7e supp

Item No: _____7e_supp________ 
Date of Meeting: __June 28, 2011__ 
RCF Construction 
June 3, 2011 




May 4, 2011

RCF Construction 

RCF North Escalator Bank Finish Work            RCF CSB Lobby Flooring Installation Progress 






BMF Bldg.  Tilt Panel Forming & Casting                 Excavating Slopes on B-Line            2

Rental Car Facility Program 
Contract - Status Summary 

Base Contract       Revised         Additional Costs *           Unallocated       Billed to date
Amount                                         Balance       (as of May.2011) 
In review **    Executed 
Consolidated Rental Car Facility 
Total Construction Costs  $224,837,739     $211,421,525       $1,526,668   $202,773,224         $7,081,179         $206,770,452 
Construction Contingency Summary 
Non Suspension Contract Changes    $5,953,159      $17,031,082      $13,879,211    $10,546,115       ($7,394,244)          $7,297,715 
Suspension Related Contract Changes                $16,800,000         89,202     $8,640,600        $8,070,198          $8,644,612 
$7,757,133 
Off Site Roads 

Construction Contract Amount    $7,627,485                              $7,627,485             $0          $4,182,569 
Construction Contingency    $1,087,000     $2,057,000          $247, 871     1,735,330          $73,780           $1,039,187 

Bus Maintenance Facility 
Construction Contract Amount   $13,086,444                             $13,096,444             $0          $2,903,864 
Construction Contingency    $1,611,000                     $176,736      $10,000         $1,424,264                $0
NOTE: * updated as of May 9, 2011 
** includes costs in dispute for entitlement or quantum 
3

Construction Contingency Trending to Date

$40,000,000

$35,000,000 

$30,000,000

$25,000,000 

$20,000,000


$15,000,000 

$10,000,000

$5,000,000 

$0
99999 9 0 0 0 Q Q Q 0          N N
99999 0 N N 'V N N '8 N              N N
O  Q  Q  Q  0  0  0  0                       Q  Q
'L '1'  '1'  'L  m  '1;  '1o  '1;  'lo '1' '1, '1' 'lo                             '1'  '1,
0'09 69 '~>\0\6"\o"\6"\9'\<\9'\6'\6                $949";
-Construction Contingency Budget                   Executed Suspension + Non-Suspension Change Orders
Suspension Change Orders                        Total Executed Change Orders + In Review
4

Consolidated Rental Car Facility 
Program Costs as of 6/16/2011 
Project       6/30/09     2/2/10        Approved   Pending     Remaining   Expended to  Forecast to
Budget     Authorization   Transfers/  Transfers/    Contingency  Date       complete 
Trends     Trends 
RCF        $350,772,000   $350,772,000  $19,516,715   $13,968,413    $7,757,133   $291,613,954   $351,102,000 
BMF       $28,282,000   $28,282,000  ($1,890,000)    $176,736   $1,424,264   $6,212,870   $26,382,000 
ORI         $19,542,000    $19,542,000  ($1,493,670)     $247,871     $73,799    $8,979,822    $17,203,000 
MTI        $3,383,000    $3,383,000      $0        $0    $338,300    $279,882    $3,383,000 
Buses       $17,327,000    $16,000,000  ($4,911,269)        $0    $219,897       $340   $12,415,731 
Unallocated
$0            $0   $8,737,269       $150,000     $8,887,269           $0           $0 
Contingency 
Total       $419,306,000   $417,979,000  $19,959,045   $14,543,020   $18,700,662  $307,086,868  $410,485,731

5

SEATTLE-TACOMA INTERNATIONAL AIRPORT
CFC REVENUE FORECAST TO ACTUAL COMPARISON
APR YTD 2011

$147.5
CUMULATIVE CFC REVENUES       ,x
"
ASOF SEP 2012
$142.5 RICONDQ
'
$146.6M         X,
"
s137.5-,X
I
22"x
I
$132.5
x'f
.x"
'
$127.5 
,
w                                              x"
g xv'
j $122.5                                                                                          1
:' '2'
E                                        X,
E $117.5                                                                                    7'
m                                    ,X
g                                   x'
$112.5R-'
E                                 O
I.>I.I x')?
"5 "$107.5
"
'
E -t'
0                       a
$102.5

$97.5 

'
$92.5

'
'
$87.5              ,

m
-----------------------------

Notes:
The forecast is from the Ricondo Feasibility Analysis which was the basis for the RCF bond issuance                                                                  6 6
No interest proceeds are reflected in actuals shown above

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.