Item 7a Report

Item Number:  7_a Report
Meeting Date: June 9, 2009


Commission Staff Brieng
Capital Improvement Projects
First Quarter Report
2009

This page intentionally left blank









ii  Port of Seattle 1Q 2009 Report

Port of Seattle
Capital Improvement Project Report
First Quarter 2009
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an
economic engine for the Puget Sound region and the State. A primary activity of the Port is to create capital
assets that allow the efficient flow of goods and people into and out of the area. The intent of this report is to
provide the public with high level information on the status of the Port's capital projects.
Background
During 2008 the Port plans to invest over $700 million to expand and upgrade the infrastructure that supports
marine and aviation commerce. Funding for the Port comes mainly from the users of its facilities, including
shipping companies, airlines, rental car companies, concessionaires and public parking. About 11 percent of
the Port's capital budget comes from a tax levy on property in King County. The Tax levy funds are used
selectively for investments in maritime transportation facilities and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its
business partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule,
budget, change orders, risks, and budget transfers. The report may include graphics that report project costs
compared to authorization, construction costs (including change orders) compared to the construction contract,
location maps, and photographs. The Port implements a number of different types of projects and not all
information may be relevant to a specific project; as such the reports may vary in detail and content. Project
types may range from construction, to noise mitigation, to technology.
The project description includes the project title, project number [Capital Improvement Project (CIP)], project
phase, and estimated completion date (beneficial occupancy). This section also includes a "Status Snapshot"
illustrating at a glance if the project is on schedule, within budget, the total number of change orders to date, and
the total value of executed change orders.
x   Significant Developments covers items such as accomplishments, significant events or milestones,
contract advertisements and awards, upcoming activities, and environmental issues.
x   Schedule includes information on the project schedule, the total schedule variance and variance
since the last report, contract extensions, and information on critical dates.
x   Budget addresses the total project budget and includes things like overall budget status, recent
Commission authorizations, forecasted overruns or savings, and scope changes.
x   Change Orders provides a description of change orders for the reporting period and information on
any change orders over $200,000 or 10% of the contract value.
x   Risks describes any significant risk of delay, any significant risk to cost, or any significant change order.
x   Budget Transfers reports any transfers of more than $200,000 between authorized projects during
the reporting period.
Additional information may include graphics indicating budget, construction costs, location, and photographs.
These reports are intended to meet the reporting requirements of Port of Seattle Commission Resolution 3605
and the Commission motion on January 8, 2008 regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page and select the Audit/Accountability button. Use the
form to ask a question, make a comment or request a copy of the State Audit Reports Response and Action
Plan.
Port of Seattle 1Q 2009 Report  1

Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000683 et al .......3rd Runway Program .............................................5 ...........zz 
C100266 et al .......Rental Car Facility .................................................6 ...........zz ...............9
C100285 ...............Communication Systems Implementation .............7 ...........zz ............... ...................9
C100451 ...............Industrial Waste System Upgrade .........................8 ...........zz ...............9
C101113 ................Stormwater Management Program .......................9 ...........zz
C102003 ...............STEP Security Baggage & Checkpoints ..............10 ..........zz ........................................9
C102038 ...............Apron Pavement Rehabilitation 3 .......................11 ..........zz
C102163................Main Terminal Baggage Screening ......................12 ..........zz ...............9
C102164................Parking Tunnel Planning and Design ...................13 ..........zz
C102461................Concessions Implementation ...............................14 ..........zz ...............9....................9
C102584 ...............Garage Floor Count ..............................................15 ..........zz ...............
C102744................2nd Floor Tenant Improvements ...........................16 ..........zz ...............
C800019 ...............Loading Bridge Utilities .........................................17 ..........zz ...............
C800020 ...............Trash Handling & Recycling System ....................18 ..........zz
C800031 ...............Ramp/North Cargo Lighting Retrot .....................19 ..........zz ...............
C800034 ...............North Expressway Relocation ..............................20 ..........zz ...............
C800036 ...............Parking Garage 4th Floor Improvements .............21 ..........zz
C800042 ...............Aircraft Rescue Fire Fighting Station Upgrade ....22 ..........zz ...............
C800061 ...............Main Terminal South Sub Low Volt ......................23 ..........zz ...............9
C800071 ...............Consolidated Warehouse .....................................24 ..........zz
C800095 ...............Alaska Air 2 Step Ticket Counter..........................25 ..........zz ...............9
C800105 ...............Airport Owned Gate Infrastructure .......................26 ..........zz ...............9
C800107 ...............C4 UPS System Improvements ............................27 ..........zz ...............
C800109 ...............Garage Escalator & "A" Elevator Upgrade ...........28 ..........zz
C800111 ................Main Terminal Roof Replacement ........................29 ..........zz ........................................
C800112................Runway 16C/34C Panel/Joint Sealant .................30 ..........zz
C800144 ...............Security CCTV System Improvements.................31 ..........zz ...............
C800146 ...............RMU/Kiosk Concession Program ........................32 ..........zz ...............
C800147 ...............Concessions Renewal/Replacement ...................33 ..........zz ...............9
C800148 ...............GML Arrivals Hall Concessions ...........................34 ..........zz ...............
C800157 ...............Concessions Flooring ...........................................35 ..........zz ...............
C800167 ...............Runway 16L/34R Reconstruction.........................36 ..........zz
C800237 ...............Renew/Replace 42 Escalators .............................37 ..........zz ...............9
C800238 ...............Central Plant Pre-Conditioned Air ........................38 ..........zz ...............
C800239 ...............Fire Piping .............................................................39 ..........zz
C800249 ...............2nd Floor HVAC ....................................................40 ..........zz ...............9....................9
C800254 ...............Aircraft RON Parking Post Ofce Site..................41 ..........zz
C800286 ...............South AOA Fence Replacement ..........................42 ..........zz

2  Port of Seattle 1Q 2009 Report

Other Aviation
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C001338 ...............Fire Vehicles .........................................................43 ..........zz
C101110 ................Rental Car Facility Property Acquisition ...............44 ..........zz
C102936 ...............Fire Vehicles .........................................................45 ..........zz
C200007...............Highline School Noise Insulation ..........................46 ..........zz ...............9
C200015 ...............3rd Runway Residential Acquisition .....................47 ..........zz
C200037 ...............FAR Part 150 Mobile Home Park Acquisition ......48 ..........zz ........................................9
C200042 ...............Highline Community College Noise Insulation .....49 ..........zz ...............9
C200048 ...............Home Insulation Retrot .......................................50 ..........zz ...............9
C200093 ...............Single Family Home Sound Insulation .................51 ..........zz
C800046 ...............Street Vacations  Des Moines Creek 1 ..............52 ..........zz ........................................9
C800150 ...............Burien Commercial Property Acquisition .............53 ..........zz
C800154 ...............Tenant Reimbursement ........................................54 ..........zz
Seaport
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C000579 ...............Alaskan Way St Vacation and Public Access ......55 ..........zz ...............9
C102451 ................T115 Dock Reconstruction....................................56 ..........zz ...............9 ....................9
C103586 ...............C36 Surplus ..........................................................57 ..........zz ...............9
C800064 ...............T25/30 Improvements 2005-2007 ........................58 ..........zz ...............9
C800085 ...............T30/T91 Program ..............................................59-60 .......zz ...............9 ....................9
C800089 ...............T91 Berth M Replacement....................................61 ..........zz ...............9
C800113................T86 Grain Spout Repair........................................62 ..........zz ...............9
C800114................P66 Bag. Corridor & Pass. Screening ..................63 ..........zz
C800121 ...............T18 South Fender Improvements .........................64 ..........zz
C800123 ...............T5 Crane Spreader Replacement ........................65 ..........zz ...............9
C800259 ...............T25 South Redevelopment ...................................66 ..........zz ...............9
C800264 ...............T10 Interim Redevelopment..................................67 ..........zz ...............
C800265 ...............T91 City Ice Bldg. W-40 Demo.............................68 ..........zz ...............9.....................
C800273 ...............T91 Mobile Gangways ..........................................69 ..........zz
WP Number  Project Title           Page
E102007 ................East Marginal Way Grade Separation ..................70 ..........zz ............... ....................9
E103705 et al ........T46 ZPMC Gearboxes ..........................................71 ..........zz
E103835 et al ........T5/T18 Maintenance Dredging .............................72 ..........zz ...............9................... 
E104011 et al ........T25/P28/T46 Barge Layberth Improvements .......73 ..........zz
E10466 .................Radio Frequency Indentication (RFID) ...............74 ..........zz

Port of Seattle 1Q 2009 Report  3

Real Estate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C001706 et al........SBM Renewal and Replacement .........................75 ..........zz ...............9
C800006...............Central Waterfront Utility Upgrade .......................76 ..........zz ...............9
C800070 ...............T102 HVAC Renewal/Replacement .....................77 ..........zz ...............9
C800125 ...............C15 Sewer Line Upgrades ....................................78 ..........zz ...............9
Corporate
Overall Project Variance since
Status     last report
CIP Number  Project Title             Page     Schedule  Budget
C800003...............Maximo Enterprise Implementation......................79 ..........zz ...............9
C800010 ...............IP Telephony .........................................................80 ..........zz ...............
C800015 ..............Public Safety CAD ................................................81 ..........zz ...............
C800066 ...............Parking System Consolidation .............................82 ..........zz
C800096 ...............Human Resources Management System ............83 ..........zz ............... .................. 
C800118................Area Surveillance .................................................84 ..........zz ...............9
C800119................Marine Domain Awareness ..................................85 ..........zz
C800172 ...............Airport Operations Dashboard .............................86 ..........zz ...............9
C800223 ...............UltraCUSE Implementation ..................................87 ..........zz
C800319 ...............Internet Redesign .................................................88 ..........zz ...............
C800320 ...............External Sharepoint ..............................................89 ..........zz
Key Project Status
zz Project within or ahead of target budget and schedule
zz Either target schedule or budget are off
zz Both target schedule & budget are off
Variance Status
Over Budget or Delayed Schedule
Under Budget or Ahead of Schedule
Potential Over Budget or Delayed Schedule
9 Previously Reported
No Diamond  On Budget or On Schedule




4  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
3rd Runway Program
Project:   C000683,      The 3rd Runway Program will      Status Snapshot
C001138, C001175,      construct a new 8,500 foot long    On Schedule
C001331, C001751,      dependent runway, connecting    On Budget
C001760, C100172      taxiways, and related infrastructure.  66 Change Orders
Budget: $979,483,541    When complete the 3rd Runway   Total Change Orders Amount:
will significantly reduce weather-     $2,928,224.37
Phase: Construction
related delays.
Start: 05/27/1997
Completion: 12/31/2011                       Budget/Costs Incurred
1200
Significant Developments                     1000
800
A construction contract to construct permanent stormwater facilities,    600
demolish the Lora Lake Apartments and complete the Des Moines
400
200
Nursery environmental mitigation is currently in final design and is      Dollars [Millions] 0
scheduled for Commission authorization to advertise and award on       Authorized Forecasted  Costs
incurred
April 21st, 2009.
Schedule                           Construction Costs
The current construction contract for the paving of the runway and     $90
taxiway and construction of related infrastructure, expansion of        $80
$70
Runway 16C Safety Area and construction of a new Airfield Lighting
$60
Facility will begin contract closeout after punch list items are
completed.
The 2009 construction contract is scheduled to advertise in early
May. Construction to be completed by November 2009.          Dollars [Millions]$50$40$30$20$10
$0
Initial Change Orders Spent
Budget
Reduced budget by $63,000,000 to the current budget of
$979,483,541. To date, $634,000,000 of construction has been     Photo
completed on the overall program.
Change Order
Fourteen change orders for a total of $374,595 have been executed
during this period. None involved extension of the contract time.
Risks
No significant risks are identified at this time.
Budget Transfers
None
AIRPORT
Port of Seattle 1Q 2009 Report  5

FIRST QUARTER REPORT, 2009
Rental Car Facility
Project:   C100266,      The program will construct a      Status Snapshot Prior Report
C100444, C101610,      consolidated rental car facility     Delayed Schedule 4Q 08
C102167, C800032,      (RCF) for all rental car companies   On Budget
C800163           at the airport, a bus maintenance   37 Change Orders
Budget: $412,320,000    facility (BMF), and mitigation with   Total Change Orders Amount:
the off-site roadway improvements   $3,987,961
Phase: Construction
(ORI) , plus purchase a fleet of
Start: 02/24/1998         buses.
Completion: Unknown                       Budget/Costs Incurred
500
Significant Developments
400
RCF construction remains suspended except for authorized work to prepare the
site for up to a years suspension, which is approximately 50% complete.
Dollars [Millions] 300
Excavation, most retaining walls, the storm detention vault and building footings
and columns in progress are complete. Work on underground utilities, site           200
drainage and erosion control continue. The 90% design is underway for both the
100
BMF and ORI. The ORI work is being coordinated with WSDOT construction
planned for the same area.                                         0
Authorized    Forecasted   Costs incurred
Schedule
RCF construction is suspended for up to one year. Program completion is        Construction Costs
unknown. BMF design schedule delayed with the addition of CNG fueling facility.
250
Budget                             200
Customer Finance Charge (CFC) funding receipts continue to run lower than
150
planned due to the economy. With suspension, current program budget is no
longer attainable. Additional budget required for Compressed Natural Gas (CNG)     Dollars [Millions] 100
fueling facility at BMF. ORI remains on budget.
50
Change Order                           0
Initial     Change Orders     Spent
Fourteen change orders in the amount of $159,830 were executed to the 3
contracts this quarter.
Risks
Financial market ability to bond. Claims due to suspension could get significant the
longer the suspension is in place. Decision to incorporate a CNG fueling facility     Photo
within the BMF will increase costs and delay schedule. ORI design delay loses
2009 construction season impacting RCF opening until fall 2011. Length of
suspension may postpone this date.
Budget Transfers
None.
AIRPORT
6  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Communication Systems Implementation
Project:   C100285      The program to modernize existing  Status Snapshot Prior Report
Budget: $68,178,575     systems and introduce state-of-the-  Delayed Schedule
Phase: Close Out      art technology to the Airport was   Under Budget   4Q 08
Start: 12/14/1999         accomplished through a suite of    No Change Orders
Completion: 03/31/2009   interrelated communications      Total Change Orders Amount:
projects.                     N/A
Significant Developments                    Budget/Costs Incurred
The project is complete and in the close out phase. This will be the
last quarterly report for this project.
Schedule
The project is complete.
Budget
The project is anticipating a savings of approximately $795,000.
Change Order
None.                                    Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT
Port of Seattle 1Q 2009 Report  7

FIRST QUARTER REPORT, 2009
Industrial Waste System Upgrade
Project:   C100451      The Industrial Wastewater System   Status Snapshot
Budget: $12,012,185     (IWS) collects and treats storm    On Schedule
Phase: Design        water that could be contaminated   On Budget
Start: 09/12/2000         by fuel, solvents or deicing        No Change Orders
Completion: 10/01/2009   chemicals. The project upgrades   Total Change Orders Amount:
the IWS to meet or exceed all      N/A
environmental permit standards.
Significant                                Budget/Costs Incurred
Developments
The final component of this project is construction and installation of
a manhole at the southwest corner of Runway 16C.
Schedule
The current schedule is to complete installation in October 2009. If
the project is delayed, the completion date will be October 2010.
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         No active contracts at this
None this quarter.                                    time.
Risks
There is a risk of delaying this project for one year if there is a lot of
rain this summer.
Budget Transfers
None this quarter.



AIRPORT
8  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
STEP Security Baggage & Checkpoints
Project:   C102003      This project created automated     Status Snapshot
Budget: $108,784,460    systems for explosive detection    On Schedule
Phase: Close Out      screening of baggage for the south  On Budget 3Q 08
Start: 05/14/2002         half of the Main Terminal. The     168 Change Orders
Completion: 03/08/2007   systems meet all security       Total Change Orders Amount:
requirements, while reducing       $19,579,510
staffing requirements.
Significant                                Budget/Costs Incurred
Developments
The main project is complete and in the process of close out. The
only remaining active work project for this program is ongoing
monitoring, and making adjustments to improve system
performance.
Schedule
Project is complete.
Budget
Project was delivered under budget.                       Construction Costs
Change Order
The final settlement change orders were issued in the amount of
$ 11,065,020 (excluding taxes).
Risks
The TSA denied reimbursement for the G&T final settlement. The
Port of Seattle is appealing this decision. The TSA reimbursement
amount is approximately $10.3 million.
Budget Transfers
None this quarter.


AIRPORT

Port of Seattle 1Q 2009 Report  9

FIRST QUARTER REPORT, 2009
Stormwater Management Program
Project:   C102030,      The program achieves permit      Status Snapshot
C800026, C800030      requirements and makes the     On Schedule
Budget: $62,488,249     Airport a leader in stormwater     On Budget
Phase: Construction     management by construction of    No Change Orders
Start: 06/11/2002         flow control, water quality treatment  Total Change Orders Amount:
and low stream flow mitigation      N/A
Completion: 12/31/2011
facilities.
Budget/Costs Incurred
Significant Developments
The stormwater program has entered its adaptive management
phase under which additional or upgraded water quality treatment
facilities are being implemented based on the requirements of the
new upcoming stormwater NPDES permit. Four projects have been
identified to date.
Schedule
The new stormwater NPDES permit, with stricter water quality
standards became effective April 1, 2009. Adaptive management
projects will be implemented in 2009 and 2010. The stormwater     Construction Costs
pipeliner project has been deferred to 2010.                   No active construction
contract at this time.
Budget
The budget has been significantly reduced several times since
program inception in 2002 due to successful system optimization
measures. Possible additional reductions are being evaluated.
Change Order
None.
Risks
Additional adaptive management facilities may be required beyond
those currently being planed.
Budget Transfers
None this quarter.

AIRPORT

10  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Apron Pavement Rehabilitation - 3
Project:   C102038      Multiyear airfield pavement       Status Snapshot
Budget: $16,100,000     replacement program. This is a    On Schedule
Phase: Construction     continuation of a program for the   On Budget
Start: 01/14/2003         removal and replacement of aged   No Change Orders
Completion: 12/31/2009   airfield apron pavement started in   Total Change Orders Amount:
1994.                    $0.00
Significant                                Budget/Costs Incurred
Developments
18
No construction work is scheduled for 2009. Future work is currently    16
14
being scoped.
12
10
Schedule                            Dollars [Millions] 8
6
The 2008 Project, including Alaska Hangar Apron Construction and     4
2
Cargo 2/3 Taxilane Apron Replacement for $4,254,587 and was
0
completed with no change orders and is currently in contract
Authorized Forecasted  Costs
closeout.                                                         incurred
Budget
CIP C102038's Current Budget is currently at $16,100,000 with cost
Photo
to date of $13,368,000.
Change Order
None
Risks
No risks have been identified at this time.
Budget Transfers
None



AIRPORT
Port of Seattle 1Q 2009 Report  11

FIRST QUARTER REPORT, 2009
Main Terminal Baggage Screening
Project:   C102163      This project creates automated     Status Snapshot Prior Report
Budget: $230,538,762    systems for explosive detection    Delayed Schedule 4Q 08
Phase: Close Out      screening of baggage for the north  On Budget
Start: 09/24/2002         Main Terminal and South Satellite.   660 Change Orders
Completion: 02/13/2009   The systems will meet all security   Total Change Orders Amount:
requirements while reducing       $51,998,527
staffing and providing capacity for
Significant           future growth.             Budget/Costs Incurred
Developments
The C-1 baggage handling/screening system has been placed into
revenue service for the Alaska Air Group. Only minor modifications
to the system remain.
Schedule
The project was delayed approximately two years from the original
completion date due to replacement of the original baggage
subcontractor, changing TSA requirements and other scope
changes. Turner Construction will demobilize on May 31. Project
closeout continues.
Construction Costs
Budget
The project forecast is within the approved budget and authorization.
Change Order
Change orders worth $1,618,413 were issued this quarter.
Risks
Risks include recent TSA changes in certification requirements and
whether they will be imposed retroactively.
Budget Transfers                        Photo
None this quarter.

AIRPORT

12  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Parking Tunnel Planning and Design
Status Snapshot
Project:   C102164      The project is to assess, define,    On Schedule
Budget: $966,500       and design the major renewal and   On Budget
Phase: Design        replacement of key systems for the  No Change Orders
Start: 10/01/2007         parking garage components and    Total Change Orders Amount:
Completion: 4/30/2009    service tunnel to extend the life of   N/A
these assets.
Significant Developments                    Budget/Costs Incurred
The structural assessment of Service Tunnel indicates it was never
1
designed for major earthquake events. Due to structural complexity,
significant retrofit strategies are needed to preserve airport            0.8
operation. Further structural assessment is needed to determine       0.6
retrofit strategies for the entire garage. Various infrastructure
0.4
systems were assessed and reported.                      Dollars [Millions]
0.2
As one of the first projects identified, the Parking Garage 8th floor
0
water proofing system is beyond its useful life, so a new project was       Authorized  Forecasted Costs incurred
created. The expansion joints in the garage are failing. On-going
maintenance costs are increasing.                        Construction Costs
Not Applicable
Current estimated costs to rehabilitate the garage and service tunnel
to ensure their long term usefulness have increased and are now
estimated to be $30 to $50 million. That work will be done through
future projects.
Schedule
Project deliverables essentially complete.
Budget
The project forecast is within the approved budget and authorization.
Change Order
Not Applicable
Risks
None identified at this time.
Budget Transfers
None
AIRPORT
Port of Seattle 1Q 2009 Report  13

FIRST QUARTER REPORT, 2009
Concessions Implementation
Project:   C102461      This project will install utility       Status Snapshot Prior Report
Budget: $4,075,254      infrastructure to suit new       Delayed Schedule 3Q 08
Phase: Close Out      concessions usage and make base  Under Budget   4Q 08
Start: 11/11/2003         building changes to accommodate   No Change Orders
Completion: 09/30/2008   specific tenants.            Total Change Orders Amount:
N/A
Significant Developments
The project is complete. This will be the last quarterly report issued   Budget/Costs Incurred
for this project.
Schedule
Project is in close out.
Budget
The project is anticipating a savings of approximately $38,000.
Change Order
None                                 Construction Costs
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT
14  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Garage Floor Count
Project:   C102584      This project is part of the Customer  Status Snapshot
Budget: $4,087,371      Service initiative. The floor count   Delayed Schedule
Phase: Testing       system will display information to   On Budget
Start: 08/06/2007         assist parking customers in finding   No Change Orders
Completion: 05/30/2009   parking spaces, especially at times  Total Change Orders Amount:
when the garage is near capacity.   N/A
Significant Developments                    Budget/Costs Incurred
The overall project was deployed on May 20, 2008. Upgrades        5.0
consisting of additional cameras, camera relocations and software
4.0
adjustments have been made to the deployed system and are
currently being calibrated.                                  3.0
Schedule                             Dollars [Millions] 2.0
1.0
Due to weather related delays, completion of the 8th Floor section
camera installation has been delayed until May 2009.              0.0
Authorized    Forecasted   Costs incurred
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
Not Applicable
Change Order
Not Applicable
Photo
Risks
Port Information and Communication Technology (ICT) Department
continues to improve the accuracy of the count system on floors 5, 6,
7 and 8.
Budget Transfers
None



AIRPORT

Port of Seattle 1Q 2009 Report  15

FIRST QUARTER REPORT, 2009
2nd Floor Tenant Improvements
Project:   C102744      Construct a shell space for new    Status Snapshot
Budget: $377,864       tenant offices. Provide utility     Delayed Schedule
Phase: Construction     pathways to the shell space and   On Budget
Start: 08/22/2006         make code improvements to       No Change Orders
Completion: (See       adjacent lobby and corridors.     Total Change Orders Amount:
N/A
C800249)
Significant Developments                    Budget/Costs Incurred
Project construction activities are substantially complete except for
one project element, which is awaiting completion of tenant office
build out and relocation of current tenant offices, which will be
completed after project C800249, 2nd Floor HVAC Upgrades.
Schedule
The remaining work is scheduled for late 2009.
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
Not Applicable
None.
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT

16  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Loading Bridge Utilities
Project:   C800019      This project will upgrade all Port-    Status Snapshot
Budget: $9,385,000      owned loading bridges to the same  Delayed Schedule
Phase: Design        standards, including 400Hz power  On Budget
Start: 06/28/2007         and potable water. It will reduce air  No Change Orders
Completion: On-Hold    emissions, improve energy      Total Change Orders Amount:
efficiency and save money for the    $0
airlines.
Significant                                Budget/Costs Incurred
Developments
The 100% design package is complete. The package was submitted
to the Airport Building Department for review, and a permit was
granted. The Port of Seattle was in negotiation for purchase of the
400Hz equipment from Northwest Airlines in the South Satellite. The
negotation has been put on-hold. Pre-purchase packages for the
400HZ equipment and the Potable Water Cabinets were started.
Further development is on-hold.
Schedule
The current schedule is on-hold until bond funding is obtained.
Construction Costs
Not Applicable
Budget
The project forecast is within the approved budget and authorization.
Change Order
None.
Risks
The project budget may increase due to the delay in the construction
of the project.
Budget Transfers
None this quarter.


AIRPORT

Port of Seattle 1Q 2009 Report  17

FIRST QUARTER REPORT, 2009
Trash Handling & Recycling System
Project:   C800020      To improve trash handling and     Status Snapshot
Budget: $1,612,000      recycling operations and to meet   On Schedule
Phase: Design        future trash volume demands;     On Budget
Start: 04/22/2008         decentralize tenant trash disposal   No Change Orders
Completion: 07/09/2010   and recycling; and centralize airline  Total Change Orders Amount:
trash disposal and recycling.       N/A
Significant Developments                    Budget/Costs Incurred
The design phase is complete and 100% bid-ready documents have
been issued. The project received Commission authorization of
construction funding and authority to advertise for construction.
Schedule
The bid process is delayed for approximately three weeks to allow
the incorporation of a sixth compactor site. The Port will advertise
for bids in late May 2009. The final completion date has not been
delayed.
Budget
Construction Costs
The project forecast is within the approved budget.
Change Order
None.
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT

18  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Ramp/North Cargo Lighting Retrofit
Project:   C800031      The project will increase         Status Snapshot
Budget: $1,915,000      illumination levels in the ramp     Delayed Schedule
Phase: Construction     areas around the North and South  Under Budget
Start: 6/27/2006          Satellites and Concourses B, C,    2 Change Orders
Completion: 05/31/2009   and D by replacing the existing    Total Change Orders Amount:
systems that are, in some cases,    $10,968
over 30 years old. Added lighting to
Significant           Gates A14 and C16.          Budget/Costs Incurred
Developments
Substantial completion has been achieved for ramp lighting at
Concourses B, C, D, and the North and South Satellite. One
additional light pole and fixture is required at Concourse A.
Schedule
Estimated completion of new light pole and fixture installation at Gate
A14 is May 2009.
Budget
The project forecast is within the approved budget and authorization.  Construction Costs
The project is anticipating a savings of approximately $70,000.
Change Order
None.
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 1Q 2009 Report  19

FIRST QUARTER REPORT, 2009
North Expressway Relocation
Project:   C800034
The project is a collaboration      Status Snapshot
Budget: $122,920,700    between the Port and Sound     Delayed Schedule
Phase: Construction     Transit. It will reconstruct the North  On Budget
Start: 07/27/2004         Airport Expressway and bring light   152 Change Orders
Completion: 10/30/2010   rail to the Airport.           Total Change Orders Amount:
$9,300,934
Significant Developments
Budget/Costs Incurred
The bulk of the work in the large contract is complete, with only
140.0
punch list work remaining.
120.0
The intelligent transportation management system is being
100.0
implemented by Port staff and a consultant.
80.0
Future contracts will do final reclamation and landscaping and make    Dollars [Millions] 60.0
other improvements.
40.0
A contract to restore traffic flows at the Doug Fox Parking Site is
20.0
underway.
0.0
Design is underway for the final paving, landscaping and reclamation       Authorized  Forecasted Costs incurred
contract.
Construction Costs
Schedule
120
The main contract received substantial completion in August 2009
and punch list work is in progress. Advertisement of the remaining      100
contract is planned for fall 2009. All construction planned to be         80
complete in the fall of 2010.                                 Dollars [Millions] 60
Budget                             40
The main contract for $93,448,650 is being managed by the Port,       20
with the cost shared between the Port of Seattle and Sound Transit
0
at approximately 56% and 44%.                             Initial  Change Orders  Spent
Change Order                         Photo
Twenty-five change orders were issued this quarter in the amount of
$438,458.
Risks
A subcontractor has requested and submitted claims for additional
reimbursement. The dispute resolution process is in progress for
two items.
Budget Transfers
None
AIRPORT
20  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Parking Garage 4th Floor Improvements
Project:   C800036
The project includes the design and  Status Snapshot
Budget: $8,991,000      construction of a pedestrian bridge  On Schedule
Phase: Construction     and a walkway from Sound      On Budget
Start: 02/14/2006         Transit's Airport Station to the      No Change Orders
Completion: 12/31/2009   Terminal.               Total Change Orders Amount:
N/A
Significant Developments
Budget/Costs Incurred
The project has been planned to be delivered in two contracts; the
10
pedestrian bridge between the Airport Station and the Parking         9
Garage and a walkway on the 4th floor of the garage between the       8
7
pedestrian bridge and northern most sky bridge to the main terminal.
6
The pedestrian bridge work has begun with drilled shaft foundations    Dollars [Millions] 5
4
installation in progress. Design of the walkway project is proceeding
3
toward a 90% design. Various delivery options are being considered    2
for the walkway in order to complete essential portions by the end of     1
0
2009.                                           Authorized  Forecasted Costs incurred
Schedule
The pedestrian bridge contract is currently in under construction with  Construction Costs
substantial completion planned for December 2009. The walkway
3
contract will likely advertise in the summer of 2009 with substantial
completion planned for the end of 2009.                       2.5
2
Budget
1.5
Authorization of the construction funding for the 4th floor garage        Dollars [Millions] 1
walkway will be requested in the second quarter.
0.5
Change Order
0
Initial    Change Orders    Spent
None
Risks
The delivery of the walkway with a desired level of finish will likely
require modification to the delivery approach. Options are currenlty
being evaluated.
Budget Transfers
None
AIRPORT

Port of Seattle 1Q 2009 Report  21

FIRST QUARTER REPORT, 2009
Aircraft Rescue & Fire Fighting Station Upgrade
Project:   C800042      Upgrade the Sea-Tac International   Status Snapshot
Budget: $5,000,000      Airport Aircraft Rescue & Fire     Delayed Schedule
Phase: Design        Fighting (ARFF) station to meet    On Budget
Start: 06/13/2006         current Airport needs and comply    No Change Orders
Completion: 01/31/2010   with current safety codes.       Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
This project was awarded in February 2009 and the contractor is due
to receive their Notice to Proceed in April 2009.
Schedule
Due to budget uncertainties, the bid award was delayed until
February 2009. The delayed award led to delayed design
amendment approval for construction support services. This
resulted in longer than anticipated Request for Information (RFI) and
submittal responses durations. This may ultimately impact the
project's final completion date, but the impact is not yet known.
Anticipated construction completion is now January 2010.
Construction Costs
Budget
The project forecast is within the approved budget and authorization.
Change Order
None.
Risks
Delays in awarding the contract may result in increased project
costs.
Budget Transfers
None this quarter.
AIRPORT


22  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Main Terminal South Sub Low Voltage
Project:   C800061      This project covers the renewal and  Status Snapshot Prior Report
Budget: $1,925,000      replacement of low voltage (600    Delayed Schedule 1Q 08
Phase: Design        volts and below) electrical       On Budget
Start: 06/28/2007         distribution equipment in the       No Change Orders
Completion: On-Hold    southern part of the Main Terminal.  Total Change Orders Amount:
NA
Significant Developments                    Budget/Costs Incurred
The design phase is complete and 100% bid-ready documents have
been submitted to the Airport Building Department to be reviewed for
building permit. The scope of work was reduced to stay within the
authorized budget.
Schedule
The project is on-hold until funding is available.
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
Not Applicable
None.
Risks
In order to reduce RMM abatement impacts to the project schedule,
the RMM contractor will be required to add additional crews to
complete work in a timely manner. It is not known when the
construction will proceed. There may be an impact on project costs
due to changes in market conditions at that time.
Budget Transfers
None this quarter.


AIRPORT
Port of Seattle 1Q 2009 Report  23

FIRST QUARTER REPORT, 2009
Consolidated Warehouse
Project:   C800071      This project will construct a 50,000   Status Snapshot
Budget: $9,000,000      square foot warehouse for storage  On Schedule
Phase: Construction     and inventory management of     On Budget
Start: 06/27/2006         spare parts for the Aviation        3 Change Orders
Completion: 03/31/2010   Maintenance Department.       Total Change Orders Amount:
$53,613.00
Significant Developments                    Budget/Costs Incurred
Panattoni Construction has removed the preload, installed all
foundations and underfloor slab utilities, installed and tested the fire
loop, and is preparing to pour the concrete slab. Grading is
complete on the roadways and parking areas.
Schedule
Project is on schedule.
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
Change orders have been approved for preload monitoring, water
and sewer permit requirements, and footing revisions required due to
debris in the fill. Construction bulletins have been issued for roofing
that will provide a better life cycle cost, mezzanine construction, and
purchase and installation of structural storage racks.
Risks
None identified at this time.
Budget Transfers
None this quarter.
Photo


AIRPORT
24  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Alaska Air 2-Step Ticket Counter
Project:   C800095      This project provides Port of      Status Snapshot Prior Report
Budget: $10,707,000     Seattle support for Alaska Airlines'  Delayed Schedule 1Q 08
Phase: Construction     2-step ticket counter projects (the   On Budget
Start: 04/11/2006         "Airport of the Future"). The work   No Change Orders
Completion: (See       includes: asbestos abatement;    Total Change Orders Amount:
concessions relocations; and      N/A
C102163)
related building modifications.
Budget/Costs Incurred
Significant Developments
The Port work to support of the opening of Alaska ticket pod 5 is
complete. This is the last facility to be activated.
Schedule
This project supports major tenant projects and is linked to the C-1
baggage system project. Delays in those projects have resulted in
delays to substantial completion of this work. Alaska Airlines placed
Pod 5 into operation in November 2008.
Budget
Construction Costs
The project will incur additional costs over the current budget for Port  Not Applicable
performed tasks which will be reimbursed by Alaska Airlines. After
reimbursement, the anticipated forecast is within the approved
budget and authorization.
Change Order
Not Applicable.
Risks
The combined work between the Port and Alaska Airlines is
dependent on the phased completion of the C-1 baggage system
project.
Budget Transfers
None this quarter.
AIRPORT

Port of Seattle 1Q 2009 Report  25

FIRST QUARTER REPORT, 2009
Airport Owned Gate Infrastructure
Project:   C800105      This project purchases and
replaces loading bridges at gates    Status Snapshot  Prior Report
Budget: $6,000,000
throughout the airport.            Delayed Schedule 4Q 08
Phase: Construction                        On Budget
Start: 07/24/2007                                 No Change Orders
Completion: 12/31/2009                       Total Change Orders Amount:
N/A
Significant Developments
Budget/Costs Incurred
The Loading Bridge at Gate B12 has been replaced and is
operational. A small works contract for the installation of Gate S5
has been executed. Design for Gate S2 is currently in review.
Purchase of the two remaining bridges is on-hold until June of 2009.
Schedule
Design is complete for the Gate S2 loading bridge. Construction is
scheduled to start at the end of April 2009 on the Gate S5 loading
bridge and is schedule to be complete May 15. The anticipated
installation of the first three loading bridges will be complete by mid-
June 2009
Construction Costs
Budget                            Not Applicable
The project forecast is within the approved budget. In October, the
Commission authorized $1,917,000 (for a total authorization of
$4,337,000) for a total for five loading bridges. The remaining
budget will be authorized in a following phase to replace additional
bridges and make other gate improvements in the future.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter.

AIRPORT

26  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
C4 UPS System Improvements
Project:   C800107      Project will purchase and install    Status Snapshot
Budget: $2,336,000      new Uninterruptible Power Supply   Delayed Schedule
Phase: Design        (UPS) units and associated equip-  On Budget
Start: 06/28/2007         ment for the Airport Combined      No Change Orders
Completion: On-Hold    Communications and Command   Total Change Orders Amount:
Center (C4).                 N/A
Significant Developments                    Budget/Costs Incurred
The design phase is complete and 100% bid-ready documents have
been submitted to the Airport Building Department to be reviewed for
building permit.
Schedule
The project is on-hold until funding is available.
Budget
The project forecast is within the approved budget and authorization.
Change Order
Construction Costs
None.                                    Not Applicable
Risks
None at this time.
Budget Transfers
None this quarter.




AIRPORT
Port of Seattle 1Q 2009 Report  27

FIRST QUARTER REPORT, 2009
Garage Escalator & "A" Elevator Upgrade
Project:   C800109      This project renews and replaces   Status Snapshot
Budget: $7,315,000      aging elevators and escalators in   On Schedule
Phase: Construction     the Parking Garage to provide    On Budget
Start: 09/11/2007         reliable vertical transportation to    No Change Orders
Completion: 02/28/2010   customers for years to come.     Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Work has begun on the East bank of elevators. Barricades have
been installed on all floor levels.
Schedule
The project is on schedule.
Budget
The project forecast is within the approved budget and authorization.
Change Order
A construction bulletin has been issued to change all lifting sheaves
due to wear.
Construction Costs
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT

28  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Main Terminal Roof Replacement
Project:   C800111      This project will remove         Status Snapshot
Budget: $1,658,000      approximately 51,840 square feet   On Schedule
Phase: Close Out      of old roofing system and replace it  Under Budget
Start: 04/24/2007         with a new 15 year membrane      4 Change Orders
Completion: 12/13/2008   roofing system.            Total Change Orders Amount:
$16,695
Significant Developments                    Budget/Costs Incurred
The project is complete. This will be the last quarterly report issued
for this project.
Schedule
The project was completed on schedule.
Budget
The project forecast is within the approved budget and authorization.
The project is anticipating a savings of approximately $110,000.
Construction Costs
Change Order
Four change orders have been issued totalling $16,695.
Risks
None identified at this time.
Budget Transfers
None this quarter.

Photo
Main Terminal Roof Replacement


CTE
RAMP
CONTROL TOWER
C1 Bldg.
PDOC

AIRPORT
Port of Seattle 1Q 2009 Report  29

FIRST QUARTER REPORT, 2009
Runway 16C/34C Panel/Joint Sealant
Replacement
Multi-year program to remove and   Status Snapshot
Project:   C800112      replace the pavement joint seal in   On Schedule
areas on Runway 16C/34C, the    On Budget
Budget: $2,415,000
center runway.               No Change Orders
Phase: Construction                        Total Change Orders Amount:
Start: 02/26/2008                                 $0.00
Completion: 12/31/2008
Significant Developments                    Budget/Costs Incurred
No work scheduled for 2009.
Schedule
Future slab replacement work is currently scheduled for 2010.
Budget
The completed Runway 16C/34C Pavement Joint Reseal project's
cost of $350,405 was determined to be non-capitalizable by Port
Accounting and was expensed at the end of 2008. Authorization of
the remaining project budget of $1,965,000 will be requested from
the Commission in the future.
Change Order
None
Risks
No risks have been identified at this time.
Budget Transfers
None



AIRPORT
30  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Security CCTV System Improvements
Project:   C800144      Install approximately 70 new      Status Snapshot
Budget: $2,037,591      cameras for TSA and integrate    Delayed Schedule
Phase: Implementation   existing Airport camera networks   On Budget
Start: 9/11/2007          which contain over 800 cameras.    No Change Orders
Completion: 06/30/2009                       Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Server and related equipment installation is nearly complete.
Integration of one-half of the airport cameras complete. The project
is awaiting for the interface to related system which is forthcoming
from vendor.
Schedule
Project completion is now expected by June 2009.
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order
Not Applicable
Not Applicable.
Risks
None identified at this time.
Budget Transfers
None this quarter.


AIRPORT


Port of Seattle 1Q 2009 Report  31

FIRST QUARTER REPORT, 2009
RMU/Kiosk Concession Program
Project:   C800146      The project will: Provide design and    Status Snapshot
Budget: $1,209,000      fabrication of eight (8) Retail       Delayed Schedule
Merchandising Units (RMUs); provide
Phase: Design                            On Budget
power, communications, and data to
Start: 11/20/2007                                 No Change Orders
the sixteen (16) RMU locations; and
Completion: 10/31/2009                       Total Change Orders Amount:
install floor-mounted receptacles for
N/A
the utilities to allow easy connection
points to the sixteen (16) RMUs, as
Significant           well as flexibility for future utilization.   Budget/Costs Incurred
Developments
The North Satellite construction is complete. The next phase of
construction is scheduled to start mid-Summer 2009.
Schedule
The design phase has been restructured and the bid packages resequenced
, with the intent to maximize the timing for new
Concessions opportunities.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.  Not Applicable
Change Order
None.
Risks
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT
32  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Concessions Renewal/Replacement
Project:   C800147      This project will upgrade         Status Snapshot
Budget: $2,231,000      concession locations which were   On Schedule
Phase: Design        previously vacated or slated to be   On Budget
Start: 08/26/2008         vacated to Port standards for use    No Change Orders
Completion: 02/23/2010   as specialty concession space.    Total Change Orders Amount:
$0
Significant Developments
The project is currently in the 30% Design Review Phase.         Budget/Costs Incurred
Schedule
The design phase has been restructured and the bid packages resequenced
, with the intent to maximize the timing for new
Concessions opportunities.
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Construction Costs
Change Order                         Not Applicable
None.
Risks
None identified at this time.
Budget Transfers
None this quarter.




AIRPORT
Port of Seattle 1Q 2009 Report  33

FIRST QUARTER REPORT, 2009
Gina Marie Lindsey (GML) Arrivals Hall
Concessions
This project will provide a new retail  Status Snapshot
Project:   C800148      merchandising corridor in the Gina   Delayed Schedule
Marie Lindsey Arrivals Hall. The     On Budget
Budget: $1,033,200
project includes installing three      No Change Orders
Phase: Design        Retail Merchandizing Units (RMUs)  Total Change Orders Amount:
Start: 11/20/2007         and providing utilities to a new      N/A
Completion: 09/04/2010   approximate 25-seat
restaurant/bar.
Significant                                Budget/Costs Incurred
Developments
The 100% design is complete.
Schedule
The project was previously reported as delayed due to infrastructure
design requirement revisions, business case revisions and additional
project process requirements. The project completion was pushed
into 2010 to coordinate with issuance of a Concessions Request for
Proposal (RFP) by the Aviation Business Development Group.
Budget                            Construction Costs
The project forecast is within the approved budget and authorization.  Not applicable
Change Order
Location
None.
Risks
Due to delay in schedule, bidding climate may change when the
project is bid and additional budget may be required.
Budget Transfers
None this quarter.



AIRPORT
34  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Concessions Flooring
Project:   C800157      Replace flooring in North and      Status Snapshot
Budget: $2,182,000      South Satellite food courts.      Delayed Schedule
Phase: Construction                        On Budget
Start: 07/24/2007                                 8 Change Orders
Completion: 05/31/2009                       Total Change Orders Amount:
$151,780
Significant Developments                    Budget/Costs Incurred
Replacement of the flooring in the North Satellite is complete, with
only punch list items remaining. The South Satellite flooring
demoliton is complete and floor tiling is scheduled to start the end of
April 2009 and will be substantially completed the end of May 2009.
Schedule
Additional construction delay is anticipated due to unforeseen preexisting
conditions in the South Satellite floors. These conditions
have complicated the installation of a replacement expansion joint
and have required additional structural infill.
Budget
Construction Costs
The project forecast is within the approved budget and authorization.
Change Order
Eight change orders have been issued.
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 1Q 2009 Report  35

FIRST QUARTER REPORT, 2009
Runway 16L/34R Reconstruction
Project:   C800167      The scope of this project includes   Status Snapshot
Budget: $85,000,000     the complete reconstruction of    On Schedule
Phase: Construction     Runway 16L/34R (the eastern    On Budget
Start: 02/26/2008         runway) and replacement of aging   No Change Orders
Completion: 12/31/2009   infrastructure.             Total Change Orders Amount:
$0.00
Significant Developments                    Budget/Costs Incurred
Runway 16L/34R Reconstruction project includes reconstruction of
11,900 foot runway and portions of five taxiways. Related work
includes pavement demolition, excavation, grading, portland cement
concrete and asphalt concrete paving, storm drainage, water mains
and flush fire hydrants, electrical ductbanks, airfield lighting systems
and guidance signs. The project was advertised in December 2008,
with bid opening on Jan 20th, 2009. Four bids were submitted with
ICON Materials being the low bidder. The project was awarded to
ICON Materials for $51,600,703.
Schedule
Construction Costs
Project was awarded to ICON Materials in February 2009, and
construction began March 30th, 2009 to be completed in late October
2009.
Budget
CIP budget of $85,000,000 is fully authorized with a cost to date of
$2,403,000.
Change Order
None
Risks                               Photo
No risks have been identified at this time.
Budget Transfers
None

AIRPORT

36  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Renew/Replace 42 Escalators
Project:   C800237      This project will renew and replace   Status Snapshot Prior Report
Budget: $55,000,000     escalators in the Main Terminal    Delayed Schedule 4Q 08
Phase: Design        and North and South Satellites. In  On Budget
Start: 11/02/2007         addition, one new escalator will be   No Change Orders
Completion: 04/22/2016   installed at the South Satellite.    Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Consultant proposals to provide the 30% Design Package were
received and evaluated. Notification of selection is underway with
cost negotiation to occur in the second quarter. This project will
utilize the Best Bid procurement method.
Schedule
The project is behind schedule three months, awaiting final
notificationof selection of the design consultant and cost negotiations
with the selected firm.
Budget                            Construction Costs
Not Applicable
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 1Q 2009 Report  37

FIRST QUARTER REPORT, 2009
Central Plant Pre-Conditioned Air
Project:   C800238      Provide a centralized Pre-        Status Snapshot
Budget: $33,360,000     conditioned Air Plant, associated   Delayed Schedule
Phase: Design        heating and cooling piping      On Budget
Start: 06/15/2009         systems, and jet bridge terminal air  No Change Orders
Completion: 07/10/2012   handling units to serve airplanes   Total Change Orders Amount:
with heating and cooling while at    $0
the gates.
Significant
Developments                        Budget/Costs Incurred
The Request for Qualifications (RFQ) has been published.
Statements of qualifications due April 21, 2009.
Schedule
Posting of the RFQ was approximately three months behind
schedule; however, modifications recovered most of the delay and
put the project within two weeks of the original schedule.
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction will
be requested when the design and bid documents are completed.
Construction Costs
Change Order                         Not applicable
None at this time.
Risks
The schedule is tied to VALE funding.
Budget Transfers
None this quarter.



AIRPORT
38  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Fire Piping Upgrades - Main Terminal
Project:   C800239      Upgrade the Main Terminal fire     Status Snapshot
Budget: $1,500,000      main piping to restore system     On Schedule
Phase: Design        reliability and provide full       On Budget
Start: 09/23/2008         monitoring capability with the fire    No Change Orders
Completion: 03/26/2010   alarm system.             Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
The 90% design was completed with no significant change in scope
or cost. Bid documents being prepared for advertisement in second
quarter.
Schedule
The project is currently on schedule.
Budget
The project forecast is within the approved budget. Authorization of
construction funding and authority to advertise for construction is
targeted for late April 2009.
Construction Costs
Change Order                         Not Applicable
None.
Risks
Bidding market conditions when the construction contract is
advertised.
Budget Transfers
None this quarter.



AIRPORT
Port of Seattle 1Q 2009 Report  39

FIRST QUARTER REPORT, 2009
2nd Floor HVAC Upgrades
Project:   C800249      Construct a new Heating        Status Snapshot Prior Report
Budget: $1,497,000      Ventilating and Air-Conditioning    Delayed Schedule 3Q 08
Phase: Design        (HVAC) air supply duct system to   On Budget
Start: 03/25/2008         the north side of the second floor of  No Change Orders
Completion: 01/31/2010   the central main terminal       Total Change Orders Amount:
administration building and the      N/A
concessions located directly below
Significant           on the ticketing level.         Budget/Costs Incurred
Developments
Commission authorized the advertisement of bids and construction
funding on February 28, 2009. The project was advertised in March
with bids due in late April 2009.
Schedule
No change in schedule.
Budget
Commission authorization of construction funding on February 28,
2009 included a $137,000 increase in project cost to improve the     Construction Costs
efficiency of the HVAC air handler ducting, to eliminate roof access   Not Applicable
restrictions, and the installation of temporary flex ducts to eliminate
impacts on existing tenants during construction.
Change Order
None.
Risks
Bidding market conditions.
Budget Transfers
From C102166 (Aeronautical Renewal/Replacement)  $137,000


AIRPORT

40  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Aircraft RON Parking USPS Site
Project:   C800254      This project will prepare the site for  Status Snapshot
Budget: $28,097,000     the construction of Hardstands for   On Schedule
Phase: Design        use as Remain Overnight parking   On Budget
Start: 04/05/2009         of aircraft at the Air Mail Center     No Change Orders
Completion: 06/30/2013   site.                  Total Change Orders Amount:
$0.00
Significant Developments
This project completed the lease buyout negotiation with the USPS   Budget/Costs Incurred
and is schedule for lease termination in 2010. Design efforts for the
demolition of the Air Mail Center including the design for minimal site
improvements allowing for temporary uses and amenities and 15%
design for the final Hardstand has been put on hold until further
analysis of use of hardstand based on future growth.
Additional Commission authorizations will be required to execute
lease termination, advertise and award the demolition of the Air Mail
Center, and for the design and construction of the hardstands.
Construction Costs
Schedule                           Not applicable.
The anticipated schedule is to complete lease buy out and demolition
design by December 2009.
Budget
The budget of $6,226,213 was authorized by the Commission on
August 26th, 2008 for the lease buyout, demolition design and 15%
Hardstand design.
Change Order
None.
Risks
No risks identified at this time.
Budget Transfers
None.
AIRPORT
Port of Seattle 1Q 2009 Report  41

FIRST QUARTER REPORT, 2009
South AOA Fence Replacement
Project:   C800286      This project provides new security   Status Snapshot
Budget: $375,000       fencing around the south end of    On Schedule
Phase: Design        Runway 34R that lies south of    On Budget
Start: 03/03/2009         188th street, meets current        No Change Orders
Completion: 06/30/2011   standards for airfield security fence,  Total Change Orders Amount:
and reduces the number of coyotes  $0.00
on the airfield to enhance aviation
Significant           safety.
Developments                        Budget/Costs Incurred
The project is currently in final design.
0.40
0.35
Schedule
0.30
The construction contract is scheduled to advertise in May and the
work is to be completed by the Fall of 2009.                    Dollars [Millions] 0.250.200.15
Budget                            0.10
The CIP budget of $375,000 was authorized on March 3rd, 2009.     0.05
0.00
Change Order                            Authorized Forecasted Costs
incurred
None.
Risks
Construction Costs
No risks have been identified at this time.                     Not applicable.
Budget Transfers
None.





AIRPORT
42  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Fire Vehicles
Project:   C001338      Purchase of fire vehicles according  Status Snapshot
Budget: $2,243,000      to the Fire Department Vehicle    On Schedule
Phase: Implementation   Replacement Master Plan.      On Budget
Start: 11/23/2008                                 0 Change Orders
Completion: 7/31/2009                        Total Change Orders Amount:
0
Significant Developments                    Budget/Costs Incurred
Contract has been executed to acquire a fire pumper vehicle.
2.5
Schedule                              2
Project is on schedule                                    1.5
Budget                             Dollars [Millions] 1
0.5
Expected to be delivered on budget
0
Change Order                             Authorized Forecasted Costs incurred
None
Construction Costs
Risks
Not applicable.
No risks have been identified this quarter
Budget Transfers
None





AIRPORT

Port of Seattle 1Q 2009 Report  43

FIRST QUARTER REPORT, 2009
Rental Car Facility Property Acquisition
Project:   C101110      Acquire real property and relocate   Status Snapshot
Budget: $16,540,000     businesses in preparation for     On Schedule
Phase: Implementation   construction of the Rental Car     On Budget
Start: 12/12/2000         Facility.                    No Change Orders
Completion: 06/01/2009                       Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Final acquisition of cemetery access road is on hold pending project     18
16
re-start.
14
12
Schedule                            Dollars [Millions] 10
8
On December 15, 2008, the Port of Seattle Commission voted to
6
temporarily suspend construction on the $400 million consolidated      4
rental car facility.                                              2
0
Authorized    Forecasted   Costs incurred
Budget
Current authorized acquisitions are within budget.               Picture
Change Order
Not Applicable
Risks
None identified at this time.
Budget Transfers
None this quarter.



AIRPORT

44  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Fire Vehicles
Project:   C102396      Purchase of fire vehicles according  Status Snapshot
Budget: $1,095,000      to Fire Dept. Vehicle Replacement  On Schedule
Phase: Implementation   Master Plan.             On Budget
Start: 11/16/2008                                     Change Orders
Completion: 7/31/2009                        Total Change Orders Amount:
0
Significant Developments
Contract for Airport Rescue Fire Fighting Vehicle has been executed.  Budget/Costs Incurred
Preparing to advertise for bid for Medical Aid Unit.
Schedule
Project is on schedule
Budget
Expected to be delivered on budget
Change Order
None
Risks                               Construction Costs
Not applicable.
No risks have been identified this quarter
Budget Transfers
None





AIRPORT
Port of Seattle 1Q 2009 Report  45

FIRST QUARTER REPORT, 2009
Highline School Noise Insulation
Project:   C200007      Highline School Insulation        Status Snapshot Prior Report
Budget: $101,797,000    Agreement will provide funding for  Delayed Schedule 3Q 08
Phase: Construction     sound mitigation for 15 schools that  On Budget
Start: 3/23/1999          are impacted by aircraft noise from   No Change Orders
Completion: 11/30/2021   Sea-Tac Airport.            Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
The insulation of seven schools has been completed and one more     120.0
is in progress.                                            100.0
80.0
Schedule                            Dollars [Millions] 60.0
Port funding is authorized and will be available when the matching
40.0
funds are provided by the state and school district. The schedule for
20.0
that is not known.
-
Authorized   Forecasted  Costs incurred
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Authorization: $102,143,877                             Not Applicable. Construction
Forecasted: $101,797,000                            is done by the Highline
Costs Incurred: $44,585,143                            School District.
Change Order
Not Applicable
Risks
This project requires matching funds from the state and voter
approved school bond funding. If the state or bonds are not
acquired, construction will be delayed.
Budget Transfers
None


AIRPORT
46  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009 
3rd Runway Residential Acquisition
Project:   C200015      Acquire single/multi-family        Status Snapshot
Budget: $34,340,000     structures located in the 3rd       On Schedule
Phase: Implementation    Runway's flight path in the City of   On Budget
Start: 05/27/1999         Burien to comply with FAA safety    No Change Orders
Completion: 06/30/2009   rules.                 Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred 
The final of three phases is nearing completion. All 29 offers have      45
40
been made, 27 offers have been accepted and 26 properties have
35
closed. One apartment building and one Single Family Residence      30
are in the negotiation phase.                               Dollars [Millions] 25
20
15
Schedule
10
Property owners have been readily accepting offers from the Port.      5
0
This is partially due to the current residential real estate market. This       Authorized  Forecasted Costs incurred
is putting this phase of the project work ahead of schedule. The
overall project schedule is not forecasted to change.
Budget                            Photo
The project forecast is within the approved budget and authorization.
Change Order
Not Applicable
Risks
Regional construction costs for demolition have been rising over the
last several years. This causes concern that total project costs may
exceed original estimates.
Budget Transfers
None

AIRPORT

Port of Seattle 1Q 2009 Report  47

FIRST QUARTER REPORT, 2009
FAR Part 150 Mobile Home Park Acquisition
Project:   C200037      Acquisition of mobile and        Status Snapshot
Budget: $47,258,000     manufactured home parks, and    On Schedule
Phase: Implementation   relocation of the tenants, to reduce  On Budget
Start: 02/12/2002         the number of people living in      No Change Orders
Completion: 06/30/2011   mobile homes within high noise    Total Change Orders Amount:
areas.                     N/A
Significant Developments                    Budget/Costs Incurred
1st Quarter of 2009 saw increased move-outs as families found
50
replacement housing.
40
Schedule                             30
Our relocation program is slightly ahead of schedule and we         Dollars [Millions] 20
traditionally see families relocate faster during the upcoming summer
10
months, when children are on their summer vacation. Abatement and
0
demolition of selected vacant mobile homes should also begin this
Authorized  Forecasted Costs incurred
summer.
Budget
Picture
Recent credit market conditions have created challenges in finding
suitable and affordable replacement housing in this housing
segment. Costs to test, abate and demolish mobile homes is
expected to exceed forecasts. Impact on budget is unknown at this
time.
Change Order
Not Applicable
Risks
Tight residential housing credit market. Abatement and demolition
costs.
Budget Transfers
None

AIRPORT
48  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Highline Community College Noise Insulation
Project:   C200042      Highline Community College      Status Snapshot Prior Report
Budget: $10,822,000     Insulation Agreement will provide   Delayed Schedule 1Q 08
Phase: Construction     funding for up to 22 eligible      On Budget
Start: 01/11/2005         buildings that are impacted by      No Change Orders
Completion: 10/01/2011   aircraft noise from Sea-Tac Airport.  Total Change Orders Amount:
N/A
Significant Developments
Twelve of the 22 eligible buildings have been sound insulated by the  Budget/Costs Incurred
college.
12.0

10.0
Schedule
8.0
Building #19 construction is complete. The schedules for the
6.0
remaining buildings are dependent on state funding. Funding from     Dollars [Millions] 4.0
the college has been delayed, therefore, delaying the overall project.
2.0
Budget                              -
Authorized   Forecasted  Costs incurred
The project forecast is within the approved budget. We are
preparing to complete noise audits on the remaining buildings that
have not been reconstructed to see if in the future any will be eligible
for FAA grant funds. Authorization of the remaining project budget of  Construction Costs
$5,828,402 will be requested from the Commission in the future     Not Applicable. Construction
when schedule is determined.                          is managed by the
community College
Authorized: $4,993,598
Forecasted: $10,822,000
Costs Incurred: $4,237,504
Change Order
Not Applicable
Risks
The Highline Community College competes for state funding with
other colleges. If they do not receive adequate funding, projects will
be delayed. Estimates for the remaining eight college buildings have
not been completed by the college.
Budget Transfers
None
AIRPORT
Port of Seattle 1Q 2009 Report  49

FIRST QUARTER REPORT, 2009
Home Insulation Retrofit
Project:   C200048      This CIP includes two projects that   Status Snapshot Prior Report
Budget: $5,344,000      provide either re-insulation or repair  Delayed Schedule 2Q 08
Phase: Construction     of previously insulated homes due  On Budget
Start: 01/11/2005         to safety and condensation issues.   No Change Orders
Completion: 12/31/2009                       Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Researching remaining eligible homes to continue and complete
project.                                                 6.0
5.0
Schedule
4.0
Will commence upon review of remaining homes.               Dollars [Millions] 3.0
2.0
Budget
1.0
Project is forecasted to be within budget.
-
Authorized    Forecasted  Costs incurred
Authorized: $5,344,000
Forecasted: $5,344,000
Costs Incurred: $3,060,564                             Construction Costs
Not Applicable
Change Order
Not Applicable
Risks
Liability associated with egress safety issues.
Budget Transfers
None



AIRPORT

50  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Single Family Home Sound Insulation
Project:   C200093      Sound insulate remaining homes    Status Snapshot
Budget: $2,450,000      that are within the 1998 65 decibel  On Schedule
Phase: Construction     day night level (DNL) noise      On Budget
Start: 03/27/2007         contour.                   No Change Orders
Completion: 12/31/2009                       Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Seven homes are in the next group to be insulated.
Schedule
On schedule.
Budget
The project forecast is within approved budget and authorization.
Authorized: $2,450,000
Forecasted: $2,450,000
Costs Incurred: $673,011
Construction Costs
Change Order
Not Applicable
Not Applicable
Risks
The ability to accomplish the insulation is dependent on the wishes
of the homeowners.
Budget Transfers
None



AIRPORT
Port of Seattle 1Q 2009 Report  51

FIRST QUARTER REPORT, 2009
Street Vacations - Des Moines Creek 1
Project:   C800046      Purchase the City of Des Moines-   Status Snapshot Prior Report
Budget: $3,850,000      owned streets in the Des Moines   On Schedule
Phase: Implementation   Creek Business Park site that are   Under Budget   3Q 08
Start: 10/01/2008         surrounded by Port-owned        No Change Orders
Completion: 08/31/2009   property. This acquisition will     Total Change Orders Amount:
enable the Port to develop the      N/A
business park site.
Significant                                Budget/Costs Incurred
Developments
Per our agreement with the City of Des Moines, the amount owed
the City has been deposited into an escrow account pending
satisfaction of all the conditions required for closing.
Schedule
Acquisition is expected to be completed by 8/31/09.
Budget
The project forecast is within the approved budget and authorization.
Construction Costs
Change Order                         Not Applicable
Not applicable.
Risks
All the conditions required for closing--most notably, the Des Moines
City Council's approval of the developer's master plan--are not yet
met. The Port may terminate the agreement if City approval does
not occur and retain the allocated funds.
Budget Transfers
None


AIRPORT

52  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Burien Commercial Property Acquisition
Project:   C800150      Acquire commercial properties     Status Snapshot
Budget: $3,000,000      along Des Moines Memorial Drive,  On Schedule
Phase: Implementation   and vacate one street, in the City of  On Budget
Start: 05/31/2007         Burien that are surrounded by Port-  No Change Orders
Completion: 12/31/2010   owned properties.           Total Change Orders Amount:
N/A
Significant Developments                    Budget/Costs Incurred
Burien Seventh Day Adventists Church and School acquired         3.0
December 31, 2008. Next acquisitions are for the Sunnydale        2.5
Substation and a street vacation in Burien.
2.0

1.5
Schedule                            Dollars [Millions] 1.0
Properties are purchased as Commission authorization is received.
0.5
Program expected to be completed in 2010.
-
Authorized    Forecasted  Costs incurred
Budget
Project is forecasted to be within budget.                     Construction
Not Applicable
Change Order
None.
Risks
None
Budget Transfers
None




AIRPORT
Port of Seattle 1Q 2009 Report  53

FIRST QUARTER REPORT, 2009
Tenant Reimbursement
Project:   C800154      Build out of spaces for new and    Status Snapshot
Budget: $4,709,577      existing tenants. If more than a    On Schedule
Phase: Construction     "basic finish" condition space is    On Budget
Start: 08/14/2007         built for the tenant, the tenant is     No Change Orders
Completion: 03/31/2010   required to reimburse the Port for   Total Change Orders Amount:
the cost of the work beyond this     N/A
"basic finish". These reimburse-
Significant           ments are allowed under the     Budget/Costs Incurred
Developments       guidelines described in the "Tenant
Reimbursement Policy".
Construction of new office space by Hawaiian Airlines was
completed in 4th Quarter 2008. Port's reimbursement for Hawaiian
handled in Q1-2009.
Virgin America reimbursement completed 1st Quarter 2009.
Port construction of the TSA Mezzanine Office Project complete.
Accounting interpretation of reimbursements back to the Port from
tenants will be considered extraodinary revenue and will not credit
reimbursement to the project.                            Construction Costs
Not Applicable.
Schedule
Work completed on schedule to meet the tenants needs.
Budget
Virgin America's $407,000 in reimbursements was approved by the
Commission and payment made in Q1.
$1,091,000 in reimbursement to the Port by TSA received in 1st
Quarter 2009.
Change Order
None
Risks
None identified at this time.
Budget Transfers
None
AIRPORT
54  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Alaskan Way St Vacation and Public Access
Project:   C000579      Scope includes all public access    Status Snapshot Prior Report
Budget: $1,036,000      improvements at multiple sites and  Delayed Schedule 2Q 08
Phase: Planning       fees as required by the City of    On Budget
Start: 1996             Seattle in order to vacate Alaskan   No Change Orders
Completion: 2011       Way South At T30 site.        Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
N/A                                      1.2
1
Schedule
0.8
No changes this quarter. Project continues to be on hold pending      Dollars [Millions] 0.6
closure of all other previous street vacations.
0.4

0.2
Budget
0
No changes this quarter                                   Authorized  Forecasted Costs incurred
Change Order
NA                             Construction Costs
None
Risks
Risks have not changed from 3rd Quarter '08 report.
Budget Transfers
NA





SEAPORT
Port of Seattle 1Q 2009 Report  55

FIRST QUARTER REPORT, 2009
T-115 Dock Reconstruction
Project:   C102451      Upgrade three areas of existing    Status Snapshot Prior Report
Budget: $26,500,000     1200 ft dock, upgrade Berth 1 and  Delayed Schedule 4Q 08
Phase: Construction     improve 15 acres of uplands for    Forecast Overrun 1Q 08
Start: 7/2003            tug/barge cargo operations.       20 Change Orders
Completion: 12/31/2009                       Total Change Orders Amount:
$1,025,338
Significant Developments                    Budget/Costs Incurred
90% Design scheduled for Completion 2Q2009. Request for
construction funding is scheduled for 2Q2009. Staff expects to
received permits 3Q 2009.
Schedule
Scheduled construction start is December 2009 and completion date
is estimated to be 4/30/10, as reported last quarter.
Budget
No change this quarter.
Change Order                         Construction Costs
No change orders this quarter
14
12
Risks
10
Schedule is contingent on receiving in-water-work and building
permits by late August 2009.                              Dollars [Millions] 8
6
Budget Transfers                          4
None                                   2
0
Initial    Change Orders    Spent



SEAPORT
56  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
C-36 Surplus
Project:   C103586      Removal or demolition of Crane 36,  Status Snapshot Prior Report
Budget: $330,000       presently located on the north end  Delayed Schedule 3Q 08
Phase: Construction     of Terminal 18. C36 was       On Budget
Start: 10/24/06          purchased in 1974.            No Change Orders
Completion: Q1 2009                         Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
The majority of the project was completed during the reporting period    0.35
0.3
Schedule                             0.25
0.2
Demolition and demobilization will completed the first week of April     Dollars [Millions] 0.15
Budget                             0.1
0.05
Forecasted costs are within budget
0
Authorized    Forecasted  Costs incurred
Change Order
None
Construction Costs
Risks                               $194,000 including
May incur weather related claim.                          contingency and WSST.
Budget Transfers
None




SEAPORT

Port of Seattle 1Q 2009 Report  57

FIRST QUARTER REPORT, 2009
T25/30 Improvements 2005-2007
Project:   C800064      Improve T25 container yard, and    Status Snapshot Prior Report
Budget: $13,787,870     build bridge between T25 and T30  Delayed Schedule 3Q 08
Phase: Construction     to improve access. Complete     On Budget
Start: 2005             street vacation at S. Forest St. and   No Change Orders
Completion: 2011       related public access         Total Change Orders Amount:
improvements.              $0
Significant Developments                    Budget/Costs Incurred
None                                   16
14
Schedule                             12
10
Completed the sidewalk improvements at East Marginal Way this      Dollars [Millions] 8
quarter. All work is done with the exception of some public access /     6
habitat improvements at South Riverside Drive at the South Park       4
Public Access site. This piece of work is on hold, pending            2
0
negotiations with the City and Washington State DOT.
Authorized    Forecasted   Costs incurred
Budget
No changes to report this quarter.                          Construction Costs
NA
Change Order
NA
Risks
NA
Budget Transfers
NA



SEAPORT
58  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Terminal 30/Terminal 91 Program
Redevelopment of Terminals     Status Snapshot
Project: C800085        25/28/30 into one combined     On Schedule
Budget: $121,525,000     container facility. Relocation of the  On Budget
existing T30 Cruise operations into  91 Change Orders
Phase: Construction
a new facility at T91, and related    Total Change Orders
Start: 10/2/2007
facility improvements and berth    Amount:
Completion:6/10/09
dredging.                  $6,044,395.
Significant                                Budget/Costs Incurred
Developments
140
T91: The Terminal 91 cruise terminal building construction by PCL is     120
estimated to be 99% complete. PCL achieved beneficial occupancy on    100
80
3/6/09 and received certificate of occupancy from the City on 4/10/09.     Dollars in Millions 60
The T91 facility is on schedule for receiving the first cruise vessel on       40
4/24/09.                                              20
0
Authorized     Forecasted    Costs incurred
Punchlist work by the PCL is in progress. Offsite signage                    Budget/Cost Incurred to Date
fabrication/installation coordination with City of Seattle continues. Office
equipment and furniture move-in for Cruise Terminals of America,      Construction Costs
Customs & Border Protection and cruise line's is complete. Cruise
80
building and yard signage fabrication/installation is mostly complete.
70
Installation of major shorepower cabling by Seattle City Light is in        Dollars in Millions 60
50
progress. Installation of fence, gates, utilities, striping and revenue        40
30
control booths and gate arms for the north end parking lot is in
20
progress. Coordination with Cochran on shorepower conduit extension    10
0
and jib crane installation is on-going. Painting of metal canopy is in           Initial   Change Orders   Spent
progress. West shorepower installation is in progress. (Continued on         Construction/Change Order Cost Incurred to Date
Page 2).
Photo
Schedule
T91: Received certificate of occupany for the cruise terminal building on
3/10/09. The T91 facility is on-schedule to be available to receive its first
vessel on April 24, 2009. (Continued on Page 2).
Budget
The current program budget is $121.5 million which includes 3.2 million
for the foundation change. The program forecast is $118.3 million.
The $3.2 million foundation change is provisional and remains unused.

SEAPORT
Port of Seattle 1Q 2009 Report  59

Change Order
There were 21 change orders this quarter for a total of $594,315.
Budget Transfers
None
Significant Developments, continued
T30: The T30 major construction is estimated at 89% complete.
Construction is progressing behind schedule and on budget. The
contractor GCC experienced schedule delays from severe weather
conditions between in 2/25/09 thru 3/15/09. The Port and the contractor
have agreed on maintaining the beneficial occupancy of the facility on
5/11/09.
Waterside crane beam is essentially complete (mechanical and
electrical work on-going). Truck scale approach slabs are complete.
Longshore building exterior sheeting, interior framing and painting is in
progress. Paving, perimeter fencing, and reefer racks electrical work are
in progress. Raising the Utility Castings is complete. Install perimeter
fencing is in progress. Fabrication of the concrete barrier is in progress.
Maintenance canopy modification work is complete. OCR structure at
T25 is complete. Install new light pole / luminaries is in progress.
Schedule, continued
T30: The current schedule is showing the project being complete on
5/11/09. The contractor and Port have settled time impacts due to sever
weather in December/January and have agreed on maintaining the
beneficial occupancy target date of 5/11/09. Paving was impacted due
to severe rain conditions in February and March, the contractor is
reviewing the Port evaluation of these impacts.
The barge for crane off-loading (relocation from T18) is scheduled for
April 7th. The substation is expected to be on on-line mid April and
available for crane commissioning.
Risks
T91: Shore power installation and mobile gangway fabrication need to
be fully completed and commissioned prior to start of 2009 cruise
season.
T30: Weather continues to be a risk factor for the project schedule.

60  Port of Seattle 1Q 2009 Report

SECOND QUARTER REPORT, 2009
T91 Berth M Replacement
Project:   C800089      Replace remaining timber portion   Status Snapshot   Prior Report
Budget: $10,654,000     of Berth M apron structure with a   Delayed Schedule  2Q 08
Phase: Close Out      concrete/steel pile supported     Under Budget    2Q 08
Start: 9/21/2007          concrete apron structure.         10 Change Orders
Completion: 5/30/2008                        Total Change Orders Amount:
$206,345
Significant Developments                    Budget/Costs Incurred
Construction completed as of 5/30/2008 and the new apron is in use.    12
Change order documentation finalized and ready for execution.        10
8
Schedule
6
Project is in the close-out phase.                             Dollars [Millions] 4
2
Budget
0
Forecasted under budget                                Authorized  Forecasted Costs incurred
Change Order
Contractor has two change orders to sign, should be executed in the  Construction Costs
second quarter 2009.
6
Risks                                5
None.                                      4
3
Budget Transfers                          Dollars [Millions] 2
None
1

0
Initial    Change Orders    Spent



SEAPORT
Port of Seattle 1Q 2009 Report  61

FIRST QUARTER REPORT, 2009
T 86 Grain Spout Repair
Project:   C800113      Replace grain spouts #1 and #4 at   Status Snapshot Prior Report
Budget: $2,136,010      T86.                 Delayed Schedule 4Q 08
Phase: Construction                          On Budget
Start: 1/2007                                    No Change Orders
Completion: 6/10/2009                        Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred
Project was bid and has been awarded.
2.5
Schedule                             2
Project is on schedule for the May-June spout installations.
Dollars [Millions] 1.5
1
Budget
0.5
Project is currently on budget.
0
Change Order                            Authorized Forecasted Costs incurred
None
Construction Costs
Risks                               None
None
Budget Transfers
Previously $97,000 was transferred from expense Project #103677
to capture capital work performed under the expense project.




SEAPORT

62  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
P66 Bag. Corridor & Pass. Screening
Project:   C800114      Provide baggage and passenger    Status Snapshot
Budget: $2,087,000      screening improvements at P66 to  On Schedule
Phase: Construction     accommodate larger cruise vessels  On Budget
Start: 1/1/2008          with 300-400 more passengers per   No Change Orders
Completion: 12/31/2009   sailing.                Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred
Canopy installed but contractor was unable to complete the project      2.5
to specifications. Port will complete project correctly and deduct
2
costs from contractor payment.
1.5
Schedule                            Dollars [Millions] 1
The elevator upgrade will be rebid in second quarter but construction    0.5
will not start until after Cruise ends in November 2009.
0
Authorized    Forecasted   Costs incurred
Budget
No change
Construction Costs
Change Order                         No Major Construction
None                                 contracts
Risks
None
Budget Transfers
None



SEAPORT

Port of Seattle 1Q 2009 Report  63

FIRST QUARTER REPORT, 2009
Terminal 18 South Fender Improvements
Status Snapshot
Project: C800121        Replace 800' of deteriorated fender
On Schedule
Budget: $450,000       system at the south end of
On Budget
Phase: Design        Terminal 18
0 Change Orders
Start: 3/26/08                                    Total Change Orders Amount:
Completion: 4/30/10                         $0
Significant Developments
Design and permitting effort started for the fender system. The
length of the fender system was extended 400 lf to have a complete   Budget/Costs Incurred
design for entire 1,200 lf length of the treminal instead of the initial
0.9
800 lf. Commission approved the change in the design scope as the     0.8
incremental cost of the additional length of the fender system will be     0.7
0.6
minimal. Design will be performed by Port Staff.                Dollars [Millions] 0.5
0.4
Schedule                             0.3
0.2
Permit applications scheduled for June '09, design completion by
0.1
September '09.                                     0
Authorized    Forecasted   Costs incurred
Budget
Project within approved budget.
Construction Costs
Change Order                          0.7
None this quarter                                      0.6
0.5
Risks                                0.4
None identified this quarter                                 Dollars [Millions] 0.3
0.2

0.1
Budget Transfers                          0
Initial    Change Orders    Spent
None



SEAPORT
64  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009 
T-5 Crane Spreader Replacement
Project:   C800123      To replace two crane cargo       Status Snapshot Prior Report 
Budget: $525,000       spreader beams that are beyond   Delayed Schedule 4Q 08 
Phase: Construction     their useful life. Spreader beams   On Budget
Start: 10/24/06          are terminal equipment used to     No Change Orders
Completion: 3/31/2009    move containers to and from ships  Total Change Orders Amount:
and trucks.                   $0
Significant Developments                    Budget/Costs Incurred 
Project was rebid in Q1 2009. Bids received on April 10, 2009
appear to be compliant. Purchase order will be executed 2Q2009.
Schedule
Schedule adjusted to reflect re-bid. Estimate completion date is 4Q
2009, 9 months later than previously thought, as reported in the
4Q08 report
Budget
CIP 800123 is funded for $2,897,000. The Commission approved
Work Project budget for procurement of 2 spreader beams is
$525,000. A request for additional authorization of the balance of     Construction Costs
funding is schedule for later this year.                        None
Change Order
None
Risks
None
Budget Transfers
None



SEAPORT
Port of Seattle 1Q 2009 Report  65

FIRST QUARTER REPORT, 2009 
T25 South Redevelopment
Project:   C800259      Redevelopment of former cold     Status Snapshot Prior Report 
Budget: $4,377,513      storage facility site at south end of  Delayed Schedule 4Q 08 
Phase: Construction     Terminal 25 into container terminal  On Budget
Start: 11/2007           yard.                     No Change Orders
Completion: Indefinite                        Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred 
Phase 2 construction on hold indefinitely.                       20
18
16
Schedule                             14
No changes from 4th Qtr 2008 report.                        Dollars [Millions] 12
10
8
6
Budget                             4
2
As per prior report, Commission approval for Phase 2 construction
0
costs will be requested if, and when the property is leased.              Authorized  Forecasted Costs incurred
Change Order
None                                 Construction Costs
1.8
Risks                                1.6
1.4
None
1.2
1
Budget Transfers                          Dollars [Millions] 0.8
0.6
None
0.4
0.2
0
Initial     Change Orders     Spent




SEAPORT
66  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2008 
T-10 Interim Redevelopment
Project:   C800264      Funding is to develop full project    Status Snapshot
Budget: $800,000       scope and design of utilities to    Delayed Schedule
Phase: Design         support terminal related activities.   On Budget
Start: 3/22/2008          Primary focus is the design of the    No Change Orders
Completion: 11/30/09    storm water drainage system and   Total Change Orders Amount:
the paving, lighting and fencing.     $0
Significant Developments                    Budget/Costs Incurred 
Staff met with Agencies to discuss proposed design. All issues
appeared to be manageable. 30% Estimate and Design received
1Q2009. Based on discussion with agencies and Designer's
evaluation and estimates, Staff is recommending the project scope
be amended to include a new 24 inch outfall and complete asphalt
overlay of the site. Staff requested and received authorization to
preceed with 100% design document on April 14, 2009.
Schedule
The addition of the new 24 inch outfall will delay completion until 3Q
2010.
Construction Costs
Budget                            None
Forecasted costs included estimated construction costs.
Authorization and forecasted budget is $800,000 for design and
permiting only. Total estimated project costs with the addition of the
new outfall and paving are $5,100,000. Staff will return to
Commission for additional construction authorization 4Q2009..
Request to Commission for additional construction authorization
scheduled for 1Q 2009.
Change Order
None
Risks
Schedule delays
Budget Transfers
None

SEAPORT
Port of Seattle 1Q 2009 Report  67

FIRST QUARTER REPORT, 2009
T91 City Ice Bldg. W-40 Demo
Project:   C800265      Partial building demolition and     Status Snapshot
Budget: $861,000       reconfiguration of Building W-40 at  On Schedule
Phase: Construction     Terminal 91 including utility      Forecast Overrun
Start: 9/11/2007          relocation, paving and possible     (5) Change Orders
Completion: 3/9/2009    fencing.                Total Change Orders Amount:
$37,102.
Significant Developments                    Budget/Costs Incurred
Construction complete. Project exceeded authorized budget, will      0.9
0.8
request Commission authorization for additional funding.
0.7
0.6
Schedule                            Dollars [Millions] 0.5
0.4
Project is tracking and is on schedule. With the request for
0.3
Commission authorization and approval to install a new forklift ramp,     0.2
the project is expected to complete in late 2Q-09.                  0.1
0
Authorized    Forecasted   Costs incurred
Budget
Project exceeded authorized budget, staff will request additional
Commission authorization of $168K.                      Construction Costs
Change Order                          0.6
Total change orders to date = $37,102                        0.5
0.4
Risks
0.3
None                                  Dollars [Millions] 0.2
Budget Transfers                          0.1
None                                   0
Initial    Change Orders    Spent



SEAPORT
68  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009 
T91 Mobile Gangways
Project:   C800273      Construct two mobile gangways    Status Snapshot
Budget: $6,460,000      and the associated support      On Schedule
Phase: Construction     infrastructures for the new T91    On Budget
Start: 6/24/2008          Cruise Terminal.              3 Change Orders
Completion: 4/30/2009                        Total Change Orders Amount:
$177,620
Significant Development                    Budget/Costs Incurred 
Design finalized with additional range of movement and automation     7
for the gangway components. Gangway fabrication well underway     6
and nearly complete.                                  5
4
Schedule                            Dollars [Millions] 3
2
Gangways are on target to be delivered on April 3rd, 2009.
1
Budget                             0
Authorized    Forecasted   Costs incurred
Change order negotiation continues for the fabrication costs to obtain
additional range of movement and automation. Anticipate all costs to
be within authorized budget.                             Construction Costs
Change Order                          7
6
Three change orders for a total of $177,620.
5
Risks                                4
Authorized funds should be adequate to cover fabrication costs of      Dollars [Millions] 3
the new design elements. The amount will be refined and finalized in    2
second quarter 2009.                                  1
0
Budget Transfers                            Initial  Change Orders  Spent
None

Photo


SEAPORT
Port of Seattle 1Q 2009 Report  69

SECOND QUARTER REPORT, 2009
East Marginal Way Grade Separation
Project: Public Expense   FAST Corridor funded project;     Status Snapshot Prior Report
102007      FHWA, State, City with Port      Delayed Schedule 1Q 08
Budget: $50,700,000     commitment of $18.8 mil. Scope is  Forecast Overrun 1Q 08
Phase: Construction     to construct grade separation in    No Change Orders
Start: 5/2006            vicinity of T5 and T18 to minimize   Total Change Orders Amount:
truck traffic/rail conflicts.            $0
Completion: Q4 2010
Budget/Costs Incurred
Significant Developments
Seattle City Light relocation efforts continue with pole foundation
contract award. Expected relocation complete in late August 2009
instead of June as previously anticipated. Funding partners continue
to express concern but have accepted current plan to advertise
project for bids per Port Commission authorization.
Schedule
Completion schedule revised due to utility relocation delay. Plan
advertisement date is May 2009. Expected substantial project
completion is delayed an additional quarter to 2Q11 due to
Construction Costs
recloation of existing light poles.
Budget
Budget overrun anticipated due to projected cost increases of Seattle
City Light facilities relocations and inflation factor of associated
delay. Commission authorization received March 24 for increased
Port funding. Column relocation construction contract has been
terminated to reduce cost obligation to complete the project.
Change Order
None
Risks
Additional delays trending to increase overall project costs based
upon uncertain inflation factors. Seattle City Light cost estimates are
increasing and schedule slipping.
Budget Transfers
Potential transfers from other Port FAST Corridor commitments
SEAPORT
70  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Terminal 46 ZPMC Gearboxes
Project:   Expense      This project is for the           Status Snapshot
103705, 103706,103707    implementation of contingency     On Schedule
Budget: $1,227,000      plans to keep the three port owned  On Budget
Phase: Construction     ZPMC cranes located at Terminal   No Change Orders
Start: 8/22/2007          46 operating while the           Total Change Orders Amount:
cause of failing gearboxes is       $0
Completion: 12/31/2009
investigated
Budget/Costs Incurred
Significant Developments                      1
0.9
Spare gearboxes and parts have been purchased and are being       0.8
stored in anticipation of the next failures. Have received some new      0.7
0.6
information regarding potential root cause of failure, which will assist
0.5
in determining final resolution.                               Dollars [Millions] 0.4
0.3
0.2
Schedule                             0.1
0
Crane 81 has been trending toward failure mode based on vibration       Authorized  Forecasted Costs incurred
testing and hours of operation. We are continuing to work with our
consultants, the designer, and the manufacturer to identify failure
Construction Costs
cause and determine permanent fix.
No Major Construction
Contracts
Budget
Project spending to date includes purchase of spare gearboxes and
parts, reimbursement to tenant for costs incurred to make repairs,    Photo
and monthly monitoring of vibrations and oil quality to document
failure trends.
Change Order
None this quarter.
Risks
Additional gearbox failures would result in further disruptions to
operations.
Budget Transfers
None

SEAPORT
Port of Seattle 1Q 2009 Report  71

FIRST QUARTER REPORT, 2009 
T5/T18 Maintenance Dredging
Project:   Expense     Mechanically dredge up to 6,900 cy   Status Snapshot
103835/103838        of sediment along approximately    On Schedule
Budget: $2,937,000     4,900' of berths at T18 and dispose   Under Budget
Phase: Construction    of the dredged material at approved  No Change Orders
Start: Feb 2008         upland disposal sites; Conduct      Total Change Orders Amount:
environmental testing, permitting,     $0
Completion: Feb 2010
and design work for T5 maintenance
dredging
Significant                                Budget/Costs Incurred 
Developments
Completed T18 Maintenance Dredging in February.
Schedule
T5 Maintenance Dredging: Due to expense budget constraints, only
limited design and permitting work is planned for 2009. Final design
is delayed to 2010, and construction completion will be delayed from
February 2010 to February 2011.
Budget
T18 Maintenance Dredging completed well under budget due to     Construction Costs
significantly lower construction bid amount. Commission authorized   None
total budget for T18 Maintenance Dredging is $2,257,000. Total cost
after all closeout activities are complete is expected to be just under
$900,000.
Change Order
N/A
Risks
N/A
Budget Transfers
N/A

SEAPORT

72  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Barge Layberth Improvements - Terminal 25/
Pier 28/Terminal 46
Status Snapshot
Improvements to the fendering and  On Schedule
Project: Expense 104011-3  terminal systems at Terminal 25,   On Budget
Pier 28 and Terminal 46 to provide
Budget: $300,000                          0 Change Orders
viable barge layberth use at these
Phase: Construction                        Total Change Orders Amount:
sites.
Start: 10/14/08                                   $0
Completion: 10/31/09
Significant Developments                    Budget/Costs Incurred
Terminal 25 construction started, design complete for fender pile
work at Pier 28 & Terminal 46. All permits received for fender pile
work.
Schedule
Terminal 25 fenced berth to be completed by 5/1/09. Fender pile
repairs to begin when fish window opens in 8/09.
Budget
Project within budget.                                  Construction Costs
Change Order
None this quarter
Risks
None identified this quarter
Budget Transfers
None
Photo



SEAPORT
Port of Seattle 1Q 2009 Report  73

FIRST QUARTER REPORT, 2009 
Radio Frequency Identification (RFID)
Status Snapshot
Project:   E104066      RFID Phase 2 (2008-2010):      On Schedule
Budget: $578,035       Expansion of RFID project to     On Budget
Phase: Planning        additional terminals and rail     0 Change Orders
Start: 10/14/2008         facilities within the Port of Seattle   Total Change Orders
Completion: 12/31/2010   harbor area.             Amount:
$0
Significant Developments
Budget/Costs Incurred 
Memorandum of Agreement with Port, SSA and eModal database
service was completed on 3/31/09.
Schedule
Late February, Seaport Container Management decided to place this
project on hold. The business group is working with the Terminal
Operators on the policies for the Clean Truck program. RFID will be
included with the future program, once the Memorandums of
Agreement have been signed the direction of this project could
change. Expected agreement timeframe is late June.
Construction Costs
Budget
The current program budget is $578,035. 86.5% is grant funded and
13.5% is Port funded.
Change Order
There were 0 change orders this quarter.
Risks
Phase I pilot program infrastructure may not be compatable with the
to Phase II infrastructure. 
Budget Transfers
None

SEAPORT

74  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009 
SBM Renewal and Replacement
Project: C001706, C001769, Address deteriorating conditions   Status Snapshot
C001716           and market demands. New     On Schedule
Budget: $80,000,000     monolithic floats, replace Admin.  On Budget
Phase: Construction     Building & N. end restroom.     149 Change Orders
Start: 1997             Upgrade utilities, access control   Total Change Orders Amount:
system, site improvements in the   $6,299,064
Completion: 4/30/2010
central area, enhance fuel
detection system.
Significant
Budget/Costs Incurred 
Developments
All major construction, handrail and esplanade paving sections are      80
complete. Design concept for interim pad site complete,
60
Commission approval of revised scope.
Dollars [Millions] 40
Schedule
20
Interim Pad Site improvements to be complete by 12/31/09.
0
Budget                               Authorized Forecasted Costs incurred
No change this quarter.
Construction Costs
Change Order 
60
None this quarter.
50
Risks                                40
None identified this quarter.                                 Dollars [Millions] 30
20
Budget Transfers
10

0
Initial    Change Orders    Spent



REAL ESTATE

Port of Seattle 1Q 2009 Report  75

FIRST QUARTER REPORT, 2009 
Central Waterfront Utility Upgrade
Project:   C800006      Upgrade existing P66 Heating     Status Snapshot Prior Report 
Budget: $617,353       Ventilation Air Conditioning (HVAC)  Delayed Schedule 4Q 08 
Phase: Construction     and Direct Digital Control (DDC)   On Budget
Start: 5/2007            system.                    No Change Orders
Completion: 11/30/08                         Total Change Orders Amount:
$0
Significant Developments
Budget/Costs Incurred 
Consultant equipment & configuration is complete. An 'S' contract
was issued to the consultant to improve the system functionality.       0.7
0.6
Schedule                             0.5
The project is expected to be completed late 2Q 09.               Dollars [Millions] 0.4
0.3
Budget                             0.2
0.1
Forecast at budget
0
Authorized    Forecasted   Costs incurred
Change Order
None
Construction Costs
Risks
0.6
None
0.5
Budget Transfers                          0.4
None                                  Dollars [Millions] 0.3
0.2

0.1

0
Initial    Change Orders    Spent



REAL ESTATE

76  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009 
T 102 HVAC Renewal/Replacement
Project:   C800070      Replace HVAC System at all four   Status Snapshot Prior Report 
Budget: $1,300,000      buildings at the Harbor Marina    Delayed Schedule 4Q 08 
Phase: Construction     Conference Center          On Budget
Start: 10/2/2005                                  No Change Orders
Completion: 12/1/2008                        Total Change Orders Amount:
$0
Significant Developments                    Budget/Costs Incurred 
Permit comments returned from DPD and are being addressed by      1.4
Engineering.                                       1.2
1
Schedule                             0.8
As previously reported the project has been delayed 6 months due to   Dollars [Millions] 0.6
design delays. Estimated completion is June 09.                 0.4
0.2
Budget                             0
Authorized    Forecasted   Costs incurred
Project is on budget
Construction Costs
Change Order
0.6
None
0.5
Risks                                0.4
Rooftop units may fail and need replacing before scheduled          0.3
construction.                                          Dollars [Millions] 0.2
0.1
Budget Transfers
0
None                                     Initial  Change Orders  Spent




REAL ESTATE
Port of Seattle 1Q 2009 Report  77

FIRST QUARTER REPORT, 2009
C15 Sewer Line Upgrades
Project:   C800125      Replace the failing sewer/drain     Status Snapshot Prior Report
Budget: $600,000       lines under the Fisherman's      Delayed Schedule 4Q 08
Phase: Construction     Terminal C-15 West Building     On Budget
Start: 4/1/2008                                   1 Change Orders
Completion: 3/31/2009                         Total Change Orders Amount:
$73K
Significant Developments                    Budget/Costs Incurred
Phase 2 Vactor/Tunnel bids received. 4 bids received, with 3 less      0.7
than engineers estimate.                                 0.6
0.5
Schedule                             0.4
Construction to begin 5/11/2009 with completion expected 6/30/09.     Dollars [Millions] 0.3
0.2
Budget                             0.1
0
Cost to date $385K. Project 80% complete.                      Authorized  Forecasted Costs incurred
Change Order
No new change orders.                             Construction Costs
No Major Construction
Risks                               Contracts
.
Budget Transfers
None




REAL ESTATE
78  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Maximo Enterprise Implementation
Project:   C800003      Implement latest version of       Status Snapshot Prior Report
Budget: $3,680,000      Maximo, merge Aviation and Real   Delayed Schedule 3Q 08
Phase: Implementation   Estate applications onto one     On Budget
Start: 11/25/2007         platform, add service desk module   0 Change Orders
Completion: 12/15/2009   and wireless handheld capabilities.  Total Change Orders Amount:
$0
Significant Developments
Service Management software deployed for ICT Service Desk.      Budget/Costs Incurred
Legacy Ticket system decommissioned.                       Dollars [Thousands]
4000
Vendor selected for Marine and Aviation Upgrade/Consolidation
3500
phase.
3000
2500
Schedule
2000
Delay of 6 months due to product delivery, as reported in the 3rd        1500
quarter report.                                           1000
500
Budget                              0
Authorized   Forecasted  Costs incurred
On Budget
Change Order
Construction Costs
None
Not Applicable
Risks
No signficant risks
Budget Transfers
None




CORPORATE
Port of Seattle 1Q 2009 Report  79

FIRST QUARTER REPORT, 2009
IP Telephony
Project:   C800010      Replacement of our existing phone  Status Snapshot
Budget: $3,726,000      systems with IP Telephony      Delayed Schedule
Phase: Design        technology for all Port of Seattle   On Budget
Start: 7/15/2007          locations. The new system       0 Change Orders
Completion: 8/31/2009    includes new features, eliminates   Total Change Orders Amount:
existing single points of failure, and   $0
reduces our leased circuit costs.
Significant
Developments                        Budget/Costs Incurred
Dollars [Thousands]
Design Complete; Implementation in progress.                  4000
3500
Schedule                             3000
2500
Three month delay in project completion due to unforeseen
2000
dependencies and resource constraints.
1500
1000
Budget                             500
0
On Budget                                      Authorized  Forecasted Costs incurred
Change Order
Construction Costs
None                                 Not Applicable
Risks
No Significant Risks
Budget Transfers
None





CORPORATE
80  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009 
Public Safety Computer Aided Dispatch
Project:   C800015      Implementation of Computer Aided  Status Snapshot
Budget: $2,250,000      Dispatch (CAD) system, including   Delayed Schedule
Phase: Implementation    basic CAD functionality, mobile    On Budget
Start: 2/19/2006          clients, and automated vehicle     0 Change Orders
Completion: 10/1/2009    location.                Total Change Orders Amount:
$0
Significant Developments
The new CAD System was deployed on 5/21/08 in Phase 1 of the    Budget/Costs Incurred 
project. Phase 2 mobility features that deliver location information to        Dollars [Thousands]
2500
Police and Fire laptops has been rescheduled for a fall 2009
deployment.                                      2000
1500
Schedule
1000                                                                                                    Next phase schedule delayed an additional 6 months due to issues
with vendor delivery.
500
Budget                              0
Authorized   Forecasted  Costs incurred
On Budget
Change Order
Construction Costs
None
Not Applicable
Risks
Vendor delivery may continue to delay project.
Budget Transfers
None




CORPORATE
Port of Seattle 1Q 2009 Report  81

FIRST QUARTER REPORT, 2009
Parking System Consolidation
Project:C800066        Consolidate four separate       Status Snapshot
Budget:$250,000       applications supporting different    On Schedule
Phase:Planning        parking programs into a single Port  On Budget
Start: 9/23/2008          Parking System.              0 Change Orders
Completion:9/30/2009                         Total Change Orders Amount:
$0
Significant Developments
Planning has been completed for last phase of project.           Budget/Costs Incurred
Dollars [Thousands)
300
Schedule
250
On Schedule
200

150
Budget
100
On Budget
50
Change Order                           0
Authorized    Forecasted   Costs incurred
None
Risks
Construction Costs
Resource constraints may impact project schedule.             Not Applicable
Budget Transfers
None




CORPORATE

82  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
Human Resources Management System
Project:   C800096      Re-implement the Peoplesoft      Status Snapshot
Budget: $3,750,000      Human Capital Management     Delayed Schedule
Phase: Implementation   system with version 9.0. Re-host   Forecast Overrun
Start: 9/16/2007          application on current           0 Change Orders
Completion: 7/30/2009    infrastructure. Move database to   Total Change Orders Amount:
SQL Server               $0
Significant
Developments                        Budget/Costs Incurred
Completed System, Integration, and Data Migration Test phases of    Dollars [Millions]
4000
Project Test Cycle
3500
3000
Schedule
2500
Additional 2 month delay in project deployment due to business
2000
process complexity and resource availability.
1500
Budget                             1000
500
Forecasting a $550,000 budget overrun due to business process
complexity and resource availability. A request for additional funds       0
Authorized  Forecasted Costs incurred
was presented to Commission on April 21, 2009. The approval will
be reflected in the budget for the next report.
Change Order                         Construction Costs
None                                 Not Applicable
Risks
Resource constraints may continue to impact project schedule but
the team is focused on minimizing disruptions.
Budget Transfers
None



CORPORATE
Port of Seattle 1Q 2009 Report  83

FIRST QUARTER REPORT, 2009
Area Surveillance
Project:   C800118      Replace 52 cameras and network   Status Snapshot Prior Report
Budget: $864,000       infrastructure at eight seaport     Delayed Schedule    4Q 08
Phase: Construction     facilities with new hardware to work  Under Budget       4Q 08
Start: 11/25/2007         with the Puretech system being     0 Change Orders
Completion: 12/30/2009   deployed by Marine Domain      Total Change Orders Amount:
Awareness project.            $0
Significant
Developments                        Budget/Costs Incurred
The construction contract for this project, managed by Seaport PMG,    1000
will be executed with the Marine Domain Awareness project          900
800
700
Schedule
600
Delay of 6 months due to change in engineering and construction       500
400
procurement processes.
300
200
Budget                             100
0
Anticipating a budget under run of $200,000 due to obtaining lower         Authorized  Forecasted Costs incurred
prices for equipment and software.
Change Order
Construction Costs
None                                 $356,000
Risks
Further delay in construction procurement will continue to delay
deployment.
Budget Transfers
None



CORPORATE

84  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009 
Marine Domain Awareness
Project:   C800119      Implement a series of Seaport     Status Snapshot
Budget: $7,130,000      Security projects, including video   On Schedule
Phase: Construction     monitoring, communication and    On Budget
Start: 12/9/2007         access control.               0 Change Orders
Completion: 12/30/2009                       Total Change Orders Amount:
$0
Significant Developments
Construction contract out for bid.                           Budget/Costs Incurred 
MDA Dashboard-Phase 1 deployed.                        Dollars [Thousands]
8000
7000
6000
Schedule                             5000
4000
On Schedule
3000
2000
Budget                             1000 
Project Budget Components include:                         0
Authorized    Forecasted   Costs incurred
? Grant Reimbursement
? 25% Port funded match
? Port funded, non-Grant Eligible employee costs
Construction Costs
As reported in 3rd quarter we are anticipating a budget underrun for   $4,290,000
the Grant Reimbursement Budget Component of $600,000. The
combined Port funded components are on budget.
Change Order
None
Risks
Delay in construction procurement will delay deployment.
Budget Transfers
None

CORPORATE


Port of Seattle 1Q 2009 Report  85

FIRST QUARTER REPORT, 2009
Airport Operations Dashboard
Project:   C800172      Deployment of a web application to  Status Snapshot Prior Report
Budget: $240,000       deliver in a single dashboard     Delayed Schedule 3Q 08
Phase: Close Out      format, metrics and current      On Budget
Start: 9/16/2007          information from multiple airport     0 Change Orders
Completion: 2/28/2009    systems.               Total Change Orders Amount:
$0
Significant Developments
System Deployed. Closing project.                        Budget/Costs Incurred
Dollars [Thousands)
300
Schedule
250
Schedule was delayed five months due to complexity of business
200
requirements and staff turnover, as reported in 3rd quarter 2008
150
report.
100
Budget                             50
On Budget                                    0
Authorized    Forecasted   Costs incurred
Change Order
Construction Costs
None
Not Applicable
Risks
No significant risks
Budget Transfers
None





CORPORATE
86  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
UltraCUSE Implementation
Project:C800223        Replace the current Airport      Status Snapshot
Budget:$1,550,000       Common Use system (CUTE) with  On Schedule
Phase:Implementation    Ultra Electronic's UltraCUSE     On Budget
Start: 9/23/2008          system.                   0 Change Orders
Completion:9/30/2009                         Total Change Orders Amount:
$0
Significant Developments
Equipment received                               Budget/Costs Incurred
Testing with most airlines completed                            Dollars [Thousands]
2000
Ready to begin implementation in April 2009                    1800
1600
1400
Schedule
1200
On Schedule                                   1000
800
600
Budget
400
On Budget                                    200
0
Authorized   Forecasted  Costs incurred
Change Order
None
Risks                               Construction Costs
Not Applicable
Prioritization of airline resources is required for network connectivity
and acceptance testing. If airline applications and network are not
established according to schedule, there will be a delay in the overall
deployment of the project.
Budget Transfers
None



CORPORATE
Port of Seattle 1Q 2009 Report  87

FIRST QUARTER REPORT, 2009
Port of Seattle Internet Redesign
Project:C800319        Create a new Internet web site, and  Status Snapshot
Budget:$500,000       underlying infrastructure, with     Delayed Schedule
Phase:Planning        dynamic content and interactive    On Budget
Start: 1/6/2009           communication tools such as blogs,  0 Change Orders
Completion:On Hold     video, podcasts, discussion forums  Total Change Orders Amount:
and interactive maps.           $0
Significant
Developments                        Budget/Costs Incurred
Project on Hold                                        Dollars [Thousands)
600

500
Schedule
400
Project was put on hold (indefinitely delayed) by Executive Team.
300

200
Budget
100
On Budget
0
Authorized    Forecasted   Costs incurred
Change Order
None
Construction Costs
Risks                               Not Applicable

Budget Transfers
None




CORPORATE

88  Port of Seattle 1Q 2009 Report

FIRST QUARTER REPORT, 2009
External Sharepoint
Project:C800320        Implement Microsoft Sharepoint    Status Snapshot
Budget:$500,000       Services to support multiple      On Schedule
Phase:Design         application consolidation, customer  On Budget
Start: 1/6/2009           collaboration, and system        0 Change Orders
Completion:9/30/2009     integration opportunities.        Total Change Orders Amount:
$0
Significant Developments
Project in Design                                    Budget/Costs Incurred
Dollars [Thousands)
600
Schedule
500
On Schedule
400

300
Budget
200
On Budget
100
Change Order                           0
Authorized    Forecasted   Costs incurred
None
Risks
Construction Costs
New procurement processes for professional service contracts have   Not Applicable
delayed completion of design phase by three months. This impact
may delay overall project delivery.
Budget Transfers
None




CORPORATE

Port of Seattle 1Q 2009 Report  89

Port Commission
Bill Bryant
John Creighton
Patricia Davis
Lloyd Hara
Gael Tarleton
www.portseattle.org       Chief Executive Ofcer
Tay Yoshitani
P.O. Box 1209
Seattle, WA 98111
U.S.A.
206.728.3000
09/2008

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.