PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 5e ACTION ITEM Date of Meeting September 11, 2012 DATE: August 31, 2012 TO: Tay Yoshitani, Chief Executive Officer FROM: Rees Robinson, Senior Marine Maintenance Project Manager SUBJECT: Request for Funding Increase for the P69 Cooling Tower Replacement (Project #104505, CIP C800359) Amount of This Request: $75,000 Source of Funds: Tax Levy Est. State and Local Taxes: $24,500 Est. Jobs Created: 8 Est. Total Project Cost: $415,000 ACTION REQUESTED: Request Commission authorization for an additional project budget authorization of $75,000 for the Pier 69 (P69) Cooling Tower Replacement project. The additional budget authorization of $75,000 will increase the total authorized project cost to $415,000. SYNOPSIS: The cooling tower at P69 is essential to the operation of the building's HVAC (heating, ventilating and air conditioning) system. It is used year-round in building operations to maintain acceptable indoor air quality and a comfortable temperature at P69 during warm/hot weather and to cool the Port's ICT equipment, which must operate in a cool environment at all times to prevent overheating and equipment failure. P69's existing cooling tower was installed in 1992 during the original renovation of the building and is at the end of its normal service life. It is located on the roof of P69 in a corrosive marine environment, which potentially reduces its expected service life. Replacement of the cooling tower has been identified as a small capital project since 2007 with a project cost under $300,000, and work began in 2011. On November 8, 2011, the Commission authorized $65,000 for a total project budget of $340,000 to complete the project. At that time, staff intended to utilize an existing on-call small works contract and to replace the cooling tower prior to spring 2012. Subsequently, staff decided to delay construction so that the cooling tower replacement would occur over the four-day Thanksgiving weekend to limit impacts to P69 facility operations and to competitively procure a project-specific small works contract. It is estimated the replacement will take four days to complete. COMMISSION AGENDA Tay Yoshitani, Chief Executive Officer August 31, 2012 Page 2 of 5 The decision to use a project-specific contract resulted in unanticipated project costs, such as additional engineering, project management and procurement costs associated with preparing documents, and executing and administering the contract, and was made because of concerns that the open order contractor had under-estimated the project. The total, previously unanticipated, costs associated with procuring and administering the contract are approximately $20,000. The lowest responsive bid of $224,400 was more than 10 percent over the engineer's estimate of $172,000. This small works contract will be authorized by the Chief Executive Officer in accordance with Section 4.3 of Resolution No. 3605, as amended. This project was approved in the 2012 Real Estate budget in the amount of $275,000. The total estimated project cost is $415,000, including this request for $75,000. Funding is available due to timing delays in other Real Estate Division Small Capital projects. BACKGROUND: The existing P69 cooling tower was installed during the building renovation in 1992. The cooling tower is at the end of a typical service life of 20 years and is located on the roof of P69, placing it in a corrosive marine environment. This location potentially reduces its expected life. Replacement of the P69 Cooling Tower has been identified as a future small capital project since 2007. Replacing the cooling tower was included as a planned project in the Real Estate 2010 Small Project CIP C800305. Since work did not begin on the project until 2011, the project moved to the Real Estate 2011 Small Project CIP and is included in the Real Estate 2012 budget. Performance of the cooling tower is essential to building operations. The cooling tower serves all of the chillers that provide cooling to the P69 building and maintains acceptable indoor air quality. I ts operation is essential to reduce the heat generated by Port's electronic equipment, which is subject to failure if not properly cooled. On April 21, 2012, the Port bid the P69 Cooling Tower Replacement Project. The Engineer's Estimate was $172,000. On April 21, 2012, the Port of Seattle received four bids ranging from $224,400 to $274,443 as shown in the table below. Bids were greater than 10 percent over the engineer's estimate. Contractor Bid % over Engineer's Estimate J.P Frances $224,400 30% Holmberg Co. $251,250 46% MacDonald-Miller $257,752 50% Design Air $274,443 60% Staff analyzed the engineer's estimate of $172,000 and found the following items were not priced appropriately for the estimate. Port staff believes the lowest responsive and responsible bid represents a fair and reasonable price. COMMISSION AGENDA Tay Yoshitani, Chief Executive Officer August 31, 2012 Page 3 of 5 The high cost of labor for off-hour and holiday work required to complete the work over Thanksgiving weekend was not adequately accounted for in the engineer's estimate. Although some upfront work can be done during regular hours, the work of removing the existing cooling tower and installing the new cooling tower, and bringing in online, must be done during non-Port business hours because of the disruption that would occur during working hours. The amount of work requires a long holiday weekend to complete. It is likely the contractor will use a crane barge for the cooling tower replacement. The cost of crane barge was not represented in the engineer's estimate. PROJECT JUSTIFICATION: The P69 cooling tower is at the end of its service life. If it is not replaced, the Port runs the risk of not being able to cool the building. The inability to cool the building would result in unacceptable indoor air quality and damage to the data center and electrical service equipment. PROJECT SCHEDULE: Replacement of the cooling tower is expected to occur over Thanksgiving weekend 2012. FINANCIAL IMPLICATIONS: Budget/Authorization Summary: Original Budget Small Project Authorization $275,000 Previous Authorizations $65,000 Current request for authorization $75,000 Total Authorizations, including this request $415,000 Remaining budget to be authorized $0 Total Estimated Project Cost $415,000 Project Cost Breakdown: This Request Total Project Construction (including in-house labor) $36,000 $236,200 Taxes $6,200 $24,500 Construction Contingency $11,800 $33,800 Project Management & Other Soft Costs $21,000 $55,500 Design and Permitting $0 $65,000 Total $75,000 $415,000 COMMISSION AGENDA Tay Yoshitani, Chief Executive Officer August 31, 2012 Page 4 of 5 Budget Status and Source of Funds: This project was included in the 2012 Approved Annual Budget under the Real Estate 2011 Small Project CIP C800359 in the amount of $275,000. An additional $65,000 funding was approved by Commission in November 2011 for a total project budget of $340,000. The additional $75,000 that is now requested to fully fund this project is available due to timing delays in other Real Estate Division Small Capital projects. This project will be funded by the Tax Levy. Financial Analysis and Summary: CIP Category Renewal/Enhancement Project Type Renewal & Replacement Risk adjusted discount rate N/A Key risk factors Project schedule could be delayed due to lead-time requirements for procurement. Due to the need to minimize tenant disruptions, procurement delays could result in deferring the project installation schedule until the Christmas holiday weekend. Project cost for analysis $415,000 Business Unit (BU) Facilities Management Effect on business performance This project will not generate any incremental revenue. Total depreciation expense from this project is estimated at $20,750 per year based on a twenty-year asset life. The allocation of actual project costs to specific assets will be finalized near the end of the project, estimated to be the end of the fourth quarter in 2012. Net Operating Income after Depreciation for this facility will decrease by the associated incremental depreciation from project. IRR/NPV N/A ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: Alternative 1: Do not replace the cooling tower. The cooling tower will eventually break down causing unacceptable indoor air quality, as well as damage to data center and electrical service equipment. This is not the recommended alternative. Alternative 2: Continue with the planned P69 Cooling Tower Replacement Project. Authorization of an additional $75,000 for a total project authorization of $415,000 will allow replacement of the cooling tower before the cooling tower breaks down permanently and before the next warm weather season. This is the recommended alternative. COMMISSION AGENDA Tay Yoshitani, Chief Executive Officer August 31, 2012 Page 5 of 5 OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: None. PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: November 8, 2011 - The Commission authorized $65,000 for a total project authorization of $340,000.
Limitations of Translatable Documents
PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.