7c

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA STAFF BRIEFING 
Item No.        7c 
Date of Meeting     February 28, 2012 

DATE:    February 21, 2012 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    Stan Shepherd, Manager Airport Noise Programs 
Tom Hooper, Aviation Planner 
SUBJECT:  Ground Run-up Enclosure Siting Study 
SYNOPSIS: 
Today's Commission update is about work in progress to analyze options for siting a
Ground Run-up Enclosure (GRE), for potential construction on the airfield. No decisions
have been made regarding the need or the siting of a GRE, as further evaluation and
Commission approval is required. No Commission action is being requested at this time.
Once further evaluation is complete, staff will return to the Commission for a follow-up
briefing and ask the Commission to provide direction on GRE construction. 
The GRE is one element of the ongoing Part 150 Noise and Land Use Compatibility
Study. If approved by the Federal Aviation Administration (FAA) through the Part 150
Study and authorized by the Commission, the GRE would become eligible for partial
funding via grant funds through the Airport Improvement Program (AIP).
BACKGROUND: 
A GRE is a large three-sided facility used by air carriers for aircraft engine testing,
following maintenance. GREs can contribute to noise reduction in surrounding 
communities of up to 15 to 20 decibels (dB). Currently, there are approximately two runups
per day. Run -ups can generate a significant amount of noise within the community,
often triggering noise complaints.
In March 1990, the Noise Mediation Committee concluded its negotiations on noise
mitigation for Seattle-Tacoma International Airport (Airport). In regard to ground noise,
the agreement stated, "If any additional maintenance base is developed at the airport, it
will require the provision of an engine 'hushing' facility (or GRE). The GRE Siting and
Feasibility Study would provide the capacity to abate the noise of the engine maintenance
run-ups." Since then, no additional maintenance bases have been developed at Sea-Tac. 
On December 12, 2000, the Commission adopted Resolution No. 3443 (Part 150 Study)
that directed staff to complete a Siting and Feasibility Study for a GRE at the Airport.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
February 21, 2012 
Page 2 of 4 
The purpose of the study was to determine whether a GRE would significantly reduce
noise impacts from aircraft engine maintenance run-ups in the surrounding communities. 
On September 30, 2001, a GRE Siting and Feasibility Study was completed. It found that
a GRE could provide significant noise reduction and included possible locations,
orientation of the facility, and percentage of anticipated use by aircraft type. The study
concluded that the best location for a GRE would be in the future proposed South
Aviation Support Area (SASA). SASA was a proposed development area at the far south
end of the airfield, determined through the master planning effort for the Airport's 1997
Master Plan to be the preferred location for relocation and expansion of cargo and aircraft
maintenance facilities. Shortly after the completion of the GRE Siting Study, further
planning analysis concluded that SASA would not be built and an alternative planned
location for the GRE would need to be identified. 
Current Part 150 GRE Feasibility Study 
The Part 150 consulting team and Port of Seattle staff have evaluated potential locations
for a GRE on the airfield. The GRE evaluation began with six general locations on the
airfield based on available land, future development, and proximity to existing aircraft
maintenance facilities. Due to physical constraints, each location presents difficult
tradeoffs. Each location was evaluated, using the following criteria: potential noise
impacts to existing facilities; compatibility with future planned facilities; operational
impacts to aircraft performing run-ups and other aircraft; height restrictions; Air Traffic
Control (ATC) line of sight constraints; community noise benefits/impacts;
environmental concerns; and construction cost.
Considering the current and anticipated future fleet mix, 96 percent of all aircraft
operating at the Airport would be able to use a GRE designed to accommodate the
Boeing 737-900 aircraft. In any location on the airfield, the GRE would be available a
high percentage of the time based on historic wind conditions and orientation of the
facility. 
The Feasibility Study work is preliminary and on-going. 
Airline Concerns
Port staff and the consulting team provided a high level briefing to the Airlines Airport
Affairs Committee (AAAC) on June 27, 2011, on the preliminary findings of the study.
At that meeting the airlines expressed concerns regarding the operational feasibility and
funding of a GRE. A letter was submitted for the record to the Port Commission at the
June 28, 2011, Commission meeting questioning the justification of, need for, and cost of
the facility.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
February 21, 2012 
Page 3 of 4 
Cost Estimate 
The cost for a GRE structure is estimated to be approximately $3 to $6 million.
Additional costs for site preparation and infrastructure are significantly different for each
possible site. 
Source of Funds 
This project is FAA AIP Grant eligible at approximately 80 percent, if approved through
the Part 150 Study; however, the availability of federal funding at this time is unknown.
The remaining portion would be funded through Airport revenues.
NEXT STEPS: 
Include the GRE as one element to the Part 150 anticipated to be submitted to the
FAA in 2012 
Public hearing and comment period for all elements of the Part 150 
Complete Environmental Review under State Environmental Policy Act (SEPA)
and National Environmental Policy Act
Airline Approval 
Commission Approval 
Submit to FAA for final review 
FAA Approval 
Commission Update 
Apply for FAA AIP grant funding 
If FAA grant secured, begin Capital Improvement Program process of design and
construction 
OTHER DOCUMENTS ASSOCIATED WITH THIS BRIEFING: 
PowerPoint Presentation 
Letter dated June 27, 2011, from the Airlines Airport Affairs Committee to the Port
Commission 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
December 12, 2000 - Commission adopted Resolution No. 3443 (Part 150 Study)
directing staff to complete a Siting and Feasibility Study for a GRE at the Airport 
December 19, 2001- Staff briefed the Commission on the GRE Siting and Feasibility
Study and the preferred outcomes 
October 16, 2007  Comprehensive Development Plan GRE Staff Briefing to
Commission

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
February 21, 2012 
Page 4 of 4 

June 22, 2010  Part 150 Noise and Land Use Compatibility Update Briefing, including
GRE information 
October 26, 2010 - Part 150 Noise and Land Use Compatibility Update Briefing,
including GRE information 
June 28, 2011 - Part 150 Noise and Land Use Compatibility Update Briefing, including
GRE information 
August 23, 2011 - Part 150 Noise and Land Use Compatibility Update Briefing,
including GRE information 
June 28, 2011  Part 150 Noise and Land Use Compatibility Update Briefing, including
GRE update, held in Federal Way

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.