9c CIP report

Item Number: 9c_Report
Meeting Date: March 13, 2018



Capital Improvement Projects
Fourth Quarter Report 2017

ii  Port of Seattle 4Q 2017 Report

Port of Seattle
Capital Improvement Project Report
Fourth Quarter 2017
Introduction
The Port of Seattle is a municipal corporation chartered by the State of Washington with the mission to be an economic 
engine for the Puget Sound region and the State. A primary activity of the Port is to create capital assets that allow the 
efficient flow of goods and people into and out of the area. The intent of this report is to provide the public with high 
level information on the status of the Port's capital projects.
Background
During 2017, the Port plans to invest $651,600,000 to expand and upgrade the infrastructure that supports marine and
aviation commerce. Funding for the Port comes mainly from the users of the facilities, including shipping companies,
airlines, rental car companies, concessionaires and public parking. About 2 percent of the Port's capital budget comes
from a tax levy on property in King County. The Tax Levy funds are used selectively for investments in transportation
facilities, real estate capital projects and environmental and noise mitigation projects.
The Port is dedicated to sound stewardship of the resources its customers and the public entrust to it. This means 
accomplishing its mission efficiently, effectively and economically, and making its actions transparent to its business 
partners and the general public.
About the Report
The report will provide general information on the project description, status, significant developments, schedule, 
budget, change orders, risks, budget transfers, and cost growth of construction if it exceeds 10% of contract. The
report may include graphics that report project costs compared to authorization, construction costs (including change
orders (CO)) compared to the construction contract, location maps, and photographs. The Port implements a number
of different types of projects and not all information may be relevant to a specific project; as such, the reports may vary
in detail and content. Project types may range from construction, to noise mitigation, to technology.
The project description includes the project title, project number (Capital Improvement Project (CIP)), project phase, 
and estimated completion date (substantial completion). This section also includes "Project Status" illustrating at a 
glance if the project is on schedule, and within budget, and the date Construction authorization received.
Significant Developments covers items such as accomplishments, significant events or milestones, contract 
advertisements and awards, upcoming activities, and environmental issues.
Schedule includes information on the project schedule, the total schedule variance and variance since the last 
report, contract extensions, and information on critical dates.
Budget addresses the total project budget and includes information on the overall budget status, recent
Commission authorizations, forecasted overruns or savings, and scope changes.
Change Orders provides information on current quarter's COs and total project COs including justification for CO's for
the reporting period and information on any CO over $200,000 or 10% of the contract value.
Cost Growth of Construction provides a brief description of any project with CO exceeding 10 percent.
Risks describe any significant risk of delay, any significant risk to cost, or any significant CO.
Budget Transfers reports any transfers between authorized projects during the reporting period.
Additional information may include graphics indicating budget, construction costs, location, and photographs. These 
reports intend to meet the reporting requirements of Port of Seattle General Delegation of Authority and the 
Commission motion on January 8, 2008' regarding "Reports on Major Capital Projects."
Additional Information
For additional information, please visit the Contact Us page on the Port of Seattle web site to ask a question, make a comment or
request a copy of the State Audit Reports Response and Action Plan.


Port of Seattle 4Q 2017 Report  1

Charts from PowerPoint
Project Title                        Page
Q4 CDD Projects by Status Chart................................................................6
Q4 CDD Projects by Dollar Value Chart......................................................7
Aviation
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C101107 ................160th GT Lot ..........................................................8 ..........................
C102112 ................Hennelly Service Tunnel Renewal Rep .................9 ...........
C102162 ................Air Cargo Road Safety Improvements..................10 ..........
C800019 ...............Gate Utilities Improvement ...................................11 .........................
C800061 ...............Main Terminal South Low Voltage ........................12 ......................... ..................
C800107 ...............C4 UPS System Improvements ............................13 .......... 
C800251 ...............Vertical Conveyance Modernization .....................14 ......................... 
C800335 ...............EGSE Electrical Charging Stations ......................15 .........................
C800483 ...............Aireld Pavement Program ..................................16 ..........
C800538 ...............Utility ER Backup Standby ....................................17 ..........
C800549 ...............SSAT Interior Renovations ...................................18 .........................
C800556 ...............NorthSTAR North Satellite Lobbies ......................19 ..........
C800583 ...............International Arrivals Facility ................................20 ..........
C800585 ...............Wi-Fi Enhancement for Ramp and Terminal ........21 ..........
C800605 ...............Security Exit Lane Breach Control Phase II .........22 ......................... 
C800612 ...............Checked Baggage Recap/Optimzation .............23-24 ......................
C800638 ...............Dining and Retail Infrastructure Modernization ....25 .........................
C800642 ...............CCTV Camera Data Improvements ....................26 ..........
C800655 ...............IWS Segregation Improvements ..........................27 ..........
C800688 ...............Construction Logistics Expansion ........................28 .........................
C800692 ...............2016 Fuel System Modications...........................29 .........................
C800695 ...............C3 Holdroom Expansion ......................................30 ......................... 
C800697 ...............Concourse B, C and D Restroom Upgrades ........31 ..........
C800699 ...............Electric Utility SCADA Utility .................................32 ......................... .................... 
C800702 ...............2015-2016 C Concourse Roof Repl .....................33 .........................
C800716 ...............Central Terminal Stairs .........................................34 .........................
C800717................N. Terminal Utilities Upgrade................................35 .........................
C800722 ...............CTE HVAC ............................................................36 ..........
C800724 ...............Concourse C New Power Center .........................37 .........................
C800743 ...............South Sattelite Terminal Renovation ....................38 ......................... 
C800760 ...............Auburn Mitigation Rd Removal .............................39 .........................


2  Port of Seattle 4Q 2017 Report

Aviation, cont.
Overall Project Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C800761 ...............Concourse B Ramp Level Holdroom ....................40 ............................................ 
C800762 ...............Telecommunications Meet Me Room ...................41 ..........
C800769 ...............Concourse D Hardstand Terminal ........................42 ..........
C800771 ...............D6 Gate Modications ..........................................43 .........................
C800781 ...............SSAT Narrow Body Conguration........................44 ..........
C800784 ...............Emergency Generator ..........................................45 ........................ ..................
C800793 ...............PLB Renew and Replace Phase 2 .......................46 ..........
C800798 ...............SSAT HVAC Infrastructure Upgrade ....................47 ..........
C800801 ...............Variable Frequency Drive .....................................48 ..........
C800818 ...............SSAT Structural Improvements ............................49 .........................
C800825 ...............Interim Baggage System Program .......................50 .........................
C800826 ...............ARC Flash Hazard Mitigation ...............................51 ..........
C800833 ...............Holdroom Seating For Concourses B and C ........52 .........................
C800834 ...............Ground Based Augmentation System Upgrade ...53 ......................... 
C800841 ...............Tenant Telecommunications DEMARC Upgrade .54 ..........
C800842 ...............AOA Perimeter Fence Line Standards Comp    55 ......................... .................... 
C800846 ...............ADR Kiosk Program Expansion 1 ........................56 ..........
C800858 ...............Checkpoint 5 Wall Replacement ..........................57 .........................
C800862 ...............Terminal Security Enhancements ........................58 ..........
C800873 ...............Concourse B Gate Reconguration .....................59 ..........
C800880 ...............Employee Security Screening ..............................60 ......................... 
C800886 ...............Central Terminal Enhancements ..........................61 ......................... 
C800898 ...............Airport Signage Phase 1 ......................................62 ..........
C800913 ...............Concourse B IWS Upgrade .................................63 ..........
C800914 ...............Taxiways ABLQ Improvements ............................64 ..........
C800917 ...............ST Walkway and Bridge Improvements ...............65 ..........
E104395-6 ............Lora Lake ..............................................................66 ..........
U00225 .................Flight Corridor Safety Prog Ph 1 ..........................67 .........................
U00239 .................NERA Program .....................................................68 ..........
U00356 .................Flight Corridor Safety Program Phase 2 and 3 ....69 ..........
U00370 .................Automated Passport Control Kiosk - Ph 3............70 .........................
Other Aviation
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C200007 ...............Highline School Noise Insulation ..........................71 .........................
C800154 ...............Tenant Reimbursement ........................................72 ..........


Port of Seattle 4Q 2017 Report  3

Maritime
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C800355 ...............Shilshole Bay Marina Paving ................................73 ..........
C800356 ...............Shilshole Tenant Service Buildings .....................74 .........................
C800525 ...............FT Redevelopment Phase I ..................................75 ..........
C800526 ...............FT Net Sheds 3, 4, 5 & 6 Roof Replacement .......76 ......................... 
C800531 ...............FT Docks 3, 4, 5 & 6 Fixed Pier Impr ...................77 ..........
C800675 ...............P91 South End Fender .........................................78 ..........
C800829 ...............T-91 C173 Building Roof Overlay .........................79 ..........
C800895 ...............T-18 Stormwater Outall Renewal & Repl ..............80 ..........
C800910 ...............T-91 StandoBarges ............................................81 ..........
C800993 ...............Salmon Bay Marina Uplands Improvements ........82 ..........
E104324 ................Viaduct Construction Coordination ......................83 .........................
U00218 .................P66 Alaskan Way Street Improvements ...............84 ..........
Economic Development
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C800196 ...............T-102 Roof and HVAC ..........................................85 ..........
C800813-105257 ..P66 Elevator 3 & 4 Control ...................................86 ..........
C800813-105261 ..P66 Elevator 2 Control System ............................87 ......................... 
C800888 ...............P69 Solar Panel System .......................................88 ..........
C800889 ...............BHICC Interior Modernization ..............................89 ..........
Joint Venture
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C102858 et al ....... Street Vacations T-5/18/105 ..............................90-91 ......................
C800546 ...............Argo Yard Truck Roadway ....................................92 ..........
C800620-U00064 T-46 Permit Mitigation ..........................................93 .........................
E102007 ................East Marginal Way Grade Separation ..................94 ......................... 
U00289 .................T-5 Pile Removal ..................................................95 ..........




4  Port of Seattle 4Q 2017 Report

Corporate
Overall Project     Variance
Status
CIP Number   Project Title                   Page       Schedule  Budget
C800162 ...............ID Badge Replacement ........................................95 .........................
C800728 ...............Parking System Replacement ..............................96 ......................... 
C800729 ...............Vessel Moorage System .......................................97 .........................
C800747................Project Delivery System .......................................98 ..........
C800748 ...............Remote Data Ctr Business Continuity ..................99 .........................
C800776 ...............POS Website Redevelopment .............................100 ........................ 
C800782 ...............Airport Subway Info Displays ..............................101 .........
C800788 ...............Airport Data Network Switch Upgrade ................102 ........................
C800790 ...............Checkpoint Wait Time..........................................103 ........................ 
C800800 ...............SEA Smartphone App .........................................104 ........................
C800827 ...............STIA Communication Infrastructure ....................105 ........................
C800835 ...............South Loop Train Displays ...................................106 ........................
C800907 ...............Supplier Outreach and Procurement System .....107 .........
C800908 ...............Enterprise Network Firewal Upgrade .................108 .........
C800909 ...............PeopleSoft Financials Upgrade ..........................109 .........
C800929 ...............Rental Car Facility Fleet Tracking System ..........109 .........

Key Project Status
Project within or ahead of target budget and schedule
Either target schedule or budget are o
Both target schedule & budget are o
Negative Variance Status
New Variance
Previously Reported
Schedule Completion on the Project Reports refers to:
Benecial Occupancy or Last Asset In-Use date






Port of Seattle 4Q 2017 Report  5

6  Port of Seattle 4Q 2017 Report

Port of Seattle 4Q 2017 Report  7

FOURTH QUARTER REPORT, 2017
So. 160th GT Lot Expansion
Project: C101107                     Improve lot drainage and complete      Project Status:
Budget: $4,326,533                   site fencing and landscaping,            Schedule:           Delayed 
Phase: Design                        rehabilitate the Ground Transportation    Budget: On or Under
Start: 2/1/2013                        (GT) Lot building, underground          Status Reset: 9/26/2017
Schedule Completion: 11/16/2018     existing overhead utility lines           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Lot improvements are complete. Final Puget Sound Energy (PSE) bill paid; the
5      4.3
federal income tax issue was resolved. The rehabilitation of the GT Lot
3.6
building, originally deleted, has been added back in and design is complete.          4
3
Schedule                                                         Dollars in Millions  2                  1.4
Project was rescoped at 100% design in 2015, resulting in project delivery            1
delay. Project had building rehabilitation scope restored by the Commission on       0
September 26, 2017. Anticipate advertising for construction bids in Q1 2018.          Authorized Forecasted   Costs
Incurred
Budget
Construction Costs
Port resolved a federal income tax issue with PSE. Commission authorized
None at this time
additional $2,231,533 on September 26, 2017 for the rehabilitation of the GT
Lot building.
Change Order
Current Quarter       Project Total
Number of COs               N/A                 N/A
Amount of COs               N/A                 N/A
Justification for COs: N/A
Risks
Long lead times during construction may further delay the schedule.
Budget Transfers
Amount           From             To
$0


AIRPORT
8  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Service Tunnel Renewal/Replace
Project: C102112                     Project will seismically retrofit and      Project Status:
Budget: $39,505,000                 structurally strengthen the airport        Schedule:           Within or Ahead 
Phase: Construction                 Service Tunnel located between the      Budget: On or Under
Start: 11/4/2012                       Main Terminal and Airport Garage.       Status Reset: 7/25/2017
Schedule Completion: 12/31/2019                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Contractor has started work within the south portion of the Service Tunnel and
$50
along the south portion of the Parking Garage courtesy van drive.                          39.5      39.5
$40
Schedule                                                         Dollars in Millions $30
The project is on schedule.                                                           $20
6.1
$10
Budget
$0
Budget was increased for a second time due to a bid irregularity (high bid).              Authorized Forecasted   Costs
Incurred
Received requested increase of $6 million. High bid was driven by the
complexity of the work, need for tunnel to remain in operation during
Construction Costs
construction, and construction market conditions.
$30
Change Order                                                      24.0
$25
Current Quarter       Project Total            Dollars in Millions $20
Number of COs                0                   1                  $15
Quarter                                                                    Amount of COs               $0                  $0                  $10
Justification for COs: None this quarter.                                               $5             0.0       2.1
$0
Risks                                                                    Initial   Change   Spent
Orders
Certain International Arrivals Facility, Supervisory Control and Data
Acquisition System, and North Terminal Utilities Update project outcomes may  Photo
impact this project. Coordinating project with those efforts as well as Aviation
Operations, Business Development, and Maintenance to minimize impacts to
airport operations.
Budget Transfers
Amount           From             To
$0


AIRPORT
Port of Seattle 4Q 2017 Report  9

FOURTH QUARTER REPORT, 2017
Air Cargo Rd Safety Improvements
Project: C102162                     Improvements along Air Cargo Rd   Project Status:
Budget: 8,819,590             and S 170th St to support Cell      Schedule:        Within or Ahead 
Phase:  Design                      Phone L and roadway operations,    Budget: On or Under
Start:  10/2/2013                       and meet current safety standards.     Status Reset: 7/11/2017
Schedule Completion: 9/11/2020                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Completed consultant selection for design services in November 2017. Began
10                 8.8
contract negotiations with HNTB Corporation and plan to execute the service
agreement in January 2018. Completed an update to the survey base map to         8
support design.                                                                     Dollars in Millions  6
3.6
4
Schedule
2
0.1
Project restarted Q2 2017 and is currently on schedule. Plan to begin design in        0
Q1 2018.                                                                    Authorized Forecasted   Costs
Incurred
Budget
Construction Contract Costs
Project is currently within budget. Overall project budget includes $ of
additional project contingency to address risks. Commission authorization
$2
includes construction of critical pavement repair on Air Cargo Rd ( workw 
Change Order
$1
Current Quarter       Project Total
Number of COs                 0                   0                Dollars in Millions       0.1     0.0     0.0
Amount of COs                $0                  $0                   $0
Initial    Change     Spent
Orders
Risks
Storm Drainage System  portions of the storm drainage system have failed   Photo
and need to be replaced.
Unknown Utilities  widening and sidewalk construction require the
relocation of a number of unknown utilities.
Traffic Growth  completion of the traffic analysis identifies the need for
additional intersection improvements to accommodate growth.
Budget Transfers
Amount           From             To            Air Cargo Rd Pavement Repair
$0
AIRPORT

10  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Gate Utility improvements
Project: C800019                     Upgrade the Concourse B loading       Project Status:
Budget: $15,737,508                bridges to the standard 4 z power.    Schedule:          Delayed 
Phase:  Construction                This will reduce aircraft emissions and   Budget: On or Under
Start:  6/28/2007                      noises improve energy efficiency and     Status Reset: N/A
Schedule Completion: 10/31/2017    save money for the airlines.             (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Concourse B 4 z construction is complete. Motor Generators are installed
20     17.2
and system is in operation at all gates. This will be the final report.
14.4       13.8
Dollars in Millions 15
Schedule
10
Substantial construction completion occurred October 31, 2017.
5
Budget
0
The project is within the existing approved budget.                                      Authorized Forecasted   Costs
Incurred
Change Order
Construction Costs
Reflecting Concourse B 4 z only.
Current Quarter       Project Total              3.5              3.2
3.0
Number of COs                0                   11                   3
Amount of COs                $0                                     Dollars in Millions  2.5
2
Justification for COs: Nothing this quarter
1.5
1
Risks
0.5            0.3
None                                                             0
Initial  Change  Spent
Budget Transfers                                                             Orders
Amount           From              To            MG Set installation photo




AIRPORT
Port of Seattle 4Q 2017 Report  11

FOURTH QUARTER REPORT, 2017
Main Terminal Low Voltage
Project: C800061                  Renewal and replacement of low          Project Status:
Budget: 100,300,000               voltage volts and belowb electrical    Schedule:           Delayed 
Phase: Design                     distribution equipment in the Main         Budget: Forecast Overrun
Start: 6/28/2007                    Terminal.                                 Status Reset: N/A
Schedule Completion: 7/2/2024                                            (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Project was taken to 30% design and has been updated through Q2 and Q3
120
2017 with action to follow in Q1 2018.                                                           100.3
100
80
Schedule                                                         Dollars in Millions 60
The scope of work, schedule and design budget will be revised in Q1 2018.
40
20      8.1                   2.8
Budget
0
The forecast has been revised at the conclusion of the 30% design. An increase          Authorized Forecasted   Costs
Incurred
in budget is expected to be required and will likely exceed the $20.7M budget.
Change Order                                               Construction Costs
Not Applicable
Current Quarter       Project Total
Number of COs                0                   0                Photo
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
This area is a 2 7/365 operation. Sequencing of this work is critical and
electrical power has to be maintained without interruptions. Significant work
growth is possible due to lack of project definition.
Budget Transfers
Amount           From             To
$0



AIRPORT
12  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
C4 UPS System Improvement
Project: C800107                  Replace existing Uninterruptible Power  Project Status:
Budget: $4,010,238               Supply !<=>) System, including         Schedule:          Within or Ahead 
Phase: Closeout                  batteries, with a new system located in    Budget: On or Under
Start: 4/14/2015                    the Airport Combined Communications    Status Reset: CA:CA&+:*
Schedule Completion: 12/8/2017   and Command Center !?C)@               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Started project closec activities, created punchc ist items, started asca 
$5      4.2
and prepared final change orders. This will be the final report.
3.7
$4
2.9
Schedule                                                          $3
Substantial completion achieved on December 8 2017.                     Dollars in Millions $2
$1
Budget
$0
A savings of $500,000 is being forecast on this project.                                  Authorized Forecasted   Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
Number of COs                18                  27                 $2
1.6
Amount of COs             !"# %&')              "%* **+                    1.5
Justification for COs: Higher level of care for Factory and Field Testing and
$2
Static Transfer switch and UPS assembly, reconfiguration of K -. K/0 cabinet   $1
permitting transfer of load from A to B sources.                                    Dollars in Millions $1
0.1
Risks                                                              $0
Initial     Change     Spent
Risk mitigated in Bid with detailed Construction Sequence Plan. Plan                             Orders
developed with involvement of Electric Shop, Commissioning Agent, FF3 and
Construction Management and CC staff. Contractor has used this plan as         Photo
foundation for his schedule. 5/ 6 5/7-6/9 from existing SSS:; November
30, 2016 failure added to scope of the project.
Budget Transfers
Amount           From             To
$0


AIRPORT
Port of Seattle 4Q 2017 Report  13

FOURTH QUARTER REPORT, 2017
Vertical Conveyance Modernization Program - Aeronautical
Project: C800251                  Perform modernization on J existing      Project Status:
Budget: $12,306,408               elevators and M escalators: SSAF, MTBIH    Schedule:           Delayed 
Phase: Construction               MTBEH MTBMH MTBNH MTBOH MTBGH SSB,   Budget: On or Under
Start: 10/25/2011                   SSC. Install new elevators SSM and        Status Reset: 11/11/2013
Schedule Completion: 6/30/2017   SSN. Install cooling packages on 12       (Commission Construction Auth.)
existing hydraulic elevators throughout
Main TerminalP 
Significant Developments                                           Budget/Costs Incurred
Substantial completion was achieved in Q2 2017. Final negotiations and
20
closeout begins with expected completion in Q1 2018.                                   16.4
15
Schedule                                                                     10.5     9.9
10
Construction is complete as of Q2 2017.                                          Dollars in Millions  5
Budget                                                        0
Authorized Forecasted    Costs
The project forecast is within the approved budget; expect savings.
Incurred
Change Order                                               Construction Costs
Current Quarter       Project Total
4.6                  4.8
Number of COs                2                  108                   5
Amount of Cos              BDEGHEIJ             $511,121                 4
Justification for COs: differing site conditions, sequencing of work, and            Dollars in Millions   3
administrative changes.
2
1                0.5
Risks
0
Contractor has exceeded contract time and has failed to complete work on time
Initial    Change     Spent
in 2016.                                                                                          Orders
Budget Transfers
Amount           From             To
$0


AIRPORT

14  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Electrical QRTUVW Support EXUYZ[\V] (EGSE) Electrical Charge Stations
Project: C800335                     Airportgopqr electrical charging      Project Status:
Budget: $30,700,000                 system for electrical ground support    Schedule:           Delayed 
Phase:  Construction                equipment at the Concourses and the   Budget: On or Under
Start:  10/26/2010                     North and South Satellitest              Status Reset: N/A
Schedule Completion: 1/29/2021                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
EGSE Phase 2 Project ^ Concourse A, Concourse B and South Satellite:
Received Concourse A _``d IFB design documents for review in December,    35        30.7
2017. Completed the 360 degree photo presentation and the Regulated              30    25.6
Materials Good Faith. Preparation of Divisions 00 and 01 and Engineeref Cost     25
18.4
estimate is complete.                                                                20
15
Schedule                                                         Dollars in Millions 10
5
Phase 2g Start construction process in Q2 i`_jk Implementation of this project    0
Authorized Forecasted    Costs
will be coordinated with the Concourse C New Power Center Project to                                  Incurred
standardize the design for the new power center in Concourse B. Schedule is
delayed to allow for better coordination with airline alignment and the IAF        Construction Costs
project.                                                                               Not Applicable
Budget
Project forecast is within the approved budget. Request authorization for
construction funds and authority to advertise for construction when the design
and bid documents are complete for EGSE Charger Phase 2 Project.
Phase 1 completed for l_mni``n```k 
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Justification for COs: None this quarter
Risks
Coordinate with other airfield projects and Airline Gate Realignment program.
Budget and schedule may affect project implementation and completion of the
EGSE Phase 2 Project.
Budget Transfers
Amount           From             To
$0
AIRPORT
Port of Seattle 4Q 2017 Report  15

FOURTH QUARTER REPORT, 2017
Airfield Pavement Program
Project: C800483                     This is a multi}~ program to       Project Status:
Budget: $10,300,000                  replace distressed pavement and       Schedule:           Within or Ahead 
Phase:  Construction                 joint seal on the airfield starting in    Budget: On or Under
Start:  5/5/2011                        2016 through 2020.                   Status Reset: 10/25/2016
Schedule Completion: 6/30/2021                                          (Commission Const Auth.)
Significant Developments                                           Budget/Costs Incurred
2017 Airfield Replacement Project was completed in Q3 2017.
12                10.3
10
2018 Airfield Replacement Project was combined with other projects into a
8
single construction contract to minimize impacts to airfield operations. The         Dollars in Millions  6
contract was advertised in Qu 2017 and bid opening was in Q1 vxyz{ 
4
1.5
2
Schedule                                                                             0.8
0
Projects will occur annually through 2020. 2017 project was completed. The            Authorized Forecasted   Costs
Incurred
contract bid opening of vxyz project was in Q1 vxyz and the review of bids is
underway.
2017 Construction Costs
Budget
0.5    0.4
Project is within budget. Work project U003u| has been moved to CIP                                  0.4
0.4
Czxx|yu{         Dollars in Millions 0.3
Change Order                                                  0.2
Current Quarter       Project Total              0.1
0.0
Number of COs                 0                   0
0
Amount of Cos                 $0                   $0                       Initial Change  Spent
Orders
Justification for COs: None at this time
Risks                                                            2017 Photo
More pavements identified needing urgent replacement and added to the scope.
Risk of delay in project delivery due to the bid protest.
Budget Transfers
Amount           From             To
$22,000,000             C800483              C800914


AIRPORT
16  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Alternate Utility Facility 
Project: C800538                     Build and house a new 30MW       Project Status:
Budget: $37,200,000                  electrical backup power generation    Schedule:           Within or Ahead 
Phase:  Construction                 facility for the Airport.              Budget: On or Under
Start:  8/4/2015                                                               Status Reset: 
Schedule Completion: 3/31/2018                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Construction has commenced and is proceeding on schedule. All permits have            37.2
40                35.0
been issued and long lead items procured. Major equipment delivery is              35
underway in Q 2017. Construction is anticipated to complete in Q1       Dollars in Millions 30
25
20                           15.1
Schedule
15
Project is currently on schedule for completion in Q2               10
5
0
Budget                                                          Authorized Forecasted  Costs
Incurred
Project is within budget per the amount authorized by the Commission.
Change Order                                               Construction Costs
Current Quarter       Project Total                   27.9
$30
Number of COs                 0                   1                  $25
Amount of Cos                 $0                   $0                 Dollars in Millions $20
12.9
Justification for COs: N/A                                                            $15
$10
Risks                                                                $5          0.0
Federal regulatory requirements may adversely impact schedule and budget.          $-
Initial    Change     Spent
Orders
Budget Transfers
Amount           From             To
$0




AIRPORT
Port of Seattle 4Q 2017 Report  17

FOURTH QUARTER REPORT, 2017
South Satellite Interior Renovations
Project: C800549                  Modify the mezzanine and concourse    Project Status:
Budget: $6,256,000               levels of the South Satellite to improve    Schedule:          Delayed 
Phase: Construction              the passenger experience.               Budget: On or Under
Start: 11/4/2012                                                              Status Reset: 3/22/2016
Schedule Completion: 6/30/2017                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Escalator panels are currently being installed.
6.4     6.26
Schedule                                                         6.2
Remaining expense work to re escalator panels was delayed due to            5.94
6
production issue during the laminating manufacturing process. Anticipate
5.8                           5.71
completion in Q1                    Dollars in Millions 5.6
Budget                                                       5.4
Authorized Forecasted    Costs
This project is on budget.                                                                                    Incurred
Change Order                                               Construction Costs
Current Quarter       Project Total
4                          3.4
Number of COs                2                   50                  3.5    3.1
Amount of COs             ($2,185)             $295,294                3
2.5
Justification for COs: Varying site conditions, design changes.                      Dollars in Millions   2
1.5
Risks                                                                1
0.5                0.3
Risks have been mitigated during construction.                                        0
Initial    Change     Spent
Orders
Budget Transfers
Amount           From             To            Photo
$0




AIRPORT
18  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Satellite Renovation and  Lobbies
Project: C800556                  Renovation and expansion of the North   Project Status:
Budget: $670,671,192              Satellite  including NSAT         Schedule:           or Ahead 
Phase: Construction               Satellite Transit System  stations     Budget: On or Under
Start: 7/24/2012                     ramp level, Concourse level,     Status Reset: 
Schedule Completion: Q3 2021    and ne rooftop airline lounge.           (Commission Construction Auth.) 
Significant Developments                                           Budget/Costs Incurred
Executed remaining Base Building subcontracts and conformed document set                TOTAL
670.6      670.6
issued. Phase 1 basement concrete is complete and started structural steel            700.0
erection. North Satellite escalator replacement started  NS4 removal.       Dollars in Millions 600.0
500.0
Decision made for HP to procure and install Holdroom Case and install
400.0
Port purchased PLBs. Rain harvest tanks are installed and buried.         300.0
Submitted LEED application to US"                   200.0         108.8
100.0
Schedule                                                           0.0
Authorized Forecasted   Costs
Coordinate and monitor  Taxi ect and NSAT Phase 1 opening.             Incurred
Finalize direction for Phase 2 ground board operations and Concourse C
vertical core STS station upgrades. Finalize agreement for Port/AS cost sharing   Construction Costs
items.
500     453.6
Budget
400
Commission authorized overall budget of  Capital and      Dollars in Millions 300
$12,300,000 Expense for a total of $670,621,192. Subse" transfer of
200
$50,000 from C STS Display Upgrade brings overall
100                          51.5
budget/authorization to $670,671,192.                                                              9.0
0
Change Order
MACC   Change   Spent
Orders
Current Quarter       Project Total
Number of Cos                61                                  Photo
Amount of Cos              $665,106             $9,072,206
Justification for COs: E varying site conditions Contract scope changes
Risks
Maintaining budget and schedule due to further changes, errors and omissions,
differing site conditions, customer service and unforeseen events during
construction. Challenge of construction phasing for maximum gate availability
during construction
Budget Transfers
Amount           From             To
$50,000              C              C
$0
Transfer of $50,000 for STS Display Upgrade at Concourse C STS Station
AIRPORT
Port of Seattle 4Q 2017 Report  19

FOURTH QUARTER REPORT, 2017
International Arrivals Facility (IAF)
Project: C800583                  Planning, design, and construction of a     Project Status:
Budget:    ne Federal pection Services (F  Schedule:    or Ahead 
Phase: Design                     facility including a pedestrian       Budget: On or Under
Start: 6/25/2013                    connecting the South Satellite and seven     Status Reset: 12/8
Schedule Completion: 6/30/2020   Concourse A gates to the ne         (Commission Authorization to start
Design & Construction)
Significant Developments                                           Budget/Costs Incurred
Revie of  design completed. The Design/Build team (DB), Clark/SOM, is
761.5      761.5
proceeding  design and procurement. Ninety percent of the  (by value)   800
has been bid out. Started ma construction of the main building and Sterile       700
Corridor.
600
500
Schedule                                                         Dollars in Millions 400
300
153.1
200
The ect remains on schedule. The DB baseline schedule completion for
100
Phase 2 is 2nd Quarter 2020.                                                         0
Authorized Forecasted   Costs
Incurred
Budget
The DB is over the Target Budget. The DB and the Port are exploring
Construction Costs
opportunities to align the design to the overall budget goal. The  
Maximum Price ( timetable is ad to allo both parties to agree that  700
573.0
the risks and opportunities presented are sufficiently identified and addressed.        600
$101M in additional Commission Authorization  obtained in August to       500
support DB design,  and sub a and Port management costs Dollars in Millions 400
until the  is negotiated.                      300
200                         86.0
100
Change Orders                                                             6.4
0
Current Quarter       Project Total                  Initial   Change   Spent
Orders
Number of COs                                   22
Amount of COs            $3,751,379           $ 
Justification for COs: O added scope on  Lot added DB fee on
previous design change orders
Risks
Potential cost and schedule impacts from forecasted shortages of materials and
skilled labor in the current robust Seattle construction market remains a risk.
Programming and scope changes driven by dynamic operational environment
and emerging customer/stakeholder interests and re
Budget Transfers
Amount              From                To
$0
AIRPORT
20  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
W Enhancement
Project: C800585                     Upgrade Wi system in the public     Project Status:
Budget: $10,676,000                 and ramp operational areas of the        Schedule:           Within or Ahead 
Phase: Construction                 Airport. Provide micro m w w       Budget: On or Under
Start: 11/4/2012                       cabinets on the ramp of each             Status Reset:
Schedule Completion: 10/2/2018      concourse to extend communications     (Commission Construction Auth.)
infrastructure.
Significant Developments                                           Budget/Costs Incurred
Construction for Concourse C and the Main Terminal is complete. Construction
12     10.68      10.68
for Ramp Wi on Concourse A, B, C, D, and the South Satellite is nearing
10
completion. Bids for Phase II Wi in the Baggage Claim, BagB G     Dollars in Millions 8
Marie Lindsey Hall, and Satellite Transit System Stations due in February.
6                           4.60
Design for passenger loading bridges and South Satellite interior moving
4
f Bard from 3 
2
0
Schedule
Authorized Forecasted    Costs
Incurred
The p ect is on schedule.
Budget                                                      Construction Costs
The p ect is B w budget.               2.75
3.00
2.50
Change Order                                                2.00
Current Quarter       Project Total            1.50
1.37
Number of COs                11                  13                1.00
Amount of COs             $3               $3               0.50  Dollars in Millions             0.03
0.00
Justification for COs: Changed conditions.
Initial     Change     Spent
Orders
Risks
Unforeseen conditionsc p ect team has mitigated through a thorough revieB 
of site conditions including opening up B and ceilings.
Budget Transfers
Amount           From             To
$0



AIRPORT
Port of Seattle 4Q 2017 Report  21

FOURTH QUARTER REPORT, 2017
Security EE L Breach Control  Phase 2
Project: C800605                     Installation of automated security     Project Status:
Budget: $11,100,000                  breach control ee'()*#+& at exits to   Schedule:           Delayed 
Phase:  Design                      ConcourseC, A, C and North and      Budget: On or Under
Start:  10/15/2015                      South Satellite Transit System         Status Reset: 7/12/2016
Schedule Completion: 1/31/2020      exits.                               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Design and procurement engineered building systems design build document              11.1      11.1
12.000
preparation underr !" 
10.000
8.000
Schedule
6.000
ProP#%& schedule delayed as design and procurement document development has                     3.1
4.000
taken longer than anticipated.
2.000    Dollars in Millions
0.000
Budget
Authorized Forecasted    Costs
ProP#%& is on budget.                                       Incurred
Change Order                                               Construction Costs
Current Quarter       Project Total          None at this time
Number of COs                 0                   0
Photo
Amount of Cos                 $0                   $0
Risks
Need to ensure that existing conditions have not significantly changed.
Budget Transfers
Amount           From             To
$0




AIRPORT
22  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Checked Baggage Recapitalization/Optimization
Project: C800612                  TSA approached the Airport in 2012      Project Status:
Budget: $445,050,000              l/:; plan to replace all federally ol0K<0:A In addition the >.-Mect          Status Reset: N/A
Schedule Completion: 2/28/2025   replaces the remainder of the outbound     (Commission Construction Auth.)
baggage system.
Significant Developments                                           Budget/Costs Incurred
Phase 1 MaM-. construction
The follol/01 activities are currently underl24 in the Central Terminal ramp    500       445.1
area:                                                                                   400
Concrete and curb demolition in the ramp area is nearing completion5      Dollars in Millions 300
Electrical and mechanical infrastructure relocations and installation is
200     136.3
ongoi015
100
The nel building bump out slab and curb l266 have been completed5                             33.8
Micro piles installations at the ramp leading to the basement have been       0
Authorized Forecasted    Costs
completed5                                                       Incurred
Pre7/09:2662:/-0 meetings for soil nail and shotcrete have been held l/:; 
the contractor5                                              Construction Costs
Chilled l2:<. piping relocation in the basement has started and is
ongoi015                    60 52.0
Contractor has started mechanical and plumbing installation in B             50
Concourse ramp area for nel maintenance locker and break area5           40
Steel erection for the north and south elevator pits has been completed5     Dollars in Millions  30
Conveyor header steel installation has started5 and                         20
8.3
Delivery of nel conveyor has been arriving -079ite.                        10         0.4
0
Initial  Change  Spent
ProM<=: coordination l/:; other Port and Tenant >.-Mects is ongoing.
Orders
Phase 2: Consultant and sub7=-09s6:20:9 have been -079ite investigating right
of l249 and reviel/01 existing conditions. They have also been l-.?/01 on
construction se@s<0=/01A
Schedule
Phase 1 is one month behind the original baseline schedule (approved in April
DFHIJ5 ;-lever, Substantial Completion is still anticipated in Q3 2019.
Phase 2 l/66 continue l-.?/01 on construction se@s<0=/01A
All phases are scheduled to be complete in Q1 2025. Consultant and sub
consultants have been on site investigating right of l249 and reviel/01 existing
conditions. They have also been l-.?/01 on construction se@s<0=/01A

Port of Seattle 4Q 2017 Report  23

Budget
The NOQRect is currently authorized for $136 million of the $445 million Budget
for completion of Phase 1 and design of Phase 2.
Change Order
Current Quarter       Project Total
Number of COs                2                   S
Amount of Cos              $135,316             $370,020
Justification for COs:
Modify utilities T Unforeseen site conditions
Accelerate phase 2 manual encode into phase 1 T Reduce risk to operations
Risks
Continuity may be lost betbUUV the different phases of the NOQRect.
EXYZN[UV\ manufacturers may differ betbUUV phases, reXYZOZV] Port
Maintenance creb^ to maintain and replace many models of eXYZN[UV\_
ShutdobV^ may impact airline operations if they last longer than
anticipated.
Budget Transfers
Amount           From             To
0







AIRPORT
24  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Dining and Retail Infrastructure Modernization
Project: C800638                  Pro|}~y is to provide infrastructure       Project Status:
Budget: $14,889,000              modifications, re}xx of spaces,     Schedule:          Delayed 
Phase: Construction              and one neu Children Play Area in     Budget: On or Under
Start: 10/28/2014                   support of the Airport Dining and         Status Reset: N/A
Schedule Completion: 6/30/2020   Retail concessions plan.                 (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Design Package `a is dggh complete. Construction to support Lease ijknq `t     14.89  14.89
16
continues for scopes of ukjv that can be completed uxyzkny impacting existing   14
tenants.                                                                               Dollars in Millions 12
10
8
Schedule                                                                            4.90
6
As the construction schedule depends on the leasing schedule, impacts to that        4
2
schedule have delayed construction from the plan. Construction ux{{ be able to     0
support the revised leasing schedule.                                                    Authorized Forecasted   Costs
Incurred
Budget
Construction Costs
Currently on budget, but delays may impact budget due to escalation and
Not applicable
extended overhead.
Change Order
Current Quarter       Project Total
Number of COs                0                   0
Amount of COs                $0                  $0
Justification for COs: N/A
Risks
Construction is linked uxyz leasing, unforeseen site conditions
Budget Transfers
Amount           From             To
$0 


AIRPORT

Port of Seattle 4Q 2017 Report  25

FOURTH QUARTER REPORT, 2017
CCTV Camera and System Enhancement
Project: C800642                  Add cameras and improve the video      Project Status:
Budget: $13,000,000              management system at the Airport.       Schedule:          Within or Ahead 
Phase: Construction              Pro funded by a TSA Other          Budget: On or Under
Start: 11/4/2012                    Transaction Agreement (OTA)            Status Reset: 5/23/2017
Schedule Completion: 12/29/2018                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Ramp cameras contract has been closed out. Construction of Terminal Building
13.00      13.00
camera installations under The video management system upgrade is       14
progressing and the cutover to the ne system is under              12
Dollars in Millions 10
8
Schedule                                                                            5.36
6
Pro is on schedule. Pro team evaluating means to ensure completion of     4
OTA grant funding  may re additional          2
0
Authorized Forecasted    Costs
Budget                                                                        Incurred
The ect is  budget.
Construction Costs
Change Order
1     0.84                 0.87
Current Quarter       Project Total
0.8
Number of COs                5                   4
Amount of COs                                            0.6
Justification for COs: Design changes.                                              Dollars in Millions  0.4
0.2
0.08
Risks                                                                0
The ect team is revie as information and site conditions in order      Initial Change  Spent
Orders
to understand variances.
Budget Transfers
Amount           From             To
$0



AIRPORT
26  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
I Segregation Improvements
Project: C800655                     Install  Total  Organic  Carbon  (TOC)  Project Status:
Budget: $1,142,000                   analyzers  into  the  exisiting  Industrial   Schedule:          Within or Ahead 
Phase:  Design                      Waste conveyance system serving   Budget: On or Under
Start:  8/1/2016                        the Terminal Areas of the Airport.           Status Reset: n/a
Schedule Completion: 2/13/2019                                               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Design completed November 21, 2017. A" Airport Building Department       1.1    1.1
1.2
building permit to be issued. Port Construction Services has scheduled cre to
on the ect during the dry season.                                                  Dollars in Millions  1
0.8
0.6
Schedule
0.4                           0.20
Design  completed on schedule, ect is scheduled for completion in     0.2
Q3 2019.                                                                  0
Authorized Forecasted    Costs
Incurred
Budget
Design: $407,000                                                          Construction Costs
Construction: $735,000                                                       Not Applicable
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Justification for COs: None at this time
Risks
Risk to ect Weather.
Budget Transfers
Amount           From             To
$0



AIRPORT
Port of Seattle 4Q 2017 Report  27

FOURTH QUARTER REPORT, 2017
Construction " Expansion
Project: C800688                     The expansion and reconfiguration of     Project Status:
Budget:                   the existing construction logistics         Schedule:          Delayed 
Phase:  Closeout                    facilities (including the contractor         Budget: On or Under
Start:  8/1/2014                        parking lot and associated bus stops),       Status Reset: 2/23/2016
Schedule Completion: 9/30/2017      and the renovation of Port field offices.     (Commission Construction Auth.) 
Significant Developments                                           Budget/Costs Incurred
Construction is complete and completion memos have been issued for the
12.0
Contractor Parking Lot (CPL), Logistics Lots, Field Office Renovation, and                10.0
10.0                8.6        8.1
CPL Bus Stops. CPL has been closed out. Logistics Lots  closed out in Q4.   Dollars in Millions  8.0
Field Office Renovation and CPL Bus Stops are in closeout. The replacement
6.0
field office (changed scope)  placed into use in December.
4.0
2.0
Schedule
0.0
The overall ect  delayed  completion dates of Q1 2017 for CPL Bus    Authorized Forecasted Costs
Incurred
Stops (delays due to  and errors and omissions), and Q4 2017 for the
replacement field office (delay due to scope change and procurement).
Construction Costs
Budget
6
4.9
Pro forecast is  the revised budget. Returned  in final closeout
5                          4.4
savings for Logistics Lots in Q4. Anticipate additional final closeout savings
4
Field Office Renovation ($121,000 in Q4  and CPL Bus Stops
3
($142,000 in Q2                    Dollars in Millions 2
1
Change Order                                                             0.1
0
Current Quarter       Project Total                  Initial   Change   Spent
Number of COs                0                   69                             Orders
Amount of COs                $0                $99,533
Justification for COs: None this rter.                                           Photo
Risks
None
Budget Transfers
Amount           From             To            Replacement Field Office
$0
Cost of Construction Gro
CPL Bus Stops: Additional ect contingency  included  the ect
budget for n substandard pavement section risk. T change orders
issued representing  of the original contract value.
AIRPORT
28  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Fuel System Modifications
Project: C800692                     There is a 2016 ect and a 2017    Project Status:
Budget: $14,480,000                  ect. The addition of fuel pits      Schedule:           Delayed 
Phase:  Construction                 accommodates gate reconfiguration   Budget: On or Under
Start:  3/31/2017                       and oo te operations.               Status Reset: 9/13/2016
Schedule Completion: 7/31/2017                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Pro is complete. This is the final report.
16     14.5
14
Schedule                                                          12          10.5
Dollars in Millions                               9.3
Waiting for the ect closeout.                          10
8
6
Budget                                                        4
2
Pro is  the authorized budget. 2017 Fuel System Modifications ect
0
returned $2,200,000 in savings in the 1st rter of 2017.                      Authorized Forecasted  Costs
Incurred
Change Orders for 2016 Fuel System Modifications
Current Quarter       Project Total          2016 Fuel SS Modification
Number of COs                 0                   17               Construction Costs
Amount of COs              $0.00             $371,149.72                   2.8
3                    2.6
Justification for COs: None this rter.                                               2.5
2
Change Orders for 2017 Fuel System Modifications                    Dollars in Millions  1.5
Current Quarter       Project Total               1
0.4
Number of COs                12                  31                  0.5
Quarter                                                                   Amount of COs            $19,909.50           $129,272.74               0
Initial  Change  Spent
Justification for COs: Provide Instrument Valves revise pneumatic test                         Orders
pressure re reconciliation of CO reconciliation of Bid Item 
additional  re to mitigate the impact to schedule caused by an    2017 Fuel SS Modification
unanticipated e procurement time and value Engineering Cost     Construction Costs
Proposal Settlement.
5
4.1             4.2
Risks                                                                4
None                                                             3
Budget Transfers                                                   Dollars in Millions   2
1
0.1
Amount           From             To
0
$300,000                                            Initial Change  Spent
Orders
AIRPORT

Port of Seattle 4Q 2017 Report  29

FOURTH QUARTER REPORT, 2017
C3 H Expansion
Project: C800695                     Provide a 1,500 sf building addition  Project Status:
Budget: $6,300,000                   to increase the size of Gw C3        Schedule:           Delayed 
Phase:  Design                      passenger holdroom. Provide 1,130    Budget: On or Under
Start:  4/4/2016                        sf renovation of existing holdroom.    Status Reset: 7/11/2017
Schedule Completion: 8/31/2019                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Building permit revier process rw completed. Design team revisions have
7.000      6.30        6.30
been completed.
6.000
5.000
Schedule
4.000
Due to designer continuity challenges, the completion of the p ect design has   3.000
fallen behind schedule.                                                            2.000   Dollars in Millions                           0.70
1.000
Budget                                                      0.000
Authorized  Forecasted     Costs
On budget                                                                                     Incurred
Change Order                                               Construction Costs
Current Quarter       Project Total          None at this time
Number of COs                 0                   0
Amount of COs                $0                  $0
Risks
None at this time
Budget Transfers
Amount           From             To
$0




AIRPORT
30  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Concourse B, C, and D Restroom Upgrades
Project: C800697                     Renovate eight sets of public         Project Status:
Budget: $33,047,000                  restrooms on Concourses B, C, and    Schedule:           Within or Ahead 
Phase:  Design                      D. Increase the size of a portion of    Budget: On or Under
Start:  7/12/2016                       the existing restrooms" build ne       Status Reset: 9/12/2017
Schedule Completion: 1/19/2022      restrooms" build space for displaced   (Commission Construction Auth.)
existing tenant functions" and
enlarge the building to add one
additional ne set of restrooms.
Significant Developments                                           Budget/Costs Incurred
Construction for the first phase is under Design for the remaining ect            33.0
$35.0
is 3 complete. The initial phase of restroom design is 6 complete.
$30.0
$25.0
Schedule                                                        $20.0
Pro P is on schedule.                            $15.0
7.6
$10.0   Dollars in Millions
Budget                                                       $5.0                 1.1
$0.0
Pro P is budget.               Authorized Forecasted Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
Number of COs                 0                   0
2
Amount of COs                $0                  $0                        1.5
1.5
Risks
1
Air handling capacity limits on Concourse C may re ! P additional to
ensure that there is enough air for additional restrooms.                              Dollars in Millions  0.5
0.0        0.1
0
Budget Transfers                                                         Initial   Change   Spent
Orders
Amount           From             To
$0
Photo


AIRPORT

Port of Seattle 4Q 2017 Report  31

FOURTH QUARTER REPORT, 2017
Electric Utility SCADA
Project: C800699                     Install a Supervisory Control and     Project Status:
Budget: $9,600,000                   Data Ace1.s.*.-4 (SCADA) system    Schedule:           Delayed 
Phase:  Design                      for the Airportms 12.47 kV Medium    Budget: Forecast Overrun
Start:  8/5/2015                        Voltage (MV) +-#er distribution      Status Reset: 8797:;<=
Schedule Completion: 7/29/2019      net#-,n&                            >Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
One hundred percent design revie# is under#$%&                          9.6
10
Schedule                                                          8
Pro'()* is behind schedule due to change in +,-'ect management and a period of   6
inactivity due to a shortage of resources.                                             Dollars in Millions  4
1.6                   1.5
2
Budget
0
The estimate at completion exceeds the original budget estimate. The budget           Authorized Forecasted   Costs
Incurred
increase is primarily related to market conditions and complexities #.*/ the
Po#(, Centers control systems interface.
Construction Costs
Not Applicable
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Justification for COs: None at this point. 
Risks
Controls #.00 be added to an existing electrical system that includes several
manufacturersm ee1.+2(4*& Unplanned shutdo#4s may be mitigated through the
Construction See1(4).45 Plan.
Budget Transfers
Amount           From             To
$0



AIRPORT
32  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Concourse B ? C Roof Replacement
Project:  C800770 ,C800702        Overlay the existing roof system        Project Status:
Budget: $13,183,000                (approximately T\Y@AA SF of roofing     Schedule:           Delayed 
Phase:  Construction              system on Concourse B and T]YAAA SF   Budget: On or Under
Start:  3/1/2010                      on Concourse C)^ install a neC            Status Reset: 1/24/2017
Schedule Completion: 6/25/2018    elastomeric roofing system^ ladders      (Commission Construction Auth.)
and fall protection^ and replace and
refurbish the existing skylight
CDE_`CaCNbbMK 
Significant Developments                                           Budget/Costs Incurred
Concourse C complete. Roof overlay on Concourse B is about @AB complete.        13.18   13.18
14
Construction has been suspended to avoid continuing roof replacement into the
12
CDEFIJK Anticipate reLMFNJFDEO and completing construction in Q2 QARTK                 10
8
5.33
Schedule                                                          6
4
Contract has been suspended over the CDEFIJ months.               Dollars in Millions 2
0
Budget                                                          Authorized Forecasted  Costs
Incurred
ProUIVF is CDFWDE budget.
Change Order                                               Construction Costs
5.7
Current Quarter       Project Total             6
Number of COs                6                   12                  5
Amount of COs             $55,245              $XTYZ[@
3.9
4
3
Risks                                                             Dollars in Millions  2
Unforeseen site conditions and adverse CINFWIJK                1      0.1
0
Initial     Change     Spent
Budget Transfers                                                              Orders
Amount           From             To
$0




AIRPORT
Port of Seattle 4Q 2017 Report  33

FOURTH QUARTER REPORT, 2017
Central Terminal Stairs
Project: C800716                     Build thf stairht}u near the central  Project Status:
Budget: $2,910,000                   checkpoint to provide egress          Schedule:           Delayed 
Phase:  Construction                 capacity from the mezzanine level     Budget: On or Under
Start:  2/15/2015                       to the ticketing level on the xfx~       Status Reset: 9/13/2016
Schedule Completion: 6/30/2017      secure side of the airport.             (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Beneficial Occupancy has been issued, lighting has been added under the stairs
3      2.9        2.9
and the cdfgect has been closed out. This hijj be the final report.
2.9
Schedule
2.8
2.7
Complete                                                             Dollars in Millions  2.6                   2.5
2.5
2.4
Budget
2.3
Progklq htu completed hiqvix budget             Authorized Forecasted Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
Number of COs                05                  16                2.0000    1.6             1.5
Amount of COs             ($76,062)            ($49,237)             1.5000
Justification for CO: Cost associated hiqv completing Work after Substantial
1.0000
Completion.
0.5000
Risks                                                              0.0000   Dollars in Millions
Initial     Change     Spent
None at this time.                                                                   yz{|zzz
Orders
(0.049)
Budget Transfers
Amount           From             To            Photo
$0




AIRPORT
34  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
North Terminal Utilities Upgrade Project
Project: C800717                     Replace and extend the steam,        Project Status:
Budget: $21,335,000                  condensate and chilled           Schedule:           Delayed 
Phase:  Construction                 supply and return piping from the     Budget: On or Under
Start:  9/21/2010                       Central Mechanical Plant to the end    Status Reset: N/A
Schedule Completion: 8/30/2019      of mechanical room four and to the    (Commission Construction Auth.)
ends of the South and West Loops 
Significant Developments                                           Budget/Costs Incurred
The  end early  ect mechanical construction contract  
25                21.3
a in Q2 2017. Commission authorized a contract duration extension for
the early  construction contract in Q3 2017.                   20
15
9.3
Schedule                                                         Dollars in Millions 10
Construction of the  end early  ect started Q4 2017. Ninety    5        2.2
percent design of the main ect is due Q4 2017. The schedule  delayed to   0
accommodate a change in the contracting method of the utility tunnel.                  Authorized Forecasted   Costs
Incurred
Budget
Construction Costs
Commission authorization to increase the ect budget is likely needed to
complete entire ect due to additional scope associated  the D Concourse
$2.0
Hardstand and Service Tunnel ects. Cost estimates are still in development.
$1.5
1.1
Change Order
$1.0
Current Quarter       Project Total            Dollars in Millions $0.5
Number of COs                 0                   0
0.0        0.0
Amount of Cos                 $0                   $0                   $-
Initial    Change     Spent
Orders
Risks
chedule and budget can be at risk due to the need to route large sections of        Photo
pipe through densely developed areas of the airport. Risks to be minimized
during design.
Budget Transfers
Amount           From             To
$0


AIRPORT
Port of Seattle 4Q 2017 Report  35

FOURTH QUARTER REPORT, 2017
Central Terminal Infrastructure Upgrade
Project: C800722                     Install HVAC, elevators, stair    Project Status:
Budget: $16,834,000                  for mezzanine levels of the central     Schedule:          Within or Ahead 
Phase:  Construction                 terminal. Reconfigure tenant spaces   Budget: On or Under
Start:  5/8/2015                        on the Concourse level of the          Status Reset: 6/27/2017
Schedule Completion: 4/30/2020      central terminal in order to improve    (Commission Construction Auth.)
customer service and experience.
Significant Developments                                           Budget/Costs Incurred
Pro bid opening  November 14, 2017. Lo bid  8.77% below the
20
engineers estimate. Construction contract was awarded.                                   16.8      16.8
Schedule                                                         Dollars in Millions 15
10
Project is now within schedule.
5
Budget                                                                          1.3
0
Project is now within budget.                                                           Authorized Forecasted   Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total          Not Applicable
Number of COs                 0                   0
Amount of Cos                 $0                   $0                Photo
Justification for COs: None at this time
Risks
Risks to project: Delayed reopening of the south tenant spaces due to project
contractor construction delays, tenant design and contractor delays.
Budget Transfers
Amount           From             To
$6,190,000             C800638              C800722




AIRPORT
36  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Concourse C New Power Center
Project: C800724                   Add ne 3200A double ended unit       Project Status:
Budget: $10,500,000                substation on Ramp level at column       Schedule:           Delayed
Phase:  Design                    line F/40 for a ne electrical room in     Budget: On or Under
Start:  10/26/2014                   Concourse C. Existing distribution        Status Reset: n/a
Schedule Completion: 11/29/2019  panels  be re from the ne         (Commission Construction Auth.)
er center, ne distribution panels
and branch circuit panels  be added. 
Significant Developments                                           Budget/Costs Incurred
Ninety percent design is complete and revie is under Engineer cost
12                 10.5
estimate for the ninety percent design revie is complete and  ect probable
10
cost is  the approved budget.
8
Schedule                                                          6
One hundred percent design bid documents are scheduled for completion Q1       Dollars in Millions  4     2.0
" Construction completion scheduled for Q4 2019. Standardization of               2                             0.8
ma electrical of e  caused design completion delays, but reduced     0
Authorized  Forecasted    Costs
further risks/cost increases by ensuring that ne electrical e   fit in             Incurred
the existing space.
Construction Costs
Budget
Not Applicable
The budget forecast, based on  design revie is  approved budget.
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
Airline  Realignment program and other ects may affect Concourse C
Ne Po Center Pro Budget and/or schedule may be affected if site
conditions differ from record files.
Budget Transfers
Amount           From             To
$0
AIRPORT

Port of Seattle 4Q 2017 Report  37

FOURTH QUARTER REPORT, 2017
South Satellite (SSAT) Terminal Renovation
Project: C800743                      Programing, planning, design and    Project Status:
Budget: TBD                      construction for renovation of the     Schedule: Delayed 
Phase:  Planning                     SSAT                            Budget: On or Under
Start:  Q1 2017                                                               Status Reset: N/A
Schedule Completion: TBD 
Significant Developments                                           Budget/Costs Incurred
Planning and programing efforts continue on a range of options including full
renovation and shorter" programs to address needs in the facility for the      6
4.6
next 10  15 years.                                       5
4
Schedule                                                         Dollars in Millions 3
1.7
2
Q4 2017 Port" goal to recommend a preferred design concept  not met.
1
By the end of Q2  ect team  identify a full range of options for
0
consideration.                                                                          Authorized Forecasted   Costs
Incurred
Budget                                                           Construction Costs
This ect  included in the   2022 capital budget and plan of finance None
preliminary estimated total cost of $600 million. This estimate  be
refined as the scope and timing of the ect is more clearly understood.       Photo
Peak Hour Operation
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                  $0
Risks
TBD
Budget Transfers
Amount            From              To
$0
Cost of Construction Growth
N/A
AIRPORT


38  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Auburn Mitigation Road Removal
Project: C800760                     Wetland mitigation site              Project Status:
Budget: $720,000                     enhancements, including installing    Schedule:          Delayed 
Phase:  Construction                 perimeter chain fence and        Budget: On or Under
Start:  8/1/2017                        converting interior paths/roads to      Status Reset: 6/2
Schedule Completion: 12/15/2017     forest.                              (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Construction started on schedule in August 2017, and road removal has been
0.8      0.7        0.7
completed. Contract for fence construction is scheduled for Authorization on        0.7
March 13th.                                                                 Dollars in Millions 0.6
0.5
0.4                            0.3
Schedule
0.3
Fencing  scheduled for October 2017, but delay in contract procurement has   0.2
0.1
pushed start date into April  Construction is scheduled for completion by   0
July 31,                    Authorized Forecasted Costs
Incurred
Budget
Construction Costs
The ect forecast is  the approved budget and authorization
Not Applicable
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Risks
None at this time
Budget Transfers
Amount           From             To
$0



AIRPORT

Port of Seattle 4Q 2017 Report  39

FOURTH QUARTER REPORT, 2017
Concourse B Ramp Level 
Project: C800761                     Construct a ramp level holdroom on  Project Status:
Budget: $5,548,000                   Concourse B to serve airline          Schedule:           Delayed 
Phase:  Construction                 passengers bussed to and from        Budget: Forecast Overrun
Start:  4/12/2015                       remotely parked flights at             Status Reset: 11/
Schedule Completion: 2/28/2018      hardstands.                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Temporary occupancy received. Anticipate activating the site in Q1                  5.9
6
Additional funds  be re in order to address several elements of the
5.8
ect. Additional budget authorization  be re in Q1                 Dollars in Millions         5.5
5.6
5.4
Schedule                                                                             5.1
5.2
The ect remains behind schedule due to a number of factors including site
5
conditions and design changes.
4.8
Authorized Forecasted    Costs
Budget                                                                        Incurred
The ect budget  need to be increased in order to address changed site
conditions, changed design elements and additional scope re     Construction Costs
Change Order                                                 3.5                 3.2
2.8
3
Current Quarter       Project Total            2.5
Number of COs                2                   21                Dollars in Millions  2
Amount of COs             $64,743             $262,673              1.5
1
Justification for COs:
0.5                 0.3
0
Risks                                                                   Initial   Change    Spent
Orders
Additional budget  be re in order to complete the ect.
Budget Transfers
Amount           From             To
$0



AIRPORT
40  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Telecommunications Meet Me Room
Project: C800762                     Airport Telecommunications "   Project Status:
Budget: $3,928,000                   Me Room is a gateg to the         Schedule:           Within or Ahead 
Phase:  Design                      internet and alloga q ck, reliable,    Budget: On or Under
Start: 11/20/2016                      and costc netgn             Status Reset: 9/26/2017
Schedule Completion: 2/4/2020        connections for all of the airport a      (Commission Construction Auth.)
tenants
Significant Developments                                           Budget/Costs Incurred
Selected A/E from IDIQ contract.
5.000
3.93        3.93
Schedule                                                        4.000
On schedule                                                               3.000
2.000
Budget                                                       Dollars in Millions                    0.67
1.000
On budget
0.000
Authorized  Forecasted     Costs
Change Order                                                                  Incurred
Current Quarter       Project Total
Number of COs                 0                   0               Construction Costs
Amount of COs                $0                  $0               None at this time
Risks
None at this time
Budget Transfers
Amount           From             To
$0





AIRPORT
Port of Seattle 4Q 2017 Report  41

FOURTH QUARTER REPORT, 2017
Concourse D H Terminal
Project: C800769                     Construct a 32,500 SF building       Project Status:
Budget: $38,400,000                  using the alternative public W w      Schedule:           Within or Ahead 
Phase:  Construction                 design/build method to support       Budget: On or Under
Start:  2/28/2016                       passengers bused to and from          Status Reset: 9/27/2017
Schedule Completion: 6/30/2018      airline flights parked at remote        (Commission Construction Auth.)
hardstands.
Significant Developments                                           Budget/Costs Incurred
Sloping WalkW construction to complete in February. Holdroom Hardstand         38.4    38.4
40.000
excavation complete and floor slab to complete in February.                      35.000
30.000
Schedule                                                        25.000
20.000
ProP is on schedule.                           15.000 Dollars in Millions            7.4
10.000
5.000
Budget
0.000
ProP is on budget.                              Authorized Forecasted Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total
Number of COs                 8                   17               30.000
24.28
Amount of COs             $190,276            $226,225.00           25.000
20.000
Risks                                                            15.000
The p Pect schedule is tight.                         10.000           4.91
5.000    Dollars in Millions                    0.23
Budget Transfers                                                  0.000
Initial     Change     Spent
Amount           From             To                      Orders
$0
Photo




AIRPORT
42  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
D6 Gate Modifications
Project: C800771                    Add case !#$ to holdroom, access     Project Status:
Budget: $2,200,000                  control to the exterior door and an       Schedule:           Delayed 
Phase:  Construction               ADA sloped % $ %& from holdroom   Budget: On or Under
Start:  9/20/2015                     to the ramp level for passengers to       Status Reset: 9/12/2017
Schedule Completion: 12/4/2017    gain access to buses to transport them    (Commission Construction Auth.)
to remotely parked aircraft.
Significant Developments                                           Budget/Costs Incurred
Pro is complete. This  be the final report.
2.3
2.2        2.2
Schedule                                                         2.2
Pro is complete.                           Dollars in Millions 2.1
2                            2.0
Budget
1.9
Pro is on budget.
1.8
Authorized Forecasted    Costs
Change Order                                                                 Incurred
Current Quarter       Project Total
Number of COs                 0                   0               Construction Costs
Amount of COs                $0                  $0               Not Applicable
Risks                                                            Photos
None at this time.
Budget Transfers
Amount           From             To
$0





AIRPORT
Port of Seattle 4Q 2017 Report  43

FOURTH QUARTER REPORT, 2017
South Satellite Narrow Body Configuration
Project: C800781                     Planning, design and construction    Project Status:
Budget: $5,500,000                   of three ne' narro' body positions    Schedule:           Within or Ahead 
Phase:  Construction                 at the S. Satellite. Scope includes     Budget: On or Under
Start:  2/23/2016                       ne'< 1 passenger loading bridge       Status Reset: 2/23/2016
Schedule Completion: 6/29/2018      (PLB), 1 fuel pit, a passenger ramp    (Commission Construction Auth.)
at S10, portable ee=(,>0:)? and
pavement marking.
Budget/Costs Incurred
Significant Developments
Construction started. Design advancing '()* overall IAF program.                         5.5       5.5
6
5
Schedule                                                         Dollars in Millions  4
3
On schedule and blends '()* the IAFI+ design and construction schedule. Final
2
design completed in Q2 2017. Due to scheduling updates for the IAF ,-./ect,                      0.9
1
completion of the Narro' Body Pro/01) '(22 be Q2 34567 G9)0 closures '(22 be
0
minimal (one or t'. days) due to the ne' design.
Authorized Forecasted    Costs
Incurred
Budget
Pro/01) is currently '()*(: budget.               Construction Costs
Not Applicable at this time
Change Order
Current Quarter       Project Total
Number of COs                 0                   0                        4.6
5
Amount of Cos                 $0                   $0
4
Dollars in Millions    3
Risks
2
Current gating needs limit the ability to take gates out of service.
0.8
All '.-; takes place outside, '09)*0- could impact construction schedule.        1
0.0
Change in the layout of the SSAT (specifically adding parking positions)         0
Initial    Change     Spent
'(22 trigger an addendum to the SEPA and NEPA for the IAF Pro/01)7
Orders
Budget Transfers
Amount           From             To
$0


AIRPORT
44  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
EmergencE Generator Control Renewal and Replacement
Project: C800784                  Replace and reiNCO\Ct] generator       Project Status:
Budget: $2,640,000               programmable logic controllers          Schedule:          Delayed 
Phase: Design                    (PLCs). Install load bank rRST controls    Budget:        Forecast Overrun
Start: 12/28/2015                   for ^R_X Safety` code reUVRCXD            Status Reset: N/A
Schedule Completion: 10/18/2019  generator load testing.                   (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Design revier is @AB complete, progressing tortCD FAB design.EngineerJK 
4                  3.0
cost estimate is underrtLM
3
Schedule
3
2
Delayed due to NCOQect coordination rRST other NCOQects that are in design or     2
construction phases.                                                               Dollars in Millions        0.8
1
0.3
1
Budget                                                         0
Authorized  Forecasted     Costs
Thirty percent design estimate indicates a budget increase may be reUVRCXDM                    Incurred
Change Orders                                               Construction Costs
Current Quarter       Project Total          Not applicable
Number of COs                0                   0
Amount of Cos                 $0                   $0
Justification for COs: None this UVtrter
Risks
During YAB design, additional iniKZONX rOC[ rtK identified that is expected to
impact NCOQect budget. Current budget forecast shorK an increase from $2.5M
to $2.9M. Completion of @AB cost estimate is underrtLM Consideration for
potential budget increase reUVXKS shall be evaluated during this revierM
Budget Transfers
Amount           From             To
$0



AIRPORT
Port of Seattle 4Q 2017 Report  45

FOURTH QUARTER REPORT, 2017
PLB Renew & Replace Phase 2
Project: C800793                     Replace nine passenger loading      Project Status:
Budget: $10,000,000                  bridges (PLBxyz                     Schedule:           Within or Ahead 
Phase:  Design                                                        Budget: On or Under
Start:  12/17/2015                                                            Status Reset: 2/2{|}~
Schedule Completion: 12/12/2020                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Proposals for PLBs bdfd received from vendors in Q4 2017. Contract abhfjdjk
12                10.0
10
Schedule
8
Proldmo is on schedule to complete in Q4 2020.
6
4      2.3
Budget                                                       Dollars in Millions 2                 0.2
Proldmo is bsousv budget
0
Authorized Forecasted    Costs
Change Order                                                                 Incurred
Current Quarter       Project Total
Construction Contract Cost
Number of COs                 0                   0
Not Applicable
Amount of COs                $0                  $0
Risks
N/A
Budget Transfers
Amount           From             To
$0





AIRPORT
46  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
SSAT  Infrastructure 
Project: C800798                     Replace hot and cold deck fans,      Project Status:
Budget: $13,925,000                  coils and controls  energy         Schedule:           Within or Ahead 
Phase:  Permitting                   efficient ne air handler, coils and    Budget: On or Under
Start:  9/19/2016                       controls.                              Status Reset: 
Schedule Completion: 6/30/2020                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Additional funds  approved in Q4 2017. Advertised in Q4 2017.
14     12.3       12.3
12
Schedule                                                         Dollars in Millions 10
Pro is on schedule                             8
6
4
Budget
2                            0.6
Budget  increased in November to account for market conditions and         0
complexity of the                      Authorized Forecasted Costs
Incurred
Change Order
Construction Contract Costs
Current Quarter       Project Total          Not Applicable
Number of COs                 0                   0
Amount of COs                $0                  $0
Risks
Market conditions and material availability may impact ect costs.
Budget Transfers
Amount           From             To
$0




AIRPORT

Port of Seattle 4Q 2017 Report  47

FOURTH QUARTER REPORT, 2017
Fre" Drive
Project: C800801                     eplace 47 of the oldest Variable  Project Status: Design
Budget: $6,834,000                   Fre" Drives (VFDs) installed   Schedule:           Within or Ahead 
Phase:  Design                      at  Seattle  Tacoma  International   Budget: On or Under
Start:  7/10/2017                       Airport.                              Status Reset: 5/23/2017
Schedule Completion: 11/29/2019                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Fifteen percent bases of design submittal  received on November 17, 2017.
8                 6.8
7
Schedule                                                          6
Design submittal  on schedule.                        Dollars in Millions 5
4
3      2.0
2
Budget
1                            0.1
Design Budget: $2,025,000                                                    0
Authorized Forecasted    Costs
Construction Budget: 
Incurred
Change Order                                               Construction Contract Costs
Current Quarter       Project Total
1
Number of COs                 0                   0
Amount of COs                $0                  $0                  0.8
0.6
Risks
0.4
None                                                          Dollars in Millions  0.2
0.0        0.0        0.0
0
Budget Transfers                                                         Initial   Change   Spent
Orders
Amount           From             To
$0
VFD powering a 350 HP motor




AIRPORT
48  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
SSAT Structural Improvements
Project: C800818                     Improvements to the SSAT          Project Status:
Budget: 4,150,000             building to address structural       Schedule:        Delayed 
Phase:  Construction                 deficiencies based upon design       Budget: On or Under
Start:  12/28/2015                      dead and live loads. Work includes    Status Reset: 
Schedule Completion: 10/6/2018      asbestos abatement.                  (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Completed ready to bid documents in October and advertised for construction
5.0
bids in November. Received and opened three bids in December that ranged                4.2      4.2
from  to  belo the engineer estimate of $1,796,000. Issued and    4.0
retracted notice of intent to a  apparent lo bidder PCL Construction   Dollars in Millions  3.0
due to a contract compliance issue involving the resolution of small business           2.0
re Submitted concourse level  for permits (PCS scope).      1.0       0.5
0.0
Schedule
Authorized Forecasted   Costs
Incurred
The completion of design has been delayed into Q4 2017 due to scope changes
and resource constraints. Contract compliance issue may delay contract
execution currently planned for January                    Construction Contract Costs
$2.00
Budget                                                              1.7
Overall ect budget has increased from $3,600,000 to $4,150,000       $1.50
$300,000 in additional ect contingency to address risks. Commission
$1.00
authorized additional funds on August  2017. Staff anticipates the return of
$300,000 of ect contingency given the good bid results.                Dollars in Millions $0.50        0.0    0.0
$-
Change Order                                                      Initial  Change   Spent
Orders
Current Quarter       Project Total
Number of COs                 0                   0
Photo
Amount of Cos                 $0                   $0
Risks
Pre Delay: Process to obtain airport badges and custom seals
for the Contractor and subcontractors delays the start of construction.
Budget Transfers
Amount           From             To
$0

Column to be Strengthened (Ramp Level)
AIRPORT
Port of Seattle 4Q 2017 Report  49

FOURTH QUARTER REPORT, 2017
C60 Interim Baggage System Project
Project: C800825                  Implement four distinct scope elements   Project Status:
Budget: $$$$$    the ective of increasing  Schedule:Delayed 
Phase:  Construction             reliability and capacity on the C60        Budget: On or Under
Start:  12/13/2015                  baggage system through the interim         Status Reset: N/A
Schedule Completion:             period before the Baggage Optimization    (Commission Construction Auth.)
10/10/2017                        Pro
Significant Developments                                           Budget/Costs Incurred
Security  Tracking Enhancements Pro TSA reimbursed the Port for
14.5     14.2
re change to operations in the C60 Search Room. C60 baggage system
14                13.5
has been operational since substantial completion  achieved in mid 
13.5
Performance improvements resulting from the Re element include      13
12.4
improved diagnostics, increased throughput, and gridlock prevention. TSA        12.5
Search Room Expansion Pro Internal Port resources completed remaining  Dollars in Millions 12
puncist items at contractor cost.                          11.5
Authorized Forecasted    Costs
Schedule                                                                           Incurred
All four elements of this ect  designed on a fast track schedule. The
re contractor completion date for the TSA Search Room Expansion    Construction Costs
delayed until Q1 2017. The completion date for the Re element  
5.4
delayed due to complications during initial TSA testing and a TSA funded             6                5.1
change to C60 operations. The overall ect reached substantial completion in     5
Q4 2017. Pro closeout process  continue during Q1        Dollars in Millions 4
3
Budget                                                          2
udget is  the authorized amount. Pro Savings is being returned.      1    0.1
0
Initial  Change  Spent
Change Order
Orders
Current Quarter       Project Total
Number of COs                2
Amount of COs                                $102,136.34
Justification for COs: Varying site conditions, error/emissions by o and
designer, and regulatory re
Risks
No risks anticipated at this time, contingency funds available if needed.
Budget Transfers
Amount           From             To
$0
AIRPORT

50  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Arc Flash H Mitigation
Project: C800826                     Replace nine medium voltage fused  Project Status:
Budget: $7,533,000                   ss s medium voltage        Schedule:           Within or Ahead 
Phase:  Design                      circuit breakers at six p ser          Budget: On or Under
Start:  9/21/2016                       centers.                               Status Reset: 9/26/2017
Schedule Completion: 12/17/2019                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Design is progressing.                                                                     7.53       7.53
8.000
7.000
Schedule
6.000
On schedule                                                               5.000
4.000
3.000
Budget
2.000    Dollars in Millions
On budget                                                               1.000                     0.12
0.000
Authorized  Forecasted     Costs
Change Order                                                                  Incurred
Current Quarter       Project Total
Number of COs                 0                   0               Construction Costs
Amount of COs                $0                  $0               None at this time
Risks
None at this time
Budget Transfers
Amount           From             To
$0





AIRPORT
Port of Seattle 4Q 2017 Report  51

FOURTH QUARTER REPORT, 2017
Seating for Concourses B & C
Project: C800833                     Replace existing passenger           Project Status:
Budget: $9,300,000                   holdroom seating in Concourses B     Schedule:           Delayed 
Phase:  Construction                 and C. Provide electrical             Budget: On or Under
Start:  9/25/2016                       improvements to support required      Status Reset: 4/11/2017
Schedule Completion: 8/10/2018       wer for new seating.               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Early w to install new seating and electrical wer at G C2 and C3 w     9.3  9.3
10
completed. Design w w completed for remainder of holdrooms in
Concourses B & C.                              8
6
Schedule                                                          4
Construction of early w at G C2 and C3 w completed in November,  Dollars in Millions 2
0.2
ahead of schedule. Balance of ect is behind schedule due to additional        0
design review for seating layout that w required.                    Authorized Forecasted  Costs
Incurred
Budget
Construction Contract Costs
Pro P expenditures are proceeding in accordance w budget.
N ApplicaA 
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                  $0
Risks
None
Budget Transfers
Amount           From             To
$0



AIRPORT
52  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Ground Based Augmentation System (GBAS) Upgrade
Project: C800834                     Upgrade Sea-Tac's Ground Based    Project Status:
Budget: $3,529,000.00                 Augmentation System (GBAS)        Schedule:           Delayed 
Phase:  Design                      from a beta system to a fully         Budget: On or Under
Start:  1/5/2017                        functioning navigational aid.          Status Reset: 9/12/2017
Schedule Completion: 12/31/2020                                         (Commission Const Auth.)
Significant Developments                                           Budget/Costs Incurred
Finalizing contract with Honeywell.                                                      4.6
5
Schedule                                                          4           3.5
Contract negotiations taking longer than anticipated.                                  3
2
Budget                                                       Dollars in Millions 1
0.1
Project is within budget.                                                               0
Authorized Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Contract Costs
Number of COs                 0                   0
Amount of COs                $0                  $0                   1
0.8
Risks                                                              Dollars in Millions  0.6
None at this time.
0.4
Budget Transfers                                                    0.2
0.0        0.0        0.0
0
Amount           From             To
Initial    Change     Spent
$0                                                                     Orders




AIRPORT

Port of Seattle 4Q 2017 Report  53

FOURTH QUARTER REPORT, 2017
Tenant Telecommunications DEMARC Upgrade
Project: C800841                     Scope:                              Project Status:
Budget: $2,815,000                   Standardize tenant network demark    Schedule:           Within or Ahead 
Phase:  Design                      packages for many existing legacy    Budget: On or Under
Start:  2/27/2017                       installations and vacant properties     Status Reset: 9/26/2017
Schedule Completion: 4/28/2021                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Designer is working on 15% design.                                                             2.82
3.000
2.500
Schedule
2.000
On schedule
1.500
1.000    Dollars in Millions         0.72
Budget
0.500                             0.01
On budget
0.000
Authorized  Forecasted     Costs
Change Order                                                                  Incurred
Current Quarter         Project Total
Number of COs                   0                     0                 Construction Costs
Amount of COs                  $0                    $0                None at this time
Risks
None at this time
Budget Transfers
Amount            From              To
$0





AIRPORT
54  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
AOA Perimeter Fence Line Standards
Compliance
Project: C800842                     This project will replace the old 7!    Project Status:
Budget: $5,680,000                   foot AOA fence line with the new     Schedule:           Delayed 
Phase:  Design                      standard height of 1 !"##% plus one    Budget: Forecast Overrun
Start:  1/29/2017                       foot barbed wire at the top.            Status Reset: 6/13/2017
Schedule Completion: 5/31/2019                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
AOA Perimeter Fence Line Standards Compliance project will replace
5.7        5.7
approximately 9800 feet of AOA perimeter fence with 1 !"##% fence plus one     6
foot barbed wire on the top. About 7000 feet of the fence will be replaced with       5
anti!a'()* fence for areas identified by Airport Security. In addition, gate E!      4
105, next to the Airport Rescue and Firefighting Facility, will be replaced with       3
a more secure and faster gate operator to shorten response time by the Fire            2
Department. Sixty percent design was completed in QQ 2017 with 90% design     Dollars in Millions  1                   0.2
due in Q1 2018. The onsite construction is estimated to start in Q4 2018.             0
Authorized Forecasted    Costs
Incurred
Schedule
The onsite construction is estimated to start in Q4 2018. The schedule is           Construction Contract Costs
delayed as more time is needed for design to include the additional scope items.
1
Budget                                                         0.8
Project cost estimate will be updated to include the added scope items to              0.6
replace additional perimeter access gates.
0.4
Change Order
Dollars in Millions   0.2
0.0        0.0        0.0
0
Current Quarter       Project Total
Initial    Change     Spent
Number of COs                 0                   0                             Orders
Amount of COs                $0                  $0
Photo
Risks
Coordination with the both the Transportation Security Agency and Federal
Aviation Administration for approvals of the fence design standards.
Budget increase and project schedule delay due to the added scope to replace
additional perimeter access gates.
Budget Transfers
Amount           From             To
$0
AIRPORT

Port of Seattle 4Q 2017 Report  55

FOURTH QUARTER REPORT, 2017
ADR K+,-. Program E/023-+,3
Project:  C800846                  Install utilities to support (8) new       Project Status:
Budget: $1,240,000                 ADR 45678 locations. (6)               Schedule:           Within or Ahead 
Phase:  Design                    Intermediate 456787 and (2)            Budget: On or Under
Start:  9/26/2017                     Introductory 4567879                     Status Reset: N/A
Schedule Completion: 12/31/2020                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Design work started for the kiosks.
1.4     1.24       1.24
1.2
Schedule
1
Project on schedule.                                                                0.8
0.6
Budget                                                       Dollars in Millions 0.4
0.2                           0.08
Project is within budget.                                                               0
Authorized Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total
Number of COs                0                    0
Amount of COs                $0                  $0
Risks
Unforeseen site conditions. Changes in site use priorities.
Budget Transfers
Amount           From             To
$0




AIRPORT

56  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Checkpoint 5 W:;l Replacement
Project: C800858                     Replace the wall at Checkpoint 5     Project Status:
Budget: $1,200,000                    with a new door system to improve    Schedule:           Delayed 
Phase:  Construction                 the efficiency and customer service    Budget: On or Under
Start:  8/7/2016                        as well as the aesthetic appearance     Status Reset: N/A
Schedule Completion: 3/31/2018      of the checkpoint entry.               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Remaining scope to provide emergency egress doors and signage approved by
1.4      1.2
the Building Department. Construction underway in January 2018.
1.2
1                 0.8
Schedule                                                         0.8                  0.6
The emergency egress doors required additional review. The project is now         0.6
0.4
anticipated to be complete in Q1 2018.                                            Dollars in Millions 0.2
0
Budget                                                          Authorized Forecasted  Costs
Incurred
Within budget.
Change Order                                               Construction Costs
Not Applicable
Current Quarter       Project Total
Number of COs                0                   0                Photos
Amount of COs              $0.00                $0.00
Risks
Security checkpoint operations can impact project construction activities.
Budget Transfers
Amount           From             To
$0                 <=>                 <=>




AIRPORT
Port of Seattle 4Q 2017 Report  57

FOURTH QUARTER REPORT, 2017
Terminal Security Enhancements (TSE)
Project: C800862                   The project includes shatter proofing     Project Status:
Budget: $12,941,000                the windows XYZ[\] I^ and security and    Schedule:           Within or Ahead 
Phase:  Design                    accessibility improvements XYZ[\] __^      Budget: On or Under
Start:  10/8/2017                     for the Main Terminal and Sky bridge      Status Reset: 10/`bc2017
entrances.
Schedule Completion: 6/30/2019                                        (Commission Construction Auth.Phase I)

Significant Developments                                           Budget/Costs Incurred
Ninety percent design plans for Phase I were submitted for review. Completed                     12.9
$14
project definition for Phase II and received approval to incorporate accessibility
$12
improvements into project.                                                        $10
$8      6.3
Schedule                                                          $6
Project on schedule. Upcoming Phase II milestone for Commission                Dollars in Millions  $4
$2                           0.1
Authorization to begin design in Q1 2018.
$0
Authorized Forecasted    Costs
Budget                                                                        Incurred
Project is within budget. The budget for Phase II was increased to address
addition of accessibility improvements.                                           Construction Contract Costs
$15
Change Order
Current Quarter       Project Total             $10
Number of COs                 0                   0
Amount of COs                $0                  $0                Dollars in Millions  $5
0.0       0.0       0.0
Risks                                                                $0
Initial    Change    Spent
Phase I:Glazing ofRMM in Windows
Orders
Phase II: Design of security and access improvement adversely impact curbside
operation along the Departures drive.                                             Photo
Phase I ?@BCDFI PJLIM II SMORT@UV
Budget Transfers
Amount           From             To
$0
Cost of Construction Growth
N/A

AIRPORT
58  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Concourse B Gate Reconfiguration
Project: C800873                     Tenant reimbursement project by     Project Status:
Budget: $9,900,000                    Delta Air hijkl to add two new       Schedule:           Within or Ahead 
Phase:  Closeout                     gates and reconfigure four others at    Budget: On or Under
Start:  1/16/2017                       Concourse B.                         Status Reset: N/A
Schedule Completion: 5/26/2017                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
The project is complete and is in closeout. Record drawings andO        de manuals
12
have been received and approved.                                                      9.9       9.5
10
Dollars in Millions                               7.2
8
Schedule
6
Scope of work is complete and the project is currently in closeout.
4
2
Budget
0
Reimbursement request fg has been received and is currently under review.          Authorized Forecasted  Costs
Incurred
Delta is reviewing a cost issue with a project supplier.
Change Order                                               Construction Contract Costs
Not Applicable
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                  $0
Risks
None identified at this time.
Budget Transfers
Amount           From             To
$0




AIRPORT
Port of Seattle 4Q 2017 Report  59

FOURTH QUARTER REPORT, 2017
mnoqrtuu Securitt Screening
Project: C800880                     Add security screening checkpoints   Project Status:
Budget: $2,950,000                   for employees entering the secure     Schedule:           Delayed 
Phase:  Construction                 areas of the airport.                 Budget: On or Under
Start:  7/3/2016                                                               Status Reset: 11/28/2017
Schedule Completion: 7/31/2018                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Both the south and central screening rooms are operational. Received additional
3.5      3.0        3.0
authorization in fourth quarter to design and construct a new Baggage Service
3
Office for Alaska Airlines to provide space to then construct the North              2.5
Employee Security Screening room. Both are currently in design.                  Dollars in Millions  2
1.5
0.8
Schedule                                                          1
0.5
Project has fallen behind schedule due to design developments uncovered            0
during design.                                                                         Authorized Forecasted   Costs
Incurred
Budget
Construction Costs
Project is within the authorized CIP budget.
Not Applicable
Change Order
Photos
Current Quarter       Project Total
Number of COs                $0                  $0
Amount of COs                $0                  $0
Risks
None identified at this time.
Budget Transfers
Amount           From             To
$0



AIRPORT
60  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Central Terminal Enhancements
Project: C800886                     Provide new passenger charging      Project Status:
Budget: $4,800,000                   station counters, furniture, music      Schedule:           Delayed 
Phase:  Construction                 performance area, waste receptacles   Budget: On or Under
Start:  8/8/2017                        and electrical floor outlets in the       Status Reset: 8/8/2017
Schedule Completion: 7/31/2021      Central Terminal                    (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
The 30% design phase was completed.                                                4.8      4.8
5
Schedule                                                          4
In order to align with other project work in the Central Terminal and provide         3
good customer service, this project schedule has been delayed. Construction          2
and furniture installation will be completed in phases that are coordinated with     Dollars in Millions  1
0.1
the timing of the other construction in the Central Terminal and the phased
0
opening of tenant restaurant spaces.                                                     Authorized Forecasted   Costs
Incurred
Budget
Project expenditures are proceeding in accordance with budget.                   Construction Contract Costs
Not Applicable
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                  $0
Risks
None at this time
Budget Transfers
Amount           From             To
$0



AIRPORT
Port of Seattle 4Q 2017 Report  61

FOURTH QUARTER REPORT, 2017
Airport Signage Phase 1
Project: C800898                     Provide shortvxyz{ improvements    Project Status:
Budget: $8,000,000                   to airport signage and wayfinding     Schedule:           Within or Ahead 
Phase:  Design                                                        Budget: On or Under
Start:  4/4/2016                                                               Status Reset: N/A
Schedule Completion: 3/30/2020                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Design work was started for early work to install dynamic signage in ticketing
10.000
lobby. Initial recommendations from the wayfinding study forthcoming.                            8.00
8.000
Schedule                                                        6.000
On schedule
4.000
0.65
2.000    Dollars in Millions
Budget                                                                           0.02
0.000
On budget
Authorized  Forecasted     Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0               None at this time
Amount of COs                $0                  $0
Risks
None at this time
Budget Transfers
Amount           From             To
$0




AIRPORT
62  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Concourse B I|} ~
Project: C800913                     Install an I flush gutter to         Project Status:
Budget: $1,750,000                   interce ential contaminated       Schedule:            or Ahead 
Phase:  Design                      runoff from aircraft rations on     Budget: On or Under
Start:  10/6/2013                       gates B- through B-9.                Status Reset: 10/ 
Schedule Completion: 12/31/2018                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
The work project was moved from this CIP to CIP C This is the final
2     1.75       1.75
re for this CIP.
1.5
Schedule                                                         Dollars in Millions  1
Transferred to C
0.5
0.04
Budget
0
Transferred to C                  Authorized Forecasted Costs
Incurred
Change Order
Construction Contract Costs
Current Quarter       Project Total
of COs                        0                             0                             1
Amount of COs                0                  0                  0.8
0.6
Risks
0.4
Coordination  Delta for gate closures on Concourse B  continue      Dollars in Millions 0.2
through construction.                                                                      0.0      0.0      0.0
0
Initial    Change     Spent
Budget Transfers                                                               Orders
Amount           From             To
C800913              C800914
AIRPORT
Port of Seattle 4Q 2017 Report  63

FOURTH QUARTER REPORT, 2017
Taxiways A/B/L/Q Improvements
Project: C800914                     Ta A/B Reconfiguration of   Project Status:
Budget: $47,500,000.00                transition and S routes,         Schedule:            or Ahead 
Phase:  Design                      Ta  Relocation and Ta    Budget: On or Under
Start:  10/11/2016                      Q partial hot spot mitigation.          Status Reset: 11/2017
Schedule Completion: 12/31/2018                                         (Commission Const Auth.)
Significant Developments                                           Budget/Costs Incurred
Project is in the final design phase. Coordinating with FAA on review                      47.5       47.5
50
comments and modifications to standards for construction documents. Review
of Engineers Design Report, Construction Safety Phasing Plan and final             40
quantities for construction estimates.                                                  30
20
Schedule                                                         Dollars in Millions 10
1.8
Project is on Schedule  Commission authorization - November 14, 2017;          0
Advertisement  December 11, 2017.  construction in spring and fall of      Authorized Forecasted  Costs
Incurred
" 
Budget                                                      Construction Contract Costs
Budget is currently under revie  final scope and construction quantities.
1
0.8
Change Order
0.6
Current Quarter       Project Total
0.4
of COs                        0                             0
Amount of COs                0                  0                Dollars in Millions  0.2
0.0        0.0        0.0
0
Risks                                                                    Initial   Change   Spent
Orders
Significant coordination bet ects and  other programs,
coordination  FAA, Operations and Airlines regarding required ay   Photo
closure and maintaining schedule regarding FAA grant funding.
Budget Transfers
Amount           From             To
22,000,000                 C800483                   C800914
"             C800913              C800914
AIRPORT
64  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Sound Transit k & Bridge Improvements
Project: C800917                     Interim improvements to the         Project Status:
Budget: $3,500,000                   walkway between the Airport light    Schedule:           Within or Ahead 
Phase:  Construction                 rail station and the Main Terminal     Budget: On or Under
Start:  11/11/2016                                                            Status Reset: 11/22/2016
Schedule Completion: 8/31/2017                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Phase I improvements (painting, wind screens, directional signage, lighting
4      3.5
alignment, floor coating and graphics) are complete. Courtesy cart service           3.5
continues. Under Phase II planning effort evaluating long-term improvements      Dollars in Millions  3
(moving walkways, full enclosure), identified potential building code and           2.5
2                 1.4
structural concerns. These efforts are being postponed at this time. This is the                                1.2
1.5
final report.                                                                                  1
0.5
0
Schedule
Authorized Forecasted    Costs
In Phase I substantial completion reached during Q3 2017. Phase II was also                              Incurred
completed during Q4 2017.
Construction Contract Costs
Budget                                                      Not applicable
Interim improvements were completed within authorized budget.
Photo
Change Order
Current Quarter       Project Total
Number of COs               N/A                 N/A
Amount of COs               N/A                 N/A
Risks
None
Budget Transfers
Completed northern wind screen,
Amount           From             To
signage, graphics and lighting
$0



AIRPORT
Port of Seattle 4Q 2017 Report  65

FOURTH QUARTER REPORT, 2017
Lora Lake Apt MTCA Remediation
Project: 104395, 104396               Remediation of contaminated soils   Project Status:
Budget: $24,300,000                  at Lora Lake Apartments site; and     Schedule:           Within or Ahead 
Phase:  Construction                 Capping and filling of the Lora       Budget: On or Under
Start:  9/26/2010                       Lake establishing wetland area        Status Reset: 9/13/2016
Schedule Completion: 12/31/2018     adjoining Miller Creek.               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Apartment site is complete. Lake site has been winterized and work will
30
resume June/July of 2018.                                                              24.3
25                21.4
Dollars in Millions 20
Schedule
15                           10.8
Phase One is on track and has been completed. Phase two will resume summer
10
of 2018.
5
0
Budget                                                          Authorized Forecasted  Costs
Incurred
Project is within budget.
Change Order                                               Construction Costs
Current Quarter       Project Total              10   8.9
Number of COs                 1                   6
8                    6.8
Amount of COs             $60,000             $135,000
6
Justification for COs: State Route 518 Slope Side Repair.
4
Risks                                                              Dollars in Millions   2
0.1
Monitoring of lake fill settlement and water flow over winter months.                  0
Initial  Change  Spent
Orders
Budget Transfers
Amount           From             To            Photo
$0



AIRPORT
66  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Flight Corridor Safety Program  Phase 1 Port Propert
Project:     Removal of obstructions to  Project Status:
Budget: $5,806,000                   navigable airspace on Port of          Schedule:           Delayed 
Phase:  Construction                 Seattle property at Seattle-Tacoma    Budget: On or Under
Start:  5/31/2015                       International Airport, including        Status Reset: 11/2017
Schedule Completion: 12/31/2017     e replanting and              (Commission Construction Auth.)
revegetating on-site.
Significant Developments                                           Budget/Costs Incurred
All obstructions on Port property have been removed. Received Commission
7
Authorization on November 14, 2017 to increase the project budget in support             5.8       5.8
6
of a new major works construction contract to complete invasive species             5
removal and revegetation of sites P4 and P5 on Port property where trees have      Dollars in Millions  4                       3.0
previously been removed.                                                        3
2
1
Schedule
0
Phase 1 construction was initially delayed due to the Contractor's bid e     Authorized Forecasted  Costs
Incurred
of the Engineer's estimate this required additional Commission action and
delayed Phase 1 construction. The Commission also requested more public
engagement. Phase 1 construction began on  17, 2017 and is on-going.   Construction Costs
Subsequent to the initial delay, additional funding authorization  required to                      1.9
2      1.7
complete the invasive species removal and revegetation  This   
occur in a ne ma  contract in Quarter           1.5
0.9
Budget
1
Additional  budget  approved to complete the Phase 1    Dollars in Millions 0.5
0
Change Order                                                      Initial  Change   Spent
Orders
Current Quarter       Project Total
of COs                                                     12                      Photo
Amount of COs                      
for COs: 1) Removal of unidentified containers and construction
debris 2) P- Redesign Deduction and Additions   Additional Costs
and Reconciliation of CO  P- Redesign Additions.
Risks
Added scope and an additional contract for vegetation management and
replanting could result in additional costs and/or schedule delays.
Budget Transfers
Amount           From             To
0
AIRPORT
Port of Seattle 4Q 2017 Report  67

FOURTH QUARTER REPORT, 2017
North East Redevelopment Area Program
Project: U00239                       This is an FAA funded p ect w   Project Status:
Budget: $5,000,000                   participation from the City of         Schedule:           W or Ahead 
Phase:  Design                      Burien but led by Port. The p ect    Budget: On or Under
Start:  8/16/2015                       is to redevelop the Area north of the   Status Reset: 10/ 1 2 1
Schedule Completion: 8/14/2018      airport in the City of Burien.          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
City of Burien received Transportation Research Board grant to fund
construction of the proposed improvements of Project Segment F. Design           $6     5.0       5.0
consultant agreement was amended to accommodate designs for all project          $5
segments. Eight design packages are being developed for the remaining Project      $4
segments.                                                                    $3
$2                            1.2
Schedule                                                         Dollars in Millions $1
Project is currently on schedule.                                                       $-
Authorized Forecasted    Costs
Incurred
Budget
Project is within budget. The project is funded by $3.8 million dollar FAA        Construction Costs
Grant and participation from the City of Burien and $by the Port. N Design Only
Change Order                                               Photo
Current Quarter       Project Total
N of COs                       N                          N 
Amount of COs               N                  N 
Risks
M design resources of the consultant so that all deliverables are complete
prior to end of grant period August 2 
Budget Transfers
Amount           From             To
0
AIRPORT

68  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Flight Corridor Safety Program Phase 2
and Phase 3
Project: U00356                       Multi-year program to manage       Project Status:
Budget: $2,605,000                   obstructions consisting of trees and    Schedule:           Within or Ahead 
Phase:  Design                      other vegetation off Port property     Budget: On or Under
Start:  1/8/2017                        around Seattle Tacoma                Status Reset: 2/28/2017
Schedule Completion: 12/31/2019     International Airport, and             (Commission Design Auth.)
replanting lower-height vegetation.
Significant Developments                                           Budget/Costs Incurred
Early planning, design and environmental work on-going.
8                 7.2
7
Schedule                                                          6
5
Overall project has been delayed due to Commission request for more public       Dollars in Millions  4     2.6
engagement during Phase 1, which in turn delayed Phase 2.                         3
2
1                            0.4
Budget
0
Project is currently within budget.                                                        Authorized Forecasted   Costs
Incurred
Change Order
Construction Contract Costs
Current Quarter       Project Total
Not Applicable
Number of Cos/                  0                     0
Amount of COs                $0                  $0
Risks
Entering into agreements with other agencies and/or property owners may cause
project delays.
Budget Transfers
Amount           From             To
$0




AIRPORT
Port of Seattle 4Q 2017 Report  69

FOURTH QUARTER REPORT, 2017
Automated Passport Control (APC) K  Phase 3
Project: U                        Install 12 additional APC     Project Status:
Budget: $1,400,000                   and 8 Document V !"# %          Schedule:           Delayed 
Phase:  Construction                 Officer podiums.                   Budget: On or Under
Start:  2/7/2017                                                               Status Reset: &'(
Schedule Completion: 2/28/2018                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Additional required signs have delayed overall completion to Q1 2018.
1.6      1.4
1.4
Schedule
Dollars in Millions 1.2
0.9
1
Project delays were due to the need for additional layout reviews and contractor                              0.7
0.8
staffing issues.                                                                           0.6
0.4
0.2
Budget
0
Project is on budget.                                                                      Authorized Forecasted   Costs
Incurred
Change Order
Construction Contract Costs
Current Quarter       Project Total
Not Applicable
Number of COs                 0                   0
Amount of COs                $0                  $0
Risks
No remaining significant risks.
Budget Transfers
Amount           From             To
$0




AIRPORT
70  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
H)*+,)-. Schools /0)3. Insulation
Project: C200007                     Highline School Insulation Agreement  Project Status:
Budget: ^_`_abcba```   C;9 intended to provide funding for Schedule:   Delayed 
Phase: Construction                 sound insulation for 1d schools that      Budget: On or Under
Start: 3/23/1999                       are impacted by aircraft noise from       Status Reset: J\]
Schedule Completion: 11/30/2021     Sea-Tac Airport                       (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Port funds authorized for availability when the FAA, the State of Washington,
120     102.1      101.8
and the Highline School District (HSD) provide matching funds. Currently
100
working with the FAA and State 4 Federal L5679:;<=>9 to provide a mechanism  Dollars in Millions 80         63.4
for release of federal Airport Improvement Program (AIP) grant funding for
60
this ?>=@ect. The Highline School District passed a bond for the construction of
40
Des A=7B59 Elementary School and Highline High School. Construction at Des
20
A=7B59 Elementary C7:: commence in Q2 DEFGI  Construction at Highline High
0
Scho0l is scheduled to commence in 2019. J=795 testing at these schools C;9           Authorized Forecasted   Costs
completed by the Port in February 2017.                                                                 Incurred
Schedule                                                        Construction Costs
If the FAA is provided a means of funding through federal legislation, then       J=< Applicable
funding for Des A=7B59 Elementary School C=O:P be required in the third
quarter of DEFGQ and Highline High School in the first quarter of 2019.
Budget
The ?>=@ect forecast is C7 of COs                        0                             0
Amount of Cos                 XE                   XE
YO9<7Z7[;<7=B for COs:  J\]
Risks
The current risr is the availability of FAA AIP funding.
Budget Transfers
Amount           From             To
XE
AIRPORT
Port of Seattle 4Q 2017 Report  71

FOURTH QUARTER REPORT, 2017
Tenant Reimbursement
Project: C800154                     Alloh| for the Port to reimburse        Project Status:
Budget: $4,709,577                   tenants for costs that are normally a      Schedule:           mj}ij or Ahead 
Phase: Construction                 landlord responsibility, such as          Budget: On or Under
Start: 8/14/2007                       upgrading currently unleasable space     Status Reset: s
Schedule Completion: TBD         to a leasable condition, or correcting     (Commission Construction Auth.)
code deficiencies hix a tenant
encounters them on a tenant
construction onect.
Significant Developments                                           Budget/Costs Incurred
During Q4, tenant reimbursements were completed for code upgrades                             4.7
5
completed by Delta Air Lines when they built out their offices on the ramp
level of Concourse B and the south Mezzanine in the Main Terminal, as well as      4
a sprinkler system upgrade completed in the hangar building efg hijki is a Port
2.8
3                            2.5
asset due to end of lease reversion.                                                   Dollars in Millions  2
1
Schedule
0
Schedules vary to meet the tenant's needs.                                              Authorized Forecasted   Costs
Incurred
Budget
Construction Costs
Additional Authorization hjll be sought as additional Tenant Reimbursement
sn} Applicable
mnoq is approved.
Change Order
Current Quarter       Project Total
stuvxo of COs                        0                             0
Amount of Cos                 yz                   yz
{t|}j~jk}jn for COs:  s
Risks
snx identified at this time
Budget Transfers
Amount           From             To
yz
AIRPORT
72  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Shilshole Bay Marina Paving
Project: C800355                     Repave areas of Shilshole Bay       Project Status:
Budget: $2,000,000                    Marina not rehabilitated in the 2004   Schedule: Within or Ahead 
Phase: Design                        major capital redevelopment. Full     Budget: On or Under
Start: 1/1/2016                         depth replacement in some failed      Status Reset: N/A
Schedule Completion: 12/31/2018     areas and extensive pavement         (Sponsor Design Auth.)
grinding and overlay.
Significant Developments                                           Budget/Costs Incurred
Ninety percent design complete. Permits submitted with Seattle Department of
2.5
Construction  Inspections (SDCI)                                2.00
1.87
2
Schedule                                                         Dollars in Millions 1.5
to be performed under a single construction contract  SB Tenant          1
Service Buildings (C800356). Target paving schedule is Q3 2018.                 0.5
0.17
0
Budget                                                          Authorized Forecasted  Costs
Incurred
Project is within the approved budget.
Construction Costs
Change Order
Current Quarter       Project Total               1
Number of COs                0                   0                   0.8
Amount of Cos                 $0                   $0                   0.6
Justification for COs: N/A                                                          Dollars in Millions  0.4
0.2
Risks                                                                     0.0     0.0     0.0
0
Work tied with Restroom schedule. Phasing and coordination will be critical
Initial    Change     Spent
on active marina parking areas.                                                                    Orders
Budget Transfers
Amount           From             To
$0



MARITIME
Port of Seattle 4Q 2017 Report  73

FOURTH QUARTER REPORT, 2017
Shilshole Tenant Service Buildings
Project: C800356                     Replacement/rehabilitation of five    Project Status:
Budget: $10,100,000                  restrooms and laundry facilities at     Schedule:           Delayed 
Phase: Design                        Shilshole Bay   by  2017   Budget: On or Under
Start: 1/6/2015                         for .                           Status Reset: 11/2017
Schedule Completion: 12/31/2018                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Ninety percent design complete. Permits submitted with Seattle Department of
12
Construction  Inspections (SDCI).                                  10.10    9.52
10
8
Schedule
6
The overall schedule  tightened due to additional design effort to evaluate
4
and perform preliminary design on the second floor option. Current target is to     Dollars in Millions                         1.20
2
have the ne facilities to be online by mid-2019.
0
Authorized Forecasted    Costs
Budget                                                                        Incurred
Pro is  the approved budget.
Construction Costs
Change Order                                                at this time
Current Quarter       Project Total          Photo
of COs                        0                             0
Amount of Cos                 0                   0
for COs: 
Risks
Schedule and phasing the   in an active site continue to be the primary
risConstruction costs in Seattle continue to be increasing and volatile  
may lead to higher than e" bids.
Budget Transfers
Amount           From             To

MARITIM
74  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
FT Redevelopment Phase I
Project: C800525                     Demolition of net sheds    and    Project Status:
Budget: $4,300,000                   the C-12 Ban Building              Schedule:            or Ahead 
Phase:  Design                      construction of 2 light industrial      Budget: On or Under
Start:  12/1/2009                       buildings, refurbishment of Ship       Status Reset: 
Schedule Completion: 12/31/2019     Supply Building, and associated       (Commission Construction Auth.)
site infrastructure improvements. 
Significant Developments                                           Budget/Costs Incurred
Project SEPA Issued. Ninety percent design for buildings demolition
5
completed and construction (demolition) funding authorized. Master planning            3.99
and 15% design for new buildings completed.                                      4
3.00
3
Schedule                                                         Dollars in Millions  2
Project currently on schedule for demolition of bank and Net Sheds 7 and 8 in                               0.65
1
2018 and start of construction of Gateway Building at Fishermen's Terminal in       0
2019.                                                                          Authorized Forecasted   Costs
Incurred
Budget
Construction Contract Costs
Pro currently  authorized budget.
1
Change Order
0.8
Current Quarter       Project Total
" of COs                        0                             0
0.6
Amount of Cos                 0                   0                 Dollars in Millions  0.4
0.2
0.0        0.0        0.0
Risks                                                                0
Initial    Change     Spent
at this time.                                                                                                   Orders
Budget Transfers
Amount           From             To
0
Cost of Construction Growth
at this time
MARITIM
Port of Seattle 4Q 2017 Report  75

FOURTH QUARTER REPORT, 2017
FT Net Sheds 3,4,5, & 6 Roof Replacement
Project: C800526                     Replace the existing roofing system  Project Status:
Budget: $3,259,000                   on all four Net sheds with new        Schedule:           Delayed 
Phase:  Construction                 security ladders, gutters, and fall      Budget: On or Under
Start:  11/16/2014                      protection system. Install 44          Status Reset: 12/13/2016
Schedule Completion: 11/30/2017     crystalline solar panels at NS 5.       (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Construction is in progress for Net Sheds 3, 4 and 5. Structural frames are in
3.25
3.5
place for the solar panels and are currently active. Inclement weather and                           3.00
3
material delays have hampered the final installation. Net Shed 6 is the last to be
2.5                           1.91
completed.                                                                  Dollars in Millions 2
1.5
Schedule                                                          1
0.5
This project is a little behind schedule due to weather delays.
0
Authorized Forecasted    Costs
Budget                                                                        Incurred
No budget issues anticipated.
Construction Contract Costs
Change Order
2
1.6
Current Quarter       Project Total                                 1.4
1.5
Number of COs                 0                   2
Amount of Cos                 $0                 $10,000               Dollars in Millions   1
Justification for COs: None this quarter
0.5
0.0
Risks                                                                0
Initial    Change     Spent
None                                                                      Orders
Budget Transfers
Photo
Amount           From             To
$0



MARITIM
76  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
FT Docks 3, 4, and 5 Fixed Pier Improvements
Project: C800531                      the e structural piling    Project Status:
Budget: $6,400,000                    Fiber Reinforced Polymer        Schedule:            or Ahead 
Phase:  Design                       on Doc  and determine   Budget: On or Under
Start:  10/10/2017                      need for replacement in  of the    Status Reset: 
Schedule Completion: 4/15/2019      e timber fender system.         (Commission Construction Auth.)
Install cathodic corrosion protection
for steel piles under Doc 
Significant Developments                                           Budget/Costs Incurred
Commission approved Design authorization on October 10, 2017. Design is              6.40      6.40
7
currently underway.
6
5
Schedule                                                         Dollars in Millions  4
The project is on schedule.                                                           3
2
1                           0.05
Budget
0
Projects U00440 (Dock  Fi Pier), Pro U00 (Doc  Fi Pier)    Authorized Forecasted Costs
Incurred
be combined into one Pro number U00 under    and  
Fi Pier Improvements utilizing the e Pro  U00 The
Construction Contract Costs
combining process  finance  ta place shortly.
1
Change Order
0.8
Current Quarter       Project Total
of COs                        0                             0
0.6
Amount of COs                0                  0                Dollars in Millions  0.4
0.2
0.0        0.0        0.0
Risks                                                                0
Initial    Change     Spent
Permit conditions, Facility Operations, Stray voltage and Sole Source.                              Orders
Budget Transfers                                                 Photo
Amount           From             To
U00440            U00379
U00440             U00379
Cost of Construction Growth

MARITIM

Port of Seattle 4Q 2017 Report  77

FOURTH QUARTER REPORT, 2017
T-91 Fender Upgrades
Project: C800675                     Upgrade/replace existing timber      Project Status:
Budget: $4,100,000                    fender system at the South end of      Schedule:           Within or Ahead 
Phase: Design                        Pier 91                             Budget: On or Under
Start: 1/31/2016                                                              Status Reset: 8/8/2017
Schedule Completion: 3/31/2018                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Favorable bids received, contract awarded to American Construction Co.
5     4.10
Schedule                                                          4
In-water work such as pile driving must be accomplished by February 15, 2018      3             2.40
to comply with permit fish window. Construction scheduled to start in Q1 2018,      2
completion by March 31, 2018.                                                Dollars in Millions  1
0.21
0
Budget                                                          Authorized Forecasted  Costs
Incurred
Project is forecast under authorization.
Change Order                                               Construction Costs
Current Quarter       Project Total          Not applicable at this time
Number of COs                0                   0
Photo
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
Procurement and construction schedule still tight. Long lead items such as pipe
piles tighten overall construction project and may be aggravated by material
demands of recovery efforts in other parts of the country.
Budget Transfers
Amount           From             To
$0



MARITIM
78  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
T-91 C173 Building Roof Overlay
Project: C800829                     Overlay the ee J standing seam   Project Status:
Budget: $1,561,000                   metal roof w J a N Single Ply     Schedule:            J or Ahead 
Phase:  Construction                 PP Roof Membrane, including      Budget: On or Under
Start:  9/13/2016                       d wnspouts w J a N Fall          Status Reset: 1/21 
Scheduled Completion: 12/29/2017    Protection system.                   (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
The PVC Membrane Overlay, Gutters and Fall Protection are all complete.
2
Substantial completion issued October 27, 2017. This will be the final report.             1.56      1.56
Dollars in Millions 1.5                           1.16
Schedule
1
Project is on schedule.
0.5
Budget
0
Project is within budget.                                                                  Authorized Forecasted   Costs
Incurred
Change Order
Construction Contract Costs
Current Quarter       Project Total
Number of COs                5                    5
1
Amount of COs             $                                   0.76            0.77
0.8
J J for COs: L  materials and equipment to coat and paint the
entire length of the interior of the roof purlin at the w J roof overhang
0.6
including inclement w J delays.                 Dollars in Millions 0.4
0.2
0.04
Risks
0
N                                                                 Initial   Change   Spent
Orders
Budget Transfers
Photo
Amount           From             To
0
MARITIMM
Port of Seattle 4Q 2017 Report  79

FOURTH QUARTER REPORT, 2017
T-18 Stormwater Outfall Renewal &
Replacement
Project: C800895                     Remove and replace the 13 outfall    Project Status:
Budget: $4,000,000                   pipes and tides gate from the last      Schedule:           Within or Ahead 
Phase:  Design                      downstream manhole to the outlet     Budget: On or Under
Start:  9/26/2016                                                             Status Reset: 4/25/2017
Schedule Completion: 12/31/2020                                         (Commission Design Auth.)
Significant Developments                                           Budget/B InI 
The geotechnical investigation for the project has been completed and design
5
work for the first phase of construction is nearing completion. Permit                              4.00
applications are under review by the tribes and agencies. Construction funding     Dollars in Millions 4     4.00
request authorized in February.                                                      3
2
Schedule
1
0.29
Construction is scheduled to begin on five of the 13 outfalls in the spring of
0
2018.                                                                         Authorized Forecasted   Costs
Incurred
Budget
B C I C B C I B 
Project is within authorization
1
Change Order
0.8
Current Quarter       Project Total
Number of COs                 0                   0
0.6
Amount of COs                $0                  $0                Dollars in Millions  0.4
0.2
0.0        0.0        0.0
Risks                                                                0
Initial    Change     Spent
Delay in receiving in-water permits could delay any anticipated field work                         Orders
Budget Transfers                                                 P 
Amount           From             To
$0
Cost of Construction G 
N/A

MARITIM 

80  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
T-91 Standoff Barges
Project: C800910                     Procure five additional cruise        Project Status:
Budget: $1,100,000                   standoff barges to replace the         Schedule: W$%&$' or Ahead 
Phase:  Construction                 existing unifloats and complement    Budget: On or Under
Start:  3/17/2017                       the existing fleet of ten purchased      Status Reset: 9/12/2017
Schedule Completion: 4/15/2018      in 2 !2"!# currently in use            (Commission Construction Auth.)
Terminal 91
Significant Developments                                           Budget/Costs Incurred
Procurement complete and awarded to PCL. Northwest Steel Fabrication
1.10       1.10
1.2
currently assembling barges.
1
Schedule
0.8
Project is on schedule. Barges to be delivered Q2 2018 to be deployed for 2018
0.6
Cruise season (One season earlier than originally planned in the capital budget)     Dollars in Millions 0.4
0.2                           0.03
0
Budget                                                          Authorized Forecasted  Costs
Incurred
Five barges procured under current authorization. Possibility of sufficient
budget to procure one additional barge within one year (allowed under current    Construction Contract Costs
contract).                                                                             Not Applicable at this time
Change Order                                               Photo
Current Quarter       Project Total
Number of COs                 0                   0
Amount of COs                $0                  $0
Risks
Tight fabrication may mean barges are delivered after first cruise call. Existing
barge fleet can accommodate this, not disruption of cruise anticipated.
Budget Transfers
Amount           From             To
$0



MARITIM 
Port of Seattle 4Q 2017 Report  81

FOURTH QUARTER REPORT, 2017
Salmon Bay Marina Uplands Improvements
Project: C800993- U00471             59> uplands flef industrial          Project Status:
Budget: $2,000,000                   building and associated site           Schedule:           ./03/4 or Ahead 
Phase:  Planning                    improvements.                     Budget: On or Under
Start:  12/6/2017                                                             Status Reset: 12/?@()*A
Schedule Completion: 12/31/2020                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Planning and design to start in 2018 once Miller Hull team is under contract.
2.5
2.0        2.0
Schedule                                                          2
Planning and design: ()*+,()*-             1.5
Construction: 2019-2020                                                      Dollars in Millions  1
0.5
0.2
Budget
0
./03/4 budget.                                                                                        Authorized Forecasted    Costs
Incurred
Change Order
Construction Contract Costs
Current Quarter       Project Total
56789: of COs                        0                             0                             1
Amount of COs                ;0                  ;0                  0.8
0.6
Risks                                                              Dollars in Millions  0.4
5<49 at this time
0.2
0.0        0.0        0.0
Budget Transfers                                                     0
Initial    Change     Spent
Amount           From             To                       Orders
;0
Photo
Cost of Construction Growth
5<49
MARITIM=

82  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Viaduct Construction Coordination
Project: E104324, E104535-38         Participate in the design E           Project Status:
Budget: $2,900,000                   construction of the bored tunnel, FH    Schedule:          Delayed 
Phase: Implementation               E S. portals, Holgate to KOQR St,      Budget: On or Under
Start: 1/1/2009                         Central STUVXYXZQU surface streets,     Status Reset: F\]
Schedule Completion: 12/31/2018     E related pXZ[ects to ensure           (Commission Construction Auth.)
adequate connection to port
facilities.
Significant Developments                                           Budget/Costs Incurred
Tunnel construction continued, including lid over Bertha disassembly pit. TTI
3.5     2.90
leasehold restoration completed and area returned to tenant. Month-to-month         3
lease continued for remaining areas, including North Pier and South Jackson        2.5
1.75
Street entry. Construction of Pier 62/63 began; Seattle City Light continued          2                       1.38
Phase 2 of the Central Waterfront Transmission Line Relocation Project; and       1.5
1
construction of Colman Dock continued.                                        Dollars in Millions 0.5
0
Schedule                                                            Authorized Forecasted   Costs
Incurred
Tunnel roadway construction is scheduled through Summer 2018. Central
Waterfront construction is expected to begin in 2019 following Viaduct
Construction Costs
demolition. Colman Dock construction to continue through 2023. Central
Waterfront construction is expected to begin in 2019 following Viaduct           Not Applicable
demolition.
Photos
Budget                                                      Girders over north SR99 tunnel
01.04.18
Costs were within anticipated 2017 spending.
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Justification for COs: N/A
Risks
NB SR99 off-ramp to Dexter Ave
Project delays due to unforeseen construction issues.                              11.15.17
Budget Transfers
Amount           From             To
$0

MARITIMD

Port of Seattle 4Q 2017 Report  83

FOURTH QUARTER REPORT, 2017
P66 Alaskan ^_` Street Improvements
Project: bccghi    Widen a segment of Alaskan Way Project Status:
Budget: $1,282,000                   in the vicinity of the Bell Street       Schedule: Within or Ahead 
Phase:  Construction                 Cruise Terminal to improve traffic    Budget: On or Under
Start:  4/1/2015                        flow and safety during cruise days.     Status Reset: 8/23/2016
Schedule Completion: 4/30/2018                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Construction began in October after the completion of the 2017 cruise season
2                 1.7
and the overall work is approximately 1/3 complete. Roadway paving is
1.3
progressing. Encountered poor soil condition which required additional             1.5
0.9
excavation and backfill materials. Burlington Northern Sante Fe imposed more       1
stringent flagging requirements than originally agreed and this resulted in
complete work resequencing and construction delays/additional costs.              Dollars in Millions 0.5
Additional construction funding is anticipated and staff will be requesting            0
additional authorization in Q1 2018.                                                    Authorized Forecasted   Costs
Incurred
Schedule
Construction Contract Costs
Despite challenging field conditions and additional requirements imposed by
the railroad, staff expects the work would be completed and roadway ready for         1
0.8
use before the start of the 2018 cruise season.                                          0.8
Budget
0.6                          0.4
Projecting that additional funding would be needed to complete the project.
0.4
Additional authorization request is planned for Q1 2018.                           Dollars in Millions  0.2
0.0
0
Change Order                                                      Initial  Change   Spent
Orders
Current Quarter       Project Total
Number of COs                 0                   0               Photo
Amount of Cos                 $0                   $0
Risks
Differing site conditions, extra monitoring/protection of aged utility
infrastructure and mature trees, working adjacent to active railroad
tracks/roadways and changing railroad requirements have contributed to
construction delays and additional project costs. Construction is closely
monitored, and necessary adjustments are being made to minimize schedule and
cost impacts.
Budget Transfers
Amount           From             To
$0
MARITIMa
84  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
T-102 jkll Roofs and jmnl oqrst Replacement
Project: C800196                     Replace Corporate Center building   Project Status:
Budget:   uvxyzzxzzz                roofs, final group (3rd phase) of       Schedule:          Within or Ahead 
Phase:  Construction                 rooftop HVAC units, and all         Budget: On or Under
Start: 9/1/2014                         rooftop gas piping. Assets are at the    Status Reset: N/A
Scheduled Completion: 10/31/2016    end of their service lives.             (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Construction completed on all buildings.
7      6.2        6.2
6
Schedule                                                                             4.7
5
Project closeout begun.                                                              4
3
Budget                                                       Dollars in Millions 2
1
Project currently within authorized budget.                                           0
Authorized Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                0                   5
Amount of COs                0                 $36,700                    3.32
3.5
Justification for COs: None this quarter.                                                3
2.5
Risks                                                                2             1.66
No risks at this time.                                                                   Dollars in Millions  1.5
1
0.5           0.00
Budget Transfers                                                     0
Initial  Change  Spent
Amount           From             To                     Orders
$0




ECON. DEVELOPMENT

Port of Seattle 4Q 2017 Report  85

FOURTH QUARTER REPORT, 2017
P66 Elevator {| and {} Control
Project: C800813              Control Systems upgrade for         Project Status:
Budget: $1,067,000                   Elevator 3 and 4 at Pier 66.           Schedule: Within or Ahead 
Phase:  Construction                                                  Budget: On or Under
Start:  5/24/2016                                                             Status Reset: N/A
Schedule Completion: 4/30/2018                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
The prime contractor mobilized and began work on a different elevator on the             1.10
1.20
same contract. Anticipate full production on these elevators after the first of the
1.00                0.85
year.
0.80
0.60
Schedule
0.40                           0.19
The external elevator at street level will not be back in service when cruise
0.20   Dollars in Millions
season begins. Project is on schedule.                                            0.00
Authorized Forecasted    Costs
Budget                                                                        Incurred
On budget
Construction Contract Costs
Change Order
0.6     0.53
Current Quarter       Project Total              0.5
Number of COs                 0                   0                  0.4
Amount of COs                $0                  $0                Dollars in Millions  0.3
0.2
Risks                                                               0.1          0.00    0.05
None                                                             0
Initial    Change     Spent
Orders
Budget Transfers
Amount           From             To
$0
Cost of Construction ~
None


ECON. DEVELOPMENT

86  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
P66 Elevator  Control S
Project: C800813  105261             Upgrades to the elevator controls     Project Status:
Budget: $728,000                     systems.                            Schedule: Delayed 
Phase:  Construction                                                  Budget: On or Under
Start:  5/24/2016                                                             Status Reset: N/A
Schedule Completion: 1/2/2018                                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
The majority of the modernization work is complete.
0.80      0.7
0.70
0.6
Schedule                                                         0.60
0.50
Anticipate a short delay due to preparing for L&I inspection. The main issue is                              0.4
0.40
a hoistway pressurization requirement which surfaced late in the construction.      0.30
Work is being phased with two elevators on Project 105257, which is on the       0.20
0.10   Dollars in Millions
same MC contract.                                                          0.00
Authorized Forecasted    Costs
Budget                                                                        Incurred
Under budget.
Construction Contract Costs
Change Order
0.40      0.3
Current Quarter       Project Total             0.35
0.3
0.30
Number of COs                 5                   5
0.25
Amount of COs            $77,075.00           $77,075.00             Dollars in Millions 0.20
0.15
0.1
0.10
Risks
0.05
Calculated available fault current for the location is higher than the rating of          0.00
Initial    Change     Spent
new elevator gear. This elevator will pass all inspections. The design consultant                     Orders
has proposed a solution, and POS Engineering is helping evaluate solution
and/or propose other solutions. The potential cost of the fault current is a risk
to the project.
Budget Transfers
Amount           From             To
$0                   
Cost of Construction 
A significant change order was approved. Contractor will now complete the
electrical scope originally slated for completion by Marine Maintenance crews.
ECON. DEVELOPMENT

Port of Seattle 4Q 2017 Report  87

FOURTH QUARTER REPORT, 2017
P69 Solar Panel System
Project: C800888                     Design and build a roof-mounted     Project Status:
Budget: $515,000                      kWh/yr photovoltaic (PV)      Schedule:          Within or Ahead 
Phase:  Construction                 solar system at Pier 69 on the         Budget: On or Under
Start:  12/12/2017                      sloped, metal-clad portion of the       Status Reset: 12/12/2017
Schedule Completion: 12/31/2018     roof.                               (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Preparing documents to advertise for a Building Engineering Systems contract,
0.6     0.52       0.52
and to execute an agreement with the WA Department Commerce to accept the
0.5
grant.
0.4
Schedule
0.3
On schedule                                                               Dollars in Millions 0.2
0.1                           0.01
0
Budget                                                          Authorized Forecasted  Costs
Incurred
On budget
Change Order                                               Construction Contract Costs
Current Quarter       Project Total               1
Number of COs                 0                   0
0.8
Amount of COs                $0                  $0                Dollars in Millions  0.6
Risks                                                               0.4
0.2
None                                                                 0.0     0.0     0.0
0
Initial    Change     Spent
Budget Transfers
Orders
Amount           From             To
$0                                                       Photo
Cost of Construction Growth
None


ECON. DEVELOPMENT
88  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
P66 Interior and Exterior Modernization
Project: C800820, C800889         Modernize the interior and            Project Status:
Budget: $2,500,000                 exterior/faade of the P66 facility to    Schedule: Within or Ahead 
Phase:  Planning                  better support the needs of our         Budget: On or Under
Start:  10/11/2016                   customers for the foreseeable future.    Status Reset: 10/11/2016
Schedule Completion: 6/30/2019                                        (Commission Design Auth.)
Budget/Costs Incurred
Significant Developments
Held Executive briefing in August and reviewed design concepts and                3     2.5       2.5
conceptual costs. However, during the subsequent 2018 capital budget              2.5
development/project prioritization, senior leadership decided the exterior             2
modernization portion of the project would be delayed by 5 years. With this         1.5
new development, the project architect team has been directed to focus only on       1
interior modernization related scope. Interior concepts refinement continues.       Dollars in Millions                          0.3
0.5
0
Authorized Forecasted    Costs
Schedule
Incurred
Detailed schedule would be developed in Q1 2018 once desired conceptual
design components are better defined. Current schedule anticipates submitting    Construction Contract Costs
building permit package late 2018 and start construction Q4 2019 to minimize
1
impacts to conference center operations.
0.8
Budget                                                         0.6
Budget is based on preliminary conceptual plans and will need to be validated        0.4
through additional planning/design efforts. Commission approved $2.5M for       Dollars in Millions  0.2
0.0        0.0        0.0
the design development phase of both the Interior Modernization and Exterior
0
Modernization Projects but with Exterior Modernization project no longer in               Initial   Change    Spent
the design scope, the cost of the design phase is expected to be reduced                             Orders
accordingly. Staff expects to renegotiate design development fees in Q1 2018.
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
Risks
Design is still in the conceptual level. LMN Architect services will help define,
refine scope, schedule and budget. Associated risks would continue to be
identified during design development.
Budget Transfers
Amount           From             To
$0
ECON. DEVELOPMENT
Port of Seattle 4Q 2017 Report  89

FOURTH QUARTER REPORT, 2017
Street Vacations T-5 and T-18
Project: C102858, C102875           Street   related real estate     Project Status:
Budget: $5,300,000                   negotiations and agreements          Schedule:           Delayed 
Phase: Implementation              Terminal 5 and Terminal 1          Budget: On or Under
Start: 6/1/2010                                                                Status Reset: 
Schedule Completion: 2018                                              (Commission Construction Auth.)
Significant Developments                                          Budget/Costs Incurred
Scope of project in  finali" property agreements with asset owners in      5.3   5.3
5.3
Port-owned land at T-5 and T-1 Includes reports on how the Port met        5.3
Seattle Department Of Transportation (SDOT) imposed project conditions to     Dollars in Millions  5.2
appro street   petition  for T-5  for T-1      5.2
5.1                          5.1
T-1 Work            5.1
5.0
passed ordinance to execute key easement agreements (SPU      5.0
4.9
Master Easement SPU-BP easement)                                 Authorized Forecasted  Costs
SPU-Port Master Easement signed and recorded by SPU                                        Incurred
SPU executed SPU-Port Asset Transfer Agreement
SPU recorded BP-SPU Easement (Port as rd Party)                      Construction Costs
" signed and returned easement with the Port for                Applicable
telecommunications facility on Harbor Island (the Hut).  in selection
Photos
process for contractor to complete the modifications to the hut.
" ded legal description of the right of way that will be  on
Harbor Island.
SDOT drafted ordinance to  streets. Plans to present to  
in late February or early March.
to negotiate with Olympic Pipeline   for their
easement re" (which are not part of the  re" for
street   appro
first round of real property appraisal of OP easement area.
T-5 Street   work includes:
Shifted efforts to T-5 mostly working on the detailed work plans and
information gathering needed for effort. The    " O"  
will be the difficult issue to resol
Schedule
is scheduling to  streets on Harbor Island in late Q1  or early
Q2  depending on the legislati calendar at   
Port and Olympic Pipeline in final re of easement for pipeline inside
Terminal 1 boundary
T-5 Street   is planned for completion at end of year 
90  Port of Seattle 4Q 2017 Report

Budget
O budget between T-1 and T-5 projects is good.  to no major
expenditures is expected in the foreseeable future. Expense items that will cut
into the budget are within the T-5 side of the project and should not
significantly impact the rall budget.
Change Order
Current Quarter       Project Total
of                    0                       2
Amount of      0    
for   this rter
Risks

Budget Transfers
Amount           From             To











V
Port of Seattle 4Q 2017 Report  91

FOURTH QUARTER REPORT, 2017
Argo  Truck Road
Project: C800546, E            New Port of Seattle owned truck     Project Status:
E                          roadway between East Marginal      Schedule: Within or Ahead 
Budget:     Way and  A South  Budget: On or Under
Phase: Construction                  right-of-way.                        Status Reset:  22 2 
Start: 3/11/2012                                                              (Commission Construction Auth.)
Schedule Completion: 4/15/2019
Significant Developments                                           Budget/Costs Incurred
Union Pacific (UPRR) track crossing impro (POS sharing costs) on
10
East Marginal Way and  A still to be completed; awaiting       7.75  7.75
finalif of construction agreements (currently in progress) between PortP       8
6.10
UPRRP and fC of Seattle; and scheduling of UPRR crew. UPRR Element III   Dollars in Millions 6
Argo Yard Automated G System impro (POS to administer FMSIB   4
funding) construction under rebid by UPRR and SDS permit still in refr      2
0
Schedule
Authorized Forecasted    Costs
Incurred
UPRR railroad crossing impro anticipated to be completed in 2 
UPRR Element III Argo freight yard Automated G System impro 
now anticipated to be completed in 2019.                                        Construction Costs
6    5.05
Budget                                                                      4.50
5
Project is currently within the budget authori by ff on April 22P    4
2                                                                                       3
2
Change Order                                                Dollars in Millions  1       0.41
Current Quarter       Project Total               0
Initial  Change  Spent
Number of       0      3 
Orders
Amount of       $0     $ P4 
Jf f f for     N/A
Risks
No significant known risks at this time.
Budget Transfers
Amount           From             To
$ 


VV V
92  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
T-46 Permit Mitigation
Project: C800620:;<<<=>              * ? v rwater public access    Project Status:
Budget: $1,250,000                   pedestrian pier to comply with        Schedule:           Delayed 
Phase:  Design                      permit re" * @ in operation of    Budget: On or Under
Start:  3/26/2013                       T-T.!                                 Status Reset: N/A
Schedule Completion: 12/20/2019                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
No change from prev reporting.  to wait for Trustee approva ! 
1.40     1.25       1.25
AuthoriAa for construction funds will be re" # in % 2018.     1.20
1.00
Schedule                                                         0.80
0.60
Project is delayed due to Port/Trustee NRD negotiation of the Sites &'(&) 
0.40
Restoration project. Schedule to commence construction on October 2018.         0.20   Dollars in Millions                          0.11
0.00
Budget                                                          Authorized Forecasted  Costs
Incurred
** + within budget
Construction Contract Costs
Change Order                                               Not Applicable
Current Quarter       Project Total
Number of ,      0      0
Amount of      -0      -0
Risks
Potential risk of T-T. container operation due to permit condition out of
compliance.
Budget Transfers
Amount           From             To
-0




/0156 V756897
Port of Seattle 4Q 2017 Report  93

FOURTH QUARTER REPORT, 2017
East Marginal WBD FHBIK Separation
Project: }~                      FAST Corridor funded project;       Project Status:
Budget: ~~    FHWA^ State^ City with Port  Schedule:   Delayed 
Phase: Closeout                       commitment of jbb^gd^dmi Scope   Budget: On or Under
Start: 5/1/2006                         is to construct grade separation in      Status Reset: gbbbdeg
Schedule Completion: 12/8/2017      cX`XYXRM of T5 and T18 to minimihL     (Commission Construction Auth.)
truck traffic/rail conflicts.
Significant Developments                                           Budget/Costs Incurred
Internal POS coordination and final preparation of documents for properties
56.4    56.25     56.25
and easements to be concLMLN to City of Seattle in conjunction with project
56.2
Memo of Agreement. Proposed OQR Boundary Adjustment for POS properties       56.0
has now been approcLN by Seattle DCI and recorded with UXYZ County. Upon    55.8
recXL[ and approc\] of properties/easements documents by SDOT^ Seattle City  Dollars in Millions 55.6
55.30
OXZ_R and Seattle Public Utilities^ concLM\Y`L to be formally approcLN by City         55.4
55.2
Council and Port Commission.
55.0
Authorized Forecasted   Costs
Schedule                                                                           Incurred
Now anticipate final acceptance by Seattle Department of Transportation
(SDOT) in 2018.                                                          Construction Costs
25    22.0            22.0
Budget
20
Project is on track within the April bb^ bdeg Commission authorih\RXQYi
15
Change Order                                                  10
Current Quarter       Project Total            Dollars in Millions   5
2.0
Number of COs                 0                   97                   0
Initial  Change  Spent
Amount of COs                j0               je^kbb^klm                       Orders
nopRXqX`\RXQY for COs:  None this so\rter.
Risks
No risks at this time.
Budget Transfers
Amount           From             To
0
tuwxy Vzxy{|z
94  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Terminal 5 Pile Removal
Project: U00289                       Demolition of existing timber piers   Project Status:
Budget: $6,800,000.00                 "   and 26 and Shipway       Schedule:           Within or Ahead 
Phase:  Construction                 north of the Inner Harbor         Budget: On or Under
Start:  5/19/2016                       Demolition of existing steel sheet      Status Reset: 6/1"
Schedule Completion: 7/31/2018      pile to the existing mud line           (Commission Construction Auth.)
regrade site and install rip-rap.
Significant Developments                                           Budget/   In 
Project is in final stages of construction.
8      6.8
7
Schedule
6                 5.3
Project is on schedule. Contractors punch list completion is expected by            Dollars in Millions  5
4                            3.0
February  2018.
3
2
Budget                                                        1
0
Within budgeted authori
Authorized Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total              
Number of COs                 5                   5
6      5.4
Amount of COs                      
5
Dollars in Millions    4
Risks
3                          2.0
No risks to report at this time.
2
1                0.1
Budget Transfers
0
Amount           From             To                  Initial  Change   Spent
Orders
0
P
V
Port of Seattle 4Q 2017 Report  95

FOURTH QUARTER REPORT, 2017
ID Badge System Replacement
Project: C800162                     Procurement and replacement of     Project Status:
Budget: $2,500,000                    the Portwide ID Badge system        Schedule: Delayed 
Phase: Closeout                       including software hardware and     Budget: On or Under
Start: 5/1/2012                         e"                            Status Reset: N/A
Schedule Completion: 11/30/2017                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
The final phase to deploy a portal for employer self-ser was completed in
2.505     2.50        2.50
Q 2017.                                 2.5
2.495
Schedule                                                         2.49
2.485                            2.48
Prior Report: A critical project to replace the  ding an interface with
2.48
TSA for the badging process security checks and focus on performance           2.475   Dollars in Millions
impro" will redirect Port and  resources resulting in a delay of the  2.47
final components of the ID Badge System Replacement project by an additional        Authorized Forecasted   Costs
Incurred
fi months.
Construction Costs
Budget
Not Applicable
On budget
Change Order
Current Quarter       Project Total
Number of COs                 0                   
Amount of Cos                                 (
for COs:  None this rter
Risks
None at this time
Budget Transfers
Amount           From             To





96  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Parking System Replacement
Project: C800728                     Replacement of the Airport Main       Project Status:
Budget: $5,500,000                     Parking System                 Schedule:           Delayed 
Phase: Implementation                                                 Budget: On or Under
Start: 1/6/2015                                                                Status Reset: N/A
Scheduled Completion: 12/30/2018                                       (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
New system was deployed on original schedule in Q 2017. Additional features          5.50     5.50
6
such as reducing impacts of bank outages and expansion to North Employee lot
5
will be deli in 2018.
4
3                           2.45
Schedule                                                         Dollars in Millions  2
Additional features will be deli throughout 2018.                  1
0
Budget                                                          Authorized Forecasted  Costs
Incurred
On budget
Construction Costs
Change Order                                               Not Applicable
Current Quarter       Project Total
Number of COs                 0                    
Amount of Cos                 0                
for COs:  None this rter
Risks
No significant risks at this time.
Budget Transfers
Amount           From             To







Port of Seattle 4Q 2017 Report  97

FOURTH QUARTER REPORT, 2017
Vessel Moorage System
Project: C800729                     Implementation of a v           Project Status:
Budget: $550,000                     moorage system to support marina     Schedule:          Delayed 
Phase: Implementation               and terminal operations.              Budget: On or Under
Start: 1/12/2016                                                              Status Reset: N/A
Schedule Completion: 12/30/2018                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Contract with selected  was completed in Q implementation is in         0.55   0.55
0.6
progress.
0.5
0.4
Schedule
0.3
Project implementation was delayed due to a lack of response to original           Dollars in Millions 0.2
procurement. A new procurement was ad and a  selected.
0.1                            0.05
0
Budget                                                          Authorized Forecasted  Costs
Incurred
On budget
Change Order                                               Construction Costs
Not Applicable
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
J    for COs: N/A
Risks
No significant risks at this time.
Budget Transfers
Amount            From              To
$ 




C 
98  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Project Delivery System
Project: C800747                     De#%& '(% of a project deli#%d)    Project Status:
Budget: $1,000,000                    system initially for construction       Schedule:           Within or Ahead 
Phase: Design                        projects. System will replace two      Budget: On or Under
Start: 12/14/2016                      legacy systems.                       Status Reset: N/A
Schedule Completion: 12/31/2018                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
DeD is currently in progress.
1.2     1.00        1.00
1
Schedule
Dollars in Millions 0.8
On schedule
0.6
0.4                            0.22
Budget
0.2
On budget                                                                 0
Authorized Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0
Not Applicable
Amount of Cos                 $0                   $0
for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount           From             To
$0
!"
Port of Seattle 4Q 2017 Report  99

FOURTH QUARTER REPORT, 2017
Data Center Operations/Business Continuity
Project: C800748                     Build out of the remote data center   Project Status:
Budget: $1,200,000                    to support automated backup and      Schedule:           Delayed 
Phase: Implementation               recor*+,                           Budget: On or Under
Start: 1/12/2016                                                              Status Reset: N/A
Schedule Completion: 5/1/2018                                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Infrastructure procurement and deployment has been completed to support
1.25
automated backup and recor*+,- The next phase to migrate applications to the         1.20    1.20
new infrastructure is in progress.                                                      1.2
1.15
Schedule                                                         Dollars in Millions                    1.08
1.1
During the design processe complexities were identified that delayed the final      1.05
deployment.                                                                 1
Authorized Forecasted    Costs
Budget                                                                        Incurred
On budget
Construction Costs
Not Applicable
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
./01232451267 for COs: N/A
Risks
Competing priorities from other projects may further delay project completion.
Budget Transfers
Amount           From             To
$0
89:;9:<=>
100  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Port of Seattle W?@ABE? Redevelopment
Project: C800776                     RedeLFZI[\FGR of the Port of        Project Status:
Budget: hijjkjjj     Seattle Website     Schedule:   Delayed 
Phase: Implementation                                                 Budget: On or Under
Start: 8/9/2016                                                                Status Reset: N/A
Schedule Completion: 3/30/2018                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Testing is in progress for a planned Q1 2018 deployment.
0.82     0.80        0.80
0.8
Schedule                                                         0.78
0.76
VFGHIK deliLFKM has delayed deployment by N months.
0.74   Dollars in Millions                               0.72
0.72
Budget
0.7
On budget                                                               0.68
Authorized Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0               Not Applicable
Amount of Cos                 $0                   $0
OPQRSTSUXRSIG for COs: N/A
Risks
With this deployment we are moLSGm to a flexible content management system
that will facilitate decentraliYFH content deLFZI[\FGR] management] and
placement. While the benefits are significant] the learning curLF for the new
technology across the Port may re^PSKF additional time to ensure website
content is appropriately deliLFKFH at launch.
Budget Transfers
Amount            From              To
$0
_`ab`acfg
Port of Seattle 4Q 2017 Report  101

FOURTH QUARTER REPORT, 2017
Airport Subway System Information Displays
Project: C800782                     Procurement and implementation of  Project Status:
Budget: $2,920,000                    an upgraded informational display     Schedule:           Within or Ahead 
Phase: Implementation               system for the Airport trains and      Budget: On or Under
Start: 8/9/2017                         stations.                               Status Reset: N/A
Schedule Completion: 12/31/2018                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Implementation is in progress.
3.5     2.97        2.97
3
Schedule                                                         Dollars in Millions 2.5                 2.00
2
On schedule
1.5
1
Budget
0.5
On budget                                                                 0
Authorized Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0               Not Applicable
Amount of Cos                 $0                   $0
lnopqsqtupqwx for COs: N/A
Risks
No significant risks at this time.
Budget Transfers
Amount            From              To
yz{|{{{              C800782              C80556





}~~
102  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Airport Data Network Switch Upgrade
Displays
Project: C800788                     E and software upgrade     Project Status:
of                                         Budget: $2,982,000                     for the network supporting Airport     Schedule:           Delayed 
Phase: Implementation               Operations systems.                 Budget: On or Under
Start: 2/23/2016                                                              Status Reset: N/A
Schedule Completion: 7/30/2018                                          (Commission Construction Auth.)
Significant Developments                                           Budget/  In 
Failure of some of the new e re a product change that will delay
3.5      2.98        2.98
the final implementation until Q2 2018. There will be no significant budget
3
impact from this de              Dollars in Millions 2.5      2.02
2
Schedule                                                         1.5
1
Prior Report: System deployment was delayed due to an unexpected firewall
0.5
procurement re and opportunity. By completing a competiti       0
procurement during this project we are able to set a standard that will reduce            Authorized Forecasted   Costs
Incurred
maintenance costs and maximi training benefits.
Quarter                                                            Budget                                                                
On budget                                                              Not Applicable
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
for COs: N/A
Risks
No significant risks at this time.
Budget Transfers
Amount            From              To
$0

Port of Seattle 4Q 2017 Report  103

FOURTH QUARTER REPORT, 2017
Checkpoint "t Time
Project: C800790                     Procure and implement an           Project Status:
Budget:     automated system to track  Schedule:   Delayed 
Phase: Implementation               mo and estimate wait times    Budget: On or Under
Start: 7/12/2016                        for checkpoints 2 through 5.           Status Reset: N/A
Schedule Completion: 6/30/2018                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Checkpoint 2 construction was completed in Q 2017. Construction begins for
Checkpoint  and 5 in Q1 2018 and Checkpoint  is estimated for Q2.          1.4   1.22    1.22
1.2
Schedule                                                          1
Schedule is delayed by  months due to competing priorities for construction      Dollars in Millions 0.8
0.6
resources.                                                                                                   0.30
0.4
0.2
Budget                                                        0
Authorized Forecasted    Costs
On budget                                                                                   Incurred
Change Order                                               Construction Costs
Current Quarter       Project Total
0.7     0.63        0.63
Number of COs                 0                   0
0.6
Amount of Cos                 $0                   $0                 0.5
for COs: N/A                                                                     Dollars in Millions 0.4
0.3
Risks                                                              0.2                  0.08
0.1
Re" construction costs are significantly higher than originally estimated prior to      0
procurement of the selected system. This may re" additional funding to complete        Authorized Forecasted  Costs
all planned checkpoints.                                                                                            Incurred
Budget Transfers
Amount            From              To
$0

104  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
SeaTac Smartphone App
Project: C800800                     De of a Mobile app with   Project Status:
Budget: $500,000                     SeaTac Maps Retail Dining and     Schedule:          Delayed 
Phase: Implementation               Ser Options and other           Budget: On or Under
Start: 2/23/2016                        important customer ser            Status Reset: N/A
Schedule Completion: 5/30/2018      features.                            (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Features for a first deployment of an iOS mobile app ha been completed but
0.6     0.50        0.50
impro on indoor turn-by-turn way-finding are in progress. Andriod
0.5
de is in progress.                Dollars in Millions 0.4      0.31
0.3
Schedule
0.2
Prior Report: The team has re-e solution and the Port de    0.1
team will partner with a design firm to deli mobile application. . The first        0
phase deployment was delayed by four months and completed in Q 2017.           Authorized Forecasted   Costs
Incurred
Budget
Incurred                                                                                                               Construction Costs
On budget                                                              Not Applicable
Quarter                                                             Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
for COs: N/A
Risks
No significant risks at this time.
Incurred
Budget Transfers
Amount           From             To
$0



CORPORATE

Port of Seattle 4Q 2017 Report  105

FOURTH QUARTER REPORT, 2017
Airport Telecommunications Capacity Increase
Project: C800827                     Increase of copper and fiber          Project Status:
Budget: $565,000                     telecommunications capacity to       Schedule:          Delayed 
Phase: Closeout                       meet Port and Tenant re    Budget: On or Under
Start: 2/23/2016                                                              Status Reset: N/A
Schedule Completion: 11/30/2017                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Additional capacity completed in Q 2017.                                      0.57     0.57
0.6
0.5
Schedule
0.4
Prior Report: Procurement took longer than expected delaying the project by
0.28
0.3
se (7) months.                         Dollars in Millions 0.2
0.1
Budget                                                        0
Authorized Forecasted    Costs
Prior Report: Contractors estimate is significantly higher than the Port
Incurred
budgetary estimate due to increasing local cost trends. Because capacity
constraints for copper will soon impact tenant operations and larger project        Construction Costs
schedules fiber for which there is no immediate need will be eliminated from   Not Applicable
the scope to complete as ckly as possible. The project will complete fiber
conduit to minimi future costs for fiber expansion.
Change Order
Current Quarter       Project Total
Number of COs                 0                   0
Amount of Cos                 $0                   $0
for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount           From             To
$0

106  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
South Loop Airport Train t Time Displa
Project: C800835                     Expand the North L Subway      Project Status:
Budget: $      Wait Time Display to the South  Schedule: Delayed 
Phase: Implementation               L and Shuttle Stations            Budget: On or Under
Start: 6/19/2016                                                              Status Reset: N/A
Schedule Completion: 11/30/2017                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Construction is in progress for Q1 2018 completion.
0.7      0.58        0.58
0.6
Schedule
0.5                             0.40
Competing projects affecting construction resources continue to delay completion.         Dollars in Millions 0.4
0.3
Budget                                                        0.2
0.1
On budget                                                                 0
Authorized  Forecasted    Costs
Change Order                                                                  Incurred
Current Quarter       Project Total
Construction Costs
Number of COs                 0                   0
Amount of Cos                 $0                   $0                 0.32    0.31      0.31
J for COs: N/A
0.3
0.28
Risks                                                             Dollars in Millions                     0.26
0.26
Resource aa from competing project may continue to delay construction
completion.                                                                          0.24
0.22
Budget Transfers                                                       Authorized Forecasted   Costs
Incurred
Amount           From             To
$0
C 
Port of Seattle 4Q 2017 Report  107

FOURTH QUARTER REPORT, 2017
Supplier Outreach and Procurement System
Project: C800907                     This project will p2)3%de an          Project Status:
Budget: $800,000                     integrated supplier outreach and       Schedule:          Within or Ahead 
Phase: Implementation               procurement solution that utiliu4"      Budget: On or Under
Start: 7/11/2017                        34*v)2 p2)3%ded systems for           Status Reset: N/A
Schedule Completion: 3/31/2019      outreach with a Port-de34P)p4v        (Commission Construction Auth.)
solution for procurement
management.
Significant Developments                                           Budget/Costs Incurred
DeD is currently in progress.
1
0.80       0.80
0.8
Schedule
0.6
On schedule
0.4
Budget                                                       Dollars in Millions 0.2
0.04
On budget                                                                 0
Authorized Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0               Not Applicable
Amount of Cos                 $0                   $0
!"#%&%'(#%)* for COs:  N/A
Risks
No significant risks at this time
Budget Transfers
Amount           From             To
$0
+,-.,-/01
108  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Enterprise Network Firewall Upgrade
Project: C800908                     Upgrade of the Enterprise Network   Project Status:
Budget: $1,500,000                    Firewall Software and EH69IKM>8N     Schedule:           Within or Ahead 
Phase: Planning                                                          Budget: On or Under
Start: 6/27/2017                                                              Status Reset: N/A
Schedule Completion: 12/31/2018                                         (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Planning and design are in progress.                                                 2
1.50     1.50
Schedule
1.5
On Schedule                                                             Dollars in Millions 1
0.58
0.5
Budget
0
On budget                                                                  AuthorizedForecasted Costs
Incurred
Change Order
Construction Costs
Current Quarter       Project Total          Not Applicable
Number of COs                 0                   0
Amount of Cos                 $0                   $0
56789:9;<89=> for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount            From              To
$0
?@AB@AEFG
Port of Seattle 4Q 2017 Report  109

FOURTH QUARTER REPORT, 2017
PeopleSoft Financials Upgrade
Project: C800909                     Upgrade of the PortcS PeopleSoft     Project Status:
Budget: $3,600,000                    Financials System.                   Schedule:           Within or Ahead 
Phase: Planning                                                          Budget: On or Under
Start: 12/12/2017                                                            Status Reset: N/A
Schedule Completion: 3/31/2019                                          (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
Planning is in progress for a QQ Deployment.
4     3.60       3.60
3.5
Schedule                                                         Dollars in Millions  3
2.5
On Schedule                                                               2
1.5
1
Budget
0.5                           0.01
On budget                                                                 0
Authorized Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0               Not Applicable
Amount of Cos                 $0                   $0
ORSTUVUWXTUYZ for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount            From              To
$0
[\]^\]_`b
110  Port of Seattle 4Q 2017 Report

FOURTH QUARTER REPORT, 2017
Rental Car Facility Fleet Tracking System
Project: C800929                     Procure a fleet tracking system and   Project Status:
Budget: $1,055,000                    |ih}nde next bus displays for          Schedule:           Within or Ahead 
Phase: Design                        passengers~ }hnce paging~ wireless     Budget: On or Under
Start: 6/27/2017                        access~ and music at all pick up        Status Reset: N/A
Schedule Completion: 3/31/2019      locations.                           (Commission Construction Auth.)
Significant Developments                                           Budget/Costs Incurred
defghi has been selected and contract negotiations are in progress.
1.2     1.06       1.06
1
Schedule
0.8
On Schedule                                                              0.6
0.4
Budget                                                       Dollars in Millions 0.2                0.02
On budget                                                                 0
Authorized Forecasted    Costs
Incurred
Change Order
Current Quarter       Project Total          Construction Costs
Number of COs                 0                   0               Not Applicable
Amount of Cos                 $0                   $0
jklmnonqrmnhf for COs: N/A
Risks
No significant risks at this time
Budget Transfers
Amount           From             To
$0
stwxtwyz{
Port of Seattle 4Q 2017 Report  111

Limitations of Translatable Documents

PDF files are created with text and images are placed at an exact position on a page of a fixed size.
Web pages are fluid in nature, and the exact positioning of PDF text creates presentation problems.
PDFs that are full page graphics, or scanned pages are generally unable to be made accessible, In these cases, viewing whatever plain text could be extracted is the only alternative.