RCF GC/CM Construction Contract 
Construction workers on site are averaging 190, with over 200 on peak days.
Work completed: 
North and south fuel farm underground tank installation 
Cleanup of contaminated soils in QTA #1 
North helix footing 
Work in progress: 
QTA #1, 3 and 4 footing and QTA #1 and 2 columns 
QTA #3 & 4 wall and civil work nearly complete 
First level underground utilities, foundations, slabs-on-grade, and columns 50% complete.
2nd and 3rd Level deck installation 
South helix formwork for footings 
Temporary erosion & sediment controls are being maintained, and oversight/maintenance has been
elevated as fall weather approaches. 
7 out of 10 remaining bid packages were advertised, and the bids were opened on October 13th.
Multiple bids were received on 3 packages, and single bids on three more, with all six apparent low
bidders pricing work below the engineer's estimate. One package did not receive any bids, and will
have to be re-bid. Turner is evaluating the bids, and will provide recommendation for award, as
appropriate. The engineers estimated costs for these bid packages are tracked as pending changes
under the Anticipated allowance and Conforming Design Development, in addition to the amounts to
be covered by current bid saving within the MACC. 
Contractor Schedule: 
Contractor's suspension mitigation schedule has been accepted by the Port, with the new substantial
completion date of November 15, 2011. Current schedule update shows a 15 days project delay due
to the contaminated soils issue. The Port continues to direct selective overtime work and work with
our GC/CM on re-sequencing of some critical activities. 
Cost Status Summary: 
See Status Summary Table in PowerPoint Supplement page 3: 
Risk Reserve  8 approvals issued, and 3 pending. 
2% MACC (Maximum Allowable Construction Costs) Contingency  8 Change Orders executed and
3 pending, which includes estimate for conforming design development allowance reallocation.
Negotiated Support Services  34 approvals issued, and one pending. 
Conforming Design Development Allowance 24 Change Orders executed, and 3 pending, which
includes estimate for conforming Electrical scope, Ornamental Metal sub-bid and MACC
contingency reallocation.
Anticipated Scope Allowance  3 Change Orders executed, and 10 pending, which includes estimate
for remaining sub-bid packages to be bid.
Page 1 of 4

Non-Suspension Related Contract Changes  76 Change Orders executed, and 87 pending. This
construction contingency bucket is trended to be consumed by the known cost issues. However, the
other cost buckets will have unspent funding (due to favorable bids, lower suspension related costs
and allowances not used) that will be available. 
Suspension Related Contract Changes  15 Change Orders executed, and 29 pending. Navigant audit
of selected contractors' costs nearly complete. Authorized funding is projected to have dollars
remaining. 
Design: 
Awaiting comments from other agencies, which is delaying start of 100% design and authorization
for construction for the Off-Site Roadway Improvement project. 
Coordinating with Qwest and Puget Sound Energy for advance utility relocations in support of the
Off-Site Roadway Improvement project. 
60% design of the CNG Fueling Facility complete and under review. Resolving 100% design review
comments for the Bus Maintenance Facility project anticipated to be complete November 3, 2009. 
Processed payment of $275,000 for some after-the-fact design services claims. Evaluating remaining
claims. 
Issued 21 Design Change Notices (DCN's) to date. Currently there are an additional 15 design
changes in process to be consolidated into future DCN's. 
Team Building effort nearing completion. 
Developing a plan to avoid overloading Design Team resources while accommodating to the greatest
extent possible Turner's needs for submittals, RFI's, DCN's and Change Orders. 
Industry: 
Continue working with the Industry's Technical Representative reviewing the details of the
authorized $32 million budget increase. 
Commission authorized extending the existing RAC lease till opening of the new RCF. 
Program Schedule 
RCF estimated to be complete by the end of 2011. 
Bus Maintenance Facility completion is still estimated to be March 31, 2012. 
Off-Site Roadway Improvements completion is still estimated to be December 2011 with signage
extending into early 2012 to coincide with the RCF opening. 
Program Cost Forecast and Budget 
The projected program budget is $419,306,000 and breakdown by project and expenditures is shown
on the attached slide 4. 
The current Turner contract value including all change orders is shown on the attached table slide 3. 
The updated CFC actual collections and projections is show on the attached slide 5. 
The Off-Site Roadways Improvements remains within budget based on 90% cost estimate. 
The Bus Maintenance Facility remains within budget based on 90% cost estimate. 
Risk Factors 
Finalizing the revised Program Schedule. 

Page 2 of 4

ORI schedule delayed awaiting 90% design review comments from outside agencies and the change
in WSDOT's team members. Construction agreements delayed, but required prior to award of ORI
contract. 
Coordinating with Utility Companies for major relocations for both BMF and ORI projects, which
require a number of agreements. 
Getting into wet season and its potential impacts to construction progress and productivity. 
Upcoming Commission Actions 
Authorize Bus Procurement  October 27, 2009 
Authorize Off-Site Roadway Improvements Construction  December 15, 2009 
Execute WSDOT Agreements supporting Off-Site Roadway Improvements  February 2010 
Execute Utility Agreements supporting Off-Site Roadway Improvements  February 2010 
Execute Concession Agreement  February 2010 
Authorize Bus Maintenance Facility Construction  February 2010 
Execute Utility Agreements in support of the Bus Maintenance Facility  February 2010 
Authorize Main Terminal Improvements Construction  September 2010 












Page 3 of 4

Page 4 of 4

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.