6d

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      6d 
ACTION ITEM             Date of Meeting    April 10, 2012 

DATE:    March 30, 2012 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    Dave Soike, Director, Aviation Facility and Capital Program 
SUBJECT:  Second Reading and Final Passage of Resolution No. 3660: Declaring
Miscellaneous Personal Property Surplus and Authorizing its Sale
ACTION REQUESTED: 
Request Second Reading and Final Passage of Resolution No. 3660: A resolution of the Port
Commission of the Port of Seattle declaring certain personal property, including copper wire,
surplus for Port District purposes and authorizing the Chief Executive Officer to execute all
documents necessary for its sale. The estimated value of the property to be surplused is $31,423. 
SYNOPSIS: 
This action surpluses both large diameter electrical cable and air conditioners no longer needed
for Port District purposes. The electrical cables originate from a temporary electrical power
project, while the air conditioners originate from the Central Terminal project. The total
estimated value of the items to be surplused is approximately $31,423, lower than the $50,000
threshold above which RCW 39.33.020 requires a public hearing. 
BACKGROUND: 
In 2009, the Howard Hansen Dam, built in 1962, developed structural problems that limited the
amount of water able to be stored behind it. That led to concerns that heavy rain storms would
require the dam operators to release large amounts of water to prevent failure of the dam
structure. The release of water into the Kent Valley areas could have resulted in flooding that
could have led to power outages because major electrical substations that feed Seattle-Tacoma
International Airport are located in the valley. As a result, the Airport teamed with Puget Sound
Energy (PSE), and both organizations put in place temporary measures to reduce the chances of
power loss to the Airport. PSE diked around its substations and added other operational
provisions while the Airport added temporary mobile generators and linked them to permanent
Airport electrical substations with large diameter copper cables. The airlines agreed with these
temporary measures for multiple winter seasons, and later agreed with the Port's decision to
forgo the generators when the risk was reduced by emergency improvements made to the dam.
As a result the generators were no longer rented, and the electrical cables are no longer necessary
to store for re-use.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
March 30, 2012 
Page 2 of 3 
In 2011, two temporary power stations were demobilized and copper cable along with
miscellaneous utilities from the project are no longer of use to the Aviation Division. The north
site included approximately 5,510 pounds of copper wire and the south site included 
approximately 7,385 pounds of copper wire with a salvage value at current market price of
$1.675/pound, totaling approximately $20,993. Other miscellaneous piping and valve assembly
that is no longer of use also remains for surplus with an approximate salvage value of $200. The
Port of Seattle continues to provide storage.
Other surplus items currently stored include Trane IntellipakTM commercial single-zone rooftop
air conditioners with controls that were previously used in the Central Terminal Expansion
project and were a direct purchase by the contractor in 2004. The Airport has no viable use for
this equipment. The estimated salvage value is approximately $10,230. 
The approximate total salvage value of all listed items is $31,423. 
SCHEDULE: 
It is requested that the Port make available the copper cable, miscellaneous personal property, 
and the Trane IntellipakTM commercial single-zone rooftop air conditioners with controls for bid
or auction as soon as is practicable.
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
The Port could continue to store the copper cable, miscellaneous personal property, and Trane
IntellipakTM commercial single-zone rooftop air conditioners with controls. This is not the
recommended alternative. 
No other appropriate Port use for the material could be found. It is requested that the Port
dispose of surplus personal property in accordance with the Revised Code of Washington
53.08.090. This is the recommended alternative. 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
Resolution No. 3660. 
PREVIOUS COMMISSION ACTIONS: 
October 16, 2009 - Declaration of Emergency was executed by Tay Yoshitani to allow staff to
lease generators for back-up power generation at the Airport. Flooding of the Green River
Valley has the real and immediate threat to significantly impact the operations of the Port of
Seattle, including interruption of electric service to Seattle-Tacoma International Airport. 
October 20, 2009 - Commission received a briefing and approved the Emergency Declaration to
provide back-up electric power at Seattle-Tacoma International Airport. 
August 24, 2010  Commission authorized to design, advertise, and award major construction
and small works contracts, to amend previous purchase orders, and execute contracts for
equipment and material, execute a contract to Puget Sound Energy and authorize utilization of
Port Crews for the Seattle-Tacoma International Airport. The total project authorization was
$3,542,000.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
March 30, 2012 
Page 3 of 3 
July 19, 2011  Commission authorized to (1) update and complete design and provide
construction support using an existing indefinite delivery/indefinite quantity contract; (2) execute
one-year contracts, with options to renew for four one-year periods, to lease or purchase nine
two-megawatt generators and associated equipment and material; (3) advertise and execute a
major construction-project-specific, unit-price contract; and (4) authorize utilization of Port
Forces for Seattle Tacoma International Airport Temporary Backup Power Project, for a total
project authorization of $3,100,397. 
April 3, 2012, First Reading  Resolution No. 3660.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.