Item 7a Report

Item Number: 7a_Report
Meeting Date: April 13, 2010


Commission Staff Brieng
Capital Improvement Projects
Fourth Quarter Report 2009

This page intentionally left blank









ii  Port of Seattle 4Q 2009 Report

3RUW RI 6HDWWOH 
&DSLWDO ,PSURYHPHQW 3URMHFW 5HSRUW 
)RXUWK 4XDUWHU 
,QWURGXFWLRQ 
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high
level information on the statue of the Port's capital projects.
%DFNJURXQG 
During 2009 the Port plans to invest over $600 million to expand and upgrade the infrastructure that supports marine
and aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping
companies, airlines, rental car companies, concessionaires and public parking. About 11 percent of the Port's capital
budget comes from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in
maritime transportation facilities and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business
partners and the general public.
$ERXW WKH 5HSRUW
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs compared
to authorization, construction costs (including change orders (CO)) compared to the construction contract, location
maps, and photographs. The Port implements a number of different types of projects and not all information may be
relevant to a specific project; as such the reports may vary in detail and content. Project types may range from
construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase,
and estimated completion date (beneficial occupancy). This section also includes a "Status Snapshot" illustrating at a
glance if the project is on schedule, within budget, the total number of change orders to date, and the total value of
executed change orders.
x 6LJQLILFDQW 'HYHORSPHQWV covers items such as accomplishments, significant events or milestones, contract
advertisements and awards, upcoming activities, and environmental issues.
x 6FKHGXOH includes information on the project schedule, the total schedule variance and variance since the last
report, contract extensions, and information on critical dates.
x %XGJHW addresses the total project budget and includes things like overall budget status, recent Commission
authorizations, forecasted overruns or savings, and scope changes.
x &KDQJH 2UGHUV provides a description of CO for the reporting period and information on any CO over $200,000 or
10% of the contract value.
x &RVW *URZWK RI &RQVWUXFWLRQ provides a brief description of any project with CO exceeding 10 percent.
x 5LVNV describe any significant risk of delay, any significant risk to cost, or any significant CO.
x %XGJHW 7UDQVIHUV reports any transfers of more than $200,000 between authorized projects during the reporting
period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These
reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605 and the
Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
$GGLWLRQDO ,QIRUPDWLRQ 
For additional information, please visit the Contact Us page and select the Audit/Accountability button. Use the form to ask a
question, make a comment or request a copy of the State Audit Reports Response and Action Plan.

Port of Seattle 4Q 2009 Report  1Port of Seattle 2Q 2009 Report  1

2  Port of Seattle 4Q 2009 Report

Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000683 et al .......3rd Runway Program .............................................6 ........... 
C100266 et al .......Rental Car Facility ...............................................7-8 .......... ...............
C100451 ...............Industrial Waste System Upgrade .........................9 ...........
C102030 ...............Stormwater Management Program ......................10 .......... ........................................
C102038 ...............Apron Pavement Rehabilitation 3 .......................11 ..........
C102163................Main Terminal Baggage Screening ....................12-13 ........ ...............
C102584 ...............Garage Floor Count ..............................................14 .......... ...............
C102744................2nd Floor Tenant Improvements ...........................15 .......... ...............
C800019 ...............Loading Bridge Utilities .........................................16 .......... ...............
C800020 ...............Trash Handling & Recycling System ....................17 ..........
C800034 ...............North Expressway Relocation ..............................18 .......... ...............
C800036 ...............Parking Garage 4th Floor Improvements .............19 ..........
C800042 ...............Aircraft Rescue Fire Fighting Station Upgrade ....20 .......... ...............
C800061 ...............Main Terminal South Sub Low Volt ......................21 .......... ...............
C800071 ...............Consolidated Warehouse .....................................22 ..........  ...............
C800095 ...............Alaska Air 2 Step Ticket Counter..........................23 .......... ...............
C800105 ...............Airport Owned Gate Infrastructure .......................24 .......... ...............
C800107 ...............C4 UPS System Improvements ............................25 .......... ...............
C800109 ...............Garage Escalator & "A" Elevator Upgrade ...........26 ..........
C800112................Runway 16C/34C Panel/Joint Sealant .................27 ..........
C800144 ...............Security CCTV System Improvements.................28 .......... ...............
C800146 ...............RMU/Kiosk Concession Program ........................29 .......... ...............
C800147 ...............Concessions Renewal/Replacement ...................30 ..........  ...............
C800148 ...............GML Arrivals Hall Concessions ...........................31 .......... ...............
C800157 ...............Concessions Flooring ...........................................32 ..........  ...............
C800167 ...............Runway 16L/34R Reconstruction.........................33 ..........
C800170 ...............Connect C1 BHS to C88 BHS ..............................34 ..........
C800237 ...............Renew/Replace 42 Escalators .............................35 .......... ...............
C800238 ...............Central Plant Pre-Conditioned Air ........................36 .......... ...............
C800239 ...............Fire Piping .............................................................37 ..........  ........................................
C800249 ...............2nd Floor HVAC ....................................................38 .......... ...............
C800254 ...............Aircraft RON Parking Post Off ce Site..................39 ..........
C800276 ...............Common Use Equipment Expansion (CUSE) ......40 ..........
C800286 ...............South AOA Fence Replacement ..........................41 ..........




Port of Seattle 4Q 2009 Report  3

Other Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C001338 ...............Fire Vehicles .........................................................42 .......... 
C102396 ...............Fire Vehicles .........................................................43 .......... 
C200007...............Highline School Noise Insulation ..........................44 .......... ...............
C200015 ...............3rd Runway Residential Acquisition .....................45 ..........
C200037 ...............FAR Part 150 Mobile Home Park Acquisition ......46 .......... ...............
C200042 ...............Highline Community College Noise Insulation .....47 .......... ...............
C200048 ...............Home Insulation Retrof t .......................................48 ..........  ...............
C200093 ...............Single Family Home Sound Insulation .................49 ..........
C800046 ...............Street Vacations  Des Moines Creek 1 ..............50 .......... ...............
C800150 ...............Burien Commercial Property Acquisition .............51 ..........
C800154 ...............Tenant Reimbursement ........................................52 .......... 
Seaport
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000579 ...............Alaskan Way St Vacation and Public Access ......53 .......... ...............
C102451 ................T115 Dock Reconstruction....................................54 .......... ............... ....................
C800064 ...............T25/30 Improvements 2005-2007 ........................55 .......... ...............
C800085 ...............T30/T91 Program ..............................................56-57 .......  ............... ....................
C800114................P66 Bag. Corridor & Pass. Screening ..................58 .......... ...............
C800121 ...............T-18 S. Fendering .. ..............................................59 .......... ...............
C800123 ...............T5 Crane Spreader Replacement ........................60 .......... ...............
C800182 ...............North Harbor Island Mooring Dolphins (4) ...........61 ..........
C800259 ...............T25 South Redevelopment ...................................62 .......... ...............
C800264 ...............T10 Interim Redevelopment..................................63 .......... ...............
C800273 ...............T91 Mobile Gangways ..........................................64 ..........
C800343 ...............T91 RD Pave Entry & Gardenshack .....................65 ..........
C800347 ...............T46 Upgrade Yard Lighting ...................................66 ..........
WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ..................67 .......... ............... ....................
E103705 et al ........T46 ZPMC Gearboxes ..........................................68 ..........
E103835 et al ........T5/T18 Maintenance Dredging .............................69 .......... ...................................
E104011 et al ........T25/P28/T46 Barge Layberth Improvements .......70 ..........
E10466 .................Radio Frequency Indentif cation (RFID) ...............71 .......... 
Multiple Exp. .........Water/Sewer Meter Upgrade ................................72 ..........


Port of Seattle 4Q 2009 Report 4

Real Estate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C001706 et al........SBM Renewal and Replacement .........................73 .......... ...............
C800070 ...............T102 HVAC Renewal/Replacement .....................74 .......... ...............
C800125 ...............C15 Sewer Line Upgrades ....................................75 .......... ...............
C800136 ...............FT South Wall Reconstruction..............................76 ..........
C800175 ...............MIC Central SeaWall Replacement ......................77 ..........
Corporate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800003...............Maximo Enterprise Implementation......................78 .......... ...............
C800015 ..............Public Safety CAD ................................................79 ..........
C800066 ...............Parking System Consolidation .............................80 .......... ...............
C800118................Area Surveillance .................................................81 .......... ...............
C800119................Marine Domain Awareness ..................................82 .......... ...............
C800223 ...............UltraCUSE Implementation ..................................83 .......... 
C800321 ...............Enterprise Project Cost Management ..................84 .......... ...............
C800322 ...............Records & Document Management .....................85 ..........
C800326 ...............Data Archive .........................................................86 .......... 
Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are off
Both target schedule & budget are off
Variance Status
Over Budget or Delayed Schedule
Under Budget or Ahead of Schedule
Potential Over Budget or Delayed Schedule
Previously Reported
No Diamond  On Budget or On Schedule




Port of Seattle 4Q 2009 Report  5

FOURTH QUARTER REPORT, 2009
3rd Runway Program
Project: C000683,       The 3rd Runway Program will      Status Snapshot
construct a new 8,500 foot long     On Schedule
C001138, C001175,                          On Budget
C001331, C001751,      dependent runway, connecting
taxiways, and related infrastructure.  4 Change Orders
C001760, C100172
When complete the 3rd Runway    Total Change Orders Amount:
Budget: $957,883,541
will significantly reduce weather-     $348,044.79
Phase: Construction    related delays.
Start: 05/27/1997                                3RW Budget/Costs Incurred
Completion: 12/31/2011                       $1,200
$1,000
Significant Developments                     $800
Lora Lake apartments were demolished and stormwater           $600
improvements were completed in 2009. The final stormwater        $400
improvements along with additional mitigation of Miller Creek are
$200
planned for construction in 2010.                           Dollars [Millions] $0
Authorized  Forecasted   Costs
Schedule                                        incurred
The 2010 construction project is scheduled to be advertised in the
1st Quarter of 2010 with construction to be completed in the Fall of    2009 Contract Construction
2010.                                              Costs
$4
Budget
$4
Reduced budget by $129,600,000 to the current budget of           $3
$957,883,541. To date, $637,969,000 of construction has been       $3
completed on the overall program.                          Millions $2
$2
Change Order                          $1
$1
Four change orders for a total of $348,044.79 have been executed
$0
during this period. None involved extension of the contract time.
Initial  Change Orders  Spent
Risks
Photo
A portion of the 2010 stormwater work may be delayed due to
potentially poor soil at the pond site. Soil explorations are currently
underway to identify the issues.
Budget Transfers
Return    to    savings       $22,405,000
AIRPORT
6  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Rental Car Facility
Project:   C100266,     The program will construct a       Status Snapshot Prior Report
C102167, C800032     consolidated rental car facility (RCF)  Delayed Schedule 4Q 08
Budget: $419,306,000   for all rental car companies at the    On Budget
Phase: Construction    airport, a bus maintenance facility    173 Change Orders
Start: 02/24/1998        (BMF), and mitigation with the off-site  Total Change Orders Amount:
roadway improvements (ORI) , plus   $11,585,277
Completion: Spring 2012
purchase a fleet of buses.
Budget/Costs Incurred
Significant Developments
Construction is progressing well on every aspect of the RCF with the
Contractor managing the inclement weather impacts well. The
concrete structure is continuing to be placed in three sections up to
the fifth and final floor. All but one retaining wall is complete.
Construction continues on all four quick turnaround areas (QTA's).
All utilities within the building footprint are complete. Averaging 230
workers daily, increasing to 260 for concrete work. Only one
conforming design change and seven suspension claims remain
open. Completed the 100% design for the BMF and 90% for the     Construction Costs
CNG facility, and continuing to complete 100% design for ORI.
Schedule
The program schedule remains on the revised track to be complete
spring 2012 as controlled by the BMF; delayed due to funding
addition of CNG Fuel Facility. ORI delayed slightly by late outside
agencies reviews, but completion remains on schedule.
Budget
Customer Finance Charge (CFC) revenues continue to run lower    Photo
than planned with the economy. The program budget remains at
$419,306,000. The estimated bus purchase and ORI are below their
budgets and BMF is within its budget.
Change Order
59 change orders were issued this quarter in the amount of
$5,206,448.


Port of Seattle 4Q 2009 Report  7

Risks
For RCF, timely resolution of larger suspension claims, inclement
weather, control of onsite stormwater and site congestion are key.
For ORI, delay in review by other agencies has impacted design
completion. For BMF, sole source and "brand name" specification
revisions will further delay schedule and potential for growth in utility
work to provide adequate power and high-pressure natural gas to the
site are key.
Budget Transfers
None
Cost Growth of Construction
GCCM Final Construction (Phase 3 of 3)  MC-0315405 - On June
30, Commission authorized the $32 million suspension impact
including a $6,973,300 budget increase and an increase in change
order limit from 10% to 18% requiring Commission notification.
TESC & Early Work (Phase 2 of 3)  MC-0315292 - Cumulative
change order percentage through this quarter is 19.5%. Primary
reason for changes is the removal of contaminated soils and
associated impacts. This work and the final contract reconciliation is
complete.
GCCM Pre-Construction (Phase 1 of 3)  MC-0314280  Cumulative
change order percentage through this quarter is 170.5%. Primary
reasons for changes are for additional contractor management,
estimating, scheduling and bidding effort for cost estimate
reconciliation, constructability reviews and value engineering beyond
the extent of the original scope to validate project costs and support
the rental car companies and the Port on final approval of the
project. This work and the final contract reconciliation is complete.



AIRPORT
8  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Industrial Waste System Upgrade
Project:   C100451    The Industrial Wastewater System     Status Snapshot
Budget: $12,012,185   (IWS) collects and treats storm water   On Schedule
Phase: Construction   that could be contaminated by fuel,    On Budget
Start: 09/12/2000      solvents or deicing chemicals. The     No Change Orders
Completion: 10/01/2009 project upgrades the IWS to meet or   Total Change Orders Amount:
exceed all environmental permit       N/A
standards.
Budget/Costs Incurred
Significant Developments
This project is in closeout. This will be the last quarterly report for this
project.
Schedule
The project was completed on schedule.
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
No active contracts at this
Change Order                         time.
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT


Port of Seattle 4Q 2009 Report  9

FOURTH QUARTER REPORT, 2009
Stormwater Management Program
Project:   C102030,    The program achieves permit       Status Snapshot Prior Report
C800026, C800030     requirements and makes the Airport a  On Schedule
Budget: $62,447,234   leader in stormwater management by  Under Budget   2Q 09
Phase: Construction   construction of flow control, water    No Change Orders
Start: 06/11/2002       quality treatment and low stream flow   Total Change Orders Amount:
mitigation facilities.                  N/A
Completion: 12/31/2011
Significant Developments                    Budget/Costs Incurred
The stormwater program is in its adaptive management phase under
which additional or upgraded water quality treatment facilities are
being implemented based on the stricter effluent standards of the
new stormwater National Pollutant Discharge Elimination System
(NPDES) permit. Five projects have been identified to date; one is
completed, one is under construction, and three are in the final
engineering phase.
Schedule                           Construction Costs
No active construction
The new stormwater NPDES permit became effective April 1, 2009.
contract at this time.
Adaptive management projects have been implemented in 2009 and
will be implemented in 2010. The stormwater and sanitary sewer
pipeliner projects, which are not part of adaptive management, have
been deferred to 2010 or later.
Budget
The budget has been significantly reduced several times since
program inception in 2002 due to successful system optimization
measures. An approximate $4,000,000 budget reduction is pending
for C102030 in Quarter 1, 2010.
Change Order
None.
Risks
Additional adaptive management facilities or upgrades may be
required beyond those currently being planned, depending upon
future water quality monitoring results.
Budget Transfers
$41,015  Expensed SDS5 Projects A, B, & D under C102030.
AIRPORT
10  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Apron Pavement Rehabilitation - 3
Multiyear airfield pavement        Status Snapshot
Project: C102038                               On Schedule
Budget: $16,100,000     replacement program. This is a
Phase: Construction    continuation of a program for the   On Budget
No Change Orders
Start: 01/14/2003        removal and replacement of aged
airfield apron pavement started in    Total Change Orders Amount:
Completion: 12/31/2010
1994.                    N/A
Budget/Costs Incurred
Significant Developments                     $16.5
$16.0
Approximately 70 concrete panels will be replaced in the 2010
$15.5
Apron Replacement Contract.
$15.0
Schedule                            Millions $14.5$14.0
$13.5
The 2010 project is scheduled to be advertised in the first Quarter of    $13.0
2010 with construction to be completed by the end of 2010.          $12.5
$12.0
Authorized    Forecasted   Costs incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                        Not applicable
None                                 Photo
Risks
No risks have been identified at this time.
Budget Transfers
None this quarter.




AIRPORT
Port of Seattle 4Q 2009 Report  11

FOURTH QUARTER REPORT, 2009
Main Terminal Baggage Screening
Project:   C102163     This project creates automated      Status Snapshot Prior Report
Budget: $230,538,762   systems for explosive detection     Delayed Schedule 4Q 08
Phase: Close Out     screening of baggage for the north   Under Budget
Start: 09/24/2002        Main Terminal and South Satellite.    665 Change Orders
Completion: 02/13/2009  The systems will meet all security    Total Change Orders Amount:
requirements while reducing staffing   $51,165,622
and providing capacity for future
growth.                    Budget/Costs Incurred
Significant Developments
The C-1 baggage handling/screening system has been placed into
revenue service for the Alaska Air Group. The only remaining work is
to relocate some fire sprinklers and to repair/replace fire proofing
material displaced from the main structural elements of the bagwell.
Schedule
The project was delayed approximately two years from the original
completion date due to replacement of the original baggage
subcontractor, changing TSA requirements and other scope        Construction Costs
changes. Turner Construction demobilized on May 31st. The GCCM
construction contract with Turner Construction has been closed. The
remaining fire sprinkler and fire proofing work is scheduled for
completion by year end.
Budget
The project forecast is within the approved budget and authorization.
The project is anticipating a return of $8,954,000 of budget.
Change Order
665 Change Orders have been issued on this project.            Photo
Risks
Risks include recent TSA changes in certification requirements and
whether they will be imposed retroactively.
Budget Transfers
None this quarter


12  Port of Seattle 4Q 2009 Report

Cost Growth of Construction
In 2006, the baggage handling system subcontractor was terminated
as they were unable to meet the project schedule requirements. The
remaining work was rebid in the fall of 2006. Alaska Airlines asked
that we include the BHS work within the 2-step ticket counter project;
which increased the amount of BHS work in the bidding (attracting
more competition), and eliminated the issues with having two
different BHS subcontractors in the same work area.











AIRPORT
Port of Seattle 4Q 2009 Report  13

FOURTH QUARTER REPORT, 2009
Garage Floor Count
Project:   C102584      This project is part of the Customer  Status Snapshot Prior Report
Budget: $4,087,371      Service initiative. The floor count   Delayed Schedule 3Q 09
Phase: Testing       system will display information to   On Budget
Start: 08/06/2007         assist parking customers in finding   No Change Orders
Completion: 11/30/2009   parking spaces, especially at times  Total Change Orders Amount:
when the garage is near capacity.   N/A
Significant Developments                    Budget/Costs Incurred
The system is operational and in production.
Schedule
System completion is 25 months behind schedule, which was
reported last quarter.
Budget
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable                                     Not Applicable
Risks
None.                                    Photo
Budget Transfers
None.



AIRPORT


14  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
2nd Floor Tenant Improvements
Project:   C102744      This project constructs a shell     Status Snapshot Prior Report
Budget: $377,864       space for new tenant offices and   Delayed Schedule 1Q 09
Phase: Construction     provides utility pathways to the    On Budget
Start: 08/22/2006         shell space and makes code       No Change Orders
Completion: (See       improvements to adjacent lobby    Total Change Orders Amount:
and corridors.                 N/A
C800249)
Significant Developments                    Budget/Costs Incurred
Project construction activities are substantially complete except for
one project element, which is awaiting completion of tenant office
build out and relocation of current tenant offices. The remaining
portion of the work will be completed after the 2nd Floor HVAC
Upgrades project (C800249).
Schedule
The remaining work is now scheduled for late 2010.
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
None.
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 4Q 2009 Report  15

FOURTH QUARTER REPORT, 2009
Loading Bridge Utilities
Project:   C800019   This project will upgrade all Port-       Status Snapshot Prior Report
Budget: $9,385,000   owned loading bridges to the same     Delayed Schedule    2Q 09
Phase: Design     standards, including 400Hz power and   On Budget
potable water. It will reduce air
Start: 06/28/2007                                 No Change Orders
emissions, improve energy efficiency
Completion: On-Hold                        Total Change Orders Amount:
and save money for the airlines.        N/A
Budget/Costs Incurred
Significant Developments
The 100% design package is complete. The package was submitted
to the Airport Building Department for review, and a permit was
granted. The Port was in negotiation for purchase of the 400Hz
equipment from Northwest Airlines in the South Satellite. The
negotiation has been put on-hold. Pre-purchase packages for the
400Hz equipment and the Potable Water Cabinets were started.
Once the Engineering contract is signed the design will be reviewed
for compliance with latest codes and changes to site conditions and
reissued as a 90% design review package.
Schedule                           Construction Costs
Not Applicable
The current schedule is on-hold until a contract is signed with the
original Engineer of Record.
Budget
The project forecast is within the approved budget and authorization.
Change Order
None.
Risks
The project budget may increase due to the delay in the construction
of the project.
Budget Transfers
None this quarter.

AIRPORT

16  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Trash Handling & Recycling System
Project:   C800020    To improve trash handling and       Status Snapshot
Budget: $1,612,000    recycling operations and to meet     On Schedule
Phase: Construction   future trash volume demands;      On Budget
Start: 04/22/2008      decentralize tenant trash disposal and   3 Change Orders
Completion: 02/28/2010 recycling; and centralize airline trash   Total Change Orders Amount:
disposal and recycling.             $12,000
Significant Developments                    Budget/Costs Incurred
MKB Constructors (Kirkland, WA) and G K Industrial Refuse
completed installing 12 compactors (Six Sites) on December 23,
2009. Certificate of Beneficial Occupancy is scheduled to be issued
during the latter part of January 2010. Punch-list items will be
resolved early January 2010. Most of the airlines have signed onto
and received training to use and operate the new compactors.
Schedule
The contractor is scheduled to complete and demobilize as
scheduled by February 28, 2010.                        Construction Costs
Budget
The budget forecast indicates a savings will be realized at project
closeout.
Change Order
Minor construction change orders were issued due to site conditions.
Eight compactors required small modifications to hydraulic and
electrical connection points. By implementing these field change
orders the project realized significant savings by field revisions to the  Photo
bid design. Southwest Airlines requested portable personal platforms
between their vehicle and the compactors at site Gate B4 before
they would commit to using the compactor program. This request will
be resolved in January 2010.
Risks
None identified at this time.
Budget Transfers
None this quarter.
AIRPORT
Port of Seattle 4Q 2009 Report  17

FOURTH QUARTER REPORT, 2009
North Expressway Relocation
Project:   C800034
The project is a collaboration       Status Snapshot  Prior Report
Budget: $110,487,700    between the Port and Sound     Delayed Schedule 1Q 09
Phase: Construction     Transit. It will reconstruct the North  On Budget
Start: 07/27/2004         Airport Expressway and bring light   187 Change Orders
Completion: 10/30/2010   rail to the Airport.           Total Change Orders Amount:
$9,300,934
Significant Developments
Budget/Costs Incurred
The majority of the work in the main contract is complete, with only
punch list work items remaining. The intelligent transportation
management system has been implemented and only an upgrade to
resolve a server issue remains. Advertisement is pending for the
final paving, landscaping and reclamation contract.
Schedule
The main contract received substantial completion in August 2008
and punch list work is being finalized. Advertisement of the
remaining contract is planned for the beginning of 2010. All
construction planned to be complete in the fall of 2010 followed by a   Construction Costs
first year plant establishment period.
Budget
The project forecast is within the approved budget and authorization.
Change Order
One change order was issued this quarter.
Risks
None identified at this time.
Budget Transfers                        Photo
Return    to    savings       $12,235,000

AIRPORT


18  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Parking Garage 4th Floor Improvements
Project:   C800036
The project includes the design and  Status Snapshot
Budget: $8,991,000      construction of a pedestrian bridge  On Schedule
Phase: Construction     and a walkway from Sound      On Budget
Start: 02/14/2006         Transit's Airport Station to the      9 Change Orders
Completion: 12/31/2009   Terminal.               Total Change Orders Amount:
$128,922
Significant Developments
Budget/Costs Incurred
The project is being delivered in two contracts: the pedestrian bridge
between the Airport Station and the Parking Garage, and a walkway
on the 4th floor of the garage between the pedestrian bridge and
northernmost sky bridge to the main terminal. Both contracts were
substantially complete and opened in conjunction with the Sound
Transit's Airport Station on December 19, 2009.
Schedule
Punch list work is in progress for the pedestrian bridge and the
walkway. The Contractor was late installing closure panels on the
Pedestrian Bridge. MUFIDS (Multiple User Flight Information Display  Construction Costs
System) and CUSS (Common Use Self Service) units will be
installed in the second quarter of 2010.
Budget
Project forecasted to remain within the authorized budget.
Change Order
Five change orders were issued for the walkway this quarter in the
amount of $28,194.
Risks
Letter of Forebearance may be issued to the Contractor for the      Photo
Pedestrian Bridge due to late delivery and installation of architectural
panels.
Budget Transfers
None
AIRPORT

Port of Seattle 4Q 2009 Report  19

FOURTH QUARTER REPORT, 2009
Aircraft Rescue & Fire Fighting Station Upgrade
Project:   C800042      Upgrade the Sea-Tac International   Status Snapshot Prior Report
Budget: $5,000,000      Airport Aircraft Rescue & Fire     Delayed Schedule 1Q 09
Phase: Close Out      Fighting (ARFF) station to meet    On Budget
Start: 06/13/2006         current Airport needs and comply    19 Change Orders
Completion: 01/31/2010   with current safety codes.       Total Change Orders Amount:
$128,300
Significant Developments                    Budget/Costs Incurred
The contractor and construction management team are currently
closing out this project. All punchlist items have been completed.
Schedule
The project is anticipated to be substantially complete in January
2010.
Budget
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
Seven change orders were issued this quarter in the amount of
$30,066.
Risks
Construction management personnel are still negotiating a credit for
waterproofing of the training tower. This work cannot be completed
until the weather is drier. Costs to perform this work later may
exceed the amount of the negotiated credit.
Budget Transfers
None this quarter


AIRPORT

20  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Main Terminal South Sub Low Voltage
Project:   C800061   This project covers the renewal and     Status Snapshot Prior Report
Budget: $1,925,000   replacement of low voltage (600 volts   Delayed Schedule 1Q 08
Phase: Design      and below) electrical distribution      On Budget
Start: 06/28/2007      equipment in the southern part of the    No Change Orders
Main Terminal.                  Total Change Orders Amount:
Completion: TBD                           NA
Significant Developments                    Budget/Costs Incurred
Due to project deferment and possibility of changes in site conditions
and building codes, the design phase is changed from 100% to 90%
complete. The Port and the Consultant have completed negotiating
the new fee rates and a new Service Agreement and Service
Directive will be signed early in 2010. Scope of work and budget will
be reviewed when Consultant completes their field investigations.
Schedule
The project was reactivated on June 24, 2009 and is in the process   Construction Costs
of determining the schedule. Expect to remobilize the Design       Not Applicable
Consultant late in the first quarter of 2010.
Budget
The project forecast is within the approved budget and authorization.  Photo
Change Order
None.
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner.
It is not known when the construction will proceed. There may be an
impact on project costs due to changes in market conditions at that
time.
Budget Transfers
None this quarter.
AIRPORT
Port of Seattle 4Q 2009 Report  21

FOURTH QUARTER REPORT, 2009
Consolidated Warehouse
Project:   C800071      This project will construct a 50,000
Budget: $9,000,000      square foot warehouse for storage  Status Snapshot Prior Report
Phase: Construction     and inventory management of     Ahead of Schedule    3Q 09
Start: 06/27/2006         spare parts for the Aviation        On Budget
Completion: 2/15/2010    Maintenance Department.       23 Change Orders
Total Change Orders Amount:
$722,048
Significant Developments
Budget/Costs Incurred
Project is nearing completion with the building shell and core
complete. The contractor is finishing the office interiors and installing
the pallet racks.
Schedule
The project has several significant issues to resolve: Bill of Sale,
Permanent Easement and Right of Entry Agreement for the Highline
Water District; As- built drawings for the Midway Sewer District; and
final closeout of the project.
Construction Costs
Budget
The project forecast is within the approved budget and authorization.
Change Order
Fourteen change orders were issued this quarter in the amount of
-$169,050. The total change order amount was reduced due to
closing out the Not To Exceed Change Orders.
Risks                               Photo
Opening on time due to unresolved issues with Highline Water
District and Midway Sewer District.
Budget Transfers
None this quarter



22  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Alaska Air 2-Step Ticket Counter
Project:   C800095      This project provides Port of      Status Snapshot Prior Report
Budget: $10,707,000     Seattle support for Alaska Airlines'  Delayed Schedule 1Q 08
Phase: Close Out      2-step ticket counter projects (the   On Budget
Start: 04/11/2006         "Airport of the Future"). The work   No Change Orders
Completion: (See       includes: asbestos abatement;    Total Change Orders Amount:
concessions relocations; and      N/A
C102163)
related building modifications.
Budget/Costs Incurred
Significant Developments
The onsite work is complete. The Port is meeting with Alaska
Airlines to reconcile the reimbursable amount.
Schedule
The project work is complete.
Budget
The project could incur additional costs over the current budget for
Port performed tasks which will be reimbursed by Alaska Airlines.
After reimbursement, the anticipated forecast is within the approved   Construction Costs
budget and authorization.                              Not Applicable
Change Order
Not Applicable
Risks
None at this time
Budget Transfers
None this quarter



AIRPORT

Port of Seattle 4Q 2009 Report  23

FOURTH QUARTER REPORT, 2009
Airport Owned Gate Infrastructure
Project:   C800105      This project purchases and
Budget: $6,000,000      replaces loading bridges at gates   Status Snapshot Prior Report
Delayed Schedule 3Q 09
Phase: Construction     throughout the airport.
On Budget
Start: 07/24/2007                                 No Change Orders
Completion: 6/30/2010                        Total Change Orders Amount:
N/A
Significant Developments
Budget/Costs Incurred
Installation of the two remaining loading bridges is moving forward.
The Port ordered one new loading bridge from the manufacturer in
October. Production of the bridge will dictate the delivery schedule;
delivery is anticipated for this loading bridge in February 2010.
Schedule
Gate N7 loading bridge is scheduled to be installed in January 2010.
The anticipated installation of the next loading bridge for Gate S1 will
be February for a completion time in late March.
Budget
The project forecast is within the approved budget. The current      Construction Costs
authorization is for $4,337,000. The remaining budget will be       Not Applicable
authorized in a following phase to replace additional bridges and
make other gate improvements in the future.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT

24  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
C4 UPS System Improvements
Project:   C800107    Project will purchase and install new    Status Snapshot Prior Report
Budget: $2,336,000   Uninterruptible Power Supply (UPS)    Delayed Schedule 1Q 09
Phase: Construction  units and associated equip-ment for the  On Budget
Start: 06/28/2007      Airport Combined Communications and   No Change Orders
Completion: TBD     Command Center (C4).          Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Due to project deferment and possibility of changes in site conditions
and building codes, the design phase is changed from 100% to 90%
complete. The Port and the Consultant have completed negotiating
the new fee rates and a new Service Agreement and Service
Directive will be signed early in 2010. Scope of work and budget will
be reviewed when Consultant completes their field investigations.
Schedule
The project was reactivated on June 24, 2009 and is in the process
of determining the schedule. Expect to remobilize the Design
Consultant late in the first quarter of 2010.                     Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None.
Risks
In order to reduce regulated materials management (RMM)
abatement impacts to the project schedule, the RMM contractor will
be required to add additional crews to complete work in a timely
manner.
It is not known when the construction will proceed. There may be an
impact on project costs due to changes in market conditions at that
time.
Budget Transfers
None this quarter.
AIRPORT
Port of Seattle 4Q 2009 Report  25

FOURTH QUARTER REPORT, 2009
Garage Escalator & "A" Elevator Upgrade
Project:   C800109    This project renews and replaces     Status Snapshot
Budget: $7,315,000    aging elevators and escalators in the   On Schedule
Phase: Construction   Parking Garage to provide reliable    On Budget
Start: 09/11/2007       vertical transportation to customers for  7 Change Orders
Completion: 02/28/2010  years to come.              Total Change Orders Amount:
$53,000
Significant Developments                    Budget/Costs Incurred
Due to the total failure of the West bank elevators, the Port
requested the contractor accelerate two of the four East bank
elevators (P-18 and P-19); these two elevators went into service
October 5, 2009. These elevators are programmed to park on Floors
1 and 4 to best serve Airport Staff using the North Employee Parking
Lot Bus service. Elevators P-20 and P-21 will be completed next,
followed by the remaining three elevators. A sole source acquisition
process is being pursued for the escalator work.
Schedule
The renewal of two elevators (P-18 and P-19) was accelerated, and   Construction Costs
the elevators began service October 5, 2009 ahead of their
December 31, 2009 schedule. Elevators P-20 and P-21 will return to
service in January 2010 and the remaining three elevators will return
to service in May 2010. Escalator work is projected to start during the
first half of 2010.
Budget
The project forecast is within the approved budget and authorization.
Change Order
Four change orders have been issued this quarter in the amount of
$21,737.
Risks
None identified at this time.
Budget Transfers
None this quarter.

AIRPORT
26  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Runway 16C/34C Panel/Joint Sealant
Replacement
The scope of work will remove and   Status Snapshot
replace the pavement and joint seal  On Schedule
Project: C800112
in areas on Runway 16C-34C.     On Budget
Budget: $5,650,000                         No Change Orders
Phase: Construction                        Total Change Orders Amount:
Start: 02/26/2008                                 N/A
Completion: 12/31/2010
Significant Developments
Budget/Costs Incurred
Budget increased in December 2009 from $2,415,000 to $5,650,000
$6.0
to replace 150 panels on Runway 16C-34C. The overall project
$5.0
objective is to maintain the runway in an operational condition until
its planned reconstruction in 2016.                           $4.0
Millions
$3.0
Schedule
$2.0
The 2010 project is scheduled to be advertised in the 1st Quarter of
$1.0
2010 with construction to be completed in the Fall of 2010.
$0.0
Authorized    Forecasted   Costs incurred
Budget
Budget increased in December 2009 from $2,415,000 to         Photo
$5,650,000. The authorization will be requested from the
Commission in January 2010.
Change Order
None
Risks
No risks have been identified at this time.
Budget Transfers
None
AIRPORT


Port of Seattle 4Q 2009 Report  27

FOURTH QUARTER REPORT, 2009
Security CCTV System Improvements
Project:   C800144      This project will install          Status Snapshot Prior Report
Budget: $2,037,591      approximately 70 new cameras for  Delayed Schedule 3Q 09
Phase: Implementation   TSA and integrate existing Airport   On Budget
Start: 9/11/2007          camera networks which contain     No Change Orders
Completion: 03/31/2010   over 800 cameras.          Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
The final cut overs are nearing completion. The Port and TSA are
evaluating follow on work.
Schedule
Project completion is still expected in March 2010. The work by the
vendor in developing the interface to the access control system took
longer than anticipated. Additionally, in order to make the interface
work, the access control system had to be updated to the next
version, which was not originally anticipated but is now complete.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
Not Applicable.
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT


28  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
RMU/Kiosk Concession Program
Project:   C800146      The project will: Provide design and    Status Snapshot
Budget: $1,209,000      fabrication of eight Retail        Delayed Schedule
Merchandising Units (RMUs); provide
Phase: Construction                        On Budget
power, communications, and data to
Start: 11/20/2007                                 No Change Orders
the sixteen RMU locations; and install
Completion: 2/29/10                         Total Change Orders Amount:
floor-mounted receptacles for the
N/A
utilities to allow easy connection points
to the sixteen RMUs, as well as
flexibility for future utilization.          Budget/Costs Incurred
Significant Developments
All RMU installations are complete. Communications connections
are scheduled to be completed mid-February.
Schedule
The design phase has been restructured and the bid packages resequenced
, with the intent to maximize the timing for new
Concessions opportunities. The project was put on hold until the
prioritization decisions were made by the Port's Business
Construction Costs
Development group, delaying the completion date by one month.
Not Applicable
The two existing communications connections have been delayed by
coordination issues with the current tenant.
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter


AIRPORT
Port of Seattle 4Q 2009 Report  29

FOURTH QUARTER REPORT, 2009
Concessions Renewal/Replacement
Project:   C800147      This project will upgrade         Status Snapshot Prior Report
Budget: $2,087,000      concession locations which were   Delayed Schedule    2Q 09
Phase: Design        previously vacated or slated to be   On Budget
Start: 08/26/2008         vacated to Port standards for use    No Change Orders
Completion: 06/30/2011   as specialty concession space.    Total Change Orders Amount:
N/A
Significant Developments
The project is in the permit planning review stage.               Budget/Costs Incurred
Schedule
The design phase has been restructured and the bid packages resequenced
, with the intent to maximize the timing for new
concessions opportunities.
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.    Construction Costs
Not Applicable
Change Order
None.
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
30  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Gina Marie Lindsey (GML) Arrivals Hall
Concessions
This project will provide a new retail  Status Snapshot
Project:   C800148      merchandising corridor in the Gina   Delayed Schedule
Marie Lindsey Arrivals Hall. The     On Budget
Budget: $1,033,000
project includes installing three      No Change Orders
Phase: Design        Retail Merchandizing Units (RMUs)  Total Change Orders Amount:
Start: 11/20/2007         and providing utilities to a new      N/A
Completion: 12/31/2011   approximate 25-seat restaurant
and bar.
Budget/Costs Incurred
Significant Developments
The 100% design is complete.
Schedule
The project completion has been pushed into 2011 to coordinate with
issuance of a Concessions Request for Proposal by the Aviation
Business Development Group.
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not applicable
Change Order
None                                 Location
Risks
Due to delay in schedule, bidding climate may change when the
project is bid and additional budget may be required.
Budget Transfers
To C800152 (Non Aeronautical New Projects)     $200



AIRPORT

Port of Seattle 4Q 2009 Report  31

FOURTH QUARTER REPORT, 2009
Concessions Flooring
Project:   C800157      This project replaces flooring in     Status Snapshot Prior Report
Budget: $2,182,000      North and South Satellite food    Delayed Schedule 2Q 09
Phase: Close Out      courts.                On Budget
Start: 07/24/2007                                 15 Change Orders
Completion: 08/05/2009                       Total Change Orders Amount:
$270,162
Budget/Costs Incurred
Significant Developments
All work is completed.
Schedule
The project is complete.
Budget
The project forecast is within the approved budget and authorization.
Change Order
No change orders were issued this quarter.                   Construction Costs
Risks
None identified at this time.
Budget Transfers
None this quarter
Cost of Construction Growth
Structural deficiencies were encountered during the demolition
phase. Changes in phasing and materials were required to expedite
curing and allow tenants to stay open during construction. Varying    Photo
site conditions such as additional demolition and regulated materials
removal were required.

AIRPORT

32  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Runway 16L/34R Reconstruction
The scope of this project includes    Status Snapshot
Project: C800167
the complete reconstruction of      On Schedule
Budget: $75,000,000                        On Budget
Phase: Close Out      Runway 16L/34R (the eastern
23 Change Orders
Start: 02/26/2008        runway) and replacement of aging
infrastructure.                  Total Change Orders Amount:
Completion: 12/31/2009                       $511,652.59
Significant Developments                    Budget/Costs Incurred
Runway 16L/34R Reconstruction project includes reconstruction of    $90
$80
11,900 foot runway and portions of five taxiways. The construction
$70
was completed on September 25, 2009 and re-opened on
$60
September 26, 2009 on schedule.                        Millions $50$40
$30
Schedule
$20
The runway was re-opened on schedule on September 26, 2009     $10
$0
and contract closeout will continue through 2010.
Authorized    Forecasted   Costs incurred
Budget
Construction Costs for
The project forecast is within the approved budget and authorization.    RW 16L-34R Contract
Change Order                          $70
$60
Nine change orders for a total of $169,962.47 have been executed
during this period. None involved extension of the contract time.       $50
$40
Risks                               Millions $30
No risk have been identified at this time.                        $20
$10
Budget Transfers
$0
To C102166 (Aeronautical Renewal/Replacement)  $10,000,000        Initial  Change Orders  Spent
Photo


AIRPORT

Port of Seattle 4Q 2009 Report  33

FOURTH QUARTER REPORT, 2009
Connect C1 BHS to C88 BHS
Project:   C800170      This project connects the C1      Status Snapshot
Budget: $2,800,000      baggage handling system (BHS) to  On Schedule
Phase: Design        the C88 BHS. It installs two High-  On Budget
Start: 8/30/2009          Speed Diverters plus additional     No Change Orders
Completion: 12/31/2010   baggage conveyor length that will   Total Change Orders Amount:
connect the two C1 sortation loops   N/A
to the C88 BHS.
Budget/Costs Incurred
Significant Developments
The project design has started and 60% drawings should be
complete in January 2010.
Schedule
Currently the project is on schedule.
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.    Construction Costs
Not Applicable
Change Order
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT
34  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Renew/Replace 42 Escalators
Project:   C800237      This project will renew and replace   Status Snapshot Prior Report
Budget: $55,000,000     42 escalators in the Main Terminal,  Ahead of Schedule 3Q 09
Phase: Design        Concourse B, and South Satellites.  On Budget
Start: 11/02/2007         In addition, one new escalator will   No Change Orders
Completion: 12/31/2013   be installed at the South Satellite.   Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Design contract notice to proceed was issued in October 2009. The
project is utilizing a design-build contract method as part of an effort
to accelerate the overall project schedule.
Schedule
The schedule has been updated to reflect an expedited design-build
procurement as well as an accelerated construction duration with a
resultant tentative completion date in 2013. The overall project
schedule will be refined during the preliminary/schematic design.
Budget                            Construction Costs
Not Applicable
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter

AIRPORT

Port of Seattle 4Q 2009 Report  35

FOURTH QUARTER REPORT, 2009
Central Plant Pre-Conditioned Air
Project:   C800238     This project will provide a centralized  Status Snapshot Prior Report
Budget: $33,360,000    pre-conditioned air plant, associated  Delayed Schedule 3Q 09
Phase: Design       heating and cooling piping systems,   On Budget
Start: 06/15/2009       and jet bridge terminal air handling    No Change Orders
Completion: 12/10/2012  units to serve airplanes with heating   Total Change Orders Amount:
and cooling while at the gates.       N/A
Significant Developments
The Design Intent document and preliminary design are complete.    Budget/Costs Incurred
This outlines the basic scope of the project. The Construction
Document phase has started.
Schedule
The negotiation process took longer than anticipated. We are still
approximately two months behind for completing the construction
documents. We are working with the consultant to try to get back on
schedule. The preliminary estimate was completed and the VALE
Grant application was submitted.
Budget
Construction Costs
The project is currently undergoing a value engineering process.     Not applicable
Authorization of construction funding and authority to advertise for
construction will be requested when the design and bid documents
are completed.
Change Order
None
Risks
The schedule is tied to VALE funding.
Budget Transfers
None this quarter.

AIRPORT

36  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Fire Piping Upgrades - Main Terminal
Project:   C800239      This project will upgrade the Main   Status Snapshot Prior Report
Budget: $1,500,000      Terminal fire piping to restore     Ahead of Schedule
Phase: Construction     system reliability and provide full   Under Budget   4Q 09
Start: 09/23/2008         monitoring capability with the fire    No Change Orders
Completion: 01/31/2010   alarm system.             Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
The project is currently in punchlist phase.
Schedule
The construction was completed ahead of schedule. The fire piping
contractor identified efficiencies and performed the work accordingly.
Budget
The project forecast is within the approved budget and authorization.
It is anticipated that this project will have a future savings of
approximately $500,000.
Construction Costs
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter




AIRPORT

Port of Seattle 4Q 2009 Report  37

FOURTH QUARTER REPORT, 2009
2nd Floor HVAC Upgrades
Project:   C800249      Construct a new Heating        Status Snapshot
Budget: $1,497,000      Ventilating and Air-Conditioning    Delayed Schedule
Phase: Construction     (HVAC) air supply duct system to   On Budget
Start: 03/25/2008         the north side of the second floor of  No Change Orders
Completion: 03/31/2010   the central main terminal       Total Change Orders Amount:
administration building and the      N/A
concessions located directly below
on the ticketing level.            Budget/Costs Incurred
Significant Developments
Construction notice to proceed was issued August 17, 2009.
Construction completion is scheduled for March 2010.
Schedule
Construction is still due to be completed in the first quarter of 2010.
Budget
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

38  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Aircraft RON Parking USPS Site           Budget Transfers
Status Snapshot
Project: C800254        This project will prepare the site for
the construction of Hardstands for    On Schedule
Budget: $28,097,000                        On Budget
Phase: Design        use as Remain Overnight parking
of aircraft at the Air Mail Center      No Change Orders
Start: 04/05/2009
site.                            Total Change Orders Amount:
Completion: 06/30/2013                       N/A
Significant Developments
This project completed the lease buyout negotiation with the USPS
Budget/Costs Incurred
and is schedule for lease termination in 2010. A new one year lease
with CBP will extend into 2011. Design efforts for the design
services for the demolition of the Air Mail Center including the         $50
$45
design for minimal site improvements allowing for temporary uses
$40
and amenities, and 15% design for the final Hardstand has been put    $35
$30
on hold until further analysis of use of hardstand based on future
growth.                                          Millions $25
$20
$15
$10
Additional Commission authorizations will be required to execute
$5
lease termination, advertise and award the demolition of the Air Mail     $0
Center, and for the design and construction of the hardstands.           Authorized  Forecasted Costs incurred
Schedule                           Construction Costs
Not Applicable
Project has been put on hold until further analysis of use of
hardstand based on future growth and economic climate.
Budget
The budget of $6,226,213 was authorized by the Commission on
August 26, 2008 for the lease buyout, demolition design and 15%
Hardstand design. The current budget was increased in December
2009 from $28,097,000 to $43,900,000.
Change Order
None.
Risks
No risks identified at this time.

AIRPORT
Port of Seattle 4Q 2009 Report  39

FOURTH QUARTER REPORT, 2009
Common Use Equipment Expansion (CUSE)
Project:   C800276      This project installs flexible       Status Snapshot
Budget: $3,090,000      common use facilities at some    On Schedule
Phase: Design        South Satellite and Concourse A   On Budget
Start: 09/01/2009         gates, as well as at Delta's former   No Change Orders
Completion: 12/31/2011   (pre-NWA merger) ticket counters.  Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Design consultant procurement continues.                    3.5
3
Schedule                             2.5
The project is on schedule.                               Dollars [Millions] 2
1.5
Budget                             1
0.5
The project forecast is within the approved budget. Authorization of
0
construction funding and authority to advertise for construction will
Authorized   Forecasted  Costs incurred
be requested when the design and bid documents are completed.
Change Order
Construction Costs
None                                 Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT

40  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009

South AOA Fence Replacement
Status Snapshot
On Schedule
Project: C800286      This project provides new security
On Budget
Budget: $375,000     fencing around the south end of
No Change Orders
Phase: Construction   Runway 34R that lies south of 188th
Total Change Orders Amount:
Start: 03/03/2009      street, meets current standards for
N/A
Completion: 11/30/2009 airfield security fence, and reduces the
number of coyotes on the airfield to
enhance aviation safety.
Budget/Costs Incurred
$0.40
Significant Developments
$0.35
Fence Replacement was completed in the Fall of 2009.            $0.30
$0.25
Schedule                            Millions $0.20
$0.15
The project is complete. Contract closeout will be in mid 2010.        $0.10
$0.05
Budget                             $0.00
Authorized     Forecasted   Costs incurred
The project forecast is within the approved budget and authorization.
Change Order                        Construction Costs
None.
$0.5
Risks
$0.4
No risks have been identified at this time.
$0.3
Budget Transfers                         Millions $0.2
None this quarter.
$0.1

$0.0
Initial     Change Orders     Spent



AIRPORT

Port of Seattle 4Q 2009 Report  41

FOURTH QUARTER REPORT, 2009
Fire Vehicles
Project:   C001338      Purchase of fire vehicles according  Status Snapshot
Budget: $2,242,000      to the Fire Department Vehicle    On Schedule
Phase: Implementation   Replacement Master Plan. Includes  On Budget
Start: 11/23/2008         Fire Pumer Vehicle purchase.      No Change Orders
Completion: 7/31/2009                        Total Change Orders Amount:
N/A
Significant Developments
Contract has been executed.                           Budget/Costs Incurred
2.5
Schedule
2
Project is on schedule.                                   ] lions
1.5
Budget                             1
The project forecast is within the approved budget and authorization.    Dollars [Mil0.5
0
Change Order
Authorized Forecasted   Costs
None                                               incurred
Risks
None identified at this time.                                Construction Costs
Not Applicable
Budget Transfers
None





AIRPORT

42  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Fire Vehicles
Project:   C102396      Purchase of fire vehicles according  Status Snapshot
Budget: $1,095,000      to the Fire Department Vehicle    On Schedule
Phase: Implementation   Replacement Master Plan. Includes  On Budget
Start: 11/16/2008         purchase of an ARFF vehicle and   No Change Orders
Completion: 7/31/2009    medical aid unit vehicle.        Total Change Orders Amount:
N/A
Significant Developments
ARFF vehicle - Contract has been executed.                 Budget/Costs Incurred
Medical Aid Unit - Contract has been awarded to Sawtooth.
Schedule
Project is on schedule.
Budget
The project forecast is within the approved budget and authorization.
Change Order
None
Construction Costs
Risks                               Not Applicable
None identified at this time.
Budget Transfers
None





AIRPORT
Port of Seattle 4Q 2009 Report  43

FOURTH QUARTER REPORT, 2009
Highline School Noise Insulation
Project:   C200007      Highline School Insulation        Status Snapshot Prior Report
Budget: $101,797,000    Agreement will provide funding for  Delayed Schedule 3Q 09
Phase: Construction     sound mitigation for 15 schools that  On Budget
Start: 03/23/1999         are impacted by aircraft noise from   No Change Orders
Completion: 11/30/2021   Sea-Tac Airport.            Total Change Orders Amount:
N/A

Budget/Costs Incurred
Significant Developments
The insulation of seven schools has been completed and one more
is in progress.
Schedule
Port funding is authorized and will be available when the matching
funds are provided by the state and school district. The schedule for
state funding is not known. The district's schedule is also dependent
on obtaining general election bonds at various intervals.
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable.
Change Order
Not applicable
Risks
This project requires matching funds from the state and voter
approved school bond funding. If the state funding or bonds are not
acquired, construction will be delayed.
Budget Transfers
None


AIRPORT

44  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
3rd Runway Residential Acquisition
Project:   C200015    Acquire single/multi-family residences   Status Snapshot
Budget: $34,340,000   located in the noise-impacted 3rd     On Schedule
Runway flight path in the City of Burien
Phase: Close Out                          On Budget
to comply with FAA noise exposure
Start: 05/27/1999                                 No Change Orders
and safety regulations.
Completion: 06/30/2009                       Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
The final of three phases is largely complete. 56 of 59 properties      45
40
have been acquired and the residents relocated to quieter           35
30
neighborhoods. Three properties have been forwarded to our        25
20
outside legal counsel for acquisition via eminent domain. Timing of     15
the remaining three properties is dependent on the legal process.      10 Dollars [Millions] 5
Demolition of vacant homes continues.                       0
Authorized Forecasted   Costs
incurred
Schedule
The project end date is dependent on the length of time the property
condemnation process takes to work through the legal system.      Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Photo
Change Order
Not Applicable
Risks
No significant risks identified.
Budget Transfers
None


AIRPORT

Port of Seattle 4Q 2009 Report  45

FOURTH QUARTER REPORT, 2009
FAR Part 150 Mobile Home Park Acquisition
Project:   C200037     Acquisition of mobile and         Status Snapshot
Budget: $52,306,110    manufactured home parks, and     Ahead of Schedule
Phase: Close Out     relocation of the tenants, to reduce   On Budget
Start: 02/12/2002       the number of people living in mobile   No Change Orders
homes within high noise areas.
Completion: 06/30/2010                       Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
All mobile home units have been purchased. Portions of the
property have been secured from unauthorized entry. Demolition
50
and site restoration began in vacant areas of the property.
Regulated materials sampling and testing on-going in preparation for
a phased PCS demolition schedule.
Schedule                            Dollars [Millions] 40302010
Our relocation program remains ahead of schedule. One family is       0
waiting to move while they effect some repairs to their replacement        Authorized ForecastedCosts incurred
home.
Construction Costs
Budget                            Not Applicable
The total budget increases for the life of this program are
approximately 2.55% above the 2001 forecast for this Capital
Improvement Project.                               Photo
Change Order
Not Applicable
Risks
Abatement and demolition costs.
Budget Transfers
None

AIRPORT


46  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Highline Community College Noise Insulation
Project:   C200042      Highline Community College      Status Snapshot Prior Report
Budget: $10,822,000     Insulation Agreement will provide   Delayed Schedule 1Q 08
Phase: Construction     funding for up to 22 eligible      On Budget
Start: 01/11/2005         buildings that are impacted by      No Change Orders
Completion: 10/01/2011   aircraft noise from Sea-Tac Airport.  Total Change Orders Amount:
N/A
Significant Developments
Twelve of the 22 eligible buildings have been sound insulated by the  Budget/Costs Incurred
college.
Schedule
Building #9 will be under construction during the summer of 2010.
The construction on building #9 is anticipated to be complete fall of
2010. The schedules for the remaining buildings are dependent on
state funding.
Budget
The project forecast is within the approved budget. We will complete
noise audits on each of the remaining buildings that have not been
reconstructed to see if in the future any will be eligible for FAA grant   Construction Costs
funds. Authorization of the remaining project budget of $4,567,070   Not Applicable.
will be requested for one building at a time from the Commission in
the future when schedule is determined.
Change Order
Not Applicable
Risks
The Highline Community College competes for state funding with
other colleges. If they do not receive adequate funding, projects will
be delayed. The Port is working with the College to determine
estimates for the remaining college buildings that have not been
completed.
Budget Transfers
None

AIRPORT
Port of Seattle 4Q 2009 Report  47

FOURTH QUARTER REPORT, 2009
Home Insulation Retrofit
Project:   C200048      This CIP includes two projects that   Status Snapshot
Budget: $5,344,000      provide either re-insulation or repair  Delayed Schedule
Phase: Construction     of previously insulated homes due  On Budget
Start: 01/11/2005         to safety and condensation issues.   No Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
N/A
Significant Developments
Budget/Costs Incurred
Researching remaining eligible homes to continue and complete
project. Waiting on approval of a new architectural service
agreement with the Central Procurement Office.
Schedule
Will commence upon review of remaining homes and having a new
architectural service agreement to design the construction.
Budget
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not Applicable                                     Not Applicable.
Risks
Liability associated with egress safety issues.
Budget Transfers
None


AIRPORT

48  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Single Family Home Sound Insulation
Project:   C200093      Sound insulate remaining homes    Status Snapshot
Budget: $2,450,000      that are within the 1998 65 decibel  On Schedule
Phase: Construction     day night level (DNL) noise      On Budget
Start: 03/27/2007         contour.                   No Change Orders
Completion: 12/31/2011                       Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Seven homes are in process and there are 28 on the waiting list for
the next group.
Schedule
This project is on schedule.
Budget
The project forecast is within approved budget and authorization.
Change Order
Not Applicable                                     Construction Costs
Not Applicable
Risks
The ability to accomplish the insulation is dependent on
homeowner's schedules, willingness to sign an aviation easement,
and structural integrity of the home.
Budget Transfers
None




AIRPORT
Port of Seattle 4Q 2009 Report  49

FOURTH QUARTER REPORT, 2009
Street Vacations - Des Moines Creek 1
Project:   C800046    Purchase the City of Des Moines-      Status Snapshot Prior Report
Budget: $3,850,000   owned streets in the Des Moines Creek  Delayed Schedule 3Q 09
Phase: Implementation Business Park site that are surrounded  On Budget
Start: 10/01/2008      by Port-owned property. This        No Change Orders
Completion: 6/30/2010  acquisition will enable the Port to     Total Change Orders Amount:
develop the business park site.        N/A
Significant Developments                    Budget/Costs Incurred
Per our agreement with the City of Des Moines, the amount owed
the City has been deposited into an escrow account pending
satisfaction of all the conditions required for closing.
Schedule
Acquisition is expected to be completed by June 30, 2010.
Budget
The project forecast is within the approved budget and authorization.
Change Order                         Construction Costs
Not applicable.                                      Not Applicable
Risks
The original conditions required for closing--most notably, the Des
Moines City Council's approval of the developer's master plan--
cannot be met now that the developer selected for the project
withdrew from ground lease negotiations. The Port anticipates
revising its existing agreement with the City to reflect a new
approach to developing the site.
Budget Transfers
None


AIRPORT

50  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Burien Commercial Property Acquisition
Project:   C800150      Acquire commercial properties     Status Snapshot
Budget: $3,000,000      along Des Moines Memorial Drive,  On Schedule
Phase: Implementation   and vacate one street, in the City of  On Budget
Start: 05/31/2007         Burien that are surrounded by Port-  No Change Orders
Completion: 12/31/2010   owned properties.           Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
The Burien Seventh Day Adventists Church and School were
acquired December 31, 2008. Next acquisitions are for the
Sunnydale Substation and a street vacation in Burien.
Schedule
Properties are purchased as Commission authorization is received.
Program expected to be completed in 2010.
Budget
Project is forecasted to be within budget.                     Construction
Not Applicable
Change Order
None
Risks
None
Budget Transfers
None



AIRPORT

Port of Seattle 4Q 2009 Report  51

FOURTH QUARTER REPORT, 2009
Tenant Reimbursement
Project:   C800154    Build out of spaces for new and      Status Snapshot
Budget: $4,709,577    existing tenants. If more than a "basic  On Schedule
On Budget
Phase: Construction   finish" condition space is built for the
tenant, the tenant is required to       No Change Orders
Start: 08/14/2007
reimburse the Port for the cost of the   Total Change Orders Amount:
Completion: 03/31/2010
work beyond this "basic finish". These   N/A
reimbursements are allowed under
the guidelines described in the       Budget/Costs Incurred
"Tenant Reimbursement Policy".
Significant Developments
Port had no tenant reimbursement activity in the fourth Quarter of
2009. It is anticipated that both Hawaiian and Delta will have a
tenant reimbursement payout in first quarter of 2010 for construction
projects that were previously completed; agreements and
documentation are being compiled.
Schedule
The project is currently on schedule to meet the tenant's needs.
Construction Costs
Budget                            Not Applicable.
The project forecast is within the approved budget.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter



AIRPORT
52  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 20102009
Alaskan Way St Vacation and Public Access
Project:   C000579      Scope includes all public access    Status Snapshot Prior Report
Budget: $1,036,000      improvements at multiple sites and  Delayed Schedule 2Q 08
Phase: Planning       fees as required by the City of    On Budget
Start: 1996             Seattle in order to vacate Alaskan   No Change Orders
Completion: 2011       Way South at T30 site.        Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Not Applicable
1.2
1
Schedule
No changes this quarter. Project continues to be on hold pending      Millions 0.8  Dollars in 
0.6
closure of all other previous street vacations.
0.4
0.2
Budget
0
No changes this quarter. Plan is to get new authorizations for future        Authorized  Forecasted Costs Incurred
work pursuant to Resolution 3605.
Change Order                         Construction Costs
Not Applicable                                     None
Risks
Risks have not changed from 3rd Quarter 2008.
Budget Transfers
Not Applicable



SEAPORT


Port of Seattle 4Q 2009 Report  53

FOURTH QUARTER REPORT, 2009
T-115 Dock Reconstruction
Project:   C102451      Upgrade three areas of existing    Status Snapshot Prior Report
Budget: $31,541,577     1200 ft dock, upgrade Berth 1 and  Delayed Schedule 4Q 08
Phase: Construction     improve 15 acres of uplands for    Forecast Overrun 1Q 08
Start: 7/2003            tug/barge cargo operations.       22 Change Orders
Completion: 12/31/2009                       Total Change Orders Amount:
$1,132,194
Significant Developments                    Budget/Costs Incurred
Construction began in Q4.
32
31
Schedule                             Millions30
No change from Q3.                                29
28
Dollars in 27                                                                             Budget                                                                  26
No change this quarter.                                  25
Authorized  Forecasted    Costs
Incurred
Change Order
No change orders this quarter
Construction Costs
Risks
25
A tenant requested change to one element of the project, a ramp
20
lifting system, may impact the schedule. Unanticipated underwater     Millions 15
obstructions encountered during installation of sheet pile may impact
budget and schedule.                                  10
Dollars in   5
Budget Transfers                           0
None                                     Initial Change Spent
Orders



SEAPORT

54  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
T25/30 Improvements 2005-2007
Project:   C800064      Improve T25 container yard, and    Status Snapshot Prior Report
Budget: $13,787,870     build bridge between T25 and T30  Delayed Schedule 3Q 08
Phase: Close Out      to improve access. Complete street  On Budget
Start: 2005             vacation at S. Forest St. and       No Change Orders
Completion: 2011       related public access         Total Change Orders Amount:
improvements.              $0
Significant Developments                    Budget/Costs Incurred
The project has started the closeout process. This will be the last
15
report on this project.
10
Schedule                            Millions
No changes to report this quarter.
5
Dollars in 
Budget
0
No changes to report this quarter
Authorized  Forecasted Costs Incurred
Change Order
Not applicable                                     Construction Costs
Not applicable
Risks
Not applicable
Budget Transfers
Not applicable



SEAPORT


Port of Seattle 4Q 2009 Report  55

FOURTH QUARTER REPORT, 2009
Terminal 30/Terminal 91 Program          Status Snapshot
On Schedule
On Budget
Project: C800085     Redevelopment of Terminals 25/28/30   129 Change Orders
Budget: $121,525,000  into one combined container facility.    Total Change Orders
Phase: Construction  Relocation of the existing T30 Cruise   Amount: $6,581,000.
Start: 10/2/07        operations into a new facility at T91, and
Completion: 4/30/11   related facility improvements and berth   Budget/Costs Incurred
dredging.
Significant Developments                     125
T91: The first cruise season at the Smith Cove Cruise Terminal
120
wrapped up in October 2009 and Port received positive feedback      Millions
from the end users and our partners/stakeholders on the facility and    115
operations. Some of the deferred project work elements began in 4th
110
quarter, and in December, Commission authorized staff to proceed     Dollars in 
with new canopies and other improvements utilizing the existing       105
budget. Cruise Terminal's art planner selection is complete and           Authorized  Forecasted Costs Incurred
planner has begun planning for terminal's public art. (Continued on
Page 2).
Construction Costs
Schedule
100
T91: Targeting completing additional canopies north of the cruise
80
terminal before the 2010 cruise season but due to aggressive
schedule, some work may be deferred after the 2010 cruise season.    Millions 60
Terminal's public art component is scheduled to be completed in        40
2011.
Dollars in   20
0
T30: Terminal became operational on August 3, 2009, as previously         Initial Change Orders Spent
reported.
Photos
Budget
The budget remains stable. As reported last quarter, current program
budget is $121,500,000 and the forecast is $115,638,000 based on a
comprehensive Monte Carlo analysis as of November 2009.
Change Order
There were 11 change orders this quarter for a total credit of
$288,458, primarily due to reconciliation of unit cost of items during
contract closeout.

56  Port of Seattle 4Q 2009 Report

Budget Transfers
There were no budget transfers in or out of the program.
Cost Growth of Construction
T91 Cruise Terminal Upgrade  MC-0314783  The Port
construction contract is in closeout. The cost growth of construction
remains as reported in 3Q 09.
T30 Upgrade  MC-103326  total change order based on the total
program construction cost decreased from 15.87% to 14.15% due to
credit change orders for reconciling unused force account pay items.
Significant Developments, continued
T-91: Environmental monitoring associated with the intertidal habitat
area at T91 is ongoing as planned. Completed Bird Control
installation contract
T-30: T30 major construction is complete. Only small works items
are yet to be finalized, as such this will be the final report on T-30.
Risks
T91: None. Facility is in operation.
T30: None. Facility is in operation .



SEAPORT



Port of Seattle 4Q 2009 Report  57

FOURTH QUARTER REPORT, 2009
P66 Bag. Corridor & Pass. Screening
Project:   C800114      Provide baggage and passenger    Status Snapshot Prior Report
Budget: $2,087,000      screening improvements at P66 to  Delayed Schedule 3Q 09
Phase: Construction     accommodate larger cruise vessels  On Budget
Start: 1/1/2008          with 300-400 more passengers per   No Change Orders
Completion: 12/31/2009   sailing.                Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The elevator upgrades were rebid a second time through the small
2.5
works process and received no bids. It was rebid again through an
advertised process and received 1 bid for $144,000.                2
Millions 1.5
Schedule
1
The schedule may be pushed back if the contractor is unable to       Dollars in 0.5
secure the required parts and equipment in a timely manner.
0
Authorized  Forecasted Costs Incurred
Budget
None
Construction Costs
Change Order                         None
None
Risks
The schedule is at risk but full impacts will not be known until the
contract is completed and the contractor provides a schedule.
Budget Transfers
None


SEAPORT


58  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Terminal 18 South Fender Improvements
Status Snapshot
Project: C800121        Replace 800' of deteriorated fender
Delayed Schedule
Budget: $450,000       system at the south end of
On Budget
Phase: Design        Terminal 18
0 Change Orders
Start: 3/26/08                                    Total Change Orders Amount:
Completion: 3/31/10                         $0
Significant Developments
Staff is working on completion of the design and permitting for the
1200 lf timber fender system replacement with steel fender system.
90% design completed. Updated cost estimates indicate expected    Budget/Costs Incurred
costs approximately $200,000 higher than original estimate for 800'
replacement, and approximately $1,200,000 differential between
800' verses 1200' replacement options.                       3.5
3
Schedule                            Millions 2.52
Permit applications completed, design completion expected by        1.5
February 2010. Finalizing the design took longer than had originally
Dollars in   1
estimated. As a result construction is scheduled to start in            0.5
December 2010 after the tribal fishing activities are complete. The      0
berth will be available for use in March 2011.                        Authorized  Forecasted Costs Incurred
Budget
Project within approved budget.                          Construction Costs
None
Change Order
None this quarter
Risks
None this quarter
Budget Transfers
None


SEAPORT
Port of Seattle 4Q 2009 Report  59

FOURTH QUARTER REPORT, 2009
T-5 Crane Spreader Replacement
Project:   C800123      To replace two crane cargo       Status Snapshot Prior Report
Budget: $525,000       spreader beams that are beyond   Delayed Schedule
Phase: Construction     their useful life. Spreader beams   On Budget
Start: 10/24/06          are terminal equipment used to     No Change Orders
Completion: 3/31/09     move containers to and from ships  Total Change Orders Amount:
and trucks.                   $0
Significant Developments                    Budget/Costs Incurred
After review of design submittals, some electrical and mechanical
3.5
changes were required to comply with code requirements and to
3
make the new spreaders compatible with some existing equipment.
Millions 2.5                                                                                   Delivery was delayed until 1Q 2010.                                           2
1.5
Schedule                            Dollars in  1
0.5
Delivery was delayed from 4Q2009 to 1Q2010.
0
Authorized  Forecasted Costs Incurred
Budget
Only two of the spreader beams will be installed due to the tenant
reprioritizing their needs. The forecast has been reduced          Construction Costs
accordingly.
0.6
Change Order
0.5
None                                   0.4
0.3
Millions
Risks                                 0.2
None                                  Dollars in  0.1
0
Budget Transfers                             Initial Change Orders Spent
None


SEAPORT

60  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
North Harbor Island Mooring Dolphins (4)
Project:   C800182      Replace four barge mooring      Status Snapshot
Budget: $1,900,000      dolphins at the north end of Harbor  On Schedule
Phase: Design        Island.                On Budget
Start: 07/05/09                                   0 Change Orders
Completion: 12/31/10                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Currently in negotiations with design consultant to complete bid
0.6
package.
0.5
0.4
Schedule                            Millions
0.3
Design contract negotiations have taken longer than expected, but
0.2
overall project is still on schedule to be completed within the 2010-11    Dollars in 0.1
permit fish window.
0
Authorized  Forecasted Costs Incurred
Budget
Project is within budget.
Construction Costs
Change Order                         Not applicable
None
Risks
None
Budget Transfers
None


SEAPORT


Port of Seattle 4Q 2009 Report  61

FOURTH QUARTER REPORT, 2009
T25 South Redevelopment
Project:   C800259      Redevelopment of former cold     Status Snapshot Prior Report
Budget: $4,377,513      storage facility site at south end of  Delayed Schedule 4Q 08
Phase: Construction     Terminal 25 into container terminal  On Budget
Start: 11/2007           yard.                     No Change Orders
Completion: Indefinite                        Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Phase 2 construction cancelled, as such this wil be the final report
20
for this project.
Millions 15                                                                                  Schedule
10
This project has been closed per decision by the Containers group.
Dollars in  5
Budget
0
This project has been closed based on lack of foreseen tenant within
Authorized    Forecasted   Cost Incurred
the next few years.
Change Order                         Construction Costs
None
1.8
1.6
Risks                                 Millions 1.4
1.2
None                                    1
0.8
Dollars in  0.6
Budget Transfers                           0.4
0.2
0
None
Initial       Change      Spent
Orders



SEAPORT

62  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
T-10 Interim Redevelopment
Project:   C800264      Funding is to develop full project    Status Snapshot Prior Report
Budget: $800,000       scope and design of utilities to    Delayed Schedule 1Q 09
Phase: Design        support terminal related activities.   On Budget
Start: 3/22/08           Primary focus is the design of the    No Change Orders
Completion: 11/30/09    storm water drainage system and   Total Change Orders Amount:
the paving, lighting and fencing.     $0
Significant Developments                    Budget/Costs Incurred
In 3Q 2009, staff completed 60 % design documents and submittal
permits to the City of Seattle, State and Federal Agencies. After
6
several discussion with Agency's representatives, the design
5
required significant modifications. The modified design was
4
resubmitted in 4Q 2009.
Millions 3
2
Schedule                            Dollars in 1
No change. Completion of the project, contingent on permit
0
approval, is scheduled for 3Q 2010.
Authorized  Forecasted Costs Incurred
Budget
Staff will return to Commission for additional construction          Construction Costs
authorization 2Q 2010.                               None
Change Order
None
Risks
Schedule delays
Budget Transfers
None

SEAPORT


Port of Seattle 4Q 2009 Report  63

FOURTH QUARTER REPORT, 2009
T91 Mobile Gangway
Project:   C800273      Construct two mobile gangways    Status Snapshot
Budget: $6,460,000      and the associated support      On Schedule
Phase: Construction     infrastructures for the new T91    On Budget
Start: 6/24/2008          Cruise Terminal              4 Change Orders
Completion: 4/30/2009                        Total Change Orders Amount:
$537,384
Significant Developments                    Budget/Costs Incurred
The new mobile gangways performed well during the first (2009)
6.5
cruise season. There is a clearance issue associated with the vessel
walkways and staff is coordinating with the supplier/fabricator for       6.4
resolution with the intent that all revision work be completed by the     Millions
6.3
2010 cruise season.
Dollars in 6.2
Schedule
6.1
Gangways are in use. Systems are under an 18 month warranty.         Authorized Forecasted Costs Incurred
Budget
Project is on budget.                                   Construction Costs
Change Order                           7
6
No change orders were issued during 4th quarter 2009.
5
4
Risks
Millions
3
None                                  Dollars in   2
1
0
Budget Transfers
InitialChange OrdersSpent
None

Photo

SEAPORT

64  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
T91 RD Pave entry & Gardshk
Project:   C800343      Repave main entryway/intersection  Status Snapshot
Budget: $138,000       west of the main guard shack.     On Schedule
Phase: Design                            On Budget
Start: 12/18/09                                   0 Change Orders
Completion: 5/1/2010                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Project design is in progress.
0.15
Schedule
Project design is currently delayed. Other design and construction     Millions 0.1  Dollars in 
elements will be investigated.
0.05
Budget
0
Project is currently on budget.
Authorized  Forecasted Costs Incurred
Change Order
None.                                    Construction Costs
None
Risks
This is a fast tracked project, and the paving is weather dependent.
Budget Transfers
None



SEAPORT


Port of Seattle 4Q 2009 Report  65

FOURTH QUARTER REPORT, 2009
T46 Upgrade Yard Lighting
Project:   C800347      Purchase and Engineering support  Status Snapshot
Budget: $680,000       for installation of energy saving    On Schedule
Phase: Design        yard lighting and equipment, as    On Budget
Start: 08/25/09          part of T46 lease negotiation.      0 Change Orders
Completion: 12/31/2010                       Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Reviewed purchase package with Tenant. Engineering is making
0.8
final revisions to the package
0.6
Schedule                            MillionsDollars in 
0.4
Purchase package ready for Central Procurement Office mid
February                                       0.2
0
Budget
Authorized  Forecasted Costs Incurred
No change
Change Order                         Construction Costs
None
0.7
Risks                                 0.6
0.5
None this quarter
0.4    Millions
0.3
Budget Transfers
Dollars in   0.2
None                                   0.1
0
Initial Change Orders Spent



SEAPORT

66  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
East Marginal Way Grade Separation
Project:   E 102007      FAST Corridor funded project;
Budget: $49,000,000     FHWA, State, City with Port      Status Snapshot Prior Report
Phase: Construction     commitment of $18,800,000. Scope  Delayed Schedule 1Q 08
Start: 5/2006            is to construct grade separation in   Forecast Overrun  1Q 08
Completion: Q3 2011     vicinity of T5 and T18 to minimize   1 Change Orders
truck traffic/rail conflicts.            Total Change Orders Amount:
($106,250) deductive
Budget/Costs Incurred
Significant Developments
Seattle City Light completed the selection of their facility on           60
September 30, 2009. Construction bids received September 22nd      50
and contract awarded to Mowatt Construction on October 23, 2009.     40
Millions 30
Schedule
20
Notice to proceed with field work granted November 2009.          Dollars in 10
Scheduled completion is September 1, 2011.                   0
Authorized  Forecasted Costs Incurred
Budget
The American Recover and Reinvestment Act (ARRA) has provided
a new funding source for the Project in the amount of $2,875,171.00  Construction Costs
which is expected to reduce amount needed from Port of Seattle.
Bidding climate of lower contract prices has allowed reduction in         60
estimated Project cost from $50.7M to $49M.                    50
40
Change Order                           30
Millions
A change order for reduced number of earthquake drains in the         20
amount of $106,250.                                 Dollars in  10
0
Risks                                   InitialChange OrdersSpent
Construction change orders could occur, which could increase cost
of construction
Budget Transfers
New source of funds indicates that no budget transfers will be
required.

SEAPORT
Port of Seattle 4Q 2009 Report  67

FOURTH QUARTER REPORT, 2009
Terminal 46 ZPMC Gearboxes
Project:   Expense      Implementation of contingency     Status Snapshot
103705,103706,103707    plans to keep the three port owned  On Schedule
Budget: $1,227,000      ZPMC cranes located at Terminal   On Budget
Phase: Construction     46 operating while          No Change Orders
Start: 8/22/2007          cause of the failing gearboxes is    Total Change Orders Amount:
investigated                  $0
Completion: 12/31/09
Budget/Costs Incurred
Significant Developments
1.25
The Port Chief Executive Officer met with ZPMC in November to
1.2
renew commitment to resolve and a spirit of cooperation.
1.15  Millions
1.1
Schedule
1.05
No change from 2009 report. Continuing to work with the designer,     Dollars in  1
consultants and manufacturer to identify a solution.
0.95
Authorized  Forecasted Costs Incurred
Budget
Budget remains unchanged from the 2Q 09 Report.
Construction Costs
Change Order                         No Major Construction
None this quarter                                    Contracts
Risks
Additional gearbox failures would result in further disruptions to
operations.                                        Photo
Budget Transfers
None



SEAPORT

68  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2010
T5/T18 Maintenance Dredging
Project:   Expense   Mechanically dredge up to 6,900 cy of   Status Snapshot
103835/103838      sediment along approximately 4,900' of  On Schedule
Budget: $2,937,000   berths at T18 and dispose of dredged   Under Budget
Phase: Construction  material at approved upland disposal   No Change Orders
Start: Feb 2008       sites; conduct environmental testing,    Total Change Orders Amount:
permitting, and design work for T5      $0
Completion: Feb 2011
maintenance dredging
Budget/Costs Incurred
Significant Developments                     3.5
T18 Maintenance dredging is complete; permitting and design work      3
for T5 Maintenance Dredging has begun. Expect requesting         Millions 2.52
Commission final approval for T5 Maintenance dredging in summer
1.5
of 2010.
Dollars in   1
0.5
Schedule
0
No changes from last quarter.                                Authorized Forecasted Costs Incurred
Budget
No changes from last quarter                           Construction Costs
None
Change Order
N/A
Risks
N/A
Budget Transfers
N/A


SEAPORT

Port of Seattle 4Q 2009 Report  69

FOURTH QUARTER REPORT, 2009
Barge Layberth Improvements -- T25/P28/T46
Project: Expense 104011-3 Improvements to the fendering and  Status Snapshot
Budget: $300,000       terminal systems at Terminal 25,   On Schedule
Phase: Construction     Pier 28 and Terminal 46 to provide  On Budget
Start: 10/14/08          viable barge layberth use at these   No Change Orders
Completion: 4/1/10      sites.                 Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
T25 construction completed. Scope of fender pile work at P28 and
0.35
T46 modified to concentrate scope in highest priority areas per
0.3
Commission authorization of 11/10/09.                       0.25 Millions 0.2
Schedule                            0.15
0.1
Construction completion expected in February 2010. Delay and
0.05
Dollars in 
resetting of the original schedule was to accommodate re-scoping
0
effort and occurred with the 11/10/09 Commission authorization.
Authorized  Forecasted Costs Incurred
Budget
Project is within budget.                                  Construction Costs
No Major Construction
Change Order                         Contracts
None this quarter
Risks
Additional damage found at P28, including at least two additional
broken piles and additional failed walkway sections.              Photo
Budget Transfers
None


SEAPORT


70  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Radio Frequency Identification (RFID)
Project:   E104066      RFID Phase 2 (2008-2010):       Status Snapshot
Budget: $578,035       Expansion of RFID project to     On Schedule
Phase: Planning       additional terminals, rail facilities   On Budget
Start: 10/14/08          and possibly freight corridors within  0 Change Orders
Completion: 12/31/10    the Port of Seattle area.        Total Change Orders Amount:
$0
Budget/Costs Incurred
Significant Developments
No change from last report. This will be the last report.              0.7
0.6
Schedule                            Millions 0.50.4
No change.                                    0.3
Dollars in 0.2
Budget                             0.1
0
The current program budget is $578,035. 86.5% is grant funded and
Authorized  Forecasted Costs Incurred
13.5% is Port funded.
Change Order
Construction Costs
None                                 None
Risks
None
Budget Transfers
None


SEAPORT


Port of Seattle 4Q 2009 Report  71

FOURTH QUARTER REPORT, 2009
Water/Sewer Meter Upgrade
Project:   Expense      Upgrade existing water and sewer   Status Snapshot
multiple work projects    meter to meet current Seattle      On Schedule
Budget: $373,000 in total  Public Utilities standards       On Budget
Phase: Planning                          0 Change Orders
Start: 09/13/09                                   Total Change Orders Amount:
$0
Completion: 12/23/2010
Budget/Costs Incurred
Significant Developments
0.4
Construction will take place as projects are created and design plans
established.                                          0.3
Millions
0.2
Schedule
Project is on schedule.                                   Dollars in 0.1
0
Budget
Authorized  Forecasted Costs Incurred
$373,000, approximately $123,000 of which is tenant reimbursable
Change Order                         Construction Costs
None                                 None at this time
Risks
POS and tenants will pay higher commercial sewer rates on meters
without upgraded technology
Budget Transfers
None


SEAPORT


72  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
SBM Renewal and Replacement
Project:   C001706,      Redevelopment Shilshole Bay     Status Snapshot Prior Report
C001769, C001716      Marina docks, landside facilities,   On Schedule
Budget: $80,000,000     infrastructure and buildings.      On Budget
Phase: Construction                        149 Change Orders
Start: 1997                                     Total Change Orders Amount:
Completion: 4/30/2010                        $6,299,064
Budget/Costs Incurred
Significant Developments
80.5
All major construction is complete. Construction of interim pad site
80
flatwork complete and landscaping to start in early Spring 2010.
Millions79.5
Schedule                             79
78.5
Interim Pad Site improvements completed except irrigation and
Dollars in  78
landscaping work to be completed by April 30, 2010 due to weather
77.5
constraints for plantings.
77
Authorized  Forecasted Cost Incurred
Budget
No change this quarter.
Construction Costs
Change Order
60
None this quarter
50
Risks
Millions 40
30
None identified this quarter.
Dollars in  20
10
Budget Transfers
0
None                                      Initial  Change  Spent
Orders



REAL ESTATE
Port of Seattle 4Q 2009 Report  73

FOURTH QUARTER REPORT, 2009
T 102 HVAC Renewal/Replacement
Project:   C800070      Replace HVAC System at all four   Status Snapshot Prior Report
Budget: $1,300,000      buildings at the Harbor Marina    Delayed Schedule 4Q 08
Phase: Construction     Conference Center          On Budget
Start: 10/2/2005                                  No Change Orders
Completion: 12/1/2008                        Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Will use Open Order Small Works contract to get the last 7 units
1.35
installed.
1.3
Schedule                            1.25 MillionsDollars in 
No changes from previous report.                          1.2
1.15
Budget
1.1
Project is on budget.
Authorized  Forecasted Costs Incurred
Change Order
None                                 Construction Costs
Risks                                 0.4
Budget is very tight.                                        0.3
Budget Transfers                          0.2
Millions
None                                  Dollars in  0.1
0
Initial Change Orders Spent



REAL ESTATE

74  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
C15 Sewer Line Upgrades
Project:   C800125      Replace the failing sewer/drain     Status Snapshot Prior Report
Budget: $600,000       lines under the Fisherman's      Delayed Schedule 3Q 09
Phase: Construction     Terminal C-15 West Building     On Budget
Start: 4/1/2008                                   3 Change Orders
Completion: 3/31/2009                        Total Change Orders Amount:
$99,000
Significant Developments                    Budget/Costs Incurred
Project is substantially complete and in closeout.
0.61
0.6
Schedule
0.59
Final closeout expected within Quarter 1, 2010.                  0.58  Millions
0.57
Budget                             0.56 Dollars in 
0.55
Anticipated budget savings of $25,000-$30,000 (approximately 5%).
0.54
Authorized  Forecasted Costs Incurred
Change Order
None this quarter
Construction Costs
Risks                               None
None
Budget Transfers
None



REAL ESTATE


Port of Seattle 4Q 2009 Report  75

FOURTH QUARTER REPORT, 2009
FT South Wall Reconstruction Phase IV
Project:   C800136      Completion of Fishermen's       Status Snapshot
Budget: $1,030,000      Terminal South Wall         On Schedule
Phase: Design        Reconstruction. Phase IV is located  On Budget
Start: 6/2009            along parcel currently leased by    No Change Orders
Completion: 6/2011      FVO.                 Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Geotechnical consultant contract and site borings completed.
7
Started on 15% engineering design. The activities on this project are
6
concurrent with the MIC Central Seawall Replacement Project.
Millions  5
4
Schedule                             3
90% design scheduled for early 3Q 2010. Request for construction     Dollars in  2
1
funding is scheduled for early 3Q 2010. Staff expects to receive
0
permits by 3Q 2010. Targeted construction start is by December
Authorized  Forecasted Costs Incurred
2010 and completion date is expected by June 2011.
Budget
Construction Costs
No change this quarter.                                None at this time
Change Order
None this quarter.
Risks
None this quarter.
Budget Transfers
None


REAL ESTATE


76  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
MIC Central Seawall Replacement
Project:   C800175      Replacement of steel sheet pile    Status Snapshot
Budget: $410,000       seawall between West Pier and    On Schedule
Phase: Design        Central Pier at Maritime Industrial   On Budget
Start: 9/2008            Center.                    No Change Orders
Completion: 6/2011                          Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Geotechnical consultant contract completed and site borings
2.5
completed. Started on 15% design. The activities on this project are
concurrent with the FT South Wall project activities.                 2
Millions 1.5
Schedule
1
90% design scheduled for early 3Q 2010. Request for construction     Dollars in 0.5
funding is scheduled for early 3Q 2010. Staff expects to receive
0
permits by 3Q 2010. Targeted construction start is by December
Authorized  Forecasted Costs Incurred
2010 and completion date is expected by June 2011.
Budget
Construction Costs
No change this quarter.                                None at this time
Change Order
None
Risks
None
Budget Transfers
None


REAL ESTATE


Port of Seattle 4Q 2009 Report  77

FOURTH QUARTER REPORT, 2009
Maximo Enterprise Implementation
Project:   C800003      Implement latest version of       Status Snapshot Prior Report
Budget: $3,680,000      Maximo, merge Aviation and Real   Delayed Schedule
Phase: Implementation   Estate applications onto one     On Budget
Start: 11/25/2007         platform, add service desk module   0 Change Orders
Completion: 9/30/2010    and wireless handheld capabilities.  Total Change Orders Amount:
$0
Significant Developments
Service Management software deployed for ICT Service Desk in     Budget/Costs Incurred
December 2008. Legacy Ticket system decommissioned.
The design and development for Phase 2, upgrade and consolidation    4
of Marine Maintenance and Aviation Maintenance Maximo systems,
3
is in progress.
Millions 2
Schedule
Dollars in  1
Prior Report - Delay of 9 months due to resource constraints and a
successful re-planning effort to mitigate potential vendor cost          0
overruns.                                             Authorized Forecasted Costs Incurred
Budget
On Budget
Change Order                         Construction Costs
Not Applicable
None
Risks
Organization requests to work on business process improvements
prior to project deployment may further delay project completion.
Budget Transfers
None



CORPORATE
78  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Public Safety Computer Aided Dispatch
Project:   C800015      Implementation of Computer Aided  Status Snapshot Prior Report
Budget: $2,250,000      Dispatch (CAD) system, including   Delayed Schedule
Phase: Close Out      basic CAD functionality, mobile    On Budget
Start: 2/19/2006          clients, and automated vehicle     0 Change Orders
Completion: 10/27/2009   location.                Total Change Orders Amount:
$0
Significant Developments
System fully operational                                Budget/Costs Incurred
Schedule                             2.3
2.25
Prior Report - Phase 2 deployment delayed 26 days for resource
Millions 2.2                                                                                   availability.
2.15
2.1
Budget
2.05  Dollars in 
On Budget                                    2
1.95
Change Order                          1.9
Authorized  Forecasted Costs Incurred
None
Risks
No significant risks
Construction Costs
Budget Transfers                        Not Applicable
None




CORPORATE

Port of Seattle 4Q 2009 Report  79

FOURTH QUARTER REPORT, 2009
Parking System Consolidation
Project:C800066        Consolidate four separate       Status Snapshot
Budget:$250,000       applications supporting different    Delayed Schedule
Phase:Testing         parking programs into a single Port  On Budget
Start: 9/23/2008          Parking System.              0 Change Orders
Completion:4/30/2010                         Total Change Orders Amount:
$0
Significant Developments
Business has requested additional features that would impact       Budget/Costs Incurred
authorized budget. To resolve, we will remove one of the four
applications from the consolidation effort. This application will be       0.252
maintained separately until it is evaluated as part of the larger         0.25
Parking Revenue Control System.
0.248
Millions
Schedule                            0.246
0.244   Dollars in
Project will require an additional three months to complete testing
and deployment activities.                                0.242
Authorized  Forecasted  Costs Incurred
Budget
On Budget
Construction Costs
Change Order                         Not Applicable
None
Risks
No significant risks
Budget Transfers
None



CORPORATE

80  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Area Surveillance
Status Snapshot Prior Report
Project:   C800118      Replace 52 cameras and network   Delayed Schedule     4Q 08
Budget: $864,000       infrastructure at eight seaport     Under Budget       4Q 08
Phase: Close Out      facilities with new hardware to work  0 Change Orders
Start: 11/25/2007         with the Puretech system being     Total Change Orders Amount:
Completion: 12/30/2009   deployed by Marine Domain      $0
Awareness project.
Budget/Costs Incurred
Significant Developments
1
New video surveillance system is operational.
0.8
Schedule                             0.6 Millions
Prior Report - delay of 6 months due to change in engineering and      0.4
construction procurement processes.                       Dollars in 0.2
0
Budget
Authorized  Forecasted Costs Incurred
Prior Report - anticipating a budget under run of $200,000 due to
obtaining lower prices for equipment and software.
Construction Costs
Change Order
None                                   0.25
0.2
Risks
Millions 0.15
No remaining significant risks.
0.1
Budget Transfers                          Dollars in  0.05
None
0
Initial   Change Orders   Spent

CORPORATE



Port of Seattle 4Q 2009 Report  81

FOURTH QUARTER REPORT, 2009
Marine Domain Awareness
Project:   C800119     Implement a series of Seaport      Status Snapshot
Budget: $7,130,000     Security projects, including video    Delayed Schedule
Phase: Construction    monitoring, communication and     Under Budget
Start: 12/9/2007        access control.                0 Change Orders
Completion: 3/31/2009                        Total Change Orders Amount:
$0
Significant Developments
Three major components of this program have been completed:     Budget/Costs Incurred
x Dashboard showing real-time information from a variety of
operational sources.
x Wireless Infrastructure across all Seaport locations.               8
x TWIC infrastructure at Pier 66.                            7
6
Most work on the remaining two components has been completed:      5
x Video Surveillance - Construction complete. Remaining work to       4
configure video software will be complete in April '10.              Dollars in Millions 3
2
x T91 Fencing- Bollard installation will be complete in April '10.
1
0
Schedule                               Budget  Forecast Cost Incurred
On Schedule
Construction Costs
Budget
Project Budget Components include:
1.2
x Grant Reimbursement
1
x 25% Port funded match
x Port funded, Non-Grant Eligible employee costs
0.8
0.6
We are anticipating a budget under run for the Grant Reimbursement    Dollars in Millions 0.4
Budget Component of $1,000,000. The combined Port funded         0.2
components are on budget.                              0
Initial      Change      Spent
Orders
Change Order
None
Risks
No Significant Risks
Budget Transfers
None
CORPORATE
82  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
UltraCUSE Implementation
Project:C800223        Replace the current Airport      Status Snapshot
Budget:$1,550,000       Common Use system (CUTE) with  On Schedule
Phase:Close Out       Ultra Electronic's UltraCUSE     On Budget
Start: 9/23/2008          system.                   0 Change Orders
Completion:9/30/2009                         Total Change Orders Amount:
$0
Significant Developments
All common use positions and airlines using the common use system  Budget/Costs Incurred
at SeaTac have been converted to the Ultra Electronics' UltraCUSE
system.
1.6
An additional requirement has been requested by Aviation          1.55
Operations to replace several aging common use printers used by
1.45  Millions 1.5
airlines to print passenger documents. These aging printers break or
1.4
jam frequently disrupting airline operations during critical passenger
1.35
processing times. This replacement will also allow us to standardize    Dollars in 
1.3
equipment configurations enabling airlines to move more freely       1.25
between common use positions. This requirement can be met with        Authorized Forecasted Costs Incurred
no additional funding.
Schedule
On Schedule                                 Construction Costs
Not Applicable
Budget
On Budget
Change Order
None
Risks
No significant risks
Budget Transfers
None

CORPORATE
Port of Seattle 4Q 2009 Report  83

FOURTH QUARTER REPORT, 2009
Enterprise Project Cost Management
Project:C800321        Replace the current construction   Status Snapshot
Budget:$1,525,000       costing systems with a common    Delayed Schedule
Phase:Planning        enterprise project cost         On Budget
Start: 4/21/2008          management system.           0 Change Orders
Completion:On-Hold                         Total Change Orders Amount:
$0
Significant Developments
Vendor did not deliver software per contract and Notice to Cancel    Budget/Costs Incurred
has been sent. Legal is assisting in the negotiations. Project has
been put on-hold while alternatives are evaluated. A recomm-         2
endation will be complete in April 2010.
1.5
Schedule                             Millions 1
On-hold
Dollars in 0.5
Budget                             0
None                                     Authorized Forecasted Costs Incurred
Change Order
None
Construction Costs
Risks
Not Applicable
See significant developments
Budget Transfers
None


CORPORATE


84  Port of Seattle 4Q 2009 Report

FOURTH QUARTER REPORT, 2009
Records and Document Management
Project:   C800322      Improve statutory compliance,     Status Snapshot
Budget: $800,000       increase functionality, and lower   On Schedule
Phase: Implementation   operating costs by replacing     On Budget
Start: 6/23/2009          Hummingbird with SharePoint for    0 Change Orders
Completion: 5/30/2010    records and document        Total Change Orders Amount:
management.             $0

Significant Developments                    Budget/Costs Incurred
Design and development in progress.
1
Schedule
0.8
On Schedule
Millions 0.6
Budget                             0.4
On Budget                                   Dollars in 0.2
0
Change Order
Authorized  Forecasted Costs Incurred
None
Risks
No Signficant Risks                                  Construction Costs
Not Applicable
Budget Transfers
None





CORPORATE
Port of Seattle 4Q 2009 Report  85

FOURTH QUARTER REPORT, 2009
Data Archive
Project:C800326        Acquire new software and       Status Snapshot
Budget:$560,000       hardware to implement an online   On Schedule
Phase:Implementation    data archival system that is      On Budget
Start: 6/23/2009          separate from the backup data     0 Change Orders
Completion:4/30/2010     storage infrastructure and process   Total Change Orders Amount:
$0
Significant Developments
Procurement complete and installation of system in Fisher Plaza     Budget/Costs Incurred
Data Center in progress. Airport Data Center installation will begin in
February.                                        0.6
0.5
Schedule                             0.4
On Schedule                                   Millions 0.3
0.2
Budget                             Dollars in 0.1
On Budget                                    0
Authorized  Forecasted Costs Incurred
Change Order
None
Risks
Construction Costs
No significant risks.                                      Not Applicable
Budget Transfers
None




CORPORATE
86  Port of Seattle 4Q 2009 Report

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.