6d

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      6d 
Date of Meeting     July 26, 2011 

DATE:    July 20, 2011 
TO:      Tay Yoshitani, Chief Executive Officer 
FROM:    Michael Ehl, Director, Airport Operations 
Wayne Grotheer, Director, Aviation Capital Improvement Program 
SUBJECT:  Design for Pavement and Joint Seal Replacement. (CIP # C102573) 
Amount of This Request: $465,000       Source of Funds: ADF 
Total Program Cost: $30,800,000 for a multi-year program. 
ACTION REQUESTED: 
Request Port Commission to authorize the Chief Executive Officer to complete the design and
perform any advance work in support of the 2012 Pavement and Joint Sealant Project for nonrunway
concrete pavement panels and joint seal replacement, spall repair and associated or
temporary facilities, such as striping, lighting, etc., on the Aircraft Operations Area in
anticipation of a 2012 construction contract. Budget requested for this work is $465,000 out of
an estimated total program cost of $30,800,000 for the multi-year program. 
SYNOPSIS: 
The Airport Airfield is a very large area where a variety of design and construction activity must
occur each year. As a result, multiple requests for authorization can reach the Commission each
year. This July 26th Commission meeting includes three separate authorization requests. The
work area for this particular authorization is shown on Attachment A. 
This authorization continues progress on a multi-year, non-runway airfield pavement
replacement program begun in 2010. This project will produce the final design for non-runway
concrete pavement panels and joint seal replacement, spall repair, and associated or temporary
facilities such as striping, lighting, etc. on the Aircraft Operations Area (AOA) in anticipation of 
a 2012 construction contract. The design is being performed by the Port's Engineering
department.  The design will include utilities and other scope items related to the project. The
final design will be completed in early 2012. Port staff will return to the Commission in early
2012 to request authorization to advertise and award a major construction contract and to provide
construction funding.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 20, 2011 
Page 2 of 6 
The scope of work associated with the advance work includes the design of temporary measures
needed to mitigate airline impacts due to anticipated gate closures. Closure of gates may be
required by the construction of the project and may cause reassignment of domestic and
international flights on multiple concourses. Advance work to mitigate these impacts may be
required to allow the major construction to occur during the 2012 construction season without
delay. The temporary measures may include infrastructure modification to existing gates,
signage, and other items to accommodate airline gate reassignments. Budget for this advance
work is in this request and is estimated to be less than $300,000. Advance work may include the
use of Port Crews, consulting services, small works contractors, and/or pre-purchasing some
materials and equipment related to the temporary measures.
BACKGROUND: 
Airport staff has been and is continuing to conduct visual surveys of the non-runway pavement
on the airfield to determine which pavement needs replacing and in what sequence. The extent
of the panel and joint seal replacement in 2012 will be based upon this ongoing monitoring. The
concrete and joint seal work must occur in a phased sequence, to minimize impacts to the airlines
and the airport patrons. Airport staff has identified multiple locations on taxiways, taxilanes, and
ramp areas for replacement, due to the deteriorating condition of the pavement, which is at the
end of its useful life. The proposed work in 2012 will focus on replacing pavement as well as
associated utilities in a number of locations on the AOA. 
Typical degradation of the concrete is occurring. Joint seal in the area has also degraded and in
some cases is nonexistent. 
This project is part of a multi-year program to replace some of the worst pavement and joint seal
on the airfield. The project will generally replace the most critical pavement first, but will
include other pavement sections when it makes sense. The criticality and order of the pavement
replacement may change over time, based on pavement deterioration, operational impacts, and
available budget. The total 2012 project cost will be developed when the scope of panel, joint
seal and associated items replacement, impact to taxilanes and taxiways, and phased sequencing
have been determined during the design phase. The overall program amount is $30.8 million, of
which $6,629,000 has been previously authorized for panel and joint seal replacement 
PROJECT JUSTIFICATION: 
In areas around the AOA, the age of the existing concrete is resulting in cracked and damaged
panels. There are areas of pavement throughout the AOA that need to be replaced. Concrete
debris resulting from the deteriorating pavement can become a hazard for aircraft and personnel. 
This project may displace airline operations at various gates located throughout the airport as
well as taxiway and taxilane configurations. Advance work, internal and external to the
terminals, may be necessary to facilitate airline temporary relocations.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 20, 2011 
Page 3 of 6 
PROJECT STATEMENT AND OBJECTIVES: 
Project Statement: 
Perform the concrete pavement panel and joint seal replacement final design including any
temporary modifications necessary to accommodate airline reassignments. 
Project Objectives: 
Complete the final design for the pavement and joint seal replacement and advance work in
preparation for construction beginning in spring of 2012. 
PROJECT SCOPE OF WORK AND SCHEDULE: 
Scope of Work: 
Produce final design for the apron pavement, and joint seal replacement. The design will include
utilities, temporary striping and lighting and other scope items related to the project. The final
design will be completed by early 2012. Construction is anticipated in 2012. 
Schedule: 
100% Design                  December 2011 
Commission Authorization           January 2012 
Advertise for Bids                  January 2012 
FINANCIAL IMPLICATIONS: 
Budget/Authorization Summary: 
Original Budget                                          $30,800,000 
Budget Increase                                             $0 
Revised Budget                                        $30,800,000 
Previous Authorizations this CIP                                 $6,629,000 
Current request for authorization                                   $465,000 
Total Authorizations, including this request                       $7,094,000 
Remaining budget to be authorized                              $23,706,000 
The $30,800,000 original budget for pavement replacement was set by the Aviation Investment
Committee and is intended to cover replacement over the next several years. Each successive
authorization will be requested on a yearly basis.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 20, 2011 
Page 4 of 6 
Project Cost Breakdown: 
Design                                                $150,000 
Project Management                                       $50,000 
Survey                                                $25,000 
Internal POS Support and Review                                $10,000 
Outside Professional Services                                     $30,000 
Port Construction Services                                      $200,000 
Total                                                      $465,000 
Budget Status and Source of Funds: 
This project is included in the 2011-15 capital budget and plan of finance within CIP #C102573.
The funding source for the 2011 and 2012 work will be existing revenue bond proceeds and the
Airport Development Fund. 
Financial Analysis and Summary: 
CIP Category                         Renewal/Enhancement 
Project Type                           Infrastructure Upgrade 
Risk adjusted Discount rate                  n/a 
Key risk factors                          n/a 
Project cost for analysis                     $30,800,000 
Business Unit (BU)                      Airfield 
Effect on business performance               NOI after depreciation will increase
since capital and operating costs will
be recovered through landing fees. 
IRR/NPV                       N/A 
CPE Impact                        Will increase CPE by $0.15 by 2015,
but no change to business plan
forecast as this project was included. 
ECONOMIC IMPACTS AND BUSINESS PLAN OBJECTIVES:
There are no new economic impacts related to renewal/enhancement projects since they are
primarily related to preservation of existing business activity. Ensuring reliable aircraft
operating surfaces aligns with the Airport's business plan that stresses providing safe and secure
airport facilities. 
STRATEGIC OBJECTIVES: 
This project supports the Port's strategy to "Ensure Airport Vitality" by maintaining a safe
operating environment as well as the Airport strategy to provide appropriate facilities and
infrastructure to ensure operation of a world class airport. 
The Airport's ramp area and taxiways are comprised of a series of concrete pavement panels, and
the associated utilities around the various Airport concourses. The ramp provides parking and

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 20, 2011 
Page 5 of 6 
access to the gate positions for aircraft. The taxiways provide access to and from the runways.
Maintaining the ramp and taxiways is critical for preserving access to aircraft parking and
runways. 
ENVIRONMENT SUSTAINABILITY AND COMMUNITY BENEFITS:
The concrete panel replacement and maintenance is eligible for a Categorical Exclusion and
Categorical Exemption under the National Environmental Policy Act (NEPA) and State
Environmental Policy Act (SEPA) due to the nature of the project. The environmental review for 
the project will be completed before the project is advertised for construction. 
During repair and maintenance activities, various sustainable practices will be considered and
implemented when practicable. These include, but are not limited to, performing a life cycle
analysis of materials used to ensure that resources being used and/or recycled are
environmentally and economically practical; utilizing onsite water for dust control and irrigation;
the reuse of materials such as concrete and soil; and employing low emission construction
equipment. 
TRIPLE BOTTOM LINE SUMMARY: 
Replacement of concrete pavement panels and the joint sealant are a financially responsible way
to ensure continued access to the gate areas and runways for the airline tenants and continued
gate availability for the traveling public. 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
1)  Do nothing: This alternative would result in operational and safety impact since the concrete
pavement is continuing to deteriorate. There would be an increase in risk of aircraft
ingesting concrete debris into aircraft engines for aircraft transiting the taxiways and
taxilanes. This is not the recommended alternative. 
2)  Replace the pavement and joint seal during the 2012 construction season as part of a
previously established, ongoing pavement panel replacement program. This is the
recommended alternative 
OTHER DOCUMENTS ASSOCIATED WITH THIS REQUEST: 
Attachment A  Map indicating where future construction may occur on a portion of the
pavement within the large ramp area.
PREVIOUS COMMISSION ACTION OR BRIEFING: 
On August 10, 2010, the Commission authorized the Chief Executive Officer to direct staff to: 1)
proceed with project management, design, environmental support, and preparation of 100 percent
design level construction documents for the replacement of slot drains, pavement and joint seal
at the South Satellite at Seattle-Tacoma International Airport; 2) execute and award outside
professional service agreements; 3) pre-purchase common-use gate equipment; and 4) allow Port

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
July 20, 2011 
Page 6 of 6 
Construction Services to self-perform, advertise for bids, and execute and award small works
construction contracts for common use equipment installation. 
On March 1, 2011, the Commission authorized the advertisement and award of a construction
contract for the 2011 Airfield Improvement Projects  Contract 2, consisting of slot drain,
pavement and joint seal replacement at Seattle-Tacoma International Airport (Airport).

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.