Item 6a Memo

PORT OF SEATTLE 
MEMORANDUM 
COMMISSION AGENDA             Item No.      6a 
Date of Meeting   September 17, 2009 
DATE:    September 8, 2009 
TO:      Tay Yoshitani, Chief Executive Officer 
FROM:    Ralph Graves, Managing Director, Capital Development 
SUBJECT:  Change Order 0094 for the Consolidated Rental Car Facility Project Contract
MC-0315405 
ACTION REQUESTED:
Request authorization for the Chief Executive Officer to issue Change Order Number 094 for the
Consolidated Rental Car Facility (RCF) in the amount of $900,000. 
SYNOPSIS:
Both unsuitable and contaminated soil was discovered during excavation on the RCF project.
Previous change orders (COs) were issued to address handling and disposal of contaminated
soils (CO #001, 003, 005 and 006 for a total not-to-exceed cost of $1,491,219) and of unsuitable
soils (CO #004 for a total not-to-exceed cost of $195,465). On August 25, 2009 the Commission
authorized Change Order (CO) 077 for $400,000 to handle removal and replacement of
unsuitable soil due to additional unsuitable soils discovered during QTA1 and North Helix
excavation. The estimate used to develop these costs was based on the assumption that a
maximum of 5 feet of overexcavation at QTA1 and 2 feet of overexcavation at the remaining
footings would be required to get to structurally sound soil that would support the building loads.
As excavation continued, the underlying soils were discovered to be in worse condition than that
evident from investigating potholes and excavations at adjacent areas. In areas at QTA1
unsuitable soil was excavated to a depth of 8 feet along with areas of petroleum contaminates
and excavated up to 10 feet at the North Helix footing. The newly discovered unsuitable and
contaminated soil observed in these areas contains oil contaminates, tree stumps and other
organic debris. This is in addition to the residential tanks, abandoned pipe and metal conduit 
previously uncovered. The Port has directed additional potholing to provide more information to
further map the extent of the buried debris.
Based on the significantly higher quantity of unsuitable and contaminated soils encountered
within the past few weeks, the existing change orders will shortly be expended. This new CO
#094 must be issued to address the additional overexcavation/disposal of
unsuitable/contaminated soils and selected backfill with imported structural fill. The work at
QTA#1 is on the critical path. Delays from unsuitable/contaminated soil excavation/removal
have impacted and continue to impact the construction schedule. The Port has directed the

COMMISSION AGENDA 
T. Yoshitani, Chief Executive Officer 
September 11, 2009September 11, 2009September 10, 2009 
Page 2 of 3 

contractor to work overtime on selective construction activities to accelerate the critical path
work and help mitigate the schedule impact and associated costs. This Change Order includes
the direct costs of the unsuitable/contaminated soil issue along with selective Port directed
overtime and a 10% contingency. A separate CO may be necessary to address any time impacts
or indirect costs that cannot be fully mitigated.
CHANGE ORDER DESCRIPTION AND JUSTIFICATION: 
The following information relates to the pending change order scope and cost: 
Change Order No. 094 
Scope of work: Remove soil identified by the Geotechnical Engineer as unsuitable 
underlying soil for the new construction and dispose of in accordance with state
regulatory requirements. Also remove soil identified to be contaminated with petroleum 
products. Replace the excavated unsuitable and contaminated soil materials with new 
native and imported structural fill. Work to be performed on a force account (time and
materials) basis. Selective overtime as directed by the Resident Engineer of critical path 
work to mitigate schedule impact. Selective potholing as directed by the Resident
Engineer. 
Justification: The existing soils under slabs and footings must be suitable to carry and
transfer the building loads. Existing site soil has been identified by the Geotechnical
Engineer of record as being unable to meet the structural requirements and must be
removed and replaced with materials that will need the structural requirements. Types of
unsuitable soils being discovered on the site include soft soils, tree stumps, organic
debris, residential tanks, buried trash and existing construction debris. The soil material
in the excavation which contains petroleum contamination must also be properly
disposed of offsite.
Consequences of not proceeding: Proceeding with construction over unsuitable soil
would result in unacceptable settlement of footings and cracks in slabs on grade and
could result in structural failure. The contaminated soil must be properly disposed of
offsite to meet our regulatory requirements. 
FINANCIAL ANALYSIS: 
Funds to pay for this change order are part of the project contingency funds that were included in
previously approved authorizations of $419,306,000.00. No additional project funds are being
requested as a result of this change order.
CONTRACT INFORMATION:  The following information relates to the contract and
competitive award: 
Contract award date:                             May 30, 2008 
Original period of performance:           May 30, 2008 to April 1, 2011

COMMISSION AGENDA 
T. Yoshitani, Chief Executive Officer 
September 11, 2009September 11, 2009September 10, 2009 
Page 3 of 3 

Previous contract extensions:                             0 Days 
Contract extension this change order:                        0 Days 
Current Contract Completion Date:                    April 1, 2011 
Original contract amount:                       $224,837,739.00 
Previous Change Order Nos. 001  093:                $3,398,794.00 
Current contract amount                         $228,236,533.00 
This request, Change Order No. 094                    $900,000.00 
Revised contract amount:                       $229,136,533.00

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.