6a

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      6a 
ACTION ITEM             Date of Meeting   March 27, 2012 

DATE:    March 16, 2012 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    Fred Chou, Project Manager, Seaport Project Management 
Kathy Bahnick, Manager, Seaport Environmental Programs 
Susan Ridgley, Senior Port Counsel 
SUBJECT:  Agreed Order No. DE 8938 with the Washington State Department of Ecology for 
Environmental Remediation at Terminal 91 
Source of Funds: Tax Levy              Est. Workers Employed: No Impact 

ACTION REQUESTED:
Request Port Commission authorization for the Chief Executive Officer to execute an Agreed
Order No. DE 8938 with Washington State Department of Ecology (Ecology) for the
implementation of the Cleanup Action Plan, and to address contamination in the Upland area of 
Terminal 91. This Order will replace the 2010 Agreed Order No. DE 7321. Execution of the
Order commits the Port to implement the work required by Ecology as outlined in the Order. 
SYNOPSIS:
The purpose of this action is to sign on to a new agreed order for (1) implementation of the work
identified in the final Cleanup Action Plan (CAP), including the installation of certain remedial
actions and the completion of compliance monitoring, and (2) continue to investigate and
manage contamination in the Upland Area of the Terminal 91 Facility (see map), including any
units newly identified during implementation of the final CAP. 
The Port developed a draft CAP which identified six cleanup alternatives for the cleanup at
Terminal 91. After the public comment period ended, Ecology selected the alternative that the
Port had recommended in the draft CAP and approved the final CAP in December 2010. In
2011, staff worked with Ecology on a new agreed order for implementation of the final CAP.
On January 20, 2012, Ecology issued a new draft agreed order for public comment. With public
comment incorporated, the 2012 agreed order is ready for execution. After execution of the
order, the project will move into the design development/permitting phase. 
The estimated total cost under this agreed order is $11,730,000. This estimated cost does not
include anticipated cost recovery opportunities, such as Ecology grants, nor does it include the

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
March 16, 2012 
Page 2 of 6 
costs to address any discrete units that may be discovered during implementation of the
CAP. To date, the Port has spent approximately $8,885,000 on work performed at the site since
1993. A portion of the funding to implement this order is already approved under the 2012
annual Environmental Remediation Liability (ERL) authorization (December 6, 2011). Over
80% of the estimated future agreed order costs have been booked. Additional funds to
implement the future work under the order will be authorized and reported under subsequent 
annual ERL spending authorizations and five-year plans. 
PROJECT DESCRIPTION AND JUSTIFICATION: 
The Terminal-91 (T-91) site consists of the entire Terminal 91 facility, including a former tank
farm that was constructed in the 1920s. A portion of the former tank farm was operated as a
dangerous waste treatment and storage facility under a Resource Conservation and Recovery Act
(RCRA) permit from 1980 until its closure in the late 1990s. The remainder of the tank farm 
was operated as a fuel storage facility until 2005. 
The T-91 site is regulated under both an RCRA permit and a Model Toxics Control Act (MTCA)
agreed order. The RCRA permit remains in place because a portion of the site (the tank farm)
was formerly permitted to operate as an RCRA-regulated dangerous waste treatment and storage
facility. The RCRA facility has not operated since 1995, and the tank farm structures that
housed these operations were in fact demolished in 2005. Both the former RCRA facility, and
the surrounding piers and terminal, are now being cleaned up under the MTCA program. The
Port, as the property owner, is required to hold the permit until cleanup ("corrective action") is
completed. The permit imposes corrective action by incorporating a separate agreed order issued
under the MTCA. 
The Port of Seattle entered into an MTCA agreed order in 1998 (the "1998 agreed order").
Philips Services Corporation (PSC) and Pacific Northern Oil Corporation (PNO), as former
operators of the tank farm, also signed the 1998 agreed order. Both PSC and PNO subsequently
went out of business, however, leaving the Port as the sole responsible party on the 1998 agreed
order. Under the 1998 agreed order, the Port was required to prepare a Remedial Investigation
and Feasibility Study, and to develop a CAP.
The 1998 order was replaced by a new agreed order in 2010. The 2010 agreed order continued
the requirement to complete the feasibility study and develop the draft CAP, and extended the
geographic definition of the site beyond the tank farm to encompass the entire Terminal 91
property owned by the Port (including submerged lands). Ecology required this change to satisfy
an RCRA permit requirement that corrective action must include all contiguous property under
the permit-holder's ownership.
Environmental investigations at the T-91 site have been ongoing since the early 1980s and
continue to the present time. A summary of past investigative activities can be found in the final
remedial investigation report and in the final feasibility study report. The primary area of
contamination at the site is the tank farm and associated operations. Chemicals of concern found
in the tank farm site groundwater and soils include total petroleum hydrocarbons (including

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
March 16, 2012 
Page 3 of 6 
floating product on the groundwater), volatile organic compounds, semi-volatile organic
compounds, polychlorinated biphenyls, and metals. The cleanup activities are designed to
address direct contact with site soil, indoor air quality due to site contamination, and impact to
aquatic receptors. 
The Ecology-selected cleanup approach is identified in the December 15, 2010, final CAP and
the new 2012 agreed order will require the Port to implement the work identified in the final
CAP, which includes remedial measures designed to prevent migration of contaminants to Elliott
Bay and to prevent direct contact with contaminants. These remedial measures include
installation of a barrier wall at the tank farm, installation of product recovery trenches, capping
the tank farm area, and removal of subsurface structures. The final CAP also includes 
excavation to address contamination from a historic pipeline release on Pier 91, and
decommissioning of old fuel pipelines located within the tank-farm-affected area and on the
piers. In addition, long-term operation and monitoring of the installed systems and compliance
monitoring are included. The order also requires investigation and cleanup of discrete units in
the upland area not included in the CAP, and placement of a restrictive covenant on the property.
The restrictive covenant will limit exposure to hazardous substances by regulating land uses on
the property and providing notice to future users as to the presence of hazardous substances. The
agreed order defers action on marine sediments in the vicinity of Terminal 91. 
An Ecology-led public comment period for the 2012 agreed order occurred from January 20
through March 5, 2012, so that community or public concerns could be addressed prior to
signing the agreed order. One comment was received during the public comment period. The
comment from King County asked Ecology to remove the west yard area from the order. 
PROJECT SCHEDULE: 
1.  Today: Obtain authorization to execute the 2012 agreed order 
2.  2Q 2012 - 3Q 2013: Develop plans and specifications. Obtain permit approvals. 
3.  4Q 2013  4Q 2014: Implement the cleanup remedy. Construction may be deferred to begin
in 2Q 2014 to avoid wet season construction. 
4.  2015  2045: Perform long-term compliance monitoring, product recovery, and inspection
and maintenance of remedial components. 
5.  Ongoing: Continued investigations into the non-tank-farm portions of the site; recovery of
petroleum product from groundwater; and groundwater monitoring if required. 
FINANCIAL ANALYSIS: 
Terminal 91 Cleanup-up Project Estimate and Sources of Funding 
Previous Amounts Spent on Cleanup                     $8,885,000 
Cost Estimated Associated with this Agreed Order             $11,730,000 
Estimated Total Project Costs                           $20,615,000

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
March 16, 2012 
Page 4 of 6 
Estimated/Actual Sources of Funding: 
Past Amount Recovered (Settlement, Insurance, Grant)          $2,933,000 
Committed Future Grant Funding1                      $2,637,000 
Port of Seattle2                                       $15,045,000 
Total Sources of Funding                             $20,615,000 
Note 1: Staff will continue to seek additional future grant funding 
Note 2: Port is also seeking recovery from insurance companies 
Cost Estimate Associated with this Agreed Order: 
The actual cost for the cleanup design and implementation, including compliance monitoring, is
expected to vary, depending on actual site conditions, labor and material costs at the time of
construction, and any changed conditions or requirements established by the oversight agency
(Ecology). However, based on the final CAP, the current estimated costs for this work are
approximately $11,730,000.
Source of Funds: 
The costs to implement the cleanup design and implementation, including compliance
monitoring, were included in the Commission's 2012 ERL spending authorization and five-year
plan, approved on December 6, 2011. The ERL cost estimates were also included in the 2012 
plan of finance. Additional costs may be incurred if continuing investigations identify any new
areas requiring cleanup. Any additional cleanup costs that may be required as the project moves
forward will be recorded as a liability and a non-operating expense in accordance with Port
Policy AC-9. These amounts will be reported annually to the Commission via routine
environmental remediation liability reports and spending authorization requests. 
The Port's Tax Levy will pay the costs for the environmental cleanup project that are not
ultimately covered by cost sharing agreements, settlements, insurance, or other cost recovery
sources. In addition, Port staff is pursuing additional grant funding from Ecology for the design
and construction work. 
Potential Net Costs to the Port: 
The cost summary table above presents a breakdown of all the paid, committed, and/or
anticipated total known costs and recoveries associated with the T-91 cleanup, including both
prior and future design and cleanup activities. As shown, the total (start to finish) Port cost is
approximately $20,615,000. The total received and committed grant funds (not including future
settlement, insurance or uncommitted grant money) are approximately $5,570,000. Therefore,
the potential net cost to the Port to complete the T-91 cleanup work is expected to be up to
approximately $15,045,000. This estimated cost does not include additional cleanup if required
for new discrete units not yet discovered or ERL costs for the marine sediments.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
March 16, 2012 
Page 5 of 6 
STRATEGIC OBJECTIVES: 
This activity will remediate known threats to the environment from contamination and further
define other threats to the environment from contamination. These efforts are required to meet
regulatory mandates and manage Port liabilities, and support the Port's objective to "Exhibit
Environmental Stewardship through our Actions." After the remedial work, the areas could be
developed to maximize asset utilization and support financial performance and to "Ensure
Airport and Seaport Vitality." 
BUSINESS PLAN OBJECTIVES: 
Proceeding with this project ensures compliance and continued cooperation with Ecology and
will allow productive use of the property in the future.
ENVIRONMENTAL SUSTAINABILITY: 
State and federal laws require elimination of unacceptable levels of environmental risk caused by
the presence of contaminants in soil, groundwater and sediment. From the perspective of the
surrounding communities and the customers that we serve, the Port's participation in site
remediation is the hallmark of responsible environmental stewardship. 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
Do not enter into a new agreed order but continue the work under the existing 2010 order and
the RCRA permit. The 2010 agreed order includes the requirement to continue investigation
of newly discovered areas of concern but does not include implementation of the CAP. If the
Port does not sign the 2012 agreed order, Ecology would likely impose the requirement
through a unilateral enforcement order issued under the MTCA (and incorporated into the
RCRA permit). Ecology would be required to do so due to its responsibilities under the
federal RCRA requirements, as overseen by the U.S. Environmental Protection Agency.
This alternative is not recommended. 
Agree to enter into the 2012 agreed order. Port staff has negotiated the terms of the 2012
agreed order and recommend them as acceptable. Staff believes that the 2012 agreed order's
terms would provide more efficient and cost-effective cleanup procedures than would be
imposed through a unilateral order. This is the recommended alternative. 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
The following documents are available electronically: 
Agreed Order No. DE 8938 (39 Pages plus Exhibits A-F) 
A copy of the Agreed Order and Exhibits will be available at the Commission Meeting.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
March 16, 2012 
Page 6 of 6 
The following documents are attached to this memorandum: 
Map - Aerial Photo of the Terminal 91 Site 
Department of Ecology Fact Sheet for Terminal 91 Site 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
May 4, 2010, Commission authorized the Chief Executive Officer to execute the 2010 agreed
order with the Washington State Department of Ecology. 
December 6, 2011, Commission authorized $23,6000,000 spending in 2012 for Environmental
Remediation Liabilities.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.