7a attach

Item No: ______7a_attach_____ __ 
Date of Meeting: July 26, 2011 
ATTACHMENT A 
TODAY'S BRIEFING FOR July 26, 2011 
RCF GC/CM Construction Contract: 
Construction Status Summary 
Construction progress is 93% complete. 
Construction costs are trending to be within authorized budget. 
An average of 125 construction workers on site daily. 
Over 1,350,000 work hours have been expended on the project to date. Based on the dollars spent to
date, over 3,700 new jobs have been created due to this project since project work commenced in
2008 (using data from the 2009 UW study performed for AGC). 
Current construction waste recycled materials rate is 97.23%. 
Recordable Incident Rate (number of injuries per 100,000 work hours) for 2011 is 3.32. Overall
project RIR is 3.56, significantly below the statewide rate of 11.0. There has been no time lost on the
job injuries for 3 years. 
Milestones Accomplished This Month 
Commissioning of the water systems has been completed. 
Customer Service Building (CSB)  Placement of the terrazzo in the lobby is substantially complete.
Installation of the bathroom fixtures and partitions is substantially complete.
Installation of electrical and mechanical systems and wall framing is substantially complete in QTA's
1 and 2. 
Architectural Stairs and Rails  Installation of north and south architectural stairs is complete.
Architectural handrail installation is complete around north escalator core openings. 
Architectural Metal Panels - Installation of architectural metal panels is complete. 
Helix Art  Installation of the helix art mesh is complete on both helices. Light fixtures are in place
as well.
Landscaping is complete in the north-west and south-west areas of the project. 
Work In Progress 
RCF Elevated Concrete Decks - Punch list work continues. 
CSB back of house floor, wall, and ceiling finishes are well under way. Installation of doors is in
progress.
RCF Operational Floor Plates - Painting of the operational floor plate ceilings and floor
waterproofing work continues. Sealing is 80% complete, and striping is in progress. Installation of
mechanical and electrical systems is in progress, and nearing completion on all levels in areas D, E
and F. Work on the core bathrooms is nearing completion. 
Seismic Joints - Installation of seismic joints on the floor plates and within the CSB is nearing
completion. 

Page 1 of 6

Elevator and Escalator Equipment - Installation is nearing completion. Installation of escalator
cladding is in progress. Significant work remains related to installation of escalator truss heaters and
associated wiring. 
Installation of electrical and mechanical systems and wall framing is nearing completion in QTA's 3
and 4. 
Car Wash Equipment  Installation is nearing completion. 
Architectural handrail installation around north escalator core openings is approximately 80%
complete around the south escalator core openings. 
Helix Art  Final adjustments remain to be completed. 
Landscaping is in progress on the south end of the project, as well as along the perimeter road next to
the main building. 
Temporary Erosion & Sediment Control  TESC items are being maintained. The Contractor
commenced infill of the TESC pond, with the runoff from the small remainder of exposed areas now
being diverted to the water quality vault. 
The Contractor is preparing to re-bid the work package for 800 MHz Communications System,
needed for police and fire response in the facility. 
Contractor Schedule 
Current RCF Substantial Completion date is November 15, 2011. Current Turner progress schedule
update shows a negative 204 day float in the project schedule, with the critical path running through
the Project power-up, and commissioning and training activities. This is approximately a 1 month slip
compared to what was reported on the last update, primarily due to electrical correction notices from
Department of Labor and Industries.
Commission approval being requested to issue up to an 80 calendar day contractual time extension to
address excusable delays. Turner and Port staff is collaborating to remove the remaining obstacles to
project power-up, along with implementing schedule revisions to improve commissioning and
training activities to recover lost time. In addition, staff continues to authorize selective overtime for
critical path activities.
Cost Status Summary 
See Cost Status Summary Table in PowerPoint Supplement page 3 for current cost information and page
4 for the trending of Construction Contingency costs over time. 
Subcontractor Bids  closed.
Risk Reserve  115 approvals have been issued, and 13 in review. 
2% MACC (Maximum Allowable Construction Costs) Contingency  151 Change Orders executed
and 22 in review.
Negotiated Support Services  44 approvals issued. 
Conforming Design Development Allowance  closed. 
Anticipated Scope Allowance  closed.
Non-Suspension Related Contract Changes  600 Change Orders executed, and 132 in review. Port
staff is currently trending approximately $8,000,000 in potential claims from the GCCM and a major
Subcontractor. 

Page 2 of 6

Suspension Related Contract Changes  58 Change Orders have been written. One last claim relates
to the unsupported cost previously rejected by the Port from one subcontractor.
Off-Site Roadway Improvements - Construction Contract 
Construction Status Summary 
Construction progress is 57% complete. 
10 to 20 construction workers on site daily. 
Overall project completion date remains the same despite many unforeseen conditions.
Construction costs are trending to be within the authorized program budget. A $650k budget
transferred was made from overall program contingency to replenish construction contingency
Milestones Accomplished This Month 
Storm drain pipe and roadway illumination foundation installations are complete on new on-ramp to
eastbound State Route (SR) 518. 
Electrical inspection complete for the roadway illumination service cabinet on S 160th St. 
Qwest installations complete at SR 99 Bridge. 
Work In Progress 
S. 160th Street: Work is 95% complete and is weather dependent for installing the final lift of asphalt
with striping, and final tie-ins at concrete sidewalks and aprons. Signalization at RCF entrance
delayed due to unknown condition.
Host Road realignment: remaining road work is weather dependent.
New on-ramp to eastbound SR518 via the North Airport Expressway continues on a weather
dependent basis. Manhole 60 vault and lid work as well as final paving is planned to commence in
the next month.
SR 99 Bridge: Demolition of existing sidewalk and guardrail for road widening is underway.
Encountered asbestos pipe which is causing some delay.
International Boulevard: Storm drainage installation work is nearing completion pending removal of
SCL facilities in early August and rough and final grading for road widening is underway.
Road widening work at the B-Line (exit ramp from SR518 to SR 99) well underway with final
grading of realignment complete and electrical conduit installation nearly complete. Initial paving is
planned this month.
Weekly meetings with Port staff, Mid Mountain and Turner and WSDOT continue for coordination
and planning purposes as work progresses for both contractors. 
Cost Status Summary 
Change Orders: 21 executed, 3 pending execution and 35 trends in review.
Bus Maintenance Facility - Construction Contract 
Construction Status Summary 
Overall project completion date remains at February 13, 2012. 
Construction progress is approximately 30%. 
Construction costs are trending to be within authorized budget. 

Page 3 of 6

Approximately 30 construction workers on site daily. 
Milestones Accomplished this Month 
Bus Maintenance Building (BMF) and Bus Wash Facility (BWF) tilt-up panel erection is complete.
The BWF concrete plank roof structure is installed and structural steel erection has begun at the BMF
building.
Offsite utility work nears completion at S 194th St, and off-site bioswales (adjacent to Tyee Golf
Course) will be punch-listed this month. 
Permanent tie-ins to Highline Water District water main are complete. 
Puget Sound Energy has completed most of their cut-over work to provide permanent power via the
new "backbone" ductbank on S 194th St. 
Work In Progress 
BMF Building structural steel erection and welding of tilt-up panels is underway. Interior rough-in
work is limited by wall panel bracing, to be removed when joists & deck are in place & welded. 
Sacrificial slabs used for casting tilt-up panels have been removed to facilitate grading & curb/gutter
work at upper and lower site paving/parking areas.
Sewer tie-ins (Midway Sewer District) are pending. Contractor has begun installation and cabling for
electrical switchgear and main distribution panels.
Foundation work is complete with under slab conduits/control circuit pathways at CNG nearly
complete. Contractor has begun pre-fabrication off site for CNG system process piping. 
Sod placed at Tyee Golf Course is being watered and maintained by the Contractor to assure viability
of turf.  Change order related to a drainage structure has been issued, and revision will not impact
tenant (golf course) operations. 
Operation and maintenance costs of TESC and Chitosan Enhanced Filtration System (CEFS)
installations remain low due to mild weather. Budget for environmental elements is tracking within
budget forecasts.
As utility excavation operations near completion, costs for management/disposal of unsuitable soils 
have decreased significantly.
Cost Status Summary 
Summary: Change Orders: 7 executed, 15 change proposals in review. 
Design 
RCF: 46 Design Change Notices (DCN's) have been issued. There are six additional design changes
that will be incorporated into future DCN or Construction Bulletins (CB's). Approximately 2,200
contractors Request for Information (RFI) have been submitted, of which 2,015 are closed. 
Main Terminal Improvements (MTI): Awarding contract to Skanska USA Building, Inc. in underway.
Must be awarded by July 29 to meet schedule. The project will carry $188,000 in construction
contingency, which is 25% of the contract value and higher than normal due to the following
risks: small project, extensive coordination with operations for traffic on lower drive and
safety with the traveling public, unforeseen RMM with sign installation, a contractor not
familiar with the Port's procedures, and contingency to add or modify signs after completion
of the project. 
Small operator area bid documents being finalized for advertisement in early mid August 2011. 
Page 4 of 6

RCF Signage: Determination made for PCS to install additional signage as determined through a
series of trial runs by Port staff before facility opens. 
AT&T's preparing final design to provide cellular phone and Wi-Fi service to the RCF as part of its
expansion of service within the terminal. Cost estimate and proposal due by end of July. 
Industry 
Held Industry business and technical meetings and presented the transportation plan for the busing
operation on July 13, 2011. All tenants have submitted 100% designs and reviews have been issued 
except for Dollar. Continued work on various technical issues. Continued coordinating with Facility 
Management Company on turnover tasks. Industry preparing Permit sets. 
Continue working with the Industry's Technical Representative reviewing the details of the
authorized $32 million budget increase. 
Shuttle Bus Acquisition 
Gillig is manufacturing the first bus for Port approval. 
Rental Car Facility Program Activation 
Work continues on the development of transit operations employee training plans and operating
procedures.
HR&D's RCF Project Employment Manager has developed a hiring plan and timeline to have
personnel on board and trained by opening date. HR&D does not anticipate having difficulty finding
qualified drivers or other employees due to the layoff of transit drivers in the Puget Sound area. 
Program Schedule 
RCF estimated to be complete by the end of 2011 with the opening planned for Spring 2012. Working
on establishing a firm opening date based on a number of key activities coming together at the same
time. 
BMF completion is estimated to be in February 2012. 
ORI completion is estimated to be December 2011 with signage completed in early 2012 to coincide
with the RCF opening. 
Main Terminal Improvements construction to begin September 2011 with completion in March 2012. 
Bus Delivery estimated for October 2011. 
Program Cost Forecast and Budget 
The current Turner contract value including all change orders is shown on the attached table slide 3. 
o  The trending over time of construction contingency for the RCF is shown on slide 4. 
o  The trending over time of construction contingency for the RCF Total Program is shown on
slide 5. 
The projected program budget is $419,306,000 and breakdown by project and expenditures is shown
on the attached slide 6. 
The updated CFC actual collections and projections are shown on the attached slide 7. 
Risk Factors 
AT&T providing full cell and Wi-Fi service in RCF. 
Accelerated BMF construction schedule may be delayed due to site conditions. 
Page 5 of 6

Coordinating with Utility companies for major relocations for both BMF and ORI projects, which
require a number of agreements with varying levels of authorization. 
Availability of qualified Bus Drivers. 
Timely award of MTI contract to Skanska. 
Upcoming Commission Actions 
None. 
















Page 6 of 6

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.