PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      6d 
Date of Meeting     June 7, 2011 

DATE:    May 27, 2011 
TO:     Tay Yoshitani, Chief Executive Officer 
FROM:    Fred Chou, Capital Construction Project Manager, Capital Development 
Dwight Rives, Director, Port Construction Services, Capital Development 
SUBJECT:  Request for Funding Increase for the Terminal 91 Roadway Pavement Project 
CIP #C800343 
Amount of This Request: $87,000           Source of Funds: General Fund 
Total Project Cost: $982,000              Total Est. State and Local Taxes: $39,000 

ACTION REQUESTED:
Request Commission authorization for additional funding in the amount of $87,000 for the
construction of the Terminal 91 Roadway Pavement Project for a total project authorization of
$982,000. 
SYNOPSIS:
Paragraph 4.2.3.3 of Resolution 3605, as amended, requires additional Commission authorization
if it becomes apparent at any time that a project cannot be completed within the authorized
amount. For the reasons described below, the work has been completed and will exceed the
current authorization. 
The pavement at two key roadway intersections and the adjacent roadway segments at Terminal 91
had exceeded its service life and was at risk of additional failure. On September 28, 2010,
Commission authorized $757,000 for the construction phase of the project, bringing the total
authorization to $895,000. Construction started in November 2010, and continued through April
2011, with a significant amount of asphalt paving work performed during the months of March and
April. During the course of construction within several large work areas, where existing pavement
was designed to be ground to a 2" depth and an overlay applied, the condition of the asphalt was
determined to be structurally unsound and that a full 4" depth replacement was needed. To ensure
proper stormwater surface drainage over existing paved surfaces, additional pavement replacement
was required beyond original design project boundaries. Consequently, the in -place asphalt
tonnage was significantly more than what was initially estimated. Furthermore, due to the record

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
May 27, 2011 
Page 2 of 4 
setting unseasonable weather conditions this spring, it was necessary to compress the paving work
to be done within conditions favorable to paving, resulting in shorter work windows and requiring
over-time hours to complete the work before opening of the cruise season. Both the unfavorable
wet weather and the need for overtime hours were not originally assumed in the project estimate.
These conditions all contributed to the additional construction costs.
These contributing factors can be mitigated by better controls and earlier communication of
potential cost overruns. Staff is currently working on deployment of a project delivery system that
will help define and manage all project costs. It will allow for the identification of all
commitments, which will be tracked to actual as reported through the Port's financial systems. It
will also include tools to identify trends, and to forecast budgets. When deployed our new controls
system should reduce the potential for unforecasted cost overruns. 
Construction is now complete and intersections/roadways are in use -- completed before the start
of the 2011 cruise season as scheduled. However, an additional $87,000 is necessary to cover these
unforeseen costs. 
BACKGROUND AND JUSTIFICATION: 
Roadway pavement at Terminal 91 adjacent to the east and west main terminal entrances and
main traffic intersections were in poor condition with a significant amount of surface breakage,
settlement, cracks and areas of pavement failure. This in turn created issues such as surface
water ponding and roadway operation/safety concerns. The pavement need ed to be replaced
before additional pavement failures occurred and to enhance terminal roadway operation and 
safety. 
Staff obtained design funding approval on December 15, 2009 and construction funding approval
on September 28, 2010. A total of $895,000 was authorized by the Commission. Construction
started November, 2010 and the team coordinated closely with the Terminal 91 Water Main
Replacement Project team, Terminal Operations and our tenants to minimize disruptions to their
operations.
A significant amount of asphalt paving work occurred in March and April 2011. During the course
of construction within several large work areas, where existing pavement was designed to be
ground to a 2" depth and an overlay applied, the condition of the asphalt was determined to be
structurally unsound and that a full 4" depth replacement was needed. The affected areas were
significantly more than what was assumed during design. Also, in order to match grade of existing
paving and to ensure proper drainage, additional pavement replacement was required beyond
original design. Furthermore, weather conditions limited our ability to work and over-time hours
were required to meet the construction completion date. These items contributed to the additional
construction costs. Construction is now complete and roadways are in use.

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
May 27, 2011 
Page 3 of 4 
FINANCIAL IMPLICATIONS: 
Budget/Authorization Summary: 
Original Budget                                         $ 0 
Previous Authorizations                                    $895,000 
Current request for authorization                                $ 87,000 
Total Authorizations, including this request                         $982,000 
Remaining budget to be authorized                            $ 0 
Total Estimated Project Cost                                 $982,000 
Project Cost Breakdown: 
Construction                                            $763,000 
Soft Costs                                               $180,000 
State & Local Taxes (estimated)                               $ 39,000 
Total                                                   $982,000 
Source of Funds: 
This project was included in the 2011 Plan of Finance under Committed CIP# C800343, T91
Roadway Pavement. The additional $87,000 which is required to fund this project is available
due to project deferrals on other 2011 Plan of Finance Committed projects, such as the Terminal
18 Pile Cap Improvements Project. This project will be funded from the general fund. 
Financial Analysis Summary:
CIP Category           Renewal/Enhancement 
Project Type            Renewal/Enhancement 
Risk adjusted Discount rate   7.0% 
Key risk factors           No remaining risk factors identified, construction is complete. 
Project cost for analysis      $982,000 
Business Unit (BU)        Seaport Industrial Properties 
Effect on business         No incremental revenue or operating expense is anticipated to be
performance           generated as a result of this Project.
The incremental increase to depreciation expense resulting
from this $87,000 funding request is $3,500/year. Total
depreciation expense from this project is estimated at
$56,000/year, based on the specific assets identified in the final
asset plan, and will reduce to $27,000/yr after 10 years as the
assets with longer useful lives continue to depreciate. 
IRR/NPV            N/A

COMMISSION AGENDA 
Tay Yoshitani, Chief Executive Officer 
May 27, 2011 
Page 4 of 4 
ALTERNATIVES CONSIDERED AND THEIR IMPLICATIONS: 
Alternative 1: Do not authorize additional funding. Without the additional funding, staff will
not be able to pay the remaining obligations. For this reason, Alternative 1 is not recommended. 
Alternative 2: Authorize additional funds needed to complete and close the project. Though
projected final construction costs are higher due to additional materials and labor, they added
values to the pavement performance, user satisfaction, and extended asset life. This is the
recommended alternative. 
PREVIOUS COMMISSION ACTIONS OR BRIEFINGS: 
On December 15, 2009, Commission approved design funding of $138,000 for the T-91
Roadway Pavement Project. 
On September 28, 2010, Commission approved construction funding of $757,000 for the T-91
Roadway Pavement Project, bringing the total authorized amount of the project to $895,000.

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.