7a supp

Item No. 7a_Supp 
Date:   September 25, 2012 

Capital Improvement Projects 
Second Quarter Report 2012 
Commission Briefing

Capital Improvement Projects 
Overall Status of Projects 
91 Total Projects in report 
53 Projects are within or ahead of target schedule and budget 
37 Projects have either target schedule or budget off 
1 Project has both target schedule and budget off 




2

Project Status 
Total CIPs Managed by CDD 
100%
90%
80%
70%
60%
50%
40%
30%
Project Distribution per Quarter
20%
10%
0%
2Q11 Report       3Q11 Report       4Q11 Report       1Q12 Report       2Q12 Report
Both Schedule and Budget off        2               1               1               0               1
Either Budget or Schedule off        26               29               29               32               32
On Schedule/On Budget          45             45             46             46             45

3

AVIATION PROJECT SUMMARY 
Five projects are behind schedule: 
Water System Isolation Valve Upgrade (4 months) - To minimize
potential for operational impacts, the final sets of valves will be
installed after the busy summer travel season. 
Parking System Replacement (3 months)  Advertisement and
negotiations took longer than anticipated; Factory Acceptance
Test was delayed due to a scheduled plant shutdown; and
installation schedule was delayed due to failure of some system
components to pass testing. 
Two New CTE Freight Elevators (12 months) The project is
anticipating a one year delay due to scope changes included in
the redesign efforts, caused by interferences with ongoing Pre-
Conditioned Air Project and Alaska Air Group (AAG) relocation
program. 
4

AVIATION PROJECT SUMMARY, Cont. 
Five projects are behind schedule (cont.): 
Access Control Door Additions (6 months)  The project is being
redesigned and rebid; original proposal only produced one
bidder, at 48% above the Engineer's Cost Estimate. 
Miscellaneous Building Improvements  Airline Realignment (5
months)  Due to a delay in final agreement on gate
assignments for regional aircraft, the project design start was
delayed, causing a delay in anticipated completion. 
Two projects are over budget: 
Two New CTE Freight Elevators ($1.6 million)  The project
forecast is increased due to the redesign efforts (discussed in
schedule delay). 
5

AVIATION PROJECT SUMMARY, Cont. 
Two projects are over budget (cont.): 
Vertical Conveyance Modernization ($2.1 million)  Total project
cost has increased due to several factors, including: relocation of
the TSA Checkpoint; additional RMM costs associated with the
demolition and construction of a new non-sterile bypass corridor;
replacing the C-23 take-away baggage belt; and increasing the
escalation rate from 3 to 3.5%. 



6

AVIATION PROJECT SUMMARY, Cont. 
Cost of Construction Growth: 
Terminal Escalator Modernization (25.7%)  Significant cost
growth due to: 
Electrical upgrades to address the condition of 40 year old
wiring and electrical panels.
Aesthetic upgrades to the escalators, associated cladding, and
passageway under escalators.
Re-phasing of work to lessen the impacts on passenger
circulation and airport operations, and address unanticipated
security concerns.
Varying site conditions impacting hoisting plans for the
escalators, escalator pit conditions/alignment to accommodate
new and wider units, and miscellaneous MEP items. 

7

SEAPORT PROJECT SUMMARY 
Two Projects had second quarter schedule variances 
T-18 Pile Cap Repair Pilot Project repairs are taking longer and
costing more than expected. 
T-5 crane cable reel installation has been postponed by the tenant
until 2013. 



8

CORPORATE PROJECT SUMMARY 
Three projects with a new reportable schedule variance this quarter: 
CUSS Kiosk Enhancement  New kiosks were installed on
schedule but project change requests to update the kiosk manager
and purchase a test kiosk were approved to improve maintenance
capability. This will result in a 3-month delay for project completion. 
Maintenance Planning & Scheduling  Software was installed on
schedule but Aviation Maintenance and Marine Maintenance are
evaluating the need for additional licenses that will delay project
completion by 3 months. 
Time Clock  Vendor was unable to deliver software that functioned
in our environment per contract. The project team is evaluating
options for moving forward. 

9

Small Business Contracting 

2010  2011   2012   2012    2013    2012
SB by SBA Standard  Actual  Actual   Goal   To Date  Proposed   SCS 
Major Construction     16%    29%    8%     30%      20%      8% 
SW Construction      83%    62%    60%    67%     60%     14% 
Goods and Services    14%    18%    10%    16%     20%      6% 
Service Agreements                5%            10% 



10

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.