5b

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      5b 
Date of Meeting     July 26, 2011 

DATE:    July 19, 2011 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    Wayne Grotheer, Director, Aviation Project Management Group 
John Christianson, General Manager, Aviation Maintenance 
SUBJECT:  2011-2013 Roof Replacement Project (CIP# C800459) 
Amount of This Request: $200,000       Source of Funds: Airport Development Fund 
Total Project Budget: $4,770,000 
ACTION REQUESTED: 
Request Commission authorization for the Chief Executive Officer to prepare design and
construction bid documents, using Port Engineers to design the replacement of approximately
167,000 square feet of roof systems located at the Fire Station and on the north end of the Main
Terminal at Seattle-Tacoma International Airport (Airport). This authorization is for $200,000 of
a total estimated project cost of $4,770,000 (CIP# C800459). 
SYNOPSIS: 
This memorandum requests authorization to proceed with the design that would remove and
replace the current roofing system on the Fire Station and sections of the north end of the Main
Terminal in order to avoid leaks that cause damage to the underlying infrastructure, equipment,
and interior facilities. Portions of the roof being replaced were installed in 1993, 1994, and 1996
and will be at or beyond their useful life expectancy when replacement takes place. This is one
of a series of necessary progressive design and construction steps to accomplish reroofing of the
airport facilities over the next several years (see attached map). Staff expects to seek
Commission authorization for similar work in each of the coming years.
BACKGROUND: 
In 1991, the Airport began a major Terminal Facility re-roofing program that was completed in
1997. Since 1997, some Airport roofs have been replaced on a project or roof-area-specific basis. 
The first phase of the cycle of roof replacements that are now under construction included
sections M-1, M-2, M-10, M-12, MP-2, and MP-3 on the south end of the Main Terminal. 
This project is the second phase of the cycle of roof replacement and includes Main Terminal
sections A, B, C, M-3, M-4, M-5, M-6, M-7, M-8, M-9, MP-1, MP-4, MP-5, MP-6, and the Fire

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 19, 2011 
Page 2 of 5 
Station roof (see attached map). When originally built, the Airport's current roofs had a 15-year
life expectancy that has been, or shortly will be, expired. 
The Airport's roof replacement program has been prioritized and phased over the next 6-10 years
by a team comprised of Engineering, Maintenance, and Project Management. This first phase of
the program was triggered by leaks and the discovery of fractured roof membranes over the last
several years. Replacement reduces the potential for facility damage and liability risks associated
with roof leaks. This is necessary in order to provide safe and reliable facilities to our business
partners, tenants, and the traveling public. 
The ability to eliminate leaks by reroofing will mitigate the cost of leak investigation,
maintenance, and repairs associated with responding to and "tracking down" the root cause of
the roof leaks. Tracking leaks and making repairs is labor intensive and does not always solve
the problem. When the roof systems are in a fractured and deteriorated state, more leaks can be
created by walking on the roof looking for the original problem. This tracking work can take
anywhere from days to months as this effort is weather dependent and success cannot be verified
until the next heavy rain. 
PROJECT JUSTIFICATION: 
Project Objectives: 
This project will remove and replace the existing roof system at the Fire Station and the north
end of the Main Terminal, eliminating costly leak repair and potential damage to existing
infrastructure. 
PROJECT SCOPE OF WORK AND SCHEDULE: 
Scope of Work: 
Remove and replace existing roof systems on the Fire Station and north end of the Main
Terminal and install a new 65 millimeter elastomeric roofing system. 
The Fire Station roof system is approximately 29,000 square feet. The north end of the Main
Terminal, roof sections A, B, C, M-3, M-4, M-5, M-6, M-7, M-8, M-9, MP-1, MP-4, MP-5, and
MP-6 (see attached map), is approximately 138,000 square feet. Together, they total 
approximately 167,000 square feet of roofing systems. 
Schedule: 
Request for Authorization for Design                                July 2011 
Request for Authorization to Advertise for Bids (Fire Station)           January 2012 
Fire Station Complete                                        October 2012 
Request for Authorization to Advertise for Bids (terminal)              January 2013 
Project Completion                                        November 2013

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 19, 2011 
Page 3 of 5 
FINANCIAL IMPLICATIONS: 
Budget/Authorization Summary: 
Original Budget                           $4,770,000 
Budget Increase                                 0 
Budget Transfers                                 0 
Revised Budget                          $4,770,000 
Previous Authorizations                             0 
Current Request for Authorization                 $200,000 
Total Authorizations, including this request           $200,000 
Remaining Budget to be Authorized              $4,570,000 

Project Cost Breakdown:            This Request:       Total Project: 
Construction Costs                               $0          $3,607,000 
Sales Tax                                     $0           $340,000 
In-house Design                            $120,000               $0 
Aviation PMG and other soft costs                 $80,000           $623,000 
Total                                      $200,000          $4,570,000 
Financial Analysis and Summary: 
CIP Category                  Renewal/Enhancement 
Project Type                    Renewal & Replacement 
Risk adjusted Discount rate           N/A 
Key risk factors                   N/A 
Project cost for analysis              $4,770,000 
Business Unit (BU)                Airfield and Terminal 
Effect on business performance        NOI after depreciation will increase 
IRR/NPV                  As a cost recovery project, traditional financial
analysis measures such as net present value
(NPV) and internal rate of return (IRR) are not
meaningful.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 19, 2011 
Page 4 of 5 
CPE Impact                  Will increase approximately $.02 in 2013, but
no change to business plan forecast as this
project was included. 
This project, CIP # C800459, is included in the 2011  2015 capital budget and plan of finance
as a business plan prospective project. The funding source for this project will be the Airport
Development Fund.
The project estimate includes $111,000 in regulated materials expense funding. 
ENVIRONMENT AND SUSTAINABILITY:
The new roof will have a minimum solar reflective index that exceeds 78, which is the value
required to obtain the LEED Credit NC7.2. This will reduce air conditioning loads and save
energy. The new roofing systems will also be Energy Star rated. The insulating value of the new
roof will be greater than that of the existing roof. By replacing the roof and preventing damage
to the underlying building systems, the life of the existing building systems will be prolonged. 
STRATEGIC OBJECTIVES: 
This project supports the Port-wide strategic objective of Ensuring Airport and Seaport Vitality.
This project will maximize facility and asset utilization by replacing the Airport's roof systems
before they fail through a systemic and timely roof replacement program. The project will reduce
risk and liability issues, and safeguard the integrity of the building envelope and underlying
infrastructure from water infiltration due to failing roof systems. 
TRIPLE BOTTOM LINE SUMMARY: 
This roof replacement project represents an investment in our current facility and supports the
long-term vitality of the Airport, businesses within the Airport, and the traveling public.
Installation of a new Energy Star roofing system will reduce the energy demand of the Airport
through insulating against heat loss. Replacing the roof will prevent water leak damage to other
building systems, disruption of Airport operations, and will prevent perceptions of poor customer
service. 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
Alternative 1: Develop a systematic replacement program for the Airport's roof systems. Phase
the replacement program over multiple years, which allows the Airport to sustain serviceable
roof systems and provide safe and productive environments for our business partners and
passengers. Through roof inspection and analysis, the second phase of the roof replacement
program has identified 167,000 square feet of roof on the north end of the Main Terminal and the
Fire Station. This phase is intended to be designed in 2011 with actual roof replacements to be
accomplished in 2012 and 2013. The rest of this prioritized replacement program would be
accomplished over the next ten years and be approved on a project-by-project basis. This
process/alternative requires securing necessary approvals and funding for each specific phase of
the roof replacement program. This is the recommended alternative. 
Alternative 2: Install a green (vegetated) roof system. Green roofs are complete roof systems
comprised of vegetation, soil, drainage and waterproof membrane, requiring specific structural

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 19, 2011 
Page 5 of 5 
integrity not currently in place as part of the Airport structure. This alternative would create an
environment that could attract birds and other wildlife; increase bird strike hazards; and escalate
nuisance-wildlife control. Installing a green roof would be in direct conflict with the Airport's
existing Wildlife Hazard Mitigation and Wildlife conservation Program and the existing FAA
approved Airport Certification Manual. This is not the recommended alternative. 
Some airports have begun to use green roofs on new construction (thereby avoiding the extensive
redesign and structural strengthening retrofit issues for existing structures) using plants that do
not attract birds or wildlife. Staff will examine recent airport green roof developments more
thoroughly and determine potential applicability for smaller or pilot-scale projects at the Airport
that do not require structural strengthening to do so. 
Alternative 3: Continue to patch and repair the leaks risking continued retrogressive
deterioration throughout the entire roof system (terminal and concourses). This alternative
increases maintenance and emergency repair response and costs, not only due to the continual
patching of the existing roof system but also due to ceiling, floor, and equipment damage caused
by the leaks. This also increases liability should customers slip and fall. This is not the
recommended alternative. 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
Roof Replacement Planning Map. 
PREVIOUS COMMISSION ACTION: 
On September 22, 2009, the Commission was briefed on facility renewal projects that were
necessary in future years. The Airport re-roofing program was included in the presentation. 
On April 27, 2010, the Commission voted to approve design funds for the first phase of the
Airport re-roofing program.
On November 30, 2010, the Commission voted to authorize construction funds for the first phase
of the Airport re-roofing program.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.