 1.5
None this quarter                                       1
Dollars in   0.5
Budget Transfers
0
None                                      InitialChange OrdersSpent




SEAPORT
Port of Seattle 2Q 2012 Report  73

SECOND QUARTER REPORT, 2012
T-10 Interim Redevelopment
Status Snapshot
Project:   C800264      Redevelop site, complete with new  On Schedule 4Q 11
Budget: $7,205,000      stormwater treatment facilities,    On Budget
Phase: Construction     outfall, yard lighting, security fence,  19 Change Orders
Start: 03/22/08          and paving to support terminal     Total Change Orders Amount:
Completion: 12/31/2011   related activities.           $401,046
Budget/Costs Incurred
Significant Developments
7.3
Substantial Completion Certification issued on December 6, 2011.
7.2
Contract Completion Memo issued on May 2, 2012. Project is in      Millions 7.1
close-out. This would be the last time reporting on this project.
7
Schedule                            Dollars in 6.9
Close-out phase underway.                             6.8
Authorized  Forecasted Costs Incurred
Budget
Forecast that all work will be completed within authorized funding.    Construction Costs
Change Order                           6
Nineteen change orders have been executed at a total of $75,037.       5
Bid Item Adjustments totals $326,009.                        Millions  4
3
Risks                                  2
None                                  Dollars in   1
0
Budget Transfers                             Initial Change Spent
Orders
None
Photo



SEAPORT
74  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
T-91 Watermain Replacement
Project:   C800298      Replace water main in the vicinity   Status Snapshot Prior Report
Budget: $4,875,000      of Magnolia Bridge and City      On Schedule
Phase: Construction     Ice/Trident areas including various  On Budget
Start: 9/20/2009          buildings at T91              0 Change Orders
Completion: 8/1/2012                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Final construction is in progress.
4.9
Schedule                             4.8
Schedule extended to Q3 2012 to accommodate construction and     Millions
4.7
site operations.
Dollars in 4.6
Budget
4.5
Project is on budget. Additional funds of approximately $300,000         Authorized  Forecasted Costs Incurred
were included in Q2 2012 to accommodate various unforeseen
conditions.
Construction Costs
Change Order
None                                    5
4
Risks                                Millions  3
None
2
Budget Transfers                          Dollars in   1
None                                    0
Initial   Change   Spent
Orders

Photo


SEAPORT

Port of Seattle 2Q 2012 Report  75

SECOND QUARTER REPORT, 2012
T-5 Crane Cable Reels
Status Snapshot Prior Report
Project:   C800349      Purchase Cable Reels for tenant.
Budget: $3,500,000                         Delayed Schedule 2Q 12
Phase: Design                            On Budget
Start: 05/04/10                                   0 Change Orders
Completion: 03/31/11                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The tenant has postponed the installation of the cable reels due to
budget reductions.
4
Schedule                             3
Millions
The tenant has fabricated the cable reel platforms but due to budget     2
reductions the tenant has postponed the installation of the cable
reels until the first quarter of 2013. The revised completion date for     Dollars in  1
the project is now the 3rd quarter 2013.
0
Authorized  Forecasted Costs Incurred
Budget
None
Construction Costs
Change Order                         Not Applicable
None
Photo
Risks
Schedule
Budget Transfers
None




SEAPORT
76  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
T18 Fender Replacement
Project:   C800416      Replacement of 202 timber fender   Status Snapshot
Budget: $5,465,000      piles and their supporting members  On Schedule
Phase: Construction     along the face of the SSA crane    On Budget
Start: 02/07/2010         terminal.                   2 Change Orders
Completion: 03/15/2012                       Total Change Orders Amount:
$16,500
Significant Developments                    Budget/Costs Incurred
Second phase of construction is complete; remaining 110 timber        6
fender piles replaced in final work phase, and beneficial occupancy 
for all work in Q2 2012. This will be the final report for this project.      Millions 4
Dollars in 
Schedule                             2
Construction scheduled in two phases to accommodate permit
windows and tenant operations. Resumption of construction of         0
Authorized  Forecasted Costs Incurred
second phase work in December 2011, all work completed by April
2012.
Construction Costs
Budget
Project is within the approved budget.                          1.2
1
Change Order
Millions  0.8
None this quarter                                       0.6
0.4
Risks                                Dollars in  0.2
None this quarter                                        0
Initial   Change   Spent
Orders
Budget Transfers
None
Photo



SEAPORT
Port of Seattle 2Q 2012 Report  77

SECOND QUARTER REPORT, 2012
SEA P66 Apron Pile Wrap
Status Snapshot
Project:   C800516      Design and install a pile wrap      On Schedule
Budget: $167,000       system for corrosion protection of   On Budget
Phase: Design        steel structural pilings associated   0 Change Orders
Start: 3/6/12            with Seaport structures at Pier 66.   Total Change Orders Amount:
Completion: 12/31/16                         $0
Budget/Costs Incurred
Significant Developments
0.02
Completed 60% design documents and circulated for review and
0.015
comments. Submitted permit applications to agencies for review and
approval. Shoreline Exemption was received from the City of Seattle    0.01  Millions
for the proposed work.
0.005   Dollars in 
Schedule                             0
Authorized  Forecasted Costs Incurred
60% Design is on track and 100% design is targeted to be completed
in 3rd Quarter 2012.
Construction Costs
Budget
Not Applicable
Project is on budget.
Change Order
N/A
Risks
Installation of pile wraps is tide and weather dependent. Army Corps
will determine if subject work must be completed within allowable inwater
work window - staff is pushing for year round work window.
Budget Transfers
None



SEAPORT

78  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Argo Yard Truck Roadway
Status Snapshot
Project:   C800546      New Port of Seattle owned truck    On Schedule
Budget: $2,200,000      roadway between SR 99 and     On Budget
Phase: Design        Colorado Way South right-of-way.   0 Change Orders
Start: 03/11/12                                   Total Change Orders Amount:
Completion: 12/31/14                         $0
Budget/Costs Incurred
Significant Developments
2.5
Preliminary roadway alignment completed and under review by
2
project stakeholders. Site survey, Phase I environmental
assessment, and SEPA research has begun.
Millions 1.5
1
Schedule                            Dollars in 0.5
Design & permitting in 2012                               0
Authorized  Forecasted Costs Incurred
Construction in 2013
Budget
Construction Costs
Final project cost to be determined as a result of design.           Not Applicable
Change Order
None
Risks
Proposed roadway utilization is dependent on separate off-site East
Marginal Way improvements required under the proposed WSDOT
timber trestle replacement. These improvements (EMWGS Phase II)
have not yet been designed or funded.
Budget Transfers
None


SEAPORT

Port of Seattle 2Q 2012 Report  79

SECOND QUARTER REPORT, 2012
East Marginal Way Grade Separation
Project:   E102007      FAST Corridor funded project;
Budget: $50,700,000     FHWA, State, City with Port      Status Snapshot Prior Report
Phase: Construction     commitment of $18,800,000. Scope  Delayed Schedule
Start: 5/2006            is to construct grade separation in   On Budget
Completion: Q2 2012     vicinity of T5 and T18 to minimize   59 Change Orders
truck traffic/rail conflicts.            Total Change Orders Amount:
$1,358,306
Budget/Costs Incurred
Significant Developments
Opening for traffic occurred in mid-March 2012. Recent development   50.75
in plans to replace adjacent highway structures have resulted in       50.7
opportunity to develop access to UPRR rail yard and improved       50.65
freight traffic flow.                                             50.6
50.55   in Millions
Schedule                            50.5 Dollars 
50.45
Substantial completion was achieved in 2nd Q 2012. Final           50.4
acceptance by SDOT is anticipated in 3rd Q 2012 followed by            Authorized  Forecasted Costs Incurred
Federal Highway Administration (FHWA) final audit.
Budget                            Construction Costs
Current construction costs based on unit line items and cost
reconciliation which are occurring 3rd Q 12 as part of the project         25
closeout. On Budget reflects the active construction budget.            20
Millions   15
Change Order
10
Fifty nine change orders have been executed for a total net amount
of $1,358,306. Change order calculations based on unit pricing and     Dollars in   5
final cost will be based on actual quantities as well as any              0
outstanding contractor claims calculated at close-out.                   Initial  Change  Spent
Orders
Risks
Construction change orders or contractor claims could occur, which   Photo
could increase cost of construction.
Budget Transfers
Budget transfer request due to potential contractor delay claim may
be required.

SEAPORT
80  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Viaduct Construction Coordination
Project:   E104324,      Participate in the design &       Status Snapshot
E104535-38          construction of the bored tunnel,   On Schedule 2Q 12
Budget: $762,400       north & south portals, Holgate to   On Budget 2Q 12
Phase: Implementation   King St, Central Waterfront surface  0 Change Orders
Start: 1/1/2009          streets, and related projects to     Total Change Orders Amount:
ensure adequate connection to port  $0
Completion: 12/31/2018
facilities.
Budget/Costs Incurred
Significant Developments
1
Excavation of future SR 99 tunnel boring machine launch pit near
0.8
Terminal 46 began in June. Crews rerouted waterfront traffic
underneath existing Viaduct between Spring and King St.           Millions 0.6
Construction began on mitigation works at T46 as a condition of       0.4
leasing 5 acres for tunnel construction staging area.               Dollars in 0.2
Schedule                             0
Authorized  Forecasted Costs Incurred
Stage 3 H2K construction is expected to begin construction in
August. Tunnel boring machine delivery is expected in Spring 2013.
Related City projects are making steady progress (Spokane/Mercer.)
Construction Costs
Not Applicable
Budget
Port staff costs are within anticipated 2012 spending.
Change Order
Not applicable
Risks
There are multiple impacts to port tenants and general freight
mobility due to temporary road closures, detours, and other
necessary construction activities.
Budget Transfers
None

SEAPORT

Port of Seattle 2Q 2012 Report  81

SECOND QUARTER REPORT, 2012
Street Vacations T5,18,105
Status Snapshot
Delayed Schedule 4Q 11
Project: Capital &     Street vacation related real estate     On Budget
Expense         negotiations and agreements --T5,    0 Change Orders
104362, 104364, 104366 T18, and T105.               Total Change Orders Amount:
Budget: $1,500,000                         $0
Phase: Permitting
Start: June 2010                                 Budget/Costs Incurred
Completion: 2014
2
1.5
Significant Developments                     Millions 1
T-105 Street Vacations were approved by the City Council and
Dollars in 0.5                                                                               signed by the Mayor, becoming effective as of mid-June. T-18 street
vacation process is behind schedule due to ongoing negotiations.       0
Authorized  Forecasted Costs Incurred
Schedule
The revised schedule anticipates that T-18 and T-5 Street Vacations  Construction Costs
will be at least 50% completed by year-end 2013 and fully completed  Not Applicable
by the end of 2014.
Photo
Budget
On Budget
Change Order
Not applicable
Risks
Not applicable
Budget Transfers
Not applicable


SEAPORT

82  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
T-18 Pile Cap Repair Pilot Project
Project:   E104559      T18 Pilot Pile Cap Repair Project    Status Snapshot
Budget: $1,000,000                         Delayed Schedule 2Q 11
Phase: Construction                        Forecast Overrun 2Q 12
Start: 3/25/11                                    0 Change Orders
Completion: 12/31/12                        Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Construction completed on first two pile cap bents in August.
1.2
Schedule
1
Repairs were to be completed by July, but are taking longer than      Millions 0.8
originally estimated. Completion now expected by November and      0.6
findings will be published in December.                        0.4
Dollars in 0.2
Budget
0
Costs to date are forecasted higher than expected due to increased        Authorized  Forecasted Costs Incurred
overall duration of construction.
Change Order                         Construction Costs
None
2
Risks
1.5
Risks include preventing deleterious materials from entering water,     Millions
1
minimizing any disruptions to tenant operations, and managing
project costs in order to stay within budget approved.               Dollars in  0.5
Budget Transfers                           0
Initial   Change   Spent
None                                         Orders



SEAPORT

Port of Seattle 2Q 2012 Report  83

SECOND QUARTER REPORT, 2012
Dock System Condition Assessments
Project:   E104610-12;    Inspections T5,18,46,25,30,66     Status Snapshot
E104695 & 98                             On Schedule 1Q 12
Budget: $2,250,000                         On Budget 1Q 12
Phase: Implementation                       0 Change Orders
Start: 1/1/2011                                   Total Change Orders Amount:
$0
Completion: 12/31/2012
Budget/Costs Incurred
Significant Developments
Final reports are complete for T-5, T-18, T-46 and results will be        2.5
incorporated into the 2013 budget planning. Field inspections are
2
completed for T-25, T-30, T-66, but consultant provided pile diving      Millions 1.5
and material testing will occur later.
1
Schedule                            Dollars in 0.5
Project is on schedule for completing 2012 assessments of T-25,       0
T-30, and P66.                                        Authorized Forecasted Costs Incurred
Budget
Budget is $2,250,000 and is on target to complete within this        Construction Costs
amount.                                    Not Applicable
Change Order
Not applicable
Risks
Service directives for pile diving and material testing are taking
longer than expected to execute and implement.
Budget Transfers
None for this period


SEAPORT

84  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
FT C15 HVAC Improvements
Status Snapshot
Project:   C800137                             Delayed Schedule 4Q 11
Budget: $4,000,000    Provide the preliminary planning,    On Budget
Phase: Design       design, and construction for replacing  0 Change Orders
Start: 05/01/10         the FT C15 HVAC System.         Total Change Orders Amount:
Completion: 12/31/2012                       $0
Budget/Costs Incurred
Significant Developments
5
60% design documents expected in July.
4
Schedule                            Millions 3
Construction is scheduled to start Q2 2013.                      2
Dollars in   1
Budget
0
On budget                                       Authorized Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
Further delays could cause construction to occur in winter (colder)
months but consultant has come up with a solution that will keep the
tenants comfortable even if the project occurs in cold weather
months. The risk now, albeit slight, is that the cost of the solution
could impact the budget.
Budget Transfers
None



REAL ESTATE
Port of Seattle 2Q 2012 Report  85

SECOND QUARTER REPORT, 2012
RE Maintenance Shop Solution
Project:   C800187      Marine Maintenance Solution CIP   Status Snapshot
Budget: $2,640,000      facilities continued operations from  Delayed Schedule
Phase: Construction     the existing shop location by     On Budget
Start: August 2010       funding the following five projects:   1 Change Orders
Completion: November   MM Office Expansion; MM North-   Total Change Orders Amount:
end Office; MM Elec Upgrade; MM   $1,890
2012
Roof Replacement; and MM
Kitchen Upgrade.             Budget/Costs Incurred
2.7
2.6
Significant Developments
All projects, except the Kitchen Upgrade, are complete and in the
Millions 2.5
Dollars in 
2.4
closing process. Design of Kitchen Upgrade is complete.
2.3
Schedule                             2.2
Authorized  Forecasted Costs Incurred
Kitchen Upgrade construction is expected to be completed by
October 31, 2012.
Construction Costs
Budget
Not applicable
Commission authorized a $340,000 increase in the CIP budget for a
total authorization of $2,640,000 on June 14, 2011. Approximately 
$2,350,000 has been spent to date.
Change Order
There was one change order for less than $2,000 to install additional
flashing as part of the roof replacement project.
Risks
No identified risks for the remainder of the project work.
Budget Transfers
None

REAL ESTATE

86  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
P69 N Apron Corrosion Control
Status Snapshot
Project:   C800313      Install a corrosion control system    On Schedule
Budget: $300,000       for the steel pilings, pile caps, and   On Budget
Phase: Design        beams under the North Apron.    0 Change Orders
Start: 02/28/12                                   Total Change Orders Amount:
Completion: 12/31/2013                       $0
Budget/Costs Incurred
Significant Developments
0.4
Design is underway.
0.3
Schedule                            Millions 0.2
Design is on schedule. We plan on proceeding with Commission
0.1
authorization for construction around the end of this year.            Dollars in 
0
Authorized  Forecasted Costs Incurred
Budget
Design is on budget.
Construction Costs
Change Order                         Not Applicable
N/A
Photo
Risks
N/A
Budget Transfers
N/A




REAL ESTATE

Port of Seattle 2Q 2012 Report  87

SECOND QUARTER REPORT, 2012
Flight Information System (FIMS) II
Project: C101117        Procure, develop, and implement a  Status Snapshot
Budget: $8,220,000      FIMS system that includes       On Schedule
Phase:Implementation    replacement monitors, an airport   On Budget
Start: 5/4/2010           resource management system, and  0 Change Orders
Completion: 12/30/2013    a flexible digital signage system    Total Change Orders Amount:
capable of displaying flight         $0
information, visual paging, and
notifications.
Budget/Costs Incurred
Significant Developments                     10
Software configuration workshops in progress. Casework            8
construction and display replacement has begun and will continue      6
through 2013.                                      in Millions 4
Schedule                            Dollars  2
0
On Schedule
Authorized Forecasted   Costs
Incurred
Budget
On Budget                                  Construction Costs
Change Order                           2.5
None                                   2
Millions  1.5
Risks
1
No significant risks at this time.
Dollars in   0.5
Budget Transfers                           0
Initial      Change      Spent
None                                          Orders



CORPORATE

88  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Maximo Enterprise Implementation
Project:   C800003      Implement latest version of       Status Snapshot Prior Report
Budget: $3,680,000      Maximo, merge Aviation and Real   Delayed Schedule
Phase: Implementation   Estate applications onto one     On Budget
Start: 11/25/2007         platform, and add service desk     0 Change Orders
Completion: 12/30/2012   module and wireless handheld    Total Change Orders Amount:
capabilities.                    $0

Significant Developments                    Budget/Costs Incurred
Major components of the program have been delivered including the
4
deployment of Service Management software for the ICT Service
Desk in December 2008 and the upgrade and consolidation of         3
Marine Maintenance and Aviation Maintenance Maximo systems in
2
September 2010. The smaller components of mobility enhancements    Millions
and additional interfaces are in progress.                       Dollars in 1
Schedule                             0
Authorized  Forecasted    Costs
Prior Report - Several of the proposed new interfaces link the                         Incurred
Maximo system to the Peoplesoft Financials Procurement module.
Because of planned changes in the procurement process with the
Construction Costs
Peoplesoft Financials Upgrade project, the delivery of these
Not Applicable
interfaces will be delayed until after the completion of the upgrade
project.
Budget
On Budget
Change Order
None
Risks
Resource constraints may continue to delay the implementation of
the interfaces and mobility enhancements.
Budget Transfers
None

CORPORATE
Port of Seattle 2Q 2012 Report  89

SECOND QUARTER REPORT, 2012
ID Badge System Replacement
Project: C800162        Procurement and replacement of   Status Snapshot
Budget: $2,500,000      the Portwide ID Badge system     On Schedule
Phase:Planning        including software, hardware, and   On Budget
Start: 5/1/2012           equipment.                 0 Change Orders
Completion: 11/30/2013                         Total Change Orders Amount:
$0

Budget/Costs Incurred
Significant Developments
3
Vendor has been selected via a competitive RFP. Contract
negotiation in progress.                                   2.5
2
Schedule                             1.5
in Millions
1
On Schedule                                  Dollars 0.5
Budget                             0
Authorized  Forecasted    Costs
On Budget                                                Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
No significant risks
Budget Transfers
None




CORPORATE

90  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Airline Activity Management
Project: C800222        Development of an airline activity   Status Snapshot
Budget: $500,000       management system that       On Schedule
Phase:Planning        integrates with several Port      On Budget
Start: 6/19/2011          systems to replace aging reporting   0 Change Orders
Completion: 5/1/2013     system and supply data for airline   Total Change Orders Amount:
activity fees.                    $0

Budget/Costs Incurred
Significant Developments
0.6
Development in progress.
0.5
Schedule                             0.4
0.3
On Schedule                                  in Millions
0.2
Dollars 
Budget                             0.1
0
On Budget
Authorized Forecasted   Costs
Incurred
Change Order
None
Construction Costs
Risks                               Not Applicable
No significant risks
Budget Transfers
None




CORPORATE

Port of Seattle 2Q 2012 Report  91

SECOND QUARTER REPORT, 2012
Enterprise Project Cost Management
Project: C800321        Replace the current construction    Status Snapshot Prior Report
Budget: $1,525,000      costing systems with a common    Delayed Schedule     3Q 11
Phase:Implementation    enterprise project cost         On Budget
Start: 4/21/2008          management system.           0 Change Orders
Completion: 9/30/2012                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
The first phase deployment was completed in July but issues with
the software delayed use until August 6.                        2
Schedule                             1.5
Prior Report - Vendor did not deliver software per original contract       Millions 1
and project was put on-hold to evaluate alternatives. A decision was
Dollars in0.5                                                                                     made to continue with Skire in July 2010. The estimated completion
date at this time is September 2011 although there may be interim      0
deliveries prior to completion.                                  Authorized Forecasted  Costs
Incurred
Prior Report - Configuration of the software took longer than
anticipated due to the availability of resources and complexity of the   Construction Costs
software delaying the start of the interface development. The system  Not Applicable
is scheduled to be deployed in May 2012 with several critical
interfaces in place.
Budget
None
Change Order
None
Risks
The issues from the software deployment will likely delay the
implementation of the final phase of this project. A detailed plan for
this remaining work is in process.
Budget Transfers
None

CORPORATE
92  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Records and Document Management
Project:   C800322      Improve statutory compliance,     Status Snapshot Prior Report
Budget: $800,000       increase functionality, and lower   Delayed Schedule
Phase: Implementation   operating costs by replacing     On Budget
Start: 6/23/2009          Hummingbird with SharePoint for    0 Change Orders
Completion: 12/30/2012   records and document         Total Change Orders Amount:
management.             $0

Significant Developments                    Budget/Costs Incurred
The Sharepoint 2010 upgrade, training, and project-led organization
1
roll-out has been completed. Design and implementation of
Sharepoint 2010 Records Center is in progress.                   0.8
0.6
Schedule                            in Millions 0.4
Resource availability has delayed the full implementation of the        Dollars   0.2
Sharepoint Records Center which is scheduled to be availabile to the
0
first Port department in May 2012. Migration of records to Sharepoint
Authorized Forecasted   Costs
will not be complete until December 2012.                                    Incurred
Prior Report: Sharepoint 2010 implementation is dependent on the
Construction Costs
completion of several infrastructure projects currently in progress
Not Applicable
and requires additional time to complete the upgrade of existing
sites.
Budget
On Budget
Change Order
None
Risks
Scope of Sharepoint 2010 upgrade may require additional funding to
complete migration activities.
Budget Transfers
None
CORPORATE

Port of Seattle 2Q 2012 Report  93

SECOND QUARTER REPORT, 2012
Propworks Upgrade
Project: C800328        Upgrade the property management  Status Snapshot
Budget: $450,000       system, Propworks, used by      On Schedule
Phase: Close Out       Aviation Properties and Real Estate  On Budget
Start: 3/1/2011           organizations.               0 Change Orders
Completion: 7/30/2012                         Total Change Orders Amount:
$0
Significant Developments
Aviation Properties upgrade was completed in April 2012 and the    Budget/Costs Incurred
Propworks upgrade for Real Estate was completed in June 2012.
0.5
Schedule                              0.4
On Schedule                                    0.3
in Millions   0.2
Budget
Dollars    0.1
On Budget
0
Authorized Forecasted   Costs
Change Order                                     Incurred
None
Construction Costs
Risks
Not Applicable
No significant risks
Budget Transfers
None





CORPORATE
94  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
Time Clock System
Project: C800387        Procure and implement a Time    Status Snapshot
Budget: $380,000       Clock System to accurately capture  Delayed Schedule
Phase: Planning        and track time and attendance for   On Budget
Start: 6/8/2010           approximately 230 employees in    0 Change Orders
Completion: TBD       Aviation Security and Airport     Total Change Orders Amount:
Operations organizations.         $0

Significant Developments                    Budget/Costs Incurred
Vendor was unable to deliver software that functioned in our
0.4
environment per the contract. We are working with the legal
department to determine our options for severing the relationship.        0.3
Millions   0.2
The project team is evaluating options and a re-planning effort is in
progress.                                         Dollars in  0.1
Schedule                              0
Authorized Forecasted   Costs
Schedule will be significantly delayed if another vendor solution is                      Incurred
implemented.
Budget                            Construction Costs
Not Applicable
There is a risk that another vendor solution would require additional
funding.
Change Order
None
Risks
See above
Budget Transfers
None


CORPORATE
Port of Seattle 2Q 2012 Report  95

SECOND QUARTER REPORT, 2012
Peoplesoft Financials Upgrade
Project: C800392        Upgrade of Peoplesoft Financials   Status Snapshot Prior Report
Budget: $5,000,000      hardware and software         Delayed Schedule
Phase:Planning                            On Budget
Start: 9/28/2010                                 0 Change Orders
Completion: 12/31/2013                         Total Change Orders Amount:
$0
Significant Developments
An implementation vendor has been selected and a contract signed   Budget/Costs Incurred
to begin work on the upgrade in August 2012.
6
5
Schedule
4
Prior Report - An implementation vendor was selected via a
3
competitive procurement but we were unsuccessful in negotiating an    in Millions
2
acceptable contract. Because of resource constraints during the       Dollars  1
year-end process, the next optimum window of opportunity for the
0
upgrade begins in mid-2012. This will delay the project one year.
Authorized  Forecasted    Costs
Incurred
Budget
On Budget                                  Construction Costs
Not Applicable
Change Order
None
Risks
Significant resources will be required across multiple organizations
which may delay other technology projects.
Budget Transfers
None



CORPORATE
96  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT,
Police Records Management System
Project: C800393        Procure and implement a       Status Snapshot Prior Report
Budget: $1,300,000      replacement Police Records      Delayed Schedule     4Q 11
Phase:Design         Management System         On Budget
Start: 10/10/2010                                0 Change Orders
Completion: 9/30/2012                         Total Change Orders Amount:
$0

Significant Developments                    Budget/Costs Incurred
Configuration and implementation in progress.
1.4
1.2
Schedule
1
Prior Report - Contract negotiations took significantly longer than       0.8
anticipated delaying project completion by 8 months.              in Millions 0.6
Dollars 0.4
0.2
Budget
0
On Budget                                      Authorized Forecasted  Costs
Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
The Police Department is evaluating the need for additional software
that will better meet business process for field reporting. If approved,
this implementation will further delay the schedule.
Budget Transfers
None




CORPORATE
Port of Seattle 2Q 2012 Report  97

SECOND QUARTER REPORT, 2012
CUSS Kiosk Expansion
Project: C800477        Procure and install 10 Common-    Status Snapshot
Budget: $425,000       use Self Service (CUSS) kiosks in   On Schedule
Phase: Implementation    the common-use ticket counter    On Budget
Start: 1/10/2012          lobby providing travelers self      0 Change Orders
Completion: 7/30/2012    service check-in options.        Total Change Orders Amount:
$0

Significant Developments                    Budget/Costs Incurred
Kiosks have been delivered and installed. Upgrade of the kiosk
0.5
manager software will be completed by the end of July 2012.
0.4
Schedule                             0.3
Millions
On Schedule                                   0.2
Dollars in  0.1
Budget
0
On Budget                                      Authorized Forecasted Costs
Incurred
Change Order
None                                 Construction Costs
Not Applicable
Risks
No significant risks identified.
Budget Transfers
None




CORPORATE
98  Port of Seattle 2Q 2012 Report

SECOND QUARTER REPORT, 2012
CUSE Migration
Project: C800481        Migrate the Airport Common-Use   Status Snapshot
Budget: $485,000       Passenger Processing System,    Delayed Schedule     4Q 11
Phase:Close Out       CUSE, from a virtual to a physical   On Budget
Start: 6/19/2011          based infrastructure            0 Change Orders
Completion: 6/30/2012                         Total Change Orders Amount:
$0
Significant Developments
The migration to the physical environment has been completed.     Budget/Costs Incurred
Schedule                            0.6
0.5
Prior Report - A project change request to update airline network
addressing was approved to provide additional capacity for          0.4
expanded CUSE positions and better protect network availability.      0.3
in Millions
This new dependency required airlines to make a change to their      0.2
Dollars 
own network before we moved to the new CUSE environment       0.1
resulting in a delay of 3 months.                              0
Authorized Forecasted   Costs
Incurred
Budget
On Budget
Change Order                         Construction Costs
Not Applicable
None
Risks
No significant risks.
Budget Transfers
None



CORPORATE

Port of Seattle 2Q 2012 Report  99

SECOND QUARTER REPORT, 2012
Maintenance Planning Software
Project: C800501        Procure and implement        Status Snapshot
Budget: $402,000       Maintenance Planning and       Delayed Schedule
Phase:Implementation    Scheduling software that integrates  On Budget
Start: 6/26/2011          with our Asset Management       0 Change Orders
Completion: 10/30/2012    system, Maximo.            Total Change Orders Amount:
$0
Significant Developments
Software deployment has been completed as originally scoped.     Budget/Costs Incurred
Schedule                             0.5
While the initial project scope has been delivered, Aviation and        0.4
Marine Maintenance departments are evaluating the need for        Millions 0.3
additional licenses and reports. This evaluation and implementation,
0.2
if approved, will delay the schedule by 5 months.
Dollars in 0.1
Budget                             0
Authorized  Forecasted    Costs
On Budget                                                Incurred
Change Order
None
Construction Costs
Not Applicable
Risks
No significant risks
Budget Transfers
None




CORPORATE

100  Port of Seattle 2Q 2012 Report

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.