5g

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      5g 
ACTION ITEM             Date of Meeting    June 26, 2012 

DATE:    June 18, 2012 
TO:      Tay Yoshitani, Chief Executive Officer 
FROM:    Nick Milos, Manager, Corporate Facilities 
Curtis Stahlecker, Capital Project Manager 
SUBJECT:  P-69 Built-up Roof Replacement - Design 
(CIP #C800314) 
Amount of This Request:    $404,000    Source of Funds:  Airport Development Fund,
General Fund (Seaport), and
Tax Levy (Real Estate) 
Est. State and Local Taxes:  N/A       Est. Jobs Created: N/A 
Est. Total Project Cost:     $2,012,000 

ACTION REQUESTED: 
Request Commission authorization for the Chief Executive Officer to proceed with design and
preparation of construction documents, project management, and permitting for the design phase
of the Pier 69 Built-up Roof Replacement Project. The amount of this request is $404,000,
bringing the current authorization for the project to $445,000 for a total estimated project cost of
$2,012,000.
SYNOPSIS: 
This memorandum requests authorization to proceed with the design of a new roofing system to
replace the built-up section of the Pier 69 roof. The built up section has had minor leaks in the
past and is nearing the end of its design life, as recommended in the condition assessment report
prepared in 2008. Additional design functions that will occur with the authorization will be to
investigate and make a determination on the remaining useful life of the metal and membrane
roof sections; investigate and incorporate environmentally sustainable practices and materials
into the roofing system using total cost of ownership as the evaluation criteria. This project was
included in the 2012 plan of finance for $1,992,000. The additional $20,000 needed to complete
the project is available due to timing delays in other projects. This project provides potential
work for small business. Design for this project will be accomplished through an indefinite
delivery, indefinite quantity (IDIQ) consultant contract.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
June 18, 2012 
Page 2 of 6 
BACKGROUND: 
The Pier 69 building is the corporate headquarters for the Port of Seattle. In addition, the
building has tenants including the Victoria Clipper, Arctic Storm, and the Portside Caf. The
building underwent a major retrofit in the early 1990s and is in good condition. The roof is
approximately 19 years old and is made up of three different roofing systems; built-up, metal, 
and membrane. The built-up and metal roof systems cover roughly the same surface area on the
roof, 32,250 square feet (sf.) and 31,000 sf., respectively. The membrane section is much
smaller at 6,250 sf. and is located under the patio pavers at each end of the building. 
The roofing systems are the original roof installed on the building in the early 1990s. The metal
and membrane roof systems have performed quite well and have had no leaks. The built-up
system has also performed very well but has had some minor leaks that were repaired in 2007.
After the repairs were made, a roofing consultant was retained in 2008 to evaluate the condition
of the roof and make an assessment report on the built-up and metal roof sections. The findings
of the condition assessment gave approximations for the remaining service life of the built-up
sections and maintenance suggestion for both systems. The suggested maintenance was
performed and an ongoing maintenance program is continuing. The membrane system was not
included in the scope of the condition assessment report. 
The report indicated the built-up section was nearing the end of the design life and the core tests
and the visual inspections showed the system is delaminating and developing surface blisters.
Additionally the report indicates the east and west sections are deteriorating at different rates.
The report recommended replacement of the eastern half of the roof in one to three years (2009
2011) and in three to four years (2011-2012) for the western half. The report also stated the
metal roof was in good condition and did not give an estimate of the remaining service life but
did say the metal roof should last for many years. 
While making preparations for this funding request, Port staff conducted a site visit on the roof.
The site visit identified that the protective finish on the metal roof was beginning to peel in
several locations. As this condition was not occurring in 2008 when the prior condition
assessment was conducted, staff recommends that during the design process a condition
assessment of the metal roof and membrane be conducted. The assessments should provide
information about the remaining service life for both roof systems and any restorative actions
that may need to be performed. 
PROJECT JUSTIFICATION: 
With the built-up portion of the Pier 69 roof nearing the end of the design service life, replacing
this section of the roofing system now will eliminate costly leak repair and potential damage to
existing infrastructure and disruption to staff activities.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
June 18, 2012 
Page 3 of 6 
Project Objectives: 
Design and install a new roofing system on a Port-owned asset. 
Minimize disruption to the staff, tenants, and tenant operations. 
Investigate environmentally sustainable practices during the design and incorporate into the
project where practical. 
Complete project on time and within budget. 
PROJECT SCOPE OF WORK AND SCHEDULE: 
Scope of Work: 
The project consists of the following components: 
Evaluate the existing condition of metal and membrane roofing systems; 
Design and install a new roofing system over the built-up roof sections at the Pier 69 facility; 
As required, remove and dispose of the materials from the existing built-up roof; and 
Include environmentally sustainable components and construction methods as appropriate. 
Schedule: 
The anticipated schedule for the project will have the installation of the new roof occurring
during the summer of 2013. The following table contains the major schedule elements. 
Start         Finish 
Commission Authorization for Design             June 2012       June 2012 
Design Process                            July 2012   February 2013 
Commission Authorization for Construction       February 2013    February 2013 
Advertise and Award                     February 2013      April 2013 
Construction                              July 2013   December 2013 
FINANCIAL IMPLICATIONS: 
Budget/Authorization Summary:                      Total Project Cost 
Previous Authorizations Manager Corporate Facilities                     $41,000 
Current request for authorization                                $404,000 
Total Authorizations, including this request                         $445,000 
Remaining budget to be authorized (pending design recommendations)        $1,547,000 
Total Estimated Project Cost                               $2,012,0000 
Project Cost Breakdown:                 Current Request       Total Project 
Construction                                   $0         $1,288,000 
Construction Management                     $27,000         $129,000 
Design                                  $258,000         $258,000 
Project Management                        $150,000        $180,000
Permitting                                  $10,000           $19,000

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
June 18, 2012 
Page 4 of 6 
State & Local Taxes (estimated)                       $0          $138,000 
Total                                     $445,000         $2,012,000 
Budget Status and Source of Funds: 
The P-69 Built-up Roof Replacement project (CIP #C800314) was included in the 2012 Plan of
Finance as a Committed- Real Estate Division Approved project, in the amount of $1,992,000.
The estimated additional $20,000 needed to complete this project is available due to timing
delays in other planned projects.
Since Pier 69 is the corporate headquarters for the Port, the funding for the project will be
allocated between the Airport Development Fund (52%), Seaport General Fund (35%) and the
Real Estate Division - Tax Levy (13%). 
Financial Analysis and Summary: 
CIP Category         Renewal/Enhancement 
Project Type          Renewal & Replacement 
Risk adjusted discount   N/A 
rate 
Key risk factors         Construction costs may increase if required work is more
extensive than currently known. The construction cost
estimate will be refined during the design process.
Project cost for analysis    $2,012,000 
Business Unit (BU)      P-69 Facilities Management 
Effect on business       This asset replacement project will not generate any
performance          incremental revenue.
Incremental depreciation expense from this project is
estimated at $101,000/year, based on a 20-year asset life.
NOI after Depreciation will decrease by the associated
depreciation from this project. 
NOI (in $000's)       Year 1  Year 2  Year 3  Year 4  Year 5
NOI             $0    $0    $0    $0    $0
Depreciation        ($101)  ($101)  ($101)  ($101)  ($101)
NOI After Depreciation   ($101)  ($101)  ($101)  ($101)  ($101)
IRR/NPV          N/A 
Lifecycle Cost and Savings: 
During the design, lifecycle cost analysis will be utilized to identify the lowest total cost of
ownership for the replacement roofing system.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
June 18, 2012 
Page 5 of 6 
STRATEGIC OBJECTIVES: 
This project enhances Real Estate Division Vitality by maintaining the roofing system's 
integrity; preserving an asset; demonstrating financial stewardship; and proactively maintaining
and preserving the Port's corporate headquarters. 
ENVIRONMENTAL SUSTAINABILITY: 
The project affords the opportunity to investigate and analyze a number of environmentally
sustainable options during the design. Options that provide the lowest total cost of ownership
and are economically sound will be advanced into the construction phase. 
Potential environmentally sustainable options to review include: rainwater harvesting, reduction
in roof heat adsorption, maximizing recycled content of new materials, evaluating future disposal
costs, and evaluating inclusion of renewable resource project as part of roof replacement project
including installing wind generation equipment or a passive solar system. The decision to install
renewable energy equipment will be based on total cost of ownership and conditions of existing
roof components. 
BUSINESS PLAN OBJECTIVES: 
The mission of Pier 69 Facilities Management is to operate and maintain a safe, secure,
comfortable, productive, and efficient workplace. One of their service strategies for
accomplishing this mission is to operate and maintain headquarter facilities with emphasis on
continuous improvement, outstanding customer service, optimal staffing levels, environmental
stewardship, and proactive maintenance. This project aids the Facilities Management group in
accomplishing their mission and one of their service strategies by proactively maintaining the
building. 
TRIPLE BOTTOM LINE SUMMARY: 
This project represents an investment in our current facility and supports the long-term vitality of
the Port by maintaining an existing valuable asset, provides potential work for small business, 
and affords opportunities to investigate and implement environmentally sustainable practices on
the roofing system. The replacement of the roof section will also prevent water leak damage to
the building systems and disruptions to the Pier 69 staff and operations. 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
Alternative 1: Increase the maintenance inspections and repair the built-up roof as layer
delamination occurs and leaks appear. While postponing the replacement costs, this alternative
allows the continuation of retrogressive deterioration of the roofing system increasing
maintenance and emergency repair costs for the roof and increases the potential for ceiling, floor, 
and equipment damage caused by the leaks. This is not the recommended alternative.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
June 18, 2012 
Page 6 of 6 
Alternative 2: Proceed with the design and replacement of the built-up roof system. This will
reduce future risks and consequences to the building, internal appurtenances and staff
disruptions, should a leak in the roofing system occur. This is the recommended alternative. 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
None. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
None.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.